Upload
owen-allen
View
212
Download
0
Embed Size (px)
Citation preview
December 3-4, 2003 Green BankGBT PTCS In Progress Review
EMS/LRF Update
Richard Prestage
2
Goals
• From April CoDR:
“….EMS/LRF…will be available as a GBT surveying tool, allowing us to measure critical dimensions and characterize the antenna with considerably higher accuracy and convenience than is possible with conventional surveying techniques”.
• Panel Report:
“…Careful measurements of simpler performance aspects are needed to evaluate if the LRF are useful in other modes of operation.....”
3
From June 16th PTCS Project Meeting
• EMS Objectives– “Production” Use, 1mm or better
– Characterization of LRF accuracy
– Develop EMS/Wit/Matlab frameworks for experiments
– Feed Arm Tip Survey
– Subreflector Survey
• Schedule– EMS Framework (completed)
– Test data set collection beginning early July, repeated at intervals
– Prototype trilateration EMS code August, developed with July data
– Completed FA survey tool September
– Prototype SR survey tool September
4
Actual Schedule
• EMS sufficiently complete to execute experiments: late May.
• EMS Refinements for real-time trilateration results: August.
• LRFs ready for basic trilateration experiment: end August
• First “successful” trilateration experiment: 5th September
5
Results
• EMS prototyping/characterization tool resounding success.
• LRF trilateration results c.f. traditional survey showed significant discrepancies.
• April to September: ~two staff years of effort.
• Clearly would not be able to make any significant performance contributions for Winter 03/04.
• Temperature sensors and traditional approaches were showing great promise.
• Postpone further LRF work until Spring 2004.