42
DAHLIA PONDS TUNNEL PROJECT CASE HISTORY Presented By: Nathan Soule, PE, PG Brierley Associates & Brenden Tippets, Project Executive, BTrenchless Dahlia Ponds Tunnel Project

Dahlia Ponds Tunnel Project Case History

  • Upload
    cicada

  • View
    51

  • Download
    0

Embed Size (px)

DESCRIPTION

Dahlia Ponds Tunnel Project . Presented By: Nathan Soule, PE, PG Brierley Associates & Brenden Tippets, Project Executive, BTrenchless. Dahlia Ponds Tunnel Project Case History . Dahlia Ponds Tunnel Project . Outline. Owner’s Approach Design & Engineering Construction. - PowerPoint PPT Presentation

Citation preview

Page 1: Dahlia Ponds  Tunnel Project Case History

DAHLIA PONDS TUNNEL PROJECTCASE HISTORY

Presented By: Nathan Soule, PE, PG Brierley Associates&

Brenden Tippets, Project Executive, BTrenchless

Dahlia Ponds Tunnel Project

Page 2: Dahlia Ponds  Tunnel Project Case History

OutlineDahlia Ponds Tunnel Project

Owner’s Approach Design & Engineering Construction

Page 3: Dahlia Ponds  Tunnel Project Case History

Project LocationDahlia Ponds Tunnel Project

Page 4: Dahlia Ponds  Tunnel Project Case History

Project LocationDahlia Ponds Tunnel Project

Page 5: Dahlia Ponds  Tunnel Project Case History

Modified Design-BuildDahlia Ponds Tunnel Project

Denver Urban Drainage needed a new approach to tunnel construction Past problems with O’Brian Canal Tunnel

Hired tunneling expert – Brierley Associates (Lyman Henn division)

Retained Qualified Contractor BTrenchless early on

Independent estimator – Bids must be within 10%

Page 6: Dahlia Ponds  Tunnel Project Case History

EngineeringDahlia Ponds Tunnel Project

Evaluate feasible/allowable methods Subsurface exploration with Contractor

involvement

Page 7: Dahlia Ponds  Tunnel Project Case History

Test PitsDahlia Ponds Tunnel Project

Cobbles & Boulders Groundwater

Page 8: Dahlia Ponds  Tunnel Project Case History

Tunneling/Trenchless MethodsDahlia Ponds Tunnel Project

Method Details Advantages Complications

Microtunnel Closed Face• Slurry• EPB

Works for most conditions

High costCobbles < 1/3 TBM dia

Pipe Ramming – Common

Rapid & lost costPenetrates through cobbles

Limited distanceLine & grade deviations

Pipe Ramming – Guided

• Pilot tube• HDD

Accurate line & grade Pilot tube penetrationMultiple up-sizes

Conventional Shield • Sand shelves• Breasting

VersatileAdaptable

Above water tableMed – large dia. only

Open Face TBM Rotating headInexpensive* Limited application

Not well suitedAuger Bore Jacked pipe w/ auger

Ground Improvement • Grouting• Dewatering

Available as supplement

Page 9: Dahlia Ponds  Tunnel Project Case History

Trial Horizontal Directional DrillDahlia Ponds Tunnel Project

Multiple Attempts

Stopped by cobbles/boulders

Determined guided ram not feasible

Team decided on microtunneling for I-76

Page 10: Dahlia Ponds  Tunnel Project Case History

Team Effort

Owner •Urban Drainage/ Adams County

Engineer •ICON Engineering/Lyman Henn, a division of Brierley Associates, LLC

Contractor •Btrenchless, a division of BT Construction, Inc.

SUBS •Kelley Dewatering, Garza Concrete, Inlet Structures, Ralph Martinez trucking.

Suppliers •Akkerman, Derrick, Microtunneling, Inc., Wyo-ben, Inc.

Dahlia Ponds Tunnel Project

Page 11: Dahlia Ponds  Tunnel Project Case History

Project Purpose

BTrenchless completed one 240 LF microtunnel and one 60 ft rescue tunnel.

Design/build of two tunnels for storm sewer, including test pits of existing ground conditions.

240 LF of 54” Tunnel to be completed without disruption of above I-76 highway.

60 LF of 84” rescue Tunnel to be completed online and grade to match existing failed tunnel 30 ft below grade.

Dahlia Ponds Tunnel Project

Page 12: Dahlia Ponds  Tunnel Project Case History

Dahlia Ponds Tunnel Project

Page 13: Dahlia Ponds  Tunnel Project Case History

Dahlia Ponds Tunnel Project

Page 14: Dahlia Ponds  Tunnel Project Case History

Project Scope

Various construction methods used to account for the diverse ground conditions:

Microtunnel Hand Tunnel

Sizes of the installed tunnels ranged from 54” to 84” diameter.

Dahlia Ponds Tunnel Project

Page 15: Dahlia Ponds  Tunnel Project Case History

Project

Test pit ground conditions

HDD Pilot hole

MTBM (Microtunnel

Boring Machine)Separation Plant

Entry Shafts and Seals

GeneratorsAutomatic Bentonite

Injection System

Dewatering system

Dahlia Ponds Tunnel Project

Page 16: Dahlia Ponds  Tunnel Project Case History

Microtunnel Machine

AKKERMAN

Microtunnel Boring Machine SL 51 125 HP Head

Dahlia Ponds Tunnel Project

Page 17: Dahlia Ponds  Tunnel Project Case History

Microtunnel MachineDahlia Ponds Tunnel Project

Page 18: Dahlia Ponds  Tunnel Project Case History

Microtunnel Machine

Akkerman MC-4 Jacking Frame

Dahlia Ponds Tunnel Project

Page 19: Dahlia Ponds  Tunnel Project Case History

Separation Plant

DERRICKSeparation Plant

(3) FLC 2000 4-Panel High “G” Shaker Decks

(1) FLC 2000 Mud Cleaner Hydrocyclone System

Dahlia Ponds Tunnel Project

Page 20: Dahlia Ponds  Tunnel Project Case History

Separation PlantDahlia Ponds Tunnel Project

Page 21: Dahlia Ponds  Tunnel Project Case History

Separation PlantDahlia Ponds Tunnel Project

Page 22: Dahlia Ponds  Tunnel Project Case History

Quantifying Material (Onboard Weighing System )

Product Totals Multiple Point Weighing Split Weighing Auto Target Function Auto Tare Function Error Alarms Data Fields Unit Conversion Multiple Batching Modes Tip-off Weighing Zeroing Auto Add Mode Data Analysis Remote Add Button

Dahlia Ponds Tunnel Project

Page 23: Dahlia Ponds  Tunnel Project Case History

Entry Shafts

GME – Slide Rail System

Dahlia Ponds Tunnel Project

Page 24: Dahlia Ponds  Tunnel Project Case History

Exit / Entry Seal

Microtunnel Inc. Entry Seals

Dahlia Ponds Tunnel Project

Page 25: Dahlia Ponds  Tunnel Project Case History

Generators

400 KW Generator 550 KW Generator

(3) 75 KW Generators

Dahlia Ponds Tunnel Project

Page 26: Dahlia Ponds  Tunnel Project Case History

Automatic Bentonite Injection System

MICROTUNNELING, INC.

Dahlia Ponds Tunnel Project

Page 27: Dahlia Ponds  Tunnel Project Case History

Dewatering System

Ground water contamination

treatment:

(6) Weir tanks(1) Air Sparging 300 cfm (4) Mezzi air injection

units

Dahlia Ponds Tunnel Project

Page 28: Dahlia Ponds  Tunnel Project Case History

Known Significant Challenges

Schedule Purchase of Equipment- Short time frame Shaft Construction Contaminated ground water up to 2000 GPM Shallow cover of tunnel under I-76

Dahlia Ponds Tunnel Project

Page 29: Dahlia Ponds  Tunnel Project Case History

Proposed Solutions

CHALLENGE•Schedule

SOLUTION•Internal weekly meetings•Detailed scheduling•Other existing tunnel

contracts

Dahlia Ponds Tunnel Project

Page 30: Dahlia Ponds  Tunnel Project Case History

Scheduling

Successful scheduling- project completed 30 days ahead of original schedule.

Provide the owner with feasible schedule in order to anticipate possible changes.

Dahlia Ponds Tunnel Project

Page 31: Dahlia Ponds  Tunnel Project Case History

Proposed Solutions

CHALLENGE•Purchase of

Equipment

SOLUTION•In-house evaluation of all equipment

needed•Research other industry leaders and their

equipment•Interview other contractors about

performance of the equipment•Date of delivery

Dahlia Ponds Tunnel Project

Page 32: Dahlia Ponds  Tunnel Project Case History

Dahlia Microtunnel Equipment

Base Microtunnel MTBM #1 MTBM #2 MTBM #3   Separation Equipment MTBM #1 MTBM #2 MTBM #3   Intermediate Jacking Equipment MTBM #1 MTBM #2 MTBM #3

Control Container         Slurry Volume         Hydraulic Hose      

Microtunneling Head         Shaker         Jacking Force      

Steering Head OD         Hydrocyclones First Stage         Trust Rings      

Steering Head Length Excl Cutter         Hydrocyclones Second Stage         Hydraulic Cylinders      

Steering Pressure         Unit Size         High Pressure Jetting      

Number of Steering Cylinders         Slurry Tank MTBM #1 MTBM #2 MTBM #3   Jetting Pump      

Steering Cylinder Stroke         First Chamber Length         Jetting Starter Hose      

Steering Cylinder Force         Second Chamber Length         Jetting Tunnel Line      

Bypass Valve         Overflow Height         Bentonite System MTBM #1 MTBM #2 MTBM #3

Drive Motor         Guidance System MTBM #1 MTBM #2 MTBM #3   Bentonite Pump      

OD Ring                   Electric Control Box      

Power Cable         Connections and Extensions MTBM #1 MTBM #2 MTBM #3   Valve and Junction      

Stand Alone Unit         Tunneling Connections         Tunnel Cords      

Starter Set         Trunk Line         Volume      

Steering Angle         Trunk Line Storage         Max Pressure      

Computer Hardware         Aux Equip Power Cable         Pressure Can      

Nominal Drive Torque         Main Control Cable         Supply Can      

Trailer Section Length         Booster Pump Cable         Volume Mixer      

Trailer Section OD         Hydro Elec Launch Connections         Volume Storage      

Lead Can Weight         Connection Cable Container         Electrical Power      

Trailer Section Weight         Steering Cable Head         Power Supply Cable      

Cutter Head Weight         Extension Hose Hydraulic         Bentonite Pipe      

Operating Pressure         Distance Wheel         Auto Bentonite Lube System MTBM #1 MTBM #2 MTBM #3

Slurry Circulation System MTBM #1 MTBM #2 MTBM #3   Emergency Shut Off                

Slurry Feed Pump         Connection Cable Power Supply Head         Entr/Recep Seal for Pipes MTBM #1 MTBM #2 MTBM #3

Slurry Return Pump         Drive Motor Cooling                

Circulation System Starter Set         Purchase Items         Training and Service MTBM #1 MTBM #2 MTBM #3

Slurry Line         Pipe Jacking Equipment MTBM #1 MTBM #2 MTBM #3   Travel Time      

Slurry Line Launching Set         Jacking Frame         Weekdays      

Set of Flow Meter         Jacking Pit         Overtime and Saturdays      

Slurry Container         Jacking Force         Sundays and Holidays      

Length         Max Pipe OD                

Width         Pipe Length                

Height         Operating Pressure                

Inlet Diameter         Number of Strokes                

Outlet Diameter         Jacking Unit Drive                

          Hydraulic Oil Tank Capacity                

          Jacking Unit Extension                

Page 33: Dahlia Ponds  Tunnel Project Case History

Proposed Solutions

CHALLENGE•Shoring of wet shafts In

cobble and running sands

SOLUTION•Provide a realistic approach

to anticipated GPM. •Determine best/cost

effective method of construction.

Dahlia Ponds Tunnel Project

Page 34: Dahlia Ponds  Tunnel Project Case History

Shaft ConstructionDahlia Ponds Tunnel Project

Page 35: Dahlia Ponds  Tunnel Project Case History

Proposed Solutions

CHALLENGE•Handling of

contaminated ground water

SOLUTION•Discuss potential problems up front

with owner. •Involve state regulatory agency, so

they are aware and will be on-board with potential problems.

•Evaluate most cost effective treatment.

Dahlia Ponds Tunnel Project

Page 36: Dahlia Ponds  Tunnel Project Case History

Contaminated ground water

Treatment of 2000 GPM system

Treatment of Dissolved Manganese Total Iron Dissolved Iron

Dahlia Ponds Tunnel Project

Page 37: Dahlia Ponds  Tunnel Project Case History

Proposed Solutions

CHALLENGE•Shallow cover of tunnel

SOLUTION•Lengthen bore to enter

farther down slope•Monitor entry point for

possible settlement

Dahlia Ponds Tunnel Project

Page 38: Dahlia Ponds  Tunnel Project Case History

Shallow cover

Slurry returning to the surface

Install foam injection to stabilize face

Dahlia Ponds Tunnel Project

Page 39: Dahlia Ponds  Tunnel Project Case History

Completion of Work

Overall BTrenchless completed the two tunnels in 3 months, including all structures and appurtenances approximately 1 month ahead of schedule

Maintained good relationships with owner, engineers and the community, with little disruptions

Dahlia Ponds Tunnel Project

Page 40: Dahlia Ponds  Tunnel Project Case History

Lessons Learned

Think outside of the box (never accept “this is how we’ve always done it”)

Practice teamwork and adhere to advice from other industry leaders

Success comes from lessons learned

Dahlia Ponds Tunnel Project

Page 41: Dahlia Ponds  Tunnel Project Case History

Questions?

Dahlia Ponds Tunnel Project

Page 42: Dahlia Ponds  Tunnel Project Case History

Phone: 303-286-0202Fax: 303-286-1262

www.BTrenchless.com

Phone: 303-469-0199Fax: 303-466-8309

www.BTConstruction.com

9885 Emporia Street Henderson, Colorado

80640

110 16th St. #700Denver, Colorado

80202

Phone: 303-534-1100Fax: 303-534-1777

www.lymanhenn.com