1
June 15, 2010DBIA
2
Dulles Corridor Metrorail ProjectAt-a-Glance
• Seamless integration with current 106-mile Metro system
• Branches off Orange Line after East Falls Church Station
• 11 new stations• 5 in Phase 1 • 6 in Phase 2
• Phase 1: East Falls Church to Wiehle Avenue in Reston; opens in 2013
• Phase 2: Wiehle Avenue through Dulles International Airport to Ashburn; opening planned for 2017
3
Route Map
A Closer Look at Tysons Corner Stations
4
5
Tysons Central 123
Future of Tysons Corner Center Site
6
Tysons 123 Station
Wiehle Avenue
7
Phase 1 Schedule
Final Design: 2008 - 2010
Utility Work Continues: 2008 – 2010
Construction Period: 2009 - 2013
Passenger Service Begins: December 2013
8
9
Phase 2
• Preliminary Engineering now underway
• Opening planned in 2017
• Six Stations: 11.5-mile alignment• Reston Parkway• Herndon Monroe• Route 28• Dulles Airport• Route 606• Ashburn/Ryan Road
• All Phase 2 stations, except for Dulles Airport, will follow the Wiehle Avenue station prototype
• All Phase 2 stations, except for Dulles Airport, will be in the median of the Dulles Airport Access Road & the Dulles Greenway
10
Construction Marching ForwardPhase 1 from I-66 to Reston
• Construction of the Dulles Corridor Metrorail Project is under way along the 11.7-mile corridor, from East Falls Church to Reston.
• All 5 Phase 1 stations will be under construction by the end of 2010.
Dulles Connector Road & I-66 Interchange
Dulles Connector Road
Dulles Connector Road Truss
Dulles Connector Road Truss
Dulles Connector Road
Tysons East Station Construction
Route 123 Construction
Phase 1 Construction Headquarters
Tunnel Excavation
Outbound Tunnel Excavation
Tunnel to Route 7
Route 7
Wiehle Avenue Station Construction
Wiehle Avenue Station Construction
Wiehle Avenue Station Construction
Precast Yard at Dulles International Airport
27
Contact Information
1593 Spring Hill Road Suite 300
Vienna, VA 22182
703-572-0500
www.dullesmetro.com