19
CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

Embed Size (px)

DESCRIPTION

1. Ensure PCS900 has valid machine measure-up and AS450 calibration –Have you restored the correct persist file? More important when: –You reinstall equipment –Have multiple machines the display is used on Note: AS450 is the slope sensor under the mast

Citation preview

Page 1: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

CTCT

PCS900 v1.10Quick Start Guide

Phil JacksonTraining Manager

March 2010

Page 2: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

Why a Quick Start Guide?• How good is your memory?• There are 17 steps to complete!• In the correct order

Page 3: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

1. Ensure PCS900 has valid machine measure-up and AS450 calibration– Have you restored the correct persist file?

• More important when:– You reinstall equipment– Have multiple machines the display is used

on

Note: AS450 is the slope sensor under the mast

Page 4: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

2. Ensure PCS400 is configured correctly• E.g. 3D elevation and 3D slope control

– Note: this applies to other 2D systems also e.g. MobaMatic

• Or 3D elevation and 2D height control

Page 5: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

3. Ensure the 2D cross-slope sensor is calibrated

• This is the AS200 on the screed• Very important for accurate 3D results• Must be in 2D slope mode to recalibrate

Page 6: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

4. Ensure the PCS900/UTS instrument and SCS900 grade check/UTS instrument set-ups have adequate range and line of sight for the desired paving run

• Has someone stood at each position and looked over the paving run?

• Will it change with trucks or other paving machinery?

• Will it change with the time of day?

Page 7: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

5. If using manual masts, ensure the correct mast extension is entered

• Are the units correct?

• Check the scale on the mast with a steel tape– Is it accurate?

Page 8: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

6. Load the design in PCS900 and optionally select a horizontal alignment

• Instructions are on the other side of the page

Page 9: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

7. Establish a connection between PCS900 and the UTS instrument that is responsible for paver control

• Make sure it is the correct UTS– Check the radio settings match the UTS

instrument– Check the MT900 IDs don't conflict with other

machines on site

Page 10: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

8. Establish a connection between the grade check SCS900 system and the UTS instrument responsible for grade checking

• Move the SCS target and make sure the correct gun follows it

Page 11: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

9. Enter any horizontal or vertical offsets in PCS900

• Be careful!– What design do you have loaded?– Is your offset UP from the base surface?– Or down from the finished surface?– What about differential compaction?

Page 12: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

10. Ensure the SCS900 setup used for grade checking uses the same design and vertical offset as PCS900

• You must be at least as accurate as the machine to be able to check it– Correct Design– Correct Offset– Correct setup and a vertical pole with a flat

base

Page 13: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

11. Prepare screed for paving using normal techniques (for example, 'Pave-by-the-Numbers')

• Try to get screed as close to grade height as possible

Page 14: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

12. With screed on starter blocks pull the machine forward until PCS900 obtains the screed orientation (~300-400 mm)– Once the orientation is known, the 'Low

Accuracy: Move' message stops– This procedure assumes that the starter blocks

get the screed on grade relative to design• Not required IF you use the v1.10 Direction

key as you back into position

Page 15: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

13. Bench PCS900 using an external reference such as a UTS rover pole

• Do NOT use a GPS rover for benching• Bench point should be at screed point, as defined by

machine measure-up– Tip - If you can, set your screed tips to be the tips

of the main screed• not the screed extensions

– That way you always know where to bench– On a cross slope, this could be a big deal!

Page 16: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

• This step only applies to US style pavers that have depth crank handles

• 14. Do not adjust the depth crank handles again!• If you re-adjust the depth crank handles,

rebench PCS900• Note – If there is a large elevation change you may run out of

cylinder• In this instance, buy back some cylinder by slowly adjusting the

depth crank handle until PCS900 adjusts to grade• If you have to crank faster than PCS900 can adjust the screed back

to grade, crank and wait until the system is on grade again• If the 2D system is back on grade and enough cylinder has been

gained back, stop the paver and rebench as outlined in step 13. Then complete the steps from step 15

Page 17: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

15. Begin paving and place the 2D system into Auto

• Initially, the grade lights on the CB440 may indicate that the 2D system is off grade but the PCS900 AutoAdjust feature quickly adjusts to bring the 2D system on grade

Page 18: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

16. Check the grade of the laid mat with an SCS900 grade check rover

Page 19: CTCT PCS900 v1.10 Quick Start Guide Phil Jackson Training Manager March 2010

17. If required, increment or decrement the CB440 responsible for 3D elevation to get on-grade– If you followed the steps above, you shouldn't

need to do this...AutoAdjust will do it for you • Only very small adjustments may be required• Be careful not to overreact to grade height

changes• The screed reacts very slowly to grade

changes