2017 PEPS Conference
LEVEL OF EFFORT & NEGOTIATIONS2017 PEPS Conference
Phil Howlett, P.E. │ Richard De La Cruz, P.E.
November 3, 2017
2017 PEPS Conference
Table of contents
2
Welcome
Pre-Level of Effort (LOE)
Level of Effort (LOE): Scopes
Level of Effort (LOE): Schedule
Level of Effort (LOE): Budget
Good Practice – Bad Practice
Closing Remarks/Questions?
11
22
33
44
55
66
77
2017 PEPS Conference
First Thought
3
Productivity is never an accident. It is always the result of a commitment to excellence, intelligent planning, and focused effort.
Paul J. Meyer
2017 PEPS Conference
Look at the Big Picture – We have different types of contracts
4
Schematic and Environmental (S&E)
Plans Specifications & Estimates (PS&E)
Utility Engineering
Traffic Engineering
Survey
Geotechnical Engineering
Materials Engineering
Value Engineering
Planning
General Engineering Consultant (GEC)
Construction Engineering Inspection (CEI)
Intelligent Traffic Systems (ITS)
Other
2017 PEPS Conference
When do we negotiate Level of Effort?
5
Master Contracts•Specific Deliverable (SD) Contracts – Negotiation
of LOE•Indefinite Deliverable (ID) Contracts – N/A
Work Authorizations•SD Contracts – Some Negotiation may be
required•ID Contracts – Negotiation of LOE
Supplemental Agreements - maybe Supplemental Work Authorizations - maybe
2017 PEPS Conference
Level of Effort (LOE)
It is absolutely necessary that both parties have a clear understanding of the work to be accomplished and deliverables expected in order to develop a Level of Effort and evaluate the reasonableness of a cost proposal.
6
Level of Effort (LOE)
–Scope (What do we want accomplished and Deliverables)
–Schedule (When are things to be accomplished)
–Budget (How much will it cost and a breakdown of who will do the work?)
2017 PEPS Conference
Level of Effort (LOE) Negotiation
Challenging
7
What would it be like to negotiate with a …..
Time Consuming
Looking for the Win-Win
Fair and Reasonable
There is no easy button
..Dentist..
…for a Tooth Extraction?
2017 PEPS Conference 8
2017 PEPS Conference
First Things First
9
(Pre-Level of Effort)
2017 PEPS Conference
Pre-Level of Effort
10
Scoping MeetingCommunication
Project Information
Scopes
Invoicing
Accountability
2017 PEPS Conference
Scoping Meeting – Communication
11
Org Charts
Points of Contact
Best method
How often
Change of Personnel
Escalation Process
2017 PEPS Conference
Scoping Meeting – Project Information
12
Project Limits
Control Section Job (CSJ) Numbers
Schedule / Milestones
• Project unknowns• Stakeholders• Drainage, driveway, seasonal work, etc.…
• Project unknowns• Stakeholders• Drainage, driveway, seasonal work, etc.…
Challenges
2017 PEPS Conference
VisionAssumptions
13
2017 PEPS Conference
Scoping Meeting - Scopes
14
Establish the basis of payment.
Review both scopes line by line.
Document what needs to be added, modified, or removed.
Very Important: clearly define all deliverables.
2017 PEPS Conference
Scoping Meeting - Invoicing
15
Obtain understanding of what will be allowed.
Remember: the basis of payment used must be in the master contract.
•Well thought out and documented deliverables.•If you need help, ask. (PEPS can help)•Well thought out and documented deliverables.•If you need help, ask. (PEPS can help)
What ensures good invoicing?
2017 PEPS Conference
Scoping Meeting - Invoicing
Remember:
Any direct labor, unit cost, or other direct expense classification not included in the contract is not eligible for use under a work authorization.
Any direct labor, unit cost, or other direct expense classification included in the contract, but not in a work authorization, is not eligible for payment under that work authorization.
If the rates are not in the work authorization, they cannot be billed.
16
2017 PEPS Conference
Scoping Meeting - Accountability
17
•Quality•Timeliness•Communication
•Quality•Timeliness•Communication
Understanding of Expectations
Provider Evaluations
2017 PEPS Conference
Scope Meeting Tips
Have an agenda
Ensure the right people attend
Everybody reviews the scopes ahead of time
Visit/Drive the project ahead of time
Bring a list of questions
Summarize
–Review understandings and expectations
–Delegate action items
Document
18
Allow time for this meeting
2017 PEPS Conference
Scopes• (What and deliverables)
Schedule• (When)
Budget• (How much and who)
Level of Effort (LOE)
19
2017 PEPS Conference
Level of Effort (LOE) - Scopes
Finalize the scopes (clean up comments from the scoping meeting).
Ensure the scopes have the level of detail needed based on the basis of payment.
– Lump Sum
– Specific Deliverable, Cost Plus Fixed Fee, Unit Cost
Be sure to elaborate on specific details where needed.
Spell out all acronyms the first time used.
List well-defined deliverables.
Consider using a phased approach when appropriate.
20
2017 PEPS Conference
Level of Effort (LOE) - Scopes
Remember:
If the services are not in the master contract’s scope, they cannot be put it in the work authorization’s scope.
If the services are not in the work authorization’s scope, those services cannot be performed and payment cannot be expected.
21
Use the master contract’s scope tocreate your work authorization’s scope.
2017 PEPS Conference
Level of Effort (LOE) - Schedule
22
Think of it as a management reporting tool as well as an implementation tool to help pace the detailed activities.
•Work Breakdown Structure•Work Breakdown Structure
Establish milestones and submittal dates.
Tasks must follow the scopes of services and the fee schedule.
Include sufficient review times (for both the State and consultant).
2017 PEPS Conference
Level of Effort (LOE) - Schedule
First activity should be “Start Date = Date of Execution” (Not an actual date)
– Do NOT use “Notice to Proceed” in schedule.
Activity dates are later than the actual (anticipated) date of execution.
Termination Date
– Indefinite deliverable (ID) contracts are limited to a 5-year maximum.
– Be sure to include “Termination Date = xx/xx/20xx.”
– Should typically be the last calendar day of a month
– Try not to end a work authorization in August or December.
– Work authorization termination date cannot go beyond the master contract’s termination date
23
2017 PEPS Conference 24
Level of Effort (LOE) - Budget
Ensure tasks identified in the fee schedule align with the scope and the work schedule.
Ensure the rates and labor classifications are used in accordance with the contract.
ODEs must be assigned a function code.
• Significantly helps with consistency for summary sheet• Significantly helps with consistency for summary sheet
Calculations should be made from numbers rounded to the nearest penny (except mileage).
• Not every item needs a quantity (classifications, unit costs, ODE, tasks)
• Primary control is that maximum amount payable is a not to exceed amount
• Not every item needs a quantity (classifications, unit costs, ODE, tasks)
• Primary control is that maximum amount payable is a not to exceed amount
Allow some flexibility.
2017 PEPS Conference
Level of Effort (LOE) - Budget
25
Ensure HUB goal or DBE goal will be met.
Include a summary sheet broken out by firm, function code, and CSJ.
•Use the latest table of deliverable template.•Align the function codes with the scope and fee schedule•Ensure each deliverable description is distinguishable from one
another.
•Use the latest table of deliverable template.•Align the function codes with the scope and fee schedule•Ensure each deliverable description is distinguishable from one
another.
Include a table of deliverables if using lump sum.
Rates, labor classifications and other direct expenses can only be invoiced if they are included in both the contract and the work authorization.
Perform a thorough quality review of spreadsheet calculations.
2017 PEPS Conference
Remember
Clearly define deliverables.
Ensure consistency between scopes, budget, and work schedule.
– Activities
– Task titles
– Function codes
– Formatting
Use the available checklists to help QC contracts and work authorizations.
26
2017 PEPS Conference
Work Authorization Review Checklist (Example)
27
EXHIBITS A & B
□ Check Headers and Footers• Legacy Contract No. & WA/SWA No. (Upper Right)• Contract PS No. & PS PO No. (Upper Right)• Page Numbers and Exhibit A/B in Footer
□ Ensure WA scope MUST match master contract scope□ Ensure Acronyms are spelled out at least once□ Find and Replace
• TxDOT to the State• the State shall to the State will• the Engineer will to Engineer shall• the Surveyor to the Engineer’s Surveyor (exception – Survey Contracts)• Do not use "you" or "we"• this Contract to this Work Authorization
□ Check General Formatting (Margins, excess spacing between paragraphs,justifications, etc.)
□ Exhibit B should have CSJ, HWY, project limits, county, and district.
2017 PEPS Conference
Work Authorization Review Checklist (Example)
28
EXHIBIT C
□ Check Headers and Footers• Legacy Contract No. & WA/SWA No. (Upper left)• Contract PS No. & PS PO No. (Upper Right)• Page Number(s) and Exhibit C in Footer
□ Dates do not begin prior to WA Execution□ Tasks follow Exhibit B and Exhibit D□ Ensure it has "Work Authorization No. XX termination date: xx/xx/20xx"□ Ensure it has "Prime Provider Name: xxxxxxxxxxx" (exact name)□ Change "Notice to Proceed" or "NTP“ to "Start Date = Date of Execution”□ Termination Date must not go beyond Contract Termination Date□ Ensure the termination date is the last working day of the month
• Avoid termination dates at the end of the fiscal year and the end ofthe calendar year
2017 PEPS Conference
Work Authorization Review Checklist (Example)
29
EXHIBIT D□ Total amount is covered in the contract (Check PS-CAMS) and correct WA number□ Fee Schedule is split out by CSJ□ Ensure the correct Method of Payment is being used and is in master contract□ Check Headers and Footers
• Legacy Contract # & WA/SWA # (Upper left)• Contract PS # & PS PO # (Upper Right)• Method of Payment (Center Header)• Page Numbers and Exhibit D in Footer
□ Ensure "Prime Provider Name: xxxxxxxxxxx" or "Sub-Provider Name: xxxxxxxxx" is on each page
□ General Formatting (Margins, excess spacing between paragraphs, justifications, etc.)□ Staffing Classification Names and Rates MUST match contract□ Formulas add up□ Tasks follow Exhibit B and Exhibit C□ Other Direct Expenses
• Function Code assigned• Names and rates match contract • Include columns: Description, Unit, Cost, Quantity
□ Summarization by Provider (Prime and Subs), Function Code and CSJ□ Lump Sum WA's have a Table of Deliverables and $ amounts match
2017 PEPS Conference
If you have any questions,
PEPS is here to help.
30
2017 PEPS Conference 31
Productivity is never an accident. It is always the result of a commitment to excellence, intelligent planning, and focused effort.
Paul J. Meyer
An effective Level of Effort
Philip Howlett
2017 PEPS Conference 32
Thank you !
Questions?
2017 PEPS Conference
Contact Information