2016/SOM1/EC/WKSP2/013 Session 4.3
Dealing with Permits in Hong Kong, China
Submitted by: Hong Kong, China
Ease of Doing Business Workshop: One-Stop Shops to Improve the Business Environment
Lima, Peru 26-27 February 2016
1
One-Stop Shops
Dealing with Permitsin Hong Kong
Mr. Michael HP LI MSc(Fire and Safety Engineering), MRICS, MHKIS
Chief Building Surveyor, Buildings Department Hong Kong, China
Background of One Stop Centre
2
2
“Be the Smart Regulator” Programme
• Launched by Hong Kong, China in February 2007
• To enhance Hong Kong’s business licensing processes and businessenvironment.
• Jointly coordinated by:– the Efficiency Unit under the Chief Secretary’s Office; and– the Business Facilitation Division of the Economic Analysis and Business
Facilitation Unit (EABFU) under the Financial Secretary’s Office
• 30 bureaux and departments joined the Programme– take forward improvement measures to streamline licensing processes– reduce compliance costs to business.– improve the “Customer friendliness”, “Efficiency” and “Transparency” of the
their business licensing services. 3
Working Group for Re-engineering and Streamlining Dealing with Construction Permits
• Established in 2007
• Comprises EABFU, Development Bureau & 6 departments:– Buildings Department– Lands Department– Fire Services Department– Drainage Services Department– Highways Department– Water Supplies Department
• Improvements achieved mainly through– streamlining workflow– eliminating unnecessary procedures– improvement in processing efficiency
• In 2008, HK’s ranking for the indicator of ‘Dealing withConstruction Permits’ was up from 60th in the preceding year to20th
2008
Rank: 20th
Procedures: 15
Time: 119 days
Cost: 18.7%
2007
Rank: 60th
Procedures: 23
Time: 155 days
Cost: 21.3%
4
3
One Stop Centre
5
One Stop Centre (OSC)
• Set up in 2008
• Administered by the Efficiency Unit
• to provide a centralized office for receiving first submissions of plans and related applications as well as coordinating joint inspections for two-storeywarehouses
• From 2009-2014, HK’s ranking for the indicator of ‘Dealing with Construction Permits’ was up to the top among all examined economies
• In 2015, HK’s ranking was 7th
2009
Rank: 1st
Procedures: 7
Time: 67 days
Cost: 18.7%
2008
Rank: 20th
Procedures: 15
Time: 119 days
Cost: 18.7%
6
4
Dealing with Permits by OSC
Pre-construction stage
• OSC receives applications for:
– approval of plans, consent for commencement of works
– excavation permit
– technical audit for water supply connection works andissue of water supply certificate
• Refer to relevant departments for process under streamlinedprocedures
• OSC to monitor progress of each application7
Dealing with Permits by OSC
Post-construction stage
• Upon completion of construction work, all relevantapplications/notifications for issuance of approvals andpermits together with applications for utility services to besubmitted to OSC in one go
• OSC refers the applications to relevant parties for processing
• A joint inspection by all departments organized by OSC onrequest of applicant
8
5
Recent Reforms of OSC
1. Highways Department• Excavation Permit Management System (XPMS) launched for
processing Excavation Permits through internet.• Processing time for excavation permit reduced from 20 days to 5
days.
2. Fire Services Department• Further streamlined the process of handling applications for
certificates of fire service installations.• Processing time further shortened from 19 days to 17 days.
9
3. Lands Department• Streamlined the related procedures.• Time for issuing certificates of compliance for two-storey
warehouses reduced from 21 days to 19 days.
4. Water Supplies Department • Application process of water supply applications streamlined• Water supply could be made available on the same day of the
joint and final inspection.
… Recent Reforms
10
6
5. Application / Notification for Utilities
• Government and some utility service providers collaborated tolaunch a Composite Form.
• Applicant can submit applications for electricity andtelecommunication services and notification to Water SuppliesDepartment for completion of plumbing works in one go via thecomposite form to OSC.
6. Buildings Department• Buildings Department dealing with construction permits for
private developments, has undertaken various reforms in recentyears to streamline the vetting procedures and hence reduce thetotal processing time.
… Recent Reforms
11
Dealing with Construction Permits
12
7
Buildings Department Vision
• To make the built environment safe and healthy for our community
Mission
• To set and enforce safety, health and environmental standards for the planning, design and construction of private buildings
13
Building Control• Authorized Persons (Architects, Surveyors, Engineers),
Structural Engineers and Geotechnical Engineers registered under the Buildings Ordinance coordinate, design and supervise the building works
• Registered contractors carry out the building works
• Prior approval and consent obtained from BD before commencement of building works
• No new building shall be occupied before an occupation permit is issued
14
8
Construction Permits in 2015
Around 19,000* nos. of plan submissions processed
Around 10,000* nos. of consent for commencement of works granted
*including all types of plan submissions, alteration and addition works re-submissions, and amendment submissions
15
Centralized PlanProcessing
16
9
Centralized Plan Processing
• Implemented since 1976
• One stop shop service to facilitate AP to obtain comments from all relevant government departments
• To collate the comments from the parties concerned within statutory time limits
17
Centralized Plan Processing
Fire Services Dept.
Lands Dept.
Drainage Services Dept.
Planning Dept. Highways Dept.
Geotechnical Engineering Office
Transport Dept.
Environmental Protection Dept.
Others depts or agencies as necessary
18
10
Other Examples of Centralized Processing
Fire Services Department Buildings Department
Restaurant License
Applications
Food, Environment and Hygiene Department
19
Curtailed Check System
20
11
Plan Checking by BD
• Check fundamental issues only
• Audit checking
AP/RSE/RGE’s Certification
• AP/RSE/RGE to certify compliance with the provisions of the Buildings Ordinance
21
Statutory Periods
60 daysApproval for first submissions and resubmissions constituting a major
revision
30 days Approval for resubmissions and amendments prior to consent
28 days Consent to commence works
14 days Occupation Permit
Approval deemed to be given unlessrefusal notified by BD to AP within thestatutory periods
22
12
Streamlined Procedures
• Concurrent processing for approval of plan and consent (30/60 days) 45 days for two-storey warehouses
meeting certain criteria (since 2008)
• Fast track applications (30 Days)
• Priority status for special projects
23
Site Auditing for Building Works
24
13
Site Auditing
• Purpose
• To bring to light structural safety-related and quality-related irregularities or procedures and practices
• Strategy
• Focus on compliance with the requirements of the Buildings Ordinance and regulations
• Surprise checks
• Performance-based approach to frequency of checks
25
Reforms Implemented by BD
26
14
Building Control for Two-storey Warehouses
Reforms implemented in Feb 2016
• Scheduled inspections
• Conduct Inspection of foundation bearing stratum within 1 working day upon receipt of notification
• Combined inspections - quality inspection to structural elements has been combined with the comprehensive inspection at superstructure construction stage
• Total no. of scheduled inspections reduced from 3 to 2
• Unscheduled inspections
• No further unscheduled audit subject to satisfactory results of initial auditing for foundation and/or superstructure works
• Total no. of unscheduled inspections reduced from 2 to 127
Dialogues with Stakeholders
• Regular discussion forums with stakeholders
• Pre-submission enquiries
• Practice Notes for AP, RSE & RGE
• Circular letters on new issues or practices
• Working Groups with stakeholders to review practices from time to time, e.g. a benchmarking exercise on the quality of plan submission to facilitate approval
28
15