3
DCP130 update 4 October 2012 1 | Energy Networks Association – DCMF Dave Wornell (DCP130 Chair)

DCP130 update

Embed Size (px)

DESCRIPTION

DCP130 update. Dave Wornell (DCP130 Chair). 4 October 2012. 1 | Energy Networks Association – DCMF. Current position – DCP130. 4 October 2012. 2 | Energy Networks Association – DCMF. New CDCM model has been created - PowerPoint PPT Presentation

Citation preview

Page 1: DCP130 update

DCP130 update

4 October 20121 | Energy Networks Association – DCMF

Dave Wornell

(DCP130 Chair)

Page 2: DCP130 update

Current position – DCP130

4 October 20122 | Energy Networks Association – DCMF

• New CDCM model has been created– Changing the method of calculating UMS charges so that the calculation is based on seasonal time of day time

bands– Increasing the number of tariffs for NHH UMS to match the categories of NHH UMS detailed in BSCP520:– A = Continuous– B = Dusk to Dawn– C = Half-night and Pre-dawn– D = Dawn to Dusk– Changing the application of charges for HH UMS to seasonal time of day.

– To remove the discrepancy in Use of System charges between HH UMS & NHH UMS.

• Analysing responses to consultation

• Drafting change report

Page 3: DCP130 update

Next steps

4 October 20123 | Energy Networks Association – DCMF

DCP 130 Timetable

Meeting 03: Review consultation responses and draft change report

02-Oct-12

Finalise change report Between 26 Sept and 9 Oct

Change Report to Panel Paper day No later than 9 Oct

Change Report issued for voting 18 October 2012 (day after Oct Panel)

Voting closes 02-Nov-12

Change Declaration 05-Nov-12

Authority Consent 05-Dec-12

CP Implemented 01-Apr-13