Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Dear Review Panel,
I am submitting my below comments with regards to CN’s submission Package 8, #705,
dated December 18, 2018.
1. No Signatures on Responses
With regards to the lack of signatures on CN’s technical reports and responses, I raised
my concerns to the Review Panel in my previous submissions (CEAR #435, #648).
However, I am still not seeing any signatures, professional designations, and
professional seals attached to these latest responses.
As I mentioned previously, attaching signatures and professional seals to final reports is
required under the Ontario Professional Engineer’s Act and its Regulation 941/90. The
Professional Engineers Ontario states that, “by sealing documents and drawings, licence
holders acknowledge that they assume professional responsibility for the design,
opinions, judgments or directions given in the documents and drawings. The seal is a
"mark of reliance," indicating that a licence holder attests that other people can rely on
the information provided in the documents and drawings.”
In fact, I believe most, if not all technical reports submitted to municipalities, and the
Ontario Ministries (e.g. Environment and Transportation, etc.) must be signed, dated,
and sealed. The submissions by the Halton Municipalities (CEAR #549) all have the
information on the authors, their professional experience, professional designations, and
professional seals (if applicable).
Since the CN Project is such a high-profile undertaking, I am wondering why the
majority, if not all, of the reports and responses bear NO signatures, professional
designations and professional seals. With the lack of these basic yet essential elements
in the CN reports and responses, how could the public trust the information,
methodology, opinions and conclusions contained in the reports and responses?
For the above rationale, I respectfully suggest that the Review Panel requires that
all CN technical reports and responses must bear the authors’ names, signatures,
processional designation, and professional seals (if applicable).
2. IR8.8 Applicability of the Ambient Noise Measurements at the Points of
Reception
In its responses, CN stated that Stantec conducted the background noise modelling. As
per CN’s statement, “The noise modelling was based on Stamson emission sound
power levels that were incorporated into CADNA to predict road and rail noise at the
monitoring locations.”
Firstly, I do not think I saw the details as to what road/rail traffic data were used, receptor
locations, heights, distances to road/rail lines, etc. Without this information, there is no
way the public and professionals can verify the calculation results.
Secondly, as far as I know, STAMSON is the only acceptable program when it comes
modeling traffic noise impact in Ontario. The calculations are acceptable to the Ontario
municipalities for subdivision applications, Ministry of Transportation for road related
projects, and Ministry of Environment for determining background noise levels in support
of applications for Environmental Compliance Approval (ECA). There are detailed
guidelines and instructions that must be followed in the calculations. STAMSON has
been used in Ontario since late1980s and has been proved to be an accurate traffic
noise modelling tool. With the output from the program, it is very easy to verify the input
data and calculation results.
CADNA, on the other hand, is not an acceptable modelling tool when it comes to
modelling traffic noise impact in Ontario. In fact, CADNA is also not accepted by the US
Federal Highway Administration (FHWA) and its state counterparts for traffic noise
related projects. The Traffic Noise Model (TNM) is the only acceptable modelling tool.
Having mentioned the above factual information, I am puzzled as to why CN/Stantec
would not use the STAMSON program to calculate the background traffic noise.
Therefore, I respectfully suggest that the Review Panel request the following additional
information:
STAMSON must be used in determining background noise levels
Provide a detailed list of traffic data, commercial vehicle breakdowns,
receptor heights, distances and exposures to the applicable road/rail.
Provide STAMSON output for each receptor calculations including Leq and
Ldn.
3. ATTACHMENTS IR8.15-1, 2, 3, 4, 5, 6
Towards the end of the responses, CN/Stantec provided the above attachments showing
output from various modelling scenarios. These output files look like the output from the
CADNA program. However, it is still hard to verify the modelling details such as the
configuration and assumptions, etc.
For the sake of verifications by the professionals, I respectfully suggest that the
Review Panel requires that CN/Stantec to provide the CADNA modelling file(s) and
make them available to the public on its website.
My rationale is that, by making the CADNA modelling files available to the public, it
would be easy for professionals to review the modelling details. I know for sure that the
acoustical consultant retained by the Halton Municipalities can review the CADNA
modelling files.
4. IR8.12Receptor Heights and Site Specific Topographic Information
Details in verifying the receptor heights were provided in this section. The acoustical
model was refined accordingly in the CN responses. However, I felt that two issues are
still needed to be addressed.
The first issue is the topographic elevation differences between the site and selected
receptors. For comparison purpose, two figures are attached with marked elevations.
One figure was taken from the CN/Stantec report showing the site and selected
receptors. The other figure was taken from a Google Earth image dated May 7, 2018. In
both figures, the elevations around the site and nearby receptors were labelled in red
color.
Based on Google Earth, the site elevations are between 179 m to the south and 184 m
to the north. As marked on the figures, the receptor ground elevations to the north range
from 186 m to 189 m. There is an elevation difference as high as 10 m! What this means
is that that those receptors will have a direct line-of-sight of the CN operations. It would
render any noise berms and barriers ineffective, as they may not provide shielding to the
noise emissions.
The second issue is that there is an application with the Town of Milton that six (6) mid-
rise residential buildings are being proposed at the northeast corner of Britannia Road
and Bronte Street South. These buildings are between 4 and 6 storey high. See the
attached site plans which are also available from the Town’s website. As these buildings
are going to be built on higher ground elevations, they would also have direct line-of-
sight to the CN operations.
The above factors mean that the acoustical model needs to be revised in order to
account for:
- Elevation differences between the site and receptors to the north of the site, along
Bronte Street South and CN railway tracks; and
- The new development at the northeast corner of Britannia Road and Bronte Street
South.
Thank you for your consideration.
Sincerely,
J. Wang
")
")")")
")
")
")
")
") ")
")
")
") ")") ")
")
")
")
")
")
")
")
") ")")
")
") ")
")
")
")")
")
")")
")
#*
#*
*
#*
#*
#*
#*
#*
#*#*
Halton Region WasteManagement Facility
Scott Boulevard
Tremaine Road
Asleton Boulevard
Brita nn ia
Road
Santa Maria Boulevard
McD
ougall Crossing Savoline Boulevard
Dymott Avenue
Whaley Way
Whewell Trail
Farmstead Drive
Bessborough D
riveUrell Way
Dice Way
McLaughlin Avenue
Sera fini Crescent
Highway407
Lower B
ase Line
Bronte Street South
Henderson Road
LouisSt Lau ren tAven ue
Derry R
oad
1st Sideroad
2nd Sideroad
Burnham
thorpe Road W
est
First Line
Bell School Line
Holm
esC
r escent
Schreyer Crescent
Le iterma n
Drive
Nairn Circle
Biason
Circle
Cedric TerraceTonelli Lane
G1-POR001
G1-POR002G1-POR003G1-POR004
G1-POR005
G1-POR006 G1-POR007G1-POR008
G1-POR009G1-POR011
G1-POR012G1-POR013 G1-POR014 G1-POR015
G1-POR016
G1-POR017
G1-POR018
G1-POR019
G1-POR020
G1-POR021
G1-POR022
G1-POR023
G1-POR024 G1-POR025
G1-POR026
G2-POR001
G2-POR002G2-POR003
G2-POR004
G3-POR001
G3-POR002G3-POR003G3-POR004
G3-POR005
G3-POR006G3-POR007G3-POR008
M01-2015
M02-2015 M03-2015
M04-2015
M05-2014
M06-2014
M07-2015
M08-2014
M09-2014 M10-2015
Legend
November 2015160960844
Client/Project
Figure No.
2Title
Points of Reception and MonitoringLocations near the ProposedProject Development Area
0 550 1 100m
1 22 000
0 550 1 100m
\\C
d12
20-f
02\0
1609
\ac
tive\
6096
0844
\dra
win
g\M
XD\A
tmos
phe
ric\A
cou
stc
\Ba
selin
e_M
onito
ring
_Re
po
rt\16
0960
844_
Noi
se_B
MR_
Fg
02_P
ORs
_Mo
nito
ring
_Lo
ca
tons
.mxd
Rev
sed
: 201
5-11
-30
By: p
wo
sel
Project ComponentsProject Development Area
Existing Single Track Mainline
Existing Double Track Mainline
Double Track - Mainline
Project Component
CN-Owned Property
SWM Pond") Receptor Location
#* Noise Monitoring Location
±
Coordinate System: NAD 1983 UTM Zone 17N
Base features produced under icense with the Ontario Ministry of Natural Resources and Forestry© Queen s Printer for Ontario, 2015. Site layout: July 10, 2015.
Orthoimagery © First Base Solutions, 2015. Imagery taken in 2014.
Notes1.
2.
3.
Milton
Oakville
4th Line 6th Line
Walkers Line
First LineTremaine Road
Appleby Line
High
way 4
07
Bell School Line
Key Map
Canadian National RailwayMilton Logistics HubTechnical Data Report - Baseline Ambient Noise Study(Appendix E.9)
182m183m
184m
188m186m
186m
189m
179m179m
182m
POR-Site Elevation Changes: 189 m -> 179 m
183m
182m
184m
POR/CN Site Elevations(From Google Earth)
186m
188m
186m
New Development
188m
The Corporation of the Town of Milton
Report To: Council
From: Barbara Koopmans, Commissioner, Planning and Development
Date: July 24, 2017
Report No: PD-034-17
Subject: Public Meeting and Initial Report: Proposed Zoning By-law Amendment for the Major Node by Main Sails Estates Inc., on Part of Lot 6, Concession 2, New Survey, Trafalgar, Town of Milton (Town File: Z-09/14-A)
Recommendation: THAT Planning and Development Report PD-034-17, BE RECEIVED FOR INFORMATION.
EXECUTIVE SUMMARY
The applicant is seeking to rezone the major node which is within the Main Sail Estates plan of subdivision from the existing site-specific Future Development Zone to a site-specific Residential High Density (RHD*AAA) Zone and a site-specific Residential Medium Density 2 (RMD2*BBB) Zone. The purpose of the application is to zone the lands to permit a condominium development consisting of a four to six-storey apartment building with 219 units and 53 townhouse dwellings on the subject lands. The zoning amendment application is complete pursuant to the requirements of the Planning Act and is being processed accordingly. Staff recommends that, upon completion of the consultation and review process of the zoning amendment application, a Technical Report, including recommendations, be prepared and brought forward for consideration by Council. The Technical Report will address any issues raised through the consultation and review process.
REPORT
Background Owner Main Sail Estates Inc., 800 Dufferin Street, Vaughan, ON L4K 5P5
Applicant Glenn Schnarr & Associates, 10 Kingsbridge Garden Circle, Mississauga, L5R 3K6
Location/Description The subject lands are legally described as Block 360 on Plan 20M-1184, Part of Lot 6, Concession 2, N.S. (Trafalgar). The lands are vacant and are 2.12 ha in size. The
The Corporation of the Town of Milton
Report #: PD-034-17
Page 2 of 4
property is located at the northeast corner of Britannia Road and Bronte Street South. The location of the subject lands is illustrated in Figure 1 attached to this report. Upon completion of the subdivision, site-specific medium density residential uses will be located to the east and north of the property. The subject lands consist of Major Node Area designated in the Boyne Survey Secondary Plan and are zoned a site-specific Future Development (FD*57) zone. This application seeks to rezone the subject lands to a site-specific Residential High Density (RHD*AAA) Zone and a Residential Medium Density 2 (RMD2*BBB) Zone to recognize that these lands will be developed for high density residential and grade-related medium density uses. The Draft Zoning By-law is attached to this report as Appendix 1. Proposal A four to six-storey condominium apartment building with 219 apartment dwelling units is proposed at the intersection of Britannia Road and Bronte Street South. In addition, 53 townhouse dwellings are proposed to transition to the planned medium density residential dwellings to the north and east. The townhouse dwellings include 38 two-storey townhouses and 15 lane access townhouses fronting onto Bronson Terrace. Parking for the apartment building is proposed at a rate of 1.05 space per apartment dwelling unit for tenant parking and 0.2 space per dwelling unit for visitor parking, totaling 230 tenant parking spaces and 44 visitor parking spaces. Approximately 256 spaces will be located in an underground parking garage. The townhouse dwellings are proposed to have individual garages and/or driveways, which will accommodate two vehicles each. An additional 14 visitor parking spaces are proposed within the development for the townhouse dwellings. The site development shows an integrated site with limited surface parking. The internal driveways provide access to both the proposed apartment building and the townhouse dwelling units with driveways connections to Chretien Street and Bronson Terrace. Internal walkways connect to the public sidewalks within the subdivision. The apartment building has direct pedestrian connections to Britannia Road and Bronte Street South. A central amenity space is located within the development and a series of smaller amenity spaces are created along the south and west sides of the apartment building abutting the arterial roads. The following information has been submitted in support of this application: A site plan prepared by Graziani + Corazza Architects Inc., dated June 14, 2017; Elevations and Floor Plans for the proposed apartment building; Urban Design Brief prepared by John G. Williams Architect, dated June 15,
2017;
The Corporation of the Town of Milton
Report #: PD-034-17
Page 3 of 4
A Shadow study Report prepared by Graziani + Corazza Architects Inc., dated
June 2017; Transportation Assessment prepared by GHD, dated June 15, 2017; Noise Feasibility Study prepared by Jade Acoustics, dated June 15, 2017; Draft Zoning By-law Amendment and Schedule A prepared by Glenn Schnarr &
Associates; and, Planning Summary prepared by Glenn Schnarr & Associates, dated June 15,
2017. Discussion Planning Policy The subject lands are located within the Urban Area and are designated Major Node on Schedule B – Urban Area Land Use Plan. This designation means that the permitted uses shall be predominantly high density residential uses. Notwithstanding, a limited extent of grade-related multiple-attached housing forms such as townhouses and back-to-back townhouses may be considered subject to the applicable policies. While a full review of the applicable planning policies will be undertaken as part of the review of the application, based on the information provided, staff is satisfied that an Official Plan amendment is not required. Zoning By-law 016-2014, as amended The subject lands are currently zoned a site-specific Future Development (FD*57) Zone, which does not permit the proposed development.
Site Plan Control
Should the application be approved, the applicant will require site plan approval prior to the commencement of any development. Plan of Condominium
The development, as proposed, requires condominium approval before dwelling units may be sold. The type of condominium and the limits of the private property will have to be determined in order to set appropriate site-specific zoning by-law provisions. Public Consultation and Review Process
Notice for the public meeting was provided pursuant to the requirements of the Planning Act on July 4, 2017. The application was circulated to internal and external agencies on June 28, 2017.
The Corporation of the Town of Milton
Report #: PD-034-17
Page 4 of 4
Staff have identified the following issues to be reviewed:
Urban/site design Provision of parking
A technical report with recommendations will be brought forward for Council consideration upon completion of the evaluation of the application.
Financial Impact
None arising from this report. Respectfully submitted, Barbara Koopmans, BES, MCIP, RPP, CMO Commissioner, Planning and Development
For questions, please contact: Maria Smith, MCIP, RPP Senior Planner
Phone: Ext. 2311
Attachments
Figure 1 – Location Map Figure 2 – Concept Plan Figure 3 – Rendering of Apartment Building Appendix 1 – Draft Zoning By-law
CAO Approval William Mann, MCIP, RPP, OALA, CSLA, MCIF, RPF Chief Administrative Officer
SHA
DE
LAN
E
COLVILLE PLACE
TASKER COURT
CA
RR
LA
ND
ING
ETHERIDGE AVENUE
CH
RET
IEN
STR
EET
SO
R ENSEN COURT
HEAVEN CRESCENT
DEV
INE
POIN
T
FIR
ST L
INE
MEN
DEL
SON
HEI
GH
TS
BR
ON
SON
TERRACE
BRITANNIA ROAD
BR
ON
TE S
TREE
T S
FIGURE 1LOCATION MAP
Council Meeting Date:July 24, 2017 Scale: File: Z-09/14-A Planning & Development Department
Subject Property
O
1: 3,000
Copyright 2017: Town of Milton, Teranet Inc.
PROP
ERTY
LIN
E11
6.86
0m
N37
°21'
25"E
22.15
0m
N5°03'1
0"W
16.058m N47°27'50"W
PROPERTY LINE
PROPERTY LINE
PROP
ERTY
LIN
E46
462
N
3°
1'40
"E1
.376
m
N34
°59'
30"E
72.6
41m
N
36°4
2'50
"E4.
105m
N36°
42'
0"E
58.357m N46°02'30"W
71.53m N48°35'15"W
R=5.
000
=8.
306
C=7.
383
N856
'50"
E
R=10
.000
A=0.
414
C0
13N3
°10'
40"E
R=26
.00
A=0.
78=
N3°
110
"
64.891m N47°27'50"W
62.071m N47°27'50"W
BLOC
K 33
8BL
OCK
337
BLOC
K 33
1
BLOCK 327
BLOCK 328
SERV
ICE/
LOA
DN
G
AMEN
TY A
REA
0.14
ac.
6 ST
OREY
S+
MPH
4 ST
OREY
S4
STOR
EYS
6ST
RYS
+ M
PH
4 ST
OREY
S
BRIT
ANNI
A RO
AD
CHRETIEN STREET
BRONTE STREET SOUTH
BRON
SON
TERR
ACE
CARRLANDING
UND
ERG
ROUN
DEN
TRA
NC
E
LINE
O U
/G B
EOW
LINE OF U/G BELOW
DROP
OFF
EXT
MOV
NG/
HOLD
ING
EXT
EXT
EXIT
3 ST
OREY
S(5
UN
TS)
3 ST
OREY
S(5
UN
TS)
3 ST
OREY
S(5
UN
TS)
3 ST
OREY
S(6
UN
TS)
3 ST
OREY
S(6
UN
TS)
3 TO
REYS
(5 U
NTS
)
3 ST
OREY
S(6
UN
TS)
3 ST
OREY
S(7
UN
TS)
3 ST
OREY
S(8
UN
TS)
ENTR
Y
6 ST
OREY
S+
MPH
2.2m SDEWALK
1.5m SDWALK
1.5m
SID
WAL
K1.
5m S
DW
ALK
1.5m SIDWAL
1.5m SDWALK
2.2m
SD
WAL
K
.5 ACCS AS
500
10000
700
9000
1000
0
300
400
1100
0
7000
250050
00
6500
7000
7000
7000
3750
7000
3750
375
3000
500
300
450
500
3000
3000
4500
4500
4500
60
6000
600
6000
1000
2.2m
SID
WAL
K
MAI
NEN
TRY
MAI
NE
TRY
11000
4500
3000
9000
7000
7000
3750
2507003000200
600
2000
1200
0
250
200
700
3000
4500
1000 1000
1000 1000
1000 1000
150
MID
-RSE
BUI
LDNG
TOW
NHOU
SES
RESI
DENT
PAR
KING
SPA
CES
PER
BY-L
AW 0
16-2
014
VS
TOR
PARK
ING
SPAC
ES P
ER B
Y-LA
W 0
16-2
014
1.5m ACCES ASLE
ARI
RRE
EA
RR
REE
1.5m ACCESS AISLE
TY A
TYE
ARI
RRE
EA
RIR
REE
TY A
TYE
3400
150
2750
2750
5800
3400
150
2750
2750
5800
AMEN
TY S
PACE
(OUT
DOOR
)
ANDS
CAPE
OPE
N SP
ACE
A101
SITE
PAN
+
TATI
STIC
S
A301
UNDE
RGRO
UND
PAN
GROU
ND F
LOOR
PLA
NA3
022N
D-TH
FLO
OR P
ANTH
-6TH
FLO
OR P
LAN
A401
SOTH
EL
VATI
ONW
EST
ELEV
ATON
A402
NOTH
EL
VATI
ONAS
T EL
EVAT
ONA4
03PE
RSPE
CTVE
VEW
S
LEGE
ND
KEY
PLAN
1:40
0
1:50
01:
500
1:50
01:
500
1:20
01:
200
1:20
01:
200
LIST
OF
DRAW
INGS
A
H
W
SUBJ
ECT
SITE
N.T.
S.
GENE
RAL
NOTE
S
1. F
OR
ANDS
APIN
G, R
EFER
TO
LAND
SCAP
EDR
AWIN
GS
2. F
OR P
ROPO
SED
GRAD
ING,
REF
ER T
O SE
RVCI
NGDR
AWIN
GS
3. A
LL P
ERIM
TER
XITI
NG IN
FORM
ATIO
NIN
DICA
TED
TAKE
N FR
OM S
UVE
Y
4. A
LL W
ORK
TO B
E DO
NE N
CON
FORM
ANCE
WTH
THE
2012
ONT
ARO
BULD
ING
CODE
. (O.
B.C.
, AS
AMEN
DED)
Poje
c A
chie
c
Assis
an D
esign
e
Chec
ked B
y
Daw
n By
Plo D
ae
1320
Sh
wson
Div
,Ph
on. 9
05.7
95.2
601
Job #
issu
ed fo
r rvi
sion
s
TTL
EBLO
CK S
IZ:
x 9
00
LW
1C3
www.
gc-a
rchi
tets
.com
Fx.9
05.7
95.2
844
Site
100
M
iis
saug
a O
tio
This
d
win
, a
s a
n i
ntru
me
t
f s
vic
, is
pr
ided
by
an
d i
s t
hep
ope
y
f Gr
aia
i + C
orzz
a A
rchi
tets
In
. Th
e c
otra
tor
mu
t v
ify a
ndac
pt r
spon
ibili
y f
r ll
dim
enio
ns a
nd
ondi
ions
on
ite
nd
u
t n
ifyG
aia
i + C
oraz
a Ar
chite
ts In
. f
ay
va
itio
n f
om t
he s
uplie
d i
form
tio.
Ga
iai +
Cor
aza
Arch
itets
In.
is n
t re
posi
bl f
or t
he a
ccur
ay
f
uv
y,st
rutu
rl,
mec
haic
al, e
letri
cl,
t, e
nin
eein
g i
form
tion
shwn
o th
is d
win
.R
fer
to t
he a
ppro
rite
en
inee
ing
dr
wing
s b
fore
pro
ceed
ing
with
the
wo
k.Co
ntru
ion
mu
t cfo
m to
al a
pplic
able
cod
es a
nd re
qire
me
ts
f the
ath
oiti
esh
vig
juis
diio
. Unl
es
thwi
se n
ted,
no
ive
igio
n h
s be
en u
ndrta
ken
orep
ote
d o
n b
y th
is
fice
in r
egrd
s to
the
evi
onm
et
l co
ndii
on
f th
is
it.
This
dwi
ng is
nt t
o be
sca
led.
All
rchi
tetu
al
ymbo
ls in
dic
ted
o th
is d
rwi
ng a
e
g
aphi
c re
pres
et
tions
oly
.
Cond
iio
for e
letro
ic i
fom
io tr
fer
Ele
toi
ifo
rmtio
is s
uppl
ied
to th
e th
er a
soi
ted
firm
s to
asi
t the
m in
the
xec
tion
f th
i wo
/vi
w. T
he re
iie
fim
s m
ut d
tem
ine
the
com
plte
nes
/app
opia
tene
s/re
leva
nce
f the
ifo
rmtio
n in
esp
et t
o th
ir p
ticul
ares
pon
ibili
ty.
Ga
iai +
Cor
aza
Arch
itets
In. s
hall
nt b
e re
spon
ibl
fo:
1.Er
ro o
mi
ion
inco
mpl
tene
ss d
u to
los
f i
form
tion
i w
hole
or p
rtwh
e i
fom
io i
ta
fere
d.2.
Tan
smis
io
f ay
irus
or d
amag
t th
e re
civ
ing
ele
troic
y
tem
whe
ni
fom
io i
ta
fere
d.
610
Jun.
14 20
17
PROP
OSED
RESD
ENTA
L CON
DOMI
NIUM
MAIN
SAIL
BRITA
NNIA
BR
ONTE
MILT
ONON
TARI
O
E.COR
AZZA
M.FA
USTIN
O
V.ZUB
EROV
SKI
D.BI
ASE
1466
.17
01.
JUN.
15.2
017
SSUE
D FO
R RE
ZON
NGE.
C.
SURV
EY IN
FORM
ATON
BLOC
K 36
0, O
N 20
M-1
184
PLAN
OF
SUBD
VISI
ON O
FAR
T OF
LOT
6CO
NCES
SION
2, N
EW S
UVE
Y(G
EOGR
APHI
C TO
WNS
HIP
OF T
RAAL
GAR)
TOW
N OF
MIL
TON
REGI
ONAL
MUN
ICPA
LTY
OF
HATO
N
SITE P
LAN
+ ST
ATIST
ICS
1400
A101
FIGURE 2 PD-034-17
PERS
PECT
IVE V
EWS A4
03
VIEW
LOO
KING
NOR
THW
EST
VIEW
LOO
KING
NOR
TH
Poje
c A
chie
c
Assis
an D
esign
e
Chec
ked B
y
Daw
n By
Plo D
ae
1320
Sh
wson
Div
,Ph
on. 9
05.7
95.2
601
Job #
issu
ed fo
r rvi
sion
s
TTL
EBLO
CK S
IZ:
x 9
00
LW
1C3
www.
gc-a
rchi
tets
.com
Fx.9
05.7
95.2
844
Site
100
M
iis
saug
a O
tio
This
d
win
, a
s a
n i
ntru
me
t
f s
vic
, is
pr
ided
by
an
d i
s t
hep
ope
y
f Gr
aia
i + C
orzz
a A
rchi
tets
In
. Th
e c
otra
tor
mu
t v
ify a
ndac
pt r
spon
ibili
y f
r ll
dim
enio
ns a
nd
ondi
ions
on
ite
nd
u
t n
ifyG
aia
i + C
oraz
a Ar
chite
ts In
. f
ay
va
itio
n f
om t
he s
uplie
d i
form
tio.
Ga
iai +
Cor
aza
Arch
itets
In.
is n
t re
posi
bl f
or t
he a
ccur
ay
f
uv
y,st
rutu
rl,
mec
haic
al, e
letri
cl,
t, e
nin
eein
g i
form
tion
shwn
o th
is d
win
.R
fer
to t
he a
ppro
rite
en
inee
ing
dr
wing
s b
fore
pro
ceed
ing
with
the
wo
k.Co
ntru
ion
mu
t cfo
m to
al a
pplic
able
cod
es a
nd re
qire
me
ts
f the
ath
oiti
esh
vig
juis
diio
. Unl
es
thwi
se n
ted,
no
ive
igio
n h
s be
en u
ndrta
ken
orep
ote
d o
n b
y th
is
fice
in r
egrd
s to
the
evi
onm
et
l co
ndii
on
f th
is
it.
This
dwi
ng is
nt t
o be
sca
led.
All
rchi
tetu
al
ymbo
ls in
dic
ted
o th
is d
rwi
ng a
e
g
aphi
c re
pres
et
tions
oly
.
Cond
iio
for e
letro
ic i
fom
io tr
fer
Ele
toi
ifo
rmtio
is s
uppl
ied
to th
e th
er a
soi
ted
firm
s to
asi
t the
m in
the
xec
tion
f th
i wo
/vi
w. T
he re
iie
fim
s m
ut d
tem
ine
the
com
plte
nes
/app
opia
tene
s/re
leva
nce
f the
ifo
rmtio
n in
esp
et t
o th
ir p
ticul
ares
pon
ibili
ty.
Ga
iai +
Cor
aza
Arch
itets
In. s
hall
nt b
e re
spon
ibl
fo:
1.Er
ro o
mi
ion
inco
mpl
tene
ss d
u to
los
f i
form
tion
i w
hole
or p
rtwh
e i
fom
io i
ta
fere
d.2.
Tan
smis
io
f ay
irus
or d
amag
t th
e re
civ
ing
ele
troic
y
tem
whe
ni
fom
io i
ta
fere
d.
610
Jun.
14 20
17
PROP
OSED
RESD
ENTA
L CON
DOMI
NIUM
MAIN
SAIL
BRITA
NNIA
BR
ONTE
MILT
ONON
TARI
O
E.COR
AZZA
M.FA
USTIN
O
V.ZUB
EROV
SKI
D.BI
ASE
1466
.17
01.
JUN.
15.2
017
SSUE
D FO
R RE
ZON
NGE.
C.
FIGURE 3 PD-034-17
PAGE 1 OF 4 BY-LAW XXX-17
APPENDIX 1 PD-034-17
THE CORPORATION OF THE TOWN OF MILTON
BY-LAW NO. XXX-2017
BEING A BY-LAW TO AMEND THE TOWN OF MILTON COMPREHENSIVE ZONING BY-LAW 016-2014, AS AMENDED, PURSUANT TO SECTION 34 OF THE PLANNING ACT IN RESPECT OF THE LANDS DESCRIBED AS PART OF LOT 6, CONCESSION 2 FORMER GEOGRAPHIC SURVEY OF TRAFALGAR, TOWN OF MILTON, REGIONAL MUNICIPALITY OF HALTON - MAIN SAIL ESTATES INC. (FILE Z-09/14-A) WHEREAS the Council of the Corporation of the Town of Milton deems it appropriate to amend Comprehensive Zoning By-law 016-2014, as amended; AND WHEREAS the Town of Milton Official Plan provides for the lands affected by this by-law to be zoned as set forth in this by-law; NOW THEREFORE the Council of the Corporation of the Town of Milton hereby enacts as follows: 1.0 THAT Schedule A to Comprehensive Zoning By-law 016-2014, as amended,
is hereby further amended by changing the existing Future Development – Exception 57 (FD*57) zone symbol to Residential High Density – Site Specific (RHD*AAA) and Residential Medium Density II – Site Specific (RMDII*BBB) zone symbols on the land shown on Schedule A attached hereto.
2.0 THAT Section 13.1 is amended by adding Section 13.1.1.X to read as follows: Residential High Density – Special AAA (RHD*AAA) Zone:
i) Notwithstanding the Zone Regulations of Section 6.2, Table 6E to the
contrary, the following Zone Regulations shall also apply for Apartment Building:
a) Minimum Front Yard Setback (Britannia Road) = 4.5 m
b) Minimum Interior Side Yard Setback (to parking)= 3.0 m c) Minimum Exterior Side Yard Setback (Chretien) = 3.0 m d) Minimum Rear Yard (Bronson Terrace) = 2.0 m e) Minimum landscaped open space = 30%
ii) Special Zone Standards:
PAGE 2 OF 4 BY-LAW XXX-17
a) Notwithstanding Section 5.14.1 (Parking Structures 1.6 m or less in height), parking structure below grade shall may encroach into a required yard and may be 0.0 metres to a street line or lot line, and may encroach within a landscaped buffer.
b) Notwithstanding Section 14.9.5, Table 4H, stairs and air vents associated with an underground parking structure shall be permitted in any yard.
c) Notwithstanding Section 5.8.1, Table 5E, the parking requirement
for an apartment building shall be a minimum of 1.05 parking spaces per unit PLUS 0.20 visitor parking spaces per unit.
d) Notwithstanding Section 5.9, Table 5H (Accessible Parking), the
minimum number of accessible parking spaces shall be 8 spaces (6 below grade and 2 above grade).
e) A minimum of 4 square metres per dwelling unit of outdoor communal amenity space shall be provided at grade and shall be maintained and operated by a common entity.
f) Notwithstanding Section 4.19.5, Table 4H (Encroachments into
Required Yards), balconies and porches may project a maximum of 2.0 m into any required yard.
g) The maximum length of a main wall of a building shall not exceed
60 metres.
Residential Medium Density 2 – Special Section BBB (RMD2*BBB) Zone:
i) Notwithstanding the Zone Regulations of Section 6.2, Table 6D to the contrary, the following Zone Regulations shall apply for Rear Lane Townhouse Dwellings – Private Street Access:
a) Minimum lot frontage, street access, interior unit = 5.5 m b) Minimum lot frontage, street access, corner/end unit = 5.6 m c) Minimum Lot Depth = 23.0 m d) Minimum Rear Yard Setback (to attached garage) = 3.0 m
ii) Notwithstanding the Zone Regulations of Section 6.2, Table 6D to the
contrary, the following Zone Regulations shall apply for Townhouse Dwellings - Private Street Access:
a) Minimum lot frontage, street access, interior unit = 5.5 m b) Minimum lot frontage, street access, corner/end unit = 5.6 m c) Minimum Interior Side Yard Setback (End Unit) = 1.0 m
PAGE 3 OF 4 BY-LAW XXX-17
d) Minimum Exterior Side Yard Setback = 1.5 m
iv) Additional Zone Regulations for Townhouse Dwellings – Private Street Access:
a) Notwithstanding Section 5.12, Table 5L to the contrary, a
common surface parking area may be setback 2.0 m from a lot line.
3.0 THAT If no appeal is filed pursuant to Section 34(19) of the Planning Act, R.S.O. 1990, c. P.13, as amended, or if an appeal is filed and the Ontario Municipal Board dismisses the appeal, this by-law shall come into force on the day of its passing. If the Ontario Municipal Board amends the by-law pursuant to Section 34 (26) of the Planning Act, as amended, the part or parts so amended come into force upon the day the Board’s Order is issued directing the amendment or amendments.
PASSED IN OPEN COUNCIL ON ……………………………2017.
_______________________________Mayor G.A. Krantz
__________________________ Town Clerk T. McHarg
FIR
ST L
INE
BRITANNIA ROAD
TASKER COURT
MEN
DEL
SON
HEI
GH
TS
CA
RR
LA
ND
ING
BR
ON
TEST
REE
TS
BRONSON TERRACE
SOR
ENSE
N C
OU
RT
HEAVEN CRESCENT
Town of Milton
OSCHEDULE A
TO BY-LAW No. -2017TOWN OF MILTON
Z-09/14-A
RHD*____- Residential High Density Zone Special
RHD*___
MAYOR - Gordon A. Krantz
CLERK - Troy McHarg
THIS IS SCHEDULE ATO BY-LAW NO. -2017 PASSEDTHIS ___ DAY OF ________, 2017.
PART OF LOT 6 CONCESSION 2 NS
RMD2*____- Residential Medium Density 2 Zone Special
RMD2*___