Daily Program Nov-2011

Embed Size (px)

Citation preview

  • 8/13/2019 Daily Program Nov-2011

    1/19

    S.l. No. Description Work Program of 1st Nov. 2011 Achievement of 31th Oct.2011 Remarks

    Drainage pipe installation Drainage pipe installation in progress

    CC casting of pipe fixing CC casting of pipe fixing in progress

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for Surcharge material placement Sand bagging in progress

    PVD Driving PVD Driving in progress

    Wall casting 2nd lift CH 800-840/Country side Rebar fabrication & shuttering executed

    Rod binding 2nd lift CH 840-860/Country side Rebar fabrication in progress

    Sub base work (CH 240-340) Sub base work (CH 240-340) in progress

    Improved sub grade work (180-240) Improved sub grade work (180-240) in progress

    6 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress

    7 Sheet Pile Concrete Pouring Concrete Pouring in progress

    8 RCC Drainage Pipe Concrete Pouring of Pipe Concrete Pouring of Pipe in progress

    9 Electric Substation Concrete Pouring of Colun & Grade beamConcrete Pouring of Column & Grade beam in

    progress

    10 Wasa Relocation Connection work of relocated line Connection work of relocated line in progress

    11 Electric Relocation Connection of relocated line in processCircuit (33/33/11/0.44 KV ) overhead cable fixing

    complete

    12 Laboratory

    13 Interlocking Block ILB production (2 Plant) ILB production in progress

    14 Dismantling work CC/RCC Dismantling work at Segment 2 & 3 CC/RCC Dismantling work at Segment 2 & 3 inprogress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    3

    Road Work5

    Segment 1A1

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,1st Nov, 2011

    Open deep drain4

    Segment 1

  • 8/13/2019 Daily Program Nov-2011

    2/19

    S.l. No. Description Work Program of 2nd Nov. 2011 Achievement of 1st Nov.2011 Remarks

    Drainage pipe installation Drainage pipe installation in progress

    CC casting of pipe fixing CC casting of pipe fixing in progress

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for Surcharge material placement Sand bagging in progress

    Surcharge material placement Surcharge material placement in progress

    Pre-cast Bracing installation

    Concrete pouring of 3rd lift CH 840-860/Country

    sideRebar fabrication & shuttering executed

    Sub base work (CH 240-340) Sub base work (CH 240-340) in progress

    Improved sub grade work (180-240) Improved sub grade work (180-240) in progress

    6 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress

    7 Sheet Pile Concrete Pouring Concrete Pouring in progress

    8 RCC Drainage Pipe Concrete Pouring of Pipe Concrete Pouring of Pipe in progress

    9 Electric Substation Concrete Pouring of Column & Grade beamConcrete Pouring of Column & Grade beam in

    progress

    10 Wasa Relocation Finshing task for connection Finshing task for connection in progress

    11 Electric Relocation Connection of relocated line in processCircuit (33/33/11/0.44 KV ) overhead cable fixing

    complete

    12 Laboratory

    13 Interlocking Block ILB production (2 Plant) ILB production in progress

    14 Dismantling work CC/RCC Dismantling work at Segment 2 & 3CC/RCC Dismantling work at Segment 2 & 3 in

    progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    1

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,2nd Nov, 2011

    Open deep drain4

    Segment 13

    Road Work5

    Segment 1A

  • 8/13/2019 Daily Program Nov-2011

    3/19

    S.l. No. Description Work Program of 3rd Nov. 2011 Achievement of 2nd Nov.2011 Remarks

    1 Segment 1A Drainage pipe installation Drainage pipe installation in progress

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for Surcharge material placement Sand bagging in progress

    Surcharge material placement Surcharge material placement in progress

    Pre-cast Bracing installation

    Concrete pouring of 3rd lif t CH 840-860/Country

    side

    Rebar fabrication & shuttering executed

    Sub base work (CH 240-340) Sub base work (CH 240-340) in progress

    Improved sub grade work (180-240) Improved sub grade work (180-240) in progress

    6 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress

    7 Sheet Pile Concrete Pouring Concrete Pouring in progress

    8 RCC Drainage Pipe Concrete Pouring of Pipe Concrete Pouring of Pipe in progress

    9 Electric Substation Concrete Pouring of Column & Grade beamConcrete Pouring of Column & Grade beam in

    progress

    10 Wasa Relocation Finshing task for connection Finshing task for connection in progress

    11 Electric Relocation Connection of relocated line in processCircuit (33/33/11/0.44 KV ) overhead cable fixing

    complete

    12 Laboratory

    13 Interlocking Block ILB production (2 Plant) ILB production in progress

    14 Dismantling work CC/RCC Dismantling work at Segment 2 & 3CC/RCC Dismantling work at Segment 2 & 3 in

    progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    5

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,3rd Nov, 2011

    Open deep drain4

    Segment 13

    Road Work

  • 8/13/2019 Daily Program Nov-2011

    4/19

    S.l. No. Description Work Program of 14th Nov. 2011 Achievement of 13th Nov Nov.2011 Remarks

    1 Segment 1A Drainage pipe installation

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for preloading work Sand bagging for preloading work in progress

    Surcharge material placement Surcharge material placement in progress

    4 Segment-2 PVD Driving PVD Driving in progress

    Sub base work (CH 240-340) Sub base work (CH 240-340) in progress

    Improved sub grade work (180-240) Improved sub grade work (180-240) in progress

    6 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress

    7 Electric Substation Concrete Pouring of Column Concrete Pouring of Column in progress

    8 Wasa Relocation Newly installed line is functioning

    Old line dismantling

    9 Laboratory / Field Test

    Field density test at segment-2 (150 mm local sand

    layer)

    10 Interlocking Block ILB production ILB production in progress

    11 Dismantling work Mosque dismantling Mosque dismantling work in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    5

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,14th Nov, 2011

    Segment 13

    Road Work

  • 8/13/2019 Daily Program Nov-2011

    5/19

    S.l. No. Description Work Program of 15th Nov. 2011 Achievement of 14th Nov Nov.2011 Remarks

    1 Segment 1A Drainage pipe installation

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for preloading work Sand bagging for preloading work in progress

    Surcharge material placement Surcharge material placement in progress

    4 Segment-2 PVD Driving PVD Driving in progress

    Sand Blanket filling Sand Blanket filling in progress

    Sub base work (CH 240-340) Sub base work (CH 240-340) in progress

    Improved sub grade work (180-240) Improved sub grade work (180-240) in progress

    6 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress

    7 Electric Substation Concrete Pouring of Column Concrete Pouring of Column in progress

    8 Wasa Relocation Newly installed line is functioning

    Old line dismantling

    9 Laboratory / Field Test

    10 Interlocking Block ILB production ILB production in progress

    11 Dismantling work Mosque dismantling Mosque dismantling work in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    5

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,15th Nov, 2011

    Segment 13

    Road Work

  • 8/13/2019 Daily Program Nov-2011

    6/19

    S.l. No. Description Work Program of 16th Nov. 2011 Achievement of 15th Nov Nov.2011 Remarks

    1 Segment 1A Drainage pipe installation

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for preloading work Sand bagging for preloading work in progress

    Surcharge material placement Surcharge material placement in progress

    Rebar fabrication & shuttering

    5 Segment-2 PVD Driving PVD Driving in progress

    Sand Blanket filling Sand Blanket filling in progress

    Sub base work (CH 240-340) Sub base work (CH 240-340) in progress

    Improved sub grade work (180-240) Improved sub grade work (180-240) in progress

    7 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress

    8 Electric Substation Concrete Pouring of Column Concrete Pouring of Column in progress

    Wasa Relocation Newly installed line is functioning

    Old line dismantling Old line dismantling in progress

    Laboratory / Field TestField density test at segment-2 (300mm sand

    blanket)

    Interlocking Block ILB production ILB production in progress

    11 Dismantling work Mosque dismantling Mosque dismantling work in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    10

    6

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,16th Nov, 2011

    Open deep drain4

    Segment 13

    Road Work

    9

  • 8/13/2019 Daily Program Nov-2011

    7/19

    S.l. No. Description Work Program of 17th Nov. 2011 Achievement of 16th Nov Nov.2011 Remarks

    Drainage pipe installation Drainage pipe installation in progress

    Sub-base work Sub-base work in progress

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for preloading work Sand bagging for preloading work in progress

    Surcharge material placement Surcharge material placement in progress

    Rebar fabrication & shuttering Rebar fabrication & shuttering in progress

    PVD Driving PVD Driving in progress

    200mm sand filling

    Sub base work (CH 240-340) Sub base work (CH 240-340) in progress

    Improved sub grade work (180-240) Improved sub grade work (180-240) in progress

    7 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress

    8 Electric Substation Concrete Pouring of Column Concrete Pouring of Column in progress

    Wasa Relocation Newly installed line is functioning

    Old line removing Old line removing in progress

    Laboratory / Field TestField density test at segment-2 (300mm sand

    blanket)

    Interlocking Block ILB production ILB production in progress

    11 Dismantling work Mosque dismantling Mosque dismantling work in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    10

    6

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,17th Nov, 2011

    Open deep drain4

    Segment 13

    Segment-2

    Segment 1A1

    9

    5

    Road Work

  • 8/13/2019 Daily Program Nov-2011

    8/19

    S.l. No. Description Work Program of 18th Nov. 2011 Achievement of 17th Nov Nov.2011 Remarks

    CC casting of Drainage pipe installation Excavation work

    Sub-base work Sub-base work in progress

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for preloading work Sand bagging for preloading work in progress

    Surcharge material placement Surcharge material placement in progress

    Bracing fixing

    PVD Driving PVD Driving in progress

    200mm sand filling 200mm sand filling in progress

    Sub base work (CH 240-340) Sub base work (CH 240-340) in progress

    Improved sub grade work (180-240) Improved sub grade work (180-240) in progress

    7 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress

    8 Electric Substation Concrete Pouring of Column Concrete Pouring of Column in progress

    Newly installed line is functioning

    Old line removing Old line removing in progress

    10 Laboratory / Field TestField density test at segment-2 (300mm sand

    blanket)300mm sand blanket filling executed

    11 Interlocking Block ILB production ILB production in progress

    12 Dismantling work Mosque dismantling Mosque dismantling work in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    9

    5

    Road Work

    Wasa Relocation

    6

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,18th Nov, 2011

    Open deep drain4

    Segment 13

    Segment-2

    Segment 1A1

  • 8/13/2019 Daily Program Nov-2011

    9/19

    S.l. No. Description Work Program of 19th Nov. 2011 Achievement of 18th Nov Nov.2011 Remarks

    CC casting of Drainage pipe installation Excavation work

    Sub-base materials laying Excavation executed

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for preloading work Sand bagging for preloading work in progress

    Surcharge material placement Surcharge material placement in progress

    Bracing fixing Bracing fixing in progress

    PVD Driving PVD Driving in progress

    200mm sand filling 200mm sand filling in progress

    Sub base work (CH 240-340) Sub base work (CH 240-340) in progress

    Improved sub grade work (180-240) Improved sub grade work (180-240) in progress

    7 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress

    8 Electric Substation Concrete Pouring of Column Concrete Pouring of Column in progress

    Newly installed line is functioning

    Old line removing Old line removing in progress

    10 Laboratory / Field Test

    11 Interlocking Block ILB production ILB production in progress

    12 Dismantling work Mosque dismantling Mosque dismantling work in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,19th Nov, 2011

    Open deep drain4

    Segment 13

    Segment-2

    Segment 1A1

    9

    5

    Road Work

    Wasa Relocation

    6

  • 8/13/2019 Daily Program Nov-2011

    10/19

    S.l. No. Description Work Program of 20th Nov. 2011 Achievement of 19th Nov Nov.2011 Remarks

    Drainage pipe installation Drainage pipe installation in progress

    Sub-base materials laying Sub-base materials laying in progress

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for preloading work Sand bagging for preloading work in progress

    Surcharge material placement Surcharge material placement in progress

    Bracing fixing Bracing fixing in progress

    PVD Driving PVD Driving in progress

    200mm sand filling 200mm sand filling in progress

    Sub base work (CH 240-340) Sub base work (CH 240-340) in progress

    Improved sub grade work (180-240) Improved sub grade work (180-240) in progress

    7 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress

    8 Electric Substation Concrete Pouring of Column Concrete Pouring of Column in progress

    Newly installed line is functioning

    Old line removing Old line removing in progress

    10 Laboratory / Field Test

    11 Interlocking Block ILB production ILB production in progress

    12 Dismantling work Mosque dismantling Mosque dismantling work in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    9

    5

    Road Work

    Wasa Relocation

    6

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,20th Nov, 2011

    Open deep drain4

    Segment 13

    Segment-2

    Segment 1A1

  • 8/13/2019 Daily Program Nov-2011

    11/19

    S.l. No. Description Work Program of 21th Nov. 2011 Achievement of 20th Nov Nov.2011 Remarks

    Drainage pipe installation Drainage pipe installation in progress

    Sub-base materials laying Sub-base materials laying in progress

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for preloading work Sand bagging for preloading work in progress

    Surcharge material placement Surcharge material placement in progress

    Concrete Pouring CH 820-840 (2nd lif t) Rebar fabrication & Shuttering executed

    PVD Driving PVD Driving in progress

    200mm sand filling 200mm sand filling in progress

    Sub base work (CH 240-340) Sub base work (CH 240-340) in progress

    Improved sub grade work (180-240) Improved sub grade work (180-240) in progress

    7 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress

    8 Electric Substation Concrete Pouring of Column Concrete Pouring of Column in progress

    Newly installed line is functioning

    Old line removing Old line removing in progress

    10 Laboratory / Field Test

    11 Interlocking Block ILB production ILB production in progress

    12 Dismantling work Mosque dismantling Mosque dismantling work in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,21th Nov, 2011

    Open deep drain4

    Segment 13

    Segment-2

    Segment 1A1

    9

    5

    Road Work

    Wasa Relocation

    6

  • 8/13/2019 Daily Program Nov-2011

    12/19

    S.l. No. Description Work Program of 22th Nov. 2011 Achievement of 21th Nov Nov.2011 Remarks

    Drainage pipe instal lation (CC casting) Drainage pipe instal lation in progress

    Sub-base materials laying Sub-base materials laying in progress

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for preloading work Sand bagging for preloading work in progress

    Surcharge material placement Surcharge material placement in progress

    PVD Driving PVD Driving in progress

    4 Open Deep Drain Earth Excavation,Soling,CC(CH 865-885)

    Sub base work (CH 240-340) Sub base work (CH 240-340) in progress

    Improved sub grade work (180-240) Improved sub grade work (180-240) in progress

    6 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress

    7 Electric Substation Concrete Pouring of Column Concrete Pouring of Column in progress

    Newly installed line is functioning

    Old line removing Old line removing in progress

    9 Laboratory / Field Test

    10 Interlocking Block ILB production ILB production in progress

    11 Dismantling work Mosque dismantling Mosque dismantling work in progress

    12 Released Material removing MS Rod deposit to CPA store-1 MS Rod deposit to CPA store-1in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Wasa Relocation

    5

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,22th Nov, 2011

    Segment 1A1

    Segment 13

    8

    Road Work

  • 8/13/2019 Daily Program Nov-2011

    13/19

    S.l.No.

    Description Work Program of 23th Nov. 2011 Achievement of 22th Nov Nov.2011 Remarks

    Drainage pipe installation (CC casting) Drainage pipe instal lation in progress

    Sub-base materials laying Sub-base materials laying in progress

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for preloading work Sand bagging for preloading work in progress

    Surcharge material placement Surcharge material placement in progress

    PVD Driving PVD Driving in progress

    4 Open Deep Drain CC(CH 865-885) Earth excavation executed

    Sub base work (CH 240-340) Sub base work (CH 240-340) in progress

    Improved sub grade work (180-240) Improved sub grade work (180-240) in progress

    6 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress

    Concrete Pouring of Column Concrete Pouring of Column in progress

    Shuttering of slab Shuttering of slab in progress

    Newly installed line is functioning

    Old line removing Old line removing in progress

    9 Laboratory / Field Test

    10 Interlocking Block ILB production ILB production in progress

    11 Dismantling work Mosque dismantling Mosque dismantling work in progress

    12 Released Material removing MS Rod deposit to CPA store-1 MS Rod deposit to CPA store-1in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    3

    8

    Road Work

    Wasa Relocation

    5

    Electric Substation7

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,23th Nov, 2011

    Segment 1A1

    Segment 1

  • 8/13/2019 Daily Program Nov-2011

    14/19

    S.l.No.

    Description Work Program of 24th Nov. 2011 Achievement of 23th Nov Nov.2011 Remarks

    Drainage pipe installation Drainage pipe installation in progress

    Sub-base materials laying Sub-base materials laying in progress

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for preloading work Sand bagging for preloading work in progress

    Surcharge material placement Surcharge material placement in progress

    CC(CH 865-885) Earth excavation executed

    3rd lift wall casting (CH 840-865)

    Sub base work (CH 240-340) Sub base work (CH 240-340) in progress

    Improved sub grade work (180-240) Improved sub grade work (180-240) in progress

    6 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress

    Concrete Pouring of Column Concrete Pouring of Column in progress

    Shuttering of slab Shuttering of slab in progress

    Newly installed line is functioning

    Old line removing Old line removing in progress

    9 Laboratory / Field Test

    10 Interlocking Block ILB production ILB production in progress

    11 Dismantling work Mosque dismantling Mosque dismantling work in progress

    12 Released Material removing MS Rod deposit to CPA store-1 MS Rod deposit to CPA store-1in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Open Deep Drain4

    Wasa Relocation

    5

    Electric Substation7

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,24th Nov, 2011

    Segment 1A1

    Segment 13

    8

    Road Work

  • 8/13/2019 Daily Program Nov-2011

    15/19

    S.l.No.

    Description Work Program of 26th Nov. 2011 Achievement of 25th Nov Nov.2011 Remarks

    Drainage pipe installation Drainage pipe installation in progress

    Sub-base materials laying Sub-base materials laying in progress

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for preloading work Sand bagging for preloading work in progress

    Surcharge material placement Surcharge material placement in progress

    CC(CH 865-885) Earth excavation executed

    Sub base work (CH 240-340) Sub base work (CH 240-340) in progress

    Improved sub grade work (180-240) Improved sub grade work (180-240) in progress

    6 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress

    Concrete Pouring of Column Concrete Pouring of Column in progress

    Shuttering of slab Shuttering of slab in progress

    Newly installed line is functioning

    Old line removing Old line removing in progress

    9 Laboratory / Field Test

    10 Interlocking Block ILB production ILB production in progress

    11 Dismantling work Mosque dismantling Mosque dismantling work in progress

    12 Released Material removing

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,26th Nov, 2011

    Segment 1A1

    Segment 13

    8

    Road Work

    Open Deep Drain4

    Wasa Relocation

    5

    Electric Substation7

  • 8/13/2019 Daily Program Nov-2011

    16/19

    S.l.No.

    Description Work Program of 27th Nov. 2011 Achievement of 26th Nov Nov.2011 Remarks

    Drainage pipe installation Drainage pipe installation in progress

    Sub-base materials laying Sub-base materials laying in progress

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for preloading work Sand bagging for preloading work in progress

    Surcharge material placement Surcharge material placement in progress

    Rebar binding of Base (CH 865-885) CC executed

    Sub base work (CH 240-340) Sub base work (CH 240-340) in progress

    Improved sub grade work (180-240) Improved sub grade work (180-240) in progress

    6 Rail Relocation Sub base preparation (CH 550-620) Sub base preparation (CH 550-620) in progress

    Concrete Pouring of Column Concrete Pouring of Column in progress

    Shuttering of slab Shuttering of slab in progress

    Newly installed line is functioning

    Old line removing Old line removing in progress

    9 Laboratory / Field Test

    10 Interlocking Block ILB production ILB production in progress

    11 Dismantling work Mosque dismantling Mosque dismantling work in progress

    12 Released Material removing

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Open Deep Drain4

    Wasa Relocation

    5

    Electric Substation7

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,27th Nov, 2011

    Segment 1A1

    Segment 13

    8

    Road Work

  • 8/13/2019 Daily Program Nov-2011

    17/19

    S.l.No.

    Description Work Program of 28th Nov. 2011 Achievement of 27th Nov Nov.2011 Remarks

    Drainage pipe installation Drainage pipe installation in progress

    Sub-base materials laying Sub-base materials laying in progress

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for preloading work Sand bagging for preloading work in progress

    Surcharge material placement Surcharge material placement in progress

    Base Casting (CH 865-885) Rebar binding & Shuttering executed

    5 Rail Relocation Sub base preparation (CH 550-620) Sub base preparation (CH 550-620) in progress

    Concrete Pouring of Column Concrete Pouring of Column in progress

    Shuttering of slab Shuttering of slab in progress

    7 Wasa Relocation Newly installed line is functioning

    8 Laboratory / Field Test

    9 Interlocking Block ILB production ILB production in progress

    10 Dismantling work Mosque dismantling Mosque dismantling work in progress

    11 Released Material removing

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    3

    Open Deep Drain4

    Electric Substation6

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,28th Nov, 2011

    Segment 1A1

    Segment 1

  • 8/13/2019 Daily Program Nov-2011

    18/19

    S.l.No.

    Description Work Program of 29th Nov. 2011 Achievement of 28th Nov Nov.2011 Remarks

    Drainage pipe installation Drainage pipe installation in progress

    Sub-base materials laying Sub-base materials laying in progress

    Water Supply pipe Installation work

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for preloading work Sand bagging for preloading work in progress

    Surcharge material placement Surcharge material placement in progress

    W all casting/1st lift (CH 865-885) Concrete pouring of Base finished

    5 Rail Relocation Sub base preparation (CH 550-620) Sub base preparation (CH 550-620) in progress

    Electric Sub station Shuttering of slab Shuttering of slab in progress

    7 Wasa Relocation Newly installed line is functioning

    8 Laboratory / Field Test

    9 Interlocking Block ILB production ILB production in progress

    10 Dismantling work Mosque dismantling Mosque dismantling work in progress

    11 Released Material removing

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Segment 1A1

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,29th Nov, 2011

    Segment 13

    Open Deep Drain4

  • 8/13/2019 Daily Program Nov-2011

    19/19

    S.l.

    No. Description Work Program of 30th Nov. 2011 Achievement of 29th Nov Nov.2011 Remarks

    Drainage pipe installation Drainage pipe installation in progress

    Sub-base materials laying Sub-base materials laying in progress

    Water Supply pipe Instal lation work Water Supply pipe Instal lation work in progress

    Layout of HT Cable Trench

    2 Segment 2A Settlement Record Settlement Record in progress

    Sand bagging for preloading work Sand bagging for preloading work in progress

    Surcharge material placement Surcharge material placement in progress

    Wall casting/1st lift (CH 865-885) Concrete pouring of Base finished

    5 Rail Relocation Sub base preparation (CH 550-620) Sub base preparation (CH 550-620) in progress

    6 Electric Sub station Shuttering of slab Shuttering of slab in progress

    7 Wasa Relocation Newly installed line is functioning

    8 Laboratory / Field Test

    9 Interlocking Block ILB production ILB production in progress

    10 Dismantling work Mosque dismantling Mosque dismantling work in progress

    11 Released Material removing

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    4

    Segment 1A1

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,30th Nov, 2011

    Segment 13

    Open Deep Drain