Solid Expandable Systems A Journey to Perfect SES Reliability through Complex Testing 23 June 2011 Rich DeLange – Director of OCTG

DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Solid Expandable SystemsA Journey to Perfect SES Reliability through Complex Testing

23 June 2011

Rich DeLange – Director of OCTG

Page 2: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Connection Background

Testing Expandable ConnectionsISO 13679 + API RP 5-EX

Downhole Expansion Variables

Testing Equipment

Contents

Page 3: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

What’s So Difficult?

Page 4: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Connection Distortion

Liner connection before expansion

Page 5: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Connection Distortion

Liner connection before expansion

Liner connection after expansion

Page 6: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Animation - 5.5” FODC-OR with 10º Cone

Page 7: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Testing ExpandableConnections

Page 8: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

What Testing is Required?

Resource Group on ExpandablesRP 5-EX Working on a connection testing procedure specifically for expandables

ISO 13679Procedures for testing casing andtubing connections

Page 9: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

ISO 13679 + API RP 5-EX

• Material • Manufacturing Samples

• Make and Break Testing Formats from ISO 13679• Connection Testing (4 levels)• Documentation

__________________________________________

• Expansion of Samples Formats from API RP 5-EX• Post Expansion Testing

“The expansion test shall reproduce the conditions experienced downhole”

Page 10: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

ISO 13679 Testing Principle

-6,000

-5,000

-4,000

-3,000

-2,000

-1,000

0

1,000

2,000

3,000

4,000

5,000

6,000

-2,000 -1,500 -1,000 -500 0 500 1,000 1,500 2,000

Pres

sure

, psi

Axial Load, kips

Pipe Body and Connection Load Diagrams11.750 in. OD, 0.582 wall, 50 ksi pre exp, 60 ksi post exp

Pipe Body VME Pre

Page 11: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

ISO 13679 Testing Principle

-6,000

-5,000

-4,000

-3,000

-2,000

-1,000

0

1,000

2,000

3,000

4,000

5,000

6,000

-2,000 -1,500 -1,000 -500 0 500 1,000 1,500 2,000

Pres

sure

, psi

Axial Load, kips

Pipe Body and Connection Load Diagrams11.750 in. OD, 0.582 wall, 50 ksi pre exp, 60 ksi post exp

Pipe Body VME Pre Pipe Body VME Post

Page 12: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

ISO 13679 Testing Principle

-6,000

-5,000

-4,000

-3,000

-2,000

-1,000

0

1,000

2,000

3,000

4,000

5,000

6,000

-2,000 -1,500 -1,000 -500 0 500 1,000 1,500 2,000

Pres

sure

, psi

Axial Load, kips

Pipe Body and Connection Load Diagrams11.750 in. OD, 0.582 wall, 50 ksi pre exp, 60 ksi post exp

Pipe Body VME Pre Pipe Body Collapse Pre

Page 13: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

ISO 13679 Testing Principle

-6,000

-5,000

-4,000

-3,000

-2,000

-1,000

0

1,000

2,000

3,000

4,000

5,000

6,000

-2,000 -1,500 -1,000 -500 0 500 1,000 1,500 2,000

Pres

sure

, psi

Axial Load, kips

Pipe Body and Connection Load Diagrams11.750 in. OD, 0.582 wall, 50 ksi pre exp, 60 ksi post exp

Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse Post

Page 14: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

ISO 13679 Testing Principle

-6,000

-5,000

-4,000

-3,000

-2,000

-1,000

0

1,000

2,000

3,000

4,000

5,000

6,000

-2,000 -1,500 -1,000 -500 0 500 1,000 1,500 2,000

Pres

sure

, psi

Axial Load, kips

Pipe Body and Connection Load Diagrams11.750 in. OD, 0.582 wall, 50 ksi pre exp, 60 ksi post exp

Pipe Body VME Pre Pipe Body Collapse Pre Connection Pre

Page 15: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

ISO 13679 Testing Principle

-6,000

-5,000

-4,000

-3,000

-2,000

-1,000

0

1,000

2,000

3,000

4,000

5,000

6,000

-2,000 -1,500 -1,000 -500 0 500 1,000 1,500 2,000

Pres

sure

, psi

Axial Load, kips

Pipe Body and Connection Load Diagrams11.750 in. OD, 0.582 wall, 50 ksi pre exp, 60 ksi post exp

Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post

Pipe Body Collapse Post Connection Pre Connection Post

Page 16: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

ISO 13679 Testing Principle

-6,000

-5,000

-4,000

-3,000

-2,000

-1,000

0

1,000

2,000

3,000

4,000

5,000

6,000

-2,000 -1,500 -1,000 -500 0 500 1,000 1,500 2,000

Pres

sure

, psi

Axial Load, kips

Pipe Body and Connection Load Diagrams11.750 in. OD, 0.582 wall, 50 ksi pre exp, 60 ksi post exp

Pipe Body VME Post Pipe Body Collapse Post Connection Post

Page 17: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

RP-5EX Pre-Expansion Test Matrix

TestLevel

Sample Number

Sample 1 Sample 2 Sample 3 Sample 4 Sample 5 Sample 6

Seals &Threads

Low SealHigh Thread

High SealLow Thread

Low SealHigh Thread

Low SealHigh Thread

High SealHigh Thread

Low SealLow Thread

A Make-Up Only Make / Break Test

5 Capped-EndPressure Cycles

5 Capped-EndPressure Cycles

B Make-Up Only Make / Break Test

5 Capped-EndPressure Cycles

5 Capped-EndPressure Cycles

C & D Make-Up Only Make / Break Test Make / Break Test Make-Up Only

ISO B 275º F ISO B 275º F

E Make-Up Only Make / Break Test Make / Break Test Make-Up Only Make / Break Test Make-Up Only

ISO B 275º F ISO B 275º F

Page 18: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

RP-5EX Expansion MatrixSample Number

Test Level Sample 1 Sample 2 Sample 3 Sample 4 Sample 5 Sample 6

A Straight Straight

Fixed-Free Fixed-Free

B Straight Straight

Fixed-Free Fixed-Free

C Straight Straight Straight Straight

Fixed-Free Fixed-Free Fixed-Free Fixed -Fixed

D Bent Straight Straight Straight

Fixed-Free Fixed-Free Fixed-Free Fixed -Fixed

E Bent Straight Straight Straight Bent Straight

Fixed-Free Fixed-Free Fixed-Free Fixed -Fixed Fixed-Free Fixed -Fixed

Page 19: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

RP-5EX Post-Expansion Test MatrixSample Number

Test Level Sample 1 Sample 2 Sample 3 Sample 4 Sample 5 Sample 6

A Installation Cycles Installation Cycles

Failure Test Failure Test

B Installation Cycles Installation Cycles

External Tests External Tests

Failure Test Failure Test

CLoad / Pressure

CyclingLoad / Pressure

CyclingLoad / Pressure

CyclingLoad / Pressure

Cycling

ISO B 275º F ISO B 275º F ISO B’ 275º F ISO B 275º F

(External)

Failure Test Failure Test Failure Test Failure Test

DLoad / Pressure

CyclingLoad / Pressure

CyclingLoad / Pressure

CyclingLoad / Pressure

Cycling

ISO B 275º F ISO B 275º F ISO B’ 275º F ISO B 275º F

(External)

Failure Test Failure Test Failure Test Failure Test

E

Load / Pressure Cycling

Load / Pressure Cycling

Load / Pressure Cycling

Load / Pressure Cycling

Load / Pressure Cycling

Load/Pressure Cycling

ISO B 275º F ISO B 275º F ISO B 275º F

ISO A 275º F ISO A 275º F ISO A 275º F

Failure Test Failure Test Failure Test Failure Test Failure Test Failure Test

Page 20: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Cone Expansion

Page 21: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Why is Testing Expandable Connections so Complicated?

Page 22: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

The Variable Challenge

ISO 13679 Connection Testing Variables

Connection Dimensional TolerancesGrade of Pipe considerations TemperatureGas or FluidThread Compounds considerations

Page 23: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

The Variable Challenge

ISO 13679 Connection Testing Variables

Connection dimensional tolerancesGrade of pipe considerations TemperatureGas or fluidThread compounds considerations

RP 5-EX Additional Connection Testing Variables

Grade of pipe / mill sourceID Coating and wellbore fluidsExpansion systems (mechanical, pressure, combination)Expansion

Constraints (tension or compression or some of both)Fixed-free or fixed-fixedDeviated hole / doglegLoad cycles during expansion process

Page 24: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

© 2008 Weatherford. All rights reserved.

Change in Connection Load during expansion:

Compression to Tension-7,000 to +394,000

100’ from TOL

1250’ from TOL

2450’ from TOL

Change in Connection Load during expansion:

Compression to Tension-87,000 to +314,000

Change in Connection Load during expansion:

Compression to Tension-170,000 to +231,000

Every connection’s load change in this example is 400,000 lbs

Example2,500’ Open Hole 11-3/4 Liner Expansion Force ~ 400,000 lbf

• 175,000 lb air weight• Pressure to drive Cone = 1,900 psi = 226,000 lbs End Thrust / Tension behind cone

Page 25: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

SPE/IADC 140262

11.75” DLX expanded FODC-OR samples

• Expanded 4 Samples simulating a 4,000’ liner set at 13,000’– 2 Expanded with top of string loads– 2 Expanded with bottom of string loads

• Critical section thicknesses were measured before and after expansion with a Coordinate Measuring Machine (CMM)

25

Page 26: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

26

-9.0 %-6.8%

-10.4%-7.0%

-9.9%-7.4%-12.3%

-9.3%

Pin Connection Section Thickness Changes

Changes in dimensions from the unexpanded condition• Top values are from the top of liner• Bottom values are from the bottom of liner

The expanded pins are different at the top and bottom

Page 27: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

27

-17.5%-16.1%

-12.3%+26.7%

-8.4%-7.2%

Changes in dimensions from the unexpanded condition• Top values are from the top of liner• Bottom values are from the bottom of liner

Box Connection Section Thickness Changes

The expanded boxes are different at the top and bottom

Page 28: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Testing Equipment

Page 29: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

ISO 13679 + API RP 5-EX

“The expansion test shall reproduce the conditions experienced downhole”

Page 30: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

© 2008 Weatherford. All rights reserved.

Expansion BenchDesign

Drill Pipe

Un-expanded Pipe

Expansion Cone

Expanded Pipe

Page 31: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

DLX Machine

31

Page 32: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Test Lab

North Cell

The DLX Simulator650,000 lbf Tension525,000 lbf Compression

Dynamic Expansion Fixed-Free Fixed-FixedTension & Compression Pre-Loads (maintained during expansion stroke)

3-1/2” thru 13-5/8” pre-expanded ODs15-foot strokeMechanical or Pressure ExpansionBent Expansions

Dynamic Load Expansion Simulator

Page 33: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

OCTG Prototype Manufacturing Line

Stations• Handling Tables• Horizontal Swage• Stress Relieve• Threading• Inspection• Magnetic Particle Inspection• Surface Treatment

Page 34: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Prep Lab

Stations• Inspection• Make-Up / Break-Out

– 3.5” thru 14”• Welding• Cone Insertion• Ultrasonic Measurement• Strain Gauging

Page 35: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

South Cell

Small Expansion Bench235,000 lbf Tension ConstraintCompression Constraint

Test Cellar12’ x 4’Steel CoversVented

Page 36: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Expansion with Bending

Constant Radius Bending Beam

• 12’ long• Up to 8” pipe• Any Deviation• MOL expansion• Fixed-Free & Fixed-Fixed

• Allows ISO 13679 testing with Load Frameafter expansion

Page 37: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Bending Beam / Load Frame Assembly

Page 38: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Summary of Expandable Connection Complexities

• Expansion creates new product downhole….which new productdepends on the variable set

Page 39: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Summary of Expandable Connection Complexities

• Expansion creates new product downhole….which new productdepends on the variable set

• Standardized test procedures are importanto ISO 13679 nowo API RP 5-EX very soon

Page 40: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Summary of Expandable Connection Complexities

• Expansion creates new product downhole….which new productdepends on the variable set

• Standardized test procedures are importanto ISO 13679 nowo API RP 5-EX very soon

• Test samples must be accurate representationso Materialo Threading process & dimensionso Pre & post load conditionso Proper constraint……fixed-fixed or fixed-free

Page 41: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Summary of Expandable Connection Complexities

• Expansion creates new product downhole….which new productdepends on the variable set

• Standardized test procedures are importanto ISO 13679 nowo API RP 5-EX very soon

• Test samples must be accurate representationso Materialo Threading process & dimensionso Pre & post load conditionso Proper constraint……fixed-fixed or fixed-free

• VME testing required to qualify performance envelopes

Page 42: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Summary of Expandable Connection Complexities

• Expansion creates new product downhole….which new productdepends on the variable set

• Standardized test procedures are importanto ISO 13679 nowo API RP 5-EX very soon

• Test samples must be accurate representationso Materialo Threading process & dimensionso Pre & post load conditionso Proper constraint……fixed-fixed or fixed-free

• VME testing required to qualify performance envelopes

• Major variable sets must all be tested to minimize risk

Page 43: DeLangeDEA June 23, 2011 Rev2dea-global.org/wp-content/uploads/2010/09/DeLangeDEA... · 2012-04-14 · Pipe Body VME Pre Pipe Body Collapse Pre Pipe Body VME Post Pipe Body Collapse

Questions