Definitions
Metric Abbrev. Description Formula/Value
Budget Cost - Completion BAC Baseline cost for 100% of project.
Actual Cost AC Total costs actually incurred so far.
Expense as per Budget BE
Amount of budget earned so far based on physical
work accomplished, without reference to actual costs.
Planned Value PV
The budget for the physical work scheduled to be
completed by the end of the time period.
Budget Variance BV
Measure of cost overrun. The difference between the
budget for the work actually done so far and the
actual costs so far.
Expense as per
Budget–Actual Cost
BE–AC
Cost Performance Index CPI
Cost efficiency ratio. A CPI of 1.0 means that the
costs so far are exactly the same as the budget for
work actually done so far.
Expense as per
Budget/Actual Cost
BE/AC
Schedule Variance SV
Measure of schedule slippage. The difference
between the budget for the work actually done so far
and the budgeted cost of work scheduled.
Expense as per
Budget–Planned Value
BE–PV
Schedule Performance Index SPI
The schedule efficiency ratio. An SPI of 1.0 means
that the project is exactly on schedule.
Expense as per
Budget/Planned Value
BE/PV
Estimate to Completion ETC The expected additional cost to complete the project.
Estimate at
Completion–Actual Cost
EAC–AC
Projected Cost at Completion PAC
Expected total cost based on the current cost
efficiency ratio.
Budget at Completion/Cost
Performance Index
BAC/CPI
Status Average of CPI & SPI
(Cost Performance
Index+Schedule
Performance Index)/2
(CPI+SPI)/2
GREEN = On track >1.0
YELLOW = Slightly behind schedule or over budget >0.85
RED = Needs immediate attention >0.65
BLACK = Killed or Restore <0.65
Definitions
Page 1 of 3
Executive
Summary
Document No.: EXES/Site Code/Meeting No.
Contr. Award Date Completion Date:
Time Elapsed Planned Progress- % Contract Duration
Delay in Days Actual Progress-% Projected Completion
Previous Rep. Delay Curr. Report Delay
Plan No of Dwg Actual No of Dwg Cum. % Planned Actual % Achieved Variance (Days) Status (G/Y/R)
Civil Works 0
MEP Works 0
Finishing 0
Façade Works 0 Elevator Works 0
Prev. Report Delay Current Rep. Delay
Planned Award Actual Award Cum. % Planned Actual % Achieved Variance (Days) Status (G/Y/R)
Civil Works
MEP Works
Finishing
Façade WorksElevator Works
Prev. Report Delay Current Rep. Delay
Planned Finish Actual Finish Cum. % Planned Actual % Achieved Variance (Days) Status (G/Y/R)
Civil Works
MEP Works
Finishing
Façade WorksElevator Works
Quality Status
Planned Actual
Civil Works Safety Status
MEP Works
Finishing Works
Façade Works
Elevator Works
Currently Open Open Last Week Incr / Decrease Closed Past Due
0
Changes Due to Requested Approved Deferred RejectedUnder
Investigation
0 0 0 0 0
Cost Effort (hours) Schedule (days)
Contingency Reserve
Last Reviewed
Overall Risk (G,Y,R)
Issue 1:
Cost of Works Prev. Report
Work Tracking
Top 3 Risks
Top 3 Issues
Risk 1:
Risks
Scope Changes
Changes Due to Approved Scope Changes (Estimate)
Comments
Issue 2:
Issue 3:
Average Labor
Project Name
Estimate to Completion (ETC)
Schedule Variance (SV)
Cost Performance Index (CPI)
Schedule Performance Index (SPI)
Projected Cost at Completion (PAC)
Project In Charge: ABC
Project Timeline
Budget Tracking
Budget Cost -Completion (BCC)
Expense as per Budget (BE)
Actual Cost to Date (AC)
Budget Varience (BV)
Planned Value (PV)
Risk 2:
Risk 3:
Design
Cost of Mitigations
Delay Efforts/day: hrs
Risks Identified
Mitigation Plans Developed
Contingency Plans Developed
Construction Requirements
Total changes
Delay Cost / Day: INR
Activity
Planned Activities (Total)
Procurement
Status (Average of CPI + SPI)
Issues
Number of issues
Statutory Requirements
Design Requirements
Resource
Cost of Works Curr. Report
Construction
Completed Activities till date
Active activities
Delayed Activities
Critical Activities
Sr. No. Description Project DepartmentPerson
Responsible
Initiation
Date
1 Finalization of carpark option Exquisite Architectural
2 Main Gate GFC package Exquisite Architectural
3 Podium Elevation section for façade Exquisite Architectural
4 CFO-NOC Ammendment Exquisite Liasoning
5 Permanent power supply to Exquisite Exquisite Liasoning
6 HE & Site storm water drain approval Exquisite Liasoning
7 External Painting Exquisite Construction
8 Duplex and PH façade works Exquisite Construction
9 Issue of Mivan Package Esquire Architectural
10 CC for above plinth work Esquire Liasoning
11 Entrance gate design Commerz-II & III Architectural
12 Entrance lobby finishes Commerz-II & III Architectural
13 Typical floor toilet details Commerz-II & III Architectural
14 Lighting fixtures details Commerz-II & III Architectural
15 Entrance canopy contract Commerz-II & III Contracts
16 Façade pandels issue -dispute Commerz-II & III Contracts
17 CC for above B2 level - connecting podium and North tower Commerz-II & III Liasoning
18 Details for retrofit and revised core Prisma Architectural
19 GFC for towerportion Prisma Architectural
20 BMC car park handing over Prisma Liasoning
21 CC for typical floor Prisma Liasoning
22 Interior design package for lobbies and apts Khar Architectural
23 Apointment of façade and lift contractor Khar Contracts
24 Slow progress by QHPL Khar Construction
Critical Issues
MIS - CONSTRUCTION
Exquisite Esquire Khar Prisma Oasis, WorliCommerz-II
& III
% Planned 89% 72% 45% 100% 24% 100%
% Completed 83% 7% 31% 30% 19% 89%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Construction Status
Exquisite Esquire Khar Prisma Oasis, WorliCommerz-II &
III
Planned 1-Dec-13 31-Aug-14 30-Oct-12 1-Jan-10 31-Dec-15 22-Aug-13
Antiipated 31-Mar-14 13-Mar-16 30-Aug-14 29-Apr-16 30-Apr-16 24-Jan-14
Project Completion Timeline