Cryo and AFE IIt Update
Fiber Tracker MeetingApril 6, 2006
Imperial CollegeA. Bross
Cryo Update I
The cryo-system for the VLPCs has been operated extremely reliably and stably from May 05, through the end of the KEK TB and now for about 2 months again at Fermilab
However, it was felt that the thermal-link design could be made more robust
A bolted concept has now been detailed and will be used in all subsequent systems
Modulo one problem Vacuum tests on the bolt to envelope weld were successful
The drawing package is complete and we have awarded the bid to Ability Engineering for $140k for 4 systems
Does not include Cryo-coolers Temperature controlers and sensors Lid Heater circuitry Cassette He gas system
Cryo Update II
Cryo Update III
However II Need to solve an assembly problem at upper thermal link
Cryo Update IV
We recently did a tilt test of the system
Operation at 25o off normal was fine
We observed an approximately 0.3K temperature increase at stage II (5.2 5.5K)
The Cryo-cooler efficiency is degraded when it is operated off-vertical, but this does not present a problem for the MICE VLPC system
Cryo Update V
Excellent temperature stability (spec is mK)
Cryo Update VI
LHC Power vs Cold End Temperature
0%
2%
4%
6%
8%
10%
12%
14%
16%
18%
20%
6.1 6.15 6.2 6.25 6.3 6.35 6.4 6.45
Cold End Temperature (K)
VL
PC
Hea
ter
Po
wer
Upright Tilted
However looking at both cassettes we see that the left-hand cassette is on the edge of being “in control”
Even in the upright position, the LHC will be on the edge with the cryo-cooler compressor operating at 50HZ
REALLY need to solve the thermal link problem
AFE IIt Update
The AFE IIt pre-production boards (15) have now all arrived at Fermilab and 5 or 6 are under test
The first boards came up very quickly In about 1 hour No green wires!
TriPt testing is done Yield is about 80% More than enough chips for D0 + MICE + Spares for both
experiments Plus second pass could yield more
Expect Production Order to be released soon New issue with discriminator threshold spread About 10 week lead for delivery of all boards
But many will arrive earlier The critical issue for MICE is MICE-specific firmware
development for AFE IIt NOT a Trivial amount of work
AFE IIt
04/20/23
LED Spectra:
AFE1 AFEII
JW@FTG, 2006Mar21
04/20/23
AFE IIt Discriminators
Turn on spread seen on the platform – much wider than expected
04/20/23
AFE IIt Discriminators II
More of same
04/20/23
AFE IIt Discriminators III
Change in AFPGA firmware – now fixed!
Issues that still Need some Thought
AFE IIt board temperature and bias calibration Does MICE need a test stand (like D0 has) to do this
operation? LED pulser data
Plan to dismount wavguides and mount a LED pulser or excite the fibers with blue LEDs?
New LVSB Board Not likely. Existing board looks OK. 6 new boards are being
assembled now. Firmware development still might be needed
– May be able to get support for this from Fermilab CD
Rate If we keep analog and timing information we are limited to:
250 muons per msec of spill– It is possible that clever (extreme) programming of the AFE IIt can
push this up a bit.
If we drop analog and timing and only use discriminators, we can run at 7 MHz.