DC Water Northeast Boundary Tunnel - For General Release 2016 06

Embed Size (px)

Citation preview

  • 7/26/2019 DC Water Northeast Boundary Tunnel - For General Release 2016 06

    1/15

    1

    DC CLEAN RIVERS PROJECT

    Northeast Boundary Tunnel

    a

    nd

    WMATA Coordination

    Florida Avenue Site

    District of Columbia Water and Sewer AuthorityGeorge S. Hawkins, General Manager

  • 7/26/2019 DC Water Northeast Boundary Tunnel - For General Release 2016 06

    2/15

    2

    Long Term Control Plan (LTCP) to: Relieve flooding in the Northeast

    Boundary Area

    Control combined sewer overflows to: Potomac River

    Anacostia River

    Rock Creek

    Meet nutrient discharge limits ofChesapeake Bay Program

    Schedule: 2005-2023

    Implemented under a Federal Consent

    Decree among: United States Environmental Protection

    Agency (US EPA) United States Department of Justice (US

    DOJ)

    District of Columbia

    DC Water

    2

    Background

    Project Snapshot

    2

    Nannie MiningLocation

  • 7/26/2019 DC Water Northeast Boundary Tunnel - For General Release 2016 06

    3/15

    3

    Summer 2012 Storm Events: Surface Flooding

    Rhode Island Metro

    1st St NW

    Flagler St NW

    Rhode Island & T St NW

    Rhode Island Between 1st & 2nd St

    Rhode Island & T St NW

    Rhode Island & 1st St NW

    3

    1st & V St NW

    Photo courtesy of: Greg Roberts

    Photo courtesy ofhuffintonpost.com

    Photo courtesy of myfox.com

    Photo courtesy of myfox.com

    3

    Photo source unknown

    Photo source unknown

    Photo source unknown

    Photo source unknown

    Photo source unknown

  • 7/26/2019 DC Water Northeast Boundary Tunnel - For General Release 2016 06

    4/15

    4

    Mayors Task Force

    Overview

    4 storms caused major

    flooding: July 10, 18, 19

    and Sept 2, 2012

    Mayor formed Task

    Force in Aug 2012

    Task Force reportdelivered end of Dec

    2012

    Over 25 Recommendations:

    Engineering Measures McMillan Stormwater Storage

    First Street Tunnel

    Northeast Boundary Tunnel

    (NEBT)

    Regulatory Code ChangesOperations &

    MaintenancePublic

    Outreach

    4

  • 7/26/2019 DC Water Northeast Boundary Tunnel - For General Release 2016 06

    5/15

    5

    Mayors Task Force

    Recommended Plan

    5

    NORTHEAST BOUNDARY TUNNEL PROJECT A large, deep sewer tunnel that will increase the capacity of

    the sewer system to current design standards and control

    combined sewer overflow discharges to the Anacostia River Completion in 2023

    MCMILLAN STORMWATER STORAGE PROJECT Repurpose McMillan Sand Filtration cells as stormwater

    storage In-line storage in a sewer that runs along First Street NW 3.6 million gallons, Completed

    IRVING STREET GREEN INFRASTRUCTURE PROJECT Construction of bioretention facilities along Irving Street NW

    0.4 million gallons, Completed

    2. MEDIUM-TERM

    FIRST STREET TUNNEL PROJECT

    Construction of a new tunnel under First Street NW Construction of diversion facilities to divert flows to tunnel 8 million gallons, Summer 2016

    3. LONG-TERM

    Construction of green infrastructure projects Installation of storm drains and a five-foot-wide storm sewer Backwater valve and rain barrel program

    1. SHORT-TERM (NOT ILLUSTRATED)

    9

  • 7/26/2019 DC Water Northeast Boundary Tunnel - For General Release 2016 06

    6/15

    6

    Significantly mitigate the frequency, magnitudeand duration of sewer flooding and basement

    backups in the Northeast Boundary drainage

    area

    Control combined sewer overflow (CSO)

    discharges to the Anacostia River, significantly

    improving water quality

    Minimize the nuisance and economic costs

    associated with flooding

    Reduce risks to human health

    Greatly reduce the discharge of untreated

    wastewater into the Districts receiving

    waterbodies

    Prevent deterioration of historic resources fromwater damage caused by flooding

    Mayors Task Force

    Benefits

    CSO Reduction Project Timeline

    CSO Overflow Volume

    to Anacostia River

    (mg/yr)

    % Reduction from

    Baseline

    1996: Baseline: Without Inflatable Dams or Pumping Station Rehab 2,142

    2008: After Inflatable Dams and Pumping Station Rehab 1,282 40%

    2018: Blue Plains and Anacostia River Tunnels 407 81%

    2023: Northeast Boundary Tunnel* 54 98%

    CSO Reduction

    * 2025 Consent Decree Deadline; Project accelerated due to Mayors Task Force recommendations.6

    Flood Relief

    SIG

    NIFICANT

    CSOREDUCTION

    Capacity provided by Long-TermImprovements (NEBT)

    Approx. capacity ofexisting system

    Capacity provided by Medium-Term Improvements

  • 7/26/2019 DC Water Northeast Boundary Tunnel - For General Release 2016 06

    7/157

    Northeast Boundary Tunnel

    What is a Diversion Facility?

    7

  • 7/26/2019 DC Water Northeast Boundary Tunnel - For General Release 2016 06

    8/158

    Northeast Boundary Tunnel

    Alignment and Chronic Flood Areas

    8

  • 7/26/2019 DC Water Northeast Boundary Tunnel - For General Release 2016 06

    9/159

    Northeast Boundary Tunnel

    Phases of Work

    9

    In order to accomplish the Mayors Task Force goals, construction work has beendivided into two distinct phases

    Phase Description Start Finish

    A Relocation of utilities (gas, electric, communication, water,

    sewer, etc.) that conflict with permanent diversion facility

    structures Typical linear trench-type utility work

    Borings

    Moving work areas

    Short durations

    May 2016 September 2017

    B Construction of NEBT and diversion facilities along tunnel

    alignment

    Stationary work areas Long durations

    September 2017 May 2023

  • 7/26/2019 DC Water Northeast Boundary Tunnel - For General Release 2016 06

    10/151010

    Northeast Boundary TunnelUtility Relocations

    Anticipated Start of Construct ion

    Washington Gas June 2016

    Pepco June 2016

    DC Water Contractor April 2017

    BORING

    LOCATION

    BORING

    LOCATION

    EXISTING G2

    BUS STOP

    EXISTING G2

    BUS STOP

  • 7/26/2019 DC Water Northeast Boundary Tunnel - For General Release 2016 06

    11/15

    1111

    Northeast Boundary TunnelFlorida Avenue Construction Site

    EXISTING G2

    BUS STOP

    EXISTING G2

    BUS STOP

    Anticipated Star t of Construction

    DC Water Contractor Sept. 2017

  • 7/26/2019 DC Water Northeast Boundary Tunnel - For General Release 2016 06

    12/15

    12

    Why is the G2 Detour Required?

    12

    Sidewalk and lane closures along the G2 route are required to complete the work

    Currently, WMATA using same 40-ft buses from existing route. Forcing less direct

    routing

    40-ft buses will be replaced with 30-ft buses at next opportunity for garage

    switchover (June 26), allowing more direct routing WMATA will increase rush hour frequency of buses to maintain capacity

    Bus detour will remain through construction (2023) and will be reevaluated at that

    time

  • 7/26/2019 DC Water Northeast Boundary Tunnel - For General Release 2016 06

    13/15

    1313

    WMATA G2 Detour Phase 1

    FLORIDA AVENUE

    CONSTRUCTION SITE

  • 7/26/2019 DC Water Northeast Boundary Tunnel - For General Release 2016 06

    14/15

    1414

    WMATA G2 Detour Phase 2

    FLORIDA AVENUE

    CONSTRUCTION SITE

  • 7/26/2019 DC Water Northeast Boundary Tunnel - For General Release 2016 06

    15/15

    15

    JUNE

    JULY

    AUG

    SEPT

    OCT

    NOV

    DEC

    JAN

    FEB

    MAR

    APRIL

    MAY

    JUNE

    JULY

    AUG

    SEPT

    OCT

    NOV

    DEC

    JAN

    FEB

    MAR

    APRIL

    MAY

    JUNE

    JULY

    AUG

    SEPT

    OCT

    NOV

    DEC

    JAN

    FEB

    MAR

    APRIL

    MAY

    JUNE

    JULY

    AUG

    SEPT

    OCT

    NOV

    DEC

    Washington Gas

    Pepco

    DC Water Borings

    DC Water Utili ty Contractor

    DC Water NEBT Contractor

    20232016 2017 2018

    Next Steps

    15

    Continue public outreach throughout the project area

    Relocate utilities in advance of construction: June 2016

    NEBT Construction: September 2017 May 2023