Upload
others
View
22
Download
0
Embed Size (px)
Citation preview
Decommissioning and Dismantling of the
Moata Reactor
Alec Kimber
Australian Nuclear Science &
Technology Organisation
A History of Moata
• Graphite
moderator /
reflector
• Cooled by light
water
• Shielding - high
density and low
density concrete
• Constructed at ANSTO in 1961
• ARGONAUT type reactor
• Built as a 10 kW reactor, but modified
in 1972 to 100 kW
The Moata Reactor
From 1961 to 1995:
– Neutron
radiography
– Training
– Soil analysis
– Cancer
treatment
research
– Quality Control
for HIFAR
Shutdown & Decommissioning
Two phases of dismantling:
– Preliminary Dismantling – the removal of the internal components of the reactor, including the steel core structures, graphite moderator and beam line facilities
– Structural (Biological Shield) Dismantling – the cutting and removal of the concrete shielding and the floor area below the shielding.
1995 1997 1998 2008 2009 2010
Sh
utd
ow
n a
fter 4
,51
9 s
tart-u
ps
Fu
el u
nlo
ad
ed
Prim
ary
co
ola
nt (lig
ht w
ate
r) dra
ine
d
Re
acto
r Co
ntro
l Syste
m re
mo
ve
d
Pre
limin
ary
Dis
mantlin
g J
uly
2009
Co
nta
inm
en
t ten
t insta
lled
Bio
logic
al S
hie
ld D
ism
antlin
g b
egan
Bio
logic
al S
hie
ld D
ism
antlin
g C
om
ple
te
Pla
nnin
g fo
r Moata
Dis
mantlin
g
2000 –
De
co
mm
issio
nin
g L
ice
nce
Characterisation – Survey • Core samples extracted
• Radiological surveys carried out
– Determine dose rates
– Allow for waste reduction
• Data used to prepare a dose estimate for
dismantling
– Internal reactor components
– Biological shield
• Radiological surveys allowed estimation of
maximum individual and collective doses
Reactor Internals - Dismantling
• Control rod & drive
assemblies
• Graphite moderator – core &
N, S, E & W cavities [approx
12 tonne]
• Aluminium core tanks
• Pipe work
• Steel framework – graphite
support
• Gamma curtain – lead sheet [approx 750kg]
Structural (Biological Shield) Dismantling
• MOATA housed in a building used for
AMS for C-14 dating
• A containment tent with HEPA filtered
extraction system built around the reactor
Biological Shield - Dismantling
Challenge 1 – An Australian first
Challenge
• Nothing similar had ever
been attempted previously
• Challenging to project team
• Slow start
Mitigation
• Identifying and developing
on-site expertise
• Explored use of external
companies – estimates:
– Turn key ($12M)
– Implementation ($8M)
– Partnership ($6M)
• Detailed planning
“we can do this”
Challenge 2 – Regulatory
Challenge
• ARPANSA had never dealt
with a reactor
decommission / dismantle
• Regulatory caution
Mitigation
• Communication
– Start early (Identification of
requirements)
– Continuous
• Detailed planning
– Development of knowledge
– Developing organisational
confidence
“They can do this”
Challenge 3 – Internal management
Challenge
• Does ANSTO have the
skills?
• Never undertaken a reactor
decommission
• Easy to be less constructive
Mitigation
• Project champion
• Staff training and expertise
• Detailed planning
– Development of knowledge
– Developing organisational
confidence
“ANSTO can do this”
• Stakeholder management
– Early communication
– Continual information
Challenge 4 – External interest
Challenge
• Pressures from external
interest groups and
stakeholders
– Politicians / government
– ANSTO Board
– IAEA
– Public
– Media
Mitigation
• Communication
– Continuous
– Factual
– Managed
• Detailed planning
– Development of knowledge
– Developing organisational
confidence
“ Lets see if ANSTO can do
this”
Challenge 5 – Project financial
Challenge
• Decommissioning estimate
developed from UK and US
reactor dismantling
• Inherited a budget (AUS$3.8M)
– Minimal contingency
• Decommission within budget
Mitigation
• Earned value analysis
employed
• Job number allocation and
control
• Early communication of cost
overrun
Challenge 6 – Tandem Accelerator
Challenge
• Adjacent Tandem accelerator
– Sensitivity to carbon14 (1x10-14)
[12 Tonne of graphite in MOATA]
• Risk to future of carbon dating
program and research at LH
Mitigation
• Localised tent and extract
• Fully enclosed and tented
work area
– Double skinned
– Air inflow through tent skin
• Extract filtration
– Primary dust
– Secondary HEPA extract
filtration
Challenge 7 – Technology
Challenge
• What methods were
applicable?
• What technology was
available and suitable?
– Lack of knowledge by project
team
Mitigation
• Research into methods
• Consultant advice sought
• Detailed planning
– Development of knowledge
– Developing organisational
confidence
“ANSTO can do this”
Challenge 8 – Drawing inaccuracies
Challenge
• 1950’s drawings
– Imperial
measurements
• Uncertainty of as-
built drawings
– Unknown details
• Known inaccuracies
Mitigation
• Expert draughtsman
• 3D CAD drawings produced
• Physical 3D model
Challenge 9 – Radiation protection
Challenge
• Doses likely to be
encountered
• Shielding methods
– Self shielding
– Distance
• No dose-sharing ALARA
Mitigation
• Characterisation
– Dose modelling
– Physical measurements
• Detailed planning
– Tooling
– PPE
– Shielding
• Contingency planning
– What if?
• Identification & removal of
hottest items
Challenge 10 – Safety
Challenge
• Industrial safety
– Working at heights
– Wire cutting
– Manual handling
– Dust
• Mechanical plant
– Mobile crane
– Excavator
Mitigation
• In-house safety expert
– OHS + Radiation
– PPE
• 3-day contractor safety
training
• Daily safety checks
– walkabout
• Daily safety talks
– Contractor
– ANSTO personnel
Challenge 11 – Contractor
engagement Challenge
• Interfacing
– ANSTO safety procedures
– ANSTO ‘systems’
• Fear of radiation
• Understanding the
decommissioning process
• An Australian first
• Keeping the cost realistic
Mitigation
• Initial contractor evaluation
• Presentation to eligible
contractors
• Detailed Specification
– Responsibilities table detailing
contractor interfaces with
ANSTO
• Final contractor evaluation
Challenge 12 – Work systems
methodology Challenge
• Day to day safe working
• Contamination minimisation
• Waste clearance methods
• Communication
Mitigation
• Site function plan
• Safe Work Method Statements
• Commitment to safety
– Full time, on-site supervisor
– Daily safety checks
– ANSTO supplied PPE
– Health physics on call
• Daily safety meetings
• Weekly project meetings
Challenge 13 – Waste removal and
clearance Challenge
• Waste handling processes
– Waste types
– Quantities
– Handling and transport
– Packaging
• Availability of staff
– Project vs operational needs
• Clearance processes
– Methods & Instrumentation
– location
Mitigation
• Knowledge of reactor
– Materials, characterisation, size
and location
• Understand demolition processes
– Consultant advice
– Contractor advice
• Consult Waste Management Team
• Utilise suitable methods
– Model and calibrate instruments
and processes
Challenge 14 – Records
Challenge
• Preparation (1995 - 2000)
– Operational records, drawings
– Preliminary planning incl DP
• Dismantling Project
– Project planning records
– Daily project records (log
books, waste assessment and
clearance, Health Physics)
– A story to be shared
Mitigation
• Identified and collected all
available historical records
• Team included former operators
• Engaged technical writer who
also collated records
• Waste management group -
“Radioactive Waste Tracking
System”
• Contractor provides records of
all wastes cleared from site.
• Project DVD
Final Survey
• Dose surveys carried out in grid pattern as per original survey
• Acceptance criteria of 0.5uSv/hr was met
• Samples taken and analysed for activity < clearance criteria
• Guides to determine the exemption and clearance criteria for the site
– IAEA No. RS-G.1.7
– ARPANSA Reg 1999, Schedule 2, Part 2
Radiation Protection -
outcomes
• Dismantling was completed safely and without incident
• Dose estimates higher than those recorded
– Overly conservative estimations
– Very detailed planning [‘what if scenarios’]
– Concrete dismantling – self shielding and greater distance
– Time taken to dismantle less than anticipated
• No surface or airborne contamination detected throughout
the project
• No personal contamination events
Radiation Protection –
Dose results
– Estimated doses vs. actual doses:
Dose ANSTO
Estimated
ARPANSA
Constraint
ANSTO
Constraint Actual
Collective 10,400 person-
μSv
13,000 person-
μSv
10,400 person-
μSv
1,679 person-
μSv
Max.
Individual 1444 μSv 1750 μSv 1500 μSv 252 μSv
Daily - - 50μSv 46μSv (max)
Project - lessons learned
• Bridging the gap – Telling the safety story in a way that the contractor can easily understand
• Documents – The level playing field – use of a single set of documents suitable for all purposes (regulator, contractor etc)
• Stakeholder – A project champion – Required to ensure early commitment from departments
• Operational v Project needs – project requires rapid responses to maintain workflow.
• Thorough planning leads to success – …and constant review!
Project Achievements • Setting Trends
– Ownership / Extending ANSTO department capabilities
– Procurement – Adjusting their mandate to be more
responsive to project requirements
• Survived it being a very high profile project
• Developed high quality stakeholder
communication
• Regulatory approval and commendation
• Internal & External QA Audit incl Environmental
• Awards including National Best Small Project
2010 (Australian Institute of Project Management)
Project Achievements • Site Function Plan
• Engagement of expert advice – Comprehensive understanding of the project
scope – High quality specification of works – Enhanced ability to deal with demolition
contractor – Significant savings on demolition contract
• Highly informed project team – Development of in-house expertise
• Development of confidence for future needs
• Final cost within approximately 10% of budget
Project Achievements
• Extremely powerful visualisation tool
• Aid to contractor understanding
• Enabled good understanding of the tasks ahead
3D Modelling including Physical Model
Project Achievements
• Physical Model
Moving forward to HIFAR
• Experienced and highly informed project team
– in-house expertise now developed
• Engagement of expert advice
– Have a comprehensive understanding of the project scope
– Enhanced ability to deal with demolition contractor
• Organisation + project confidence in capabilities
• Proceed with detailed planning whilst local knowledge is available