Cranes Hoisting and Rigging

Embed Size (px)

Citation preview

  • 7/29/2019 Cranes Hoisting and Rigging

    1/25

    Cranes Hoisting and Rigging

    Contents

    Approved by Michael Wisherop

    Revised 09/11

    NOTE:

    . . . . . Denotes a new section.

    . . . . . . . . Denotes the beginning of changed text within a section.

    . . . . . . . . Denotes the end of changed text within a section.

    ____________________

    27.1 Policy

    27.2 Scope

    27.3 Applicability

    27.4 Roles and Responsibilities

    27.5 Definitions

    27.6 Required Work Processes

    Work Process A. General Requirements for Crane Operation

    Work Process B. Procurement and Maintenance of Cranes and Hoisting and Rigging

    Equipment

    Work Process C. Authorization and Qualification to Use Cranes

    Work Process D. Restricted Operations

    Work Process E. Mobile Cranes

    http://www.lbl.gov/ehs/pub3000/CH27.html#27.1http://www.lbl.gov/ehs/pub3000/CH27.html#27.2http://www.lbl.gov/ehs/pub3000/CH27.html#27.3http://www.lbl.gov/ehs/pub3000/CH27.html#27.3http://www.lbl.gov/ehs/pub3000/CH27.html#27.4http://www.lbl.gov/ehs/pub3000/CH27.html#27.4http://www.lbl.gov/ehs/pub3000/CH27.html#27.5http://www.lbl.gov/ehs/pub3000/CH27.html#27.5http://www.lbl.gov/ehs/pub3000/CH27.html#27.6http://www.lbl.gov/ehs/pub3000/CH27.html#27.6http://www.lbl.gov/ehs/pub3000/CH27.html#27.6ahttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6ahttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6bhttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6bhttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6bhttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6chttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6chttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6dhttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6dhttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6ehttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6ehttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6ehttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6dhttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6chttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6bhttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6bhttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6ahttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6http://www.lbl.gov/ehs/pub3000/CH27.html#27.5http://www.lbl.gov/ehs/pub3000/CH27.html#27.4http://www.lbl.gov/ehs/pub3000/CH27.html#27.3http://www.lbl.gov/ehs/pub3000/CH27.html#27.2http://www.lbl.gov/ehs/pub3000/CH27.html#27.1
  • 7/29/2019 Cranes Hoisting and Rigging

    2/25

    Work Process F. Crane Inspections

    Work Process G. Rigging and Other Below-the-Hook Devices and Fixtures

    27.7 Standards

    27.8 Related PUB-3000 Chapters

    27.9 References

    Appendix A. Typical Pre-use Inspection Tags

    ____________________

    27.1 Policy

    Persons involved in crane or hoist operations at Lawrence Berkeley National Laboratory

    (Berkeley Lab) must:

    Be awareof the hazards related to the equipment and the load

    Know the methods for controlling those hazards Follow the proper operating procedures applicable to the type of lift and equipment

    The designated operator must be qualified and authorized to use specific equipment.

    Crane, hoist, and rigging equipment must be procured through the Facilities Division, as

    well as properly inspected, tested, and maintained.

    27.2 Scope

    Berkeley Labs Crane Safety Program is implemented through planning, authorization,

    qualification, and the appropriate use of properly inspected and rated hoisting equipment

    and rigging. Lifting and moving loads with forklifts is covered in PUB-3000, Chapter 28,

    Forklifts and Other Powered Industrial Trucks. Construction operations involving cranes are

    covered in Chapter 10, Construction Safety.

    http://www.lbl.gov/ehs/pub3000/CH27.html#27.6fhttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6fhttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6ghttp://www.lbl.gov/ehs/pub3000/CH27.html#27.7http://www.lbl.gov/ehs/pub3000/CH27.html#27.7http://www.lbl.gov/ehs/pub3000/CH27.html#27.8http://www.lbl.gov/ehs/pub3000/CH27.html#27.8http://www.lbl.gov/ehs/pub3000/CH27.html#27.9http://www.lbl.gov/ehs/pub3000/CH27.html#27.ahttp://www.lbl.gov/ehs/pub3000/CH27.html#27.ahttp://www.lbl.gov/ehs/pub3000/CH27.html#27.9http://www.lbl.gov/ehs/pub3000/CH27.html#27.8http://www.lbl.gov/ehs/pub3000/CH27.html#27.7http://www.lbl.gov/ehs/pub3000/CH27.html#27.6ghttp://www.lbl.gov/ehs/pub3000/CH27.html#27.6f
  • 7/29/2019 Cranes Hoisting and Rigging

    3/25

    27.3 Applicability

    This policy establishes requirements for Berkeley Labs Crane, Hoisting, and Rigging Safety

    Program and applies to work with any crane or hoist operated at Laboratory-owned or -

    leased property, as well as Laboratory-managed field research. This program applies to thefollowing Berkeley Lab personnel:

    1. Employees2. Affiliates3. Construction contractors4. Nonconstruction contractors and vendors

    27.4 Roles and Responsibilities

    27.4.1 Supervisors and Work Leads

    Supervisors must make certain that personnel know how to safely operate cranes and

    hoists, and how to move objects safely. Only those employees who are formally qualified by

    training and certification may operate a crane or hoist. Qualified supervisors or designated

    qualified work leads must enforce the use of safe lifting techniques, and maintain lifting

    equipment in good mechanical and operating condition.

    27.4.2 Crane Manager

    A Berkeley Lab employee must be identified as the Crane Manager for each Laboratory-

    owned crane or hoist (unless it is locked out). The following requirements for the Crane

    Manager apply:

    The identification of the Crane Manager must be made in writing to the Environment,Health & Safety (EH&S) Division Crane Safety Subject Matter Expert (SME),

    [email protected], or Mail Stop 75B0101.

    The Crane Manager must have a valid certificate for the operation of the crane inquestion.

    The Crane Manager is responsible for controlling use of the crane, and limiting use ofthe crane to qualified operators. The Crane Manager is the custodian of any keys or

    other mechanisms for limiting use of the crane.

    The Crane Manager is responsible for maintaining any logbooks used in lieu ofinspection tags.

    mailto:[email protected]:[email protected]:[email protected]
  • 7/29/2019 Cranes Hoisting and Rigging

    4/25

    If a Crane Manager is absent, cranes under his or her control may be used only bypreviously authorized operators, unless a qualified backup Crane Manager has been

    identified to the Crane Safety SME.

    When a Crane Manager vacancy occurs, the Division Safety Coordinator must identify areplacement, and notify the EH&S Crane Safety SME ([email protected], Mail Stop

    75B0101) of the change. The Crane Safety SME will notify the Facilities Division Crane

    Maintenance Vendor to lock all cranes and hoists for which no Crane Manager has been

    identified. These cranes and hoists will be locked in the OFF position until a Crane Manager

    is identified.

    27.4.3 Employees (Operators, Riggers, and Helpers)

    Employees must be appropriately trained, medically qualified, and demonstrate safe

    operation of the cranes they use. For cranes with greater than two-ton capacity, operators

    must possess a valid Berkeley Lab Crane Operators License. Operation of mobile cranes is

    restricted to those who have been certified as competent and qualified mobile crane

    operators by an independent certification agency. All employees involved in hoisting

    operations including riggers, helpers, and observers are required to follow all established

    safety regulations relating to safe lifting and handling techniques.

    27.4.4 Mechanical Engineering Designee

    The Mechanical Engineering Designee will review and approve Engineering Safety Notes for

    lifting fixtures and high-value/high-consequence lifts/moves on behalf of the Engineering

    Division Director and for the Mechanical Engineering Subcommittee of the Safety Review

    Committee. The Mechanical Engineering Designee may approve reasonable engineering

    alternatives not in conflict with the Laboratory Environment, Safety & Health Standards Set.

    He or she is also available to furnish guidance to Laboratory staff, free of charge. Contact

    [email protected] contact the Mechanical Engineering Designee.

    27.4.5 Responsible Designer

    The Responsible Designer is accountable for incorporating the requirements of this chapter

    into the design of lifting fixtures and procedures, and for initiating the required proof

    testing. The Responsible Designer must obtain design approval by means of an Engineering

    Safety Note.

    27.4.6 Customer Management

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]
  • 7/29/2019 Cranes Hoisting and Rigging

    5/25

    Customer Management is accountable for defining and requesting any lift/move;

    determining which lifts are high-consequence/high-value lifts/moves; writing lifting

    procedures where required; providing technical information on relevant characteristics of

    the apparatus, including special lifting fixtures when required; providing suggestions on

    rigging and moving; and assigning someone to represent the customer during planning andcoordination of all aspects of the job being performed. Customer Management can have the

    Facilities Division prepare the Engineering Safety Note and manage the move if requested

    by the customer on the Work Request. Customer Management is also responsible for

    ensuring that lifting devices and lifting fixtures are properly documented and inspected, and

    that they are used and maintained safely.

    27.4.7 Facilities Division Structural Engineering Group Designee

    The Facilities Division Structural Engineering Group Designee will evaluate building floor

    loading, lifting fixtures, and lifting devices for structural adequacy; review and approve

    Engineering Safety Notes for lifting fixtures, lifting devices, and high-consequence/high-

    value lifts on behalf of the Facilities Division and the Safety Advisory Committee (SAC)

    Mechanical Engineering Subcommittee; establish design parameters for all cranes and

    hoists; and provide guidance on wind loading for outdoor moves/lifts. The Facilities Division

    Structural Engineering Group Designee is also available to provide guidance to Laboratory

    staff on these matters, free of charge. [email protected] contact the Facilities

    Division Structural Engineering Group Designee.

    27.4.8 Facilities Division Rigging Supervisor

    The Facilities Division Rigging Supervisor or his or her designee will provide guidance and

    supervision for routine lifts when requested, participate in the development and review of

    high-consequence/high-value lifts/moves, and participate in pre-lift meetings.

    27.4.9 Facilities Division Crane Maintenance Vendor

    The Facilities Division Crane Maintenance Vendor will arrange for all inspection, testing, and

    certification of cranes, hoists, and rigging. On request, the subcontractor will also arrangefor the testing and certification of lifting devices and lifting fixtures. Call ext. 7667 or e-mail

    [email protected] contact the Crane Maintenance Vendor.

    27.4.10 Facilities Division Maintenance Manager

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]
  • 7/29/2019 Cranes Hoisting and Rigging

    6/25

    The Facilities Division Maintenance Manager establishes the scope of work for the Facilities

    Division Crane Maintenance Vendor. Additionally, the Maintenance Manager ensures (by

    using technical advice from the Crane Maintenance Vendor) that Laboratory purchases of

    crane, hoist, and rigging equipment, components, and devices are traceable (through

    documentation) to a reputable U.S. manufacturer.

    27.4.11 EH&S Division Crane Safety SME

    The EH&S Division Crane Safety SME manages this program. Furthermore, the SME will

    review all high-consequence/high-value lift/move Engineering Safety Notes for conformance

    to the Crane, Hoisting and Rigging Program Requirements, and will participate in pre-lift

    meetings for high-consequence/high-value lifts/moves. [email protected]

    contact the Crane Safety SME.

    27.4.12 Person In Charge

    The Person In Charge (PIC) is the (customer) manager, engineer, or other responsible

    person (other than the operator) appointed to be responsible for the safe handling of high-

    consequence/ high-value loads.

    27.5 Definitions

    Crane A machine that is used for lifting and lowering a load vertically and moving it

    horizontally, and that has a hoisting mechanism as an integral part of it

    Engineering Note A detailed description of a (fixture) design; or a detailed description

    of a high- consequence/ high- value lift/move, including protection of the load, rigging, and

    method(s) of transport5

    High-Consequence/High-Value Lift/Move A designation of parts, components,

    assemblies, or lifting operations by the customer (i.e., the manager who requires the items

    to be moved) or a program organization, because the effect of those items falling from the

    crane, or colliding with other objects, could:

    Cause damage in excess of $500,000o This requirement does not apply to routine movements of shielding blocks

    performed by members of the professional rigging crew

    Cause significant work delay or programmatic impact Cause undetectable damage resulting in future operational or safety problems

    mailto:[email protected]:[email protected]:[email protected]:[email protected]
  • 7/29/2019 Cranes Hoisting and Rigging

    7/25

    Result in significant release of radioactivity or other undesirable conditions Present a potentially unacceptable risk of personnel injury or property damage

    In addition, any lift/move that requires the simultaneous use of both the main and auxiliary

    hoists of a given crane or the simultaneous use of two cranes shall be considered a high-consequence/high-value lift/move.

    Hoist A device that applies a force for lifting and lowering.

    Lifting Device A device used below the hoisting hook, other than a sling, for attaching

    loads to a hoist. These devices are arranged into four categories:

    Structural and Mechanical Lifting Devices (e.g., spreader bars, plate clamps, grippingdevices, etc.)

    Vacuum Lifting Devices Close Proximity Lifting Magnets Remotely Operated Lifting Magnets

    Lifting Fixture A fixture used below the hoisting hook designed and engineered for

    lifting a specific item

    Mobile Crane A crane system fixed to a vehicle (typically a truck)

    Overhead Crane

    A crane system fixed to a structure, including but not limited to bridgecranes, monorail cranes, gantry cranes, and jib cranes

    Rigging The hardware or equipment used to safely attach a load to a hook or lifting

    device. The art or process of safely attaching a load to a hook by means of an adequately

    rated and properly applied sling and related hardware

    27.6 Required Work Processes

    Work Process A. General Requirements for Crane Operation

    The work flowchart below provides a step-by-step overview of crane and hoist operations

    requirements (gohereto download a PDF of the flowchart):

    http://www.lbl.gov/ehs/pub3000/CH27-CraneProcess.pdfhttp://www.lbl.gov/ehs/pub3000/CH27-CraneProcess.pdfhttp://www.lbl.gov/ehs/pub3000/CH27-CraneProcess.pdfhttp://www.lbl.gov/ehs/pub3000/CH27-CraneProcess.pdf
  • 7/29/2019 Cranes Hoisting and Rigging

    8/25

    The following rules apply to all use of crane and hoist operations at Berkeley Lab.

    Whoever needs to move a load must:o First determine the value of the load and consequences of a failed moveo Determine if the load needs to be moved by a craneo Determine who can operate the crane

  • 7/29/2019 Cranes Hoisting and Rigging

    9/25

    Loads meeting the definition of High-Consequence/High-Value Lifts/Moves or otherrestricted operations (see Work Process D) require more detailed planning and may

    require the lift to be performed by the Facilities Division Riggers.

    Operators must be authorized by Line Management to use cranes. Operators must be authorized by the Crane Manager to use a specific crane. Operators must be qualified to use the type of crane they intend to use. Operators must plan each lift, taking into account the path of travel to avoid contact

    with personnel and objects.

    Loads meeting the definition of High-Consequence/High-Value Lifts/Moves or otherrestricted operations (see Work Process B) require more detailed planning and may

    require the lift to be performed by the Facilities Division Riggers.

    Operators must inspect the crane and associated rigging prior to using the crane. Cranes and rigging found to be deficient must be taken out of service, and cannot be

    used unless repaired and recertified by the Facilities Division Crane MaintenanceVendor.

    Cranes and rigging must be rated to lift the intended load; no load (including rigging,devices, and lifting fixtures) may exceed the limits of the crane and rigging. If an

    employee is unsure of the weight of a load, or if the load weight exceeds 75% of the

    cranes capacity, contact the Facilities Division Rigging Supervisor for assistance.

    Crane testing by the Facilities Division Crane Service contractor is the only exception

    to this rule.

    Operators are responsible for ensuring that the load is properly rigged to avoidshifting during the lift. Test lifts of less than one foot from the ground to check forload shifting are permitted.

    All personnel who are operating a crane or hoist, are participating in the lift, or arelocated within 15 feet of the vertical plane of the load where the undercarriage of

    the bridge is more than 12 feet from the ground must wear hard hats. Post or

    barricade the area as needed.

    Sturdy work gloves must be worn when handling wire rope or loads with rough orsharp edges or splinters.

    Suspended Loads

    These rules apply to operators of suspended loads:

    Test brakes under load when load is 80% of the crane's rated load. Raise the load afew inches and apply the brakes.

  • 7/29/2019 Cranes Hoisting and Rigging

    10/25

    Ensure loads are never lowered below the point where less than two full wraps ofrope remain on the hoisting drum.

    Do not allow hoisting chains or ropes to kink or twist, or to wrap around the load. Attach the load to the load block hook ONLY by means of slings or other approved

    devices; NEVER wrap the hoist rope around the load. Ensure loads are well secured and properly balanced in the sling or lifting device

    before it is lifted more than a few inches.

    Avoid suddenly accelerating or decelerating the moving load. Do not allow the load to contact obstructions. Do not allow loads moved with any material-handling equipment to pass over any

    personnel.

    Select the load path to eliminate the possibility of injury to employees should thematerial-handling equipment fail.

    Do not permit work on suspended loads. Rest the load on adequate cribbing if itneeds to be worked on.

    Never leave a suspended load unattended nor leave the controls while the load issuspended. Lower the load to the floor or the working surface or onto cribbing, and

    secure the material-handling equipment before leaving the load unattended.

    Component Failure or Unintended Movement

    If any component fails during a lift, or if there is any uncontrolled or unintended motion of

    the load during the lift, the lift must be terminated immediately in the safest manner

    possible. Immediately notify the Crane Manager of the component failure. Contact EH&S

    and the Facilities Division Rigging Supervisor.

    Lifting may only resume after the failure or unintended motion has been investigated, and

    appropriate corrective steps have been implemented.

    Securing Cranes

    Any electric-powered crane, when not attended by a qualified operator during an entire shift

    and off-hours, must be secured by locked controls or equivalent means to prevent access to

    the crane, such as locking the doors or locking up radio controls. Only the Crane Manager or

    another qualified and authorized user of the secured crane may have control of the locking

    mechanism.

    Work Process B. Procurement and Maintenance of Cranes and Hoisting and Rigging

    Equipment

  • 7/29/2019 Cranes Hoisting and Rigging

    11/25

    Approval from the Facilities Division Maintenance Manager must be obtained before

    purchasing hoists or cranes, or lifting equipment such as shackles, clevises, wire rope or

    fabric slings, or spreader bars (strongbacks). Procurement will not process any purchase

    orders for such equipment without this approval. The preferred method for ordering hoisting

    and rigging equipment is to request that the Facilities Division Maintenance Manager ordesignee (ext. 7667) order the items, using an account number provided by the requester.

    If used equipment is procured, it must be inspected and certified to meet all applicable

    standards in force at the time of the acquisition.

    For Berkeley Labdesigned and/or fabricated lifting devices, see Work Process G.

    When equipment is received, the recipient must contact the Facilities Division Crane

    Maintenance Vendor (ext. 7667 [email protected]) to have the equipment inventoried

    for routine inspection and maintenance. All hoisting and rigging equipment (except when

    impractical, e.g., shackles, swivel lifting rings, etc.) used at the Laboratory must have a

    Laboratory proof-load tag attached with a current inspection sticker. The user, supervisor,

    and operator are directly responsible for verifying the presence of current, proper tagging of

    hoisting and rigging equipment prior to use.

    Work Process C. Authorization and Qualification to Use Cranes

    All crane use must be authorized by an employees Job Hazards Analysis (JHA), and by the

    Crane Manager for the particular crane(s) to be operated. The Crane Manager is a qualified

    crane operator who has been designated as the individual responsible for the safe operation

    of a specific crane. Before operating a crane in an area for the first time or in a new

    application, employees must discuss the proposed crane use with the Crane Manager and

    obtain approval. The Crane Manager will determine whether the operator is familiar with the

    controls for that particular crane and knows how to properly rig loads, and will verify that

    crane use will not conflict with other operations in the area.

    Cranes may also be operated by qualified Crane Service personnel who have been

    authorized by either a JHA (for the on-site Facilities Division Crane Maintenance Vendor) ora SWJHA, and have been subcontracted to install, maintain, or repair cranes.

    Qualifications, Training, Certification, and Approval Requirements for Overhead Crane

    and Hoist Operators

    mailto:[email protected]:[email protected]:[email protected]:[email protected]
  • 7/29/2019 Cranes Hoisting and Rigging

    12/25

    The operation of overhead cranes and hoists is restricted to trained personnel who have

    completed Berkeley Labrequired training, and who have been certified in accordance with

    the requirements of this chapter. This includes the operation of cranes without a load for

    any reason. Requirements for operating mobile cranes can be found in Work Process F.

    To become certified for operating cranes up to a two-ton capacity, the following

    requirements must be met:

    All prospective operators of cranes and hoists up to a two-ton capacity must meetthe health requirements that would entitle them to operate a motor vehicle in the

    state of California. Individuals who do not hold a valid drivers license must be

    examined and approved by Health Services at Berkeley Lab.

    The prospective operator must complete EHS0210, Crane/Hoist Operator 2 Tonsor Less. This course includes hands-on instruction, and a certificate will be issued

    after the successful completion of the course.

    Note that crane and hoist operators with this certification may NOT operate cranes

    or hoists with a capacity of greater than two tons to lift loads of less than two tons

    or without any load.

    To become certified for operating overhead cranes or hoists with a capacity of greater than

    two tons, the following is required:

    All prospective crane operators must complete an application and must pass amedical examination and/or review of medical information on file at Health Services

    prior to training. The application must identify a qualified crane operator who will

    provide hands-on instruction and close supervision during an initial training period.

    The supervisor and the operator who will provide the instruction must sign the

    application and agree to the initial training. If the prospective operator has prior

    experience operating cranes, he or she may be examined and certified without an

    initial training period.

    The prospective operator must complete EHS0206 (Crane/Hoist Operator Greaterthan 2 Tons). Upon completion ofthis classroom training, a learners permit is issued

    when needed, and the individual may operate cranes and hoists under the direct

    supervision of the operator identified on the application. The learners permit will

    expire no later than 60 days from the date of issuance.

    When the prospective operator is ready, he or she may contact an overhead-cranepractical-examination instructor to be examined on the operation of the specific

  • 7/29/2019 Cranes Hoisting and Rigging

    13/25

    crane to be operated most frequently. A list of qualified overhead-crane practical-

    examination instructors is maintained by the EH&S Division Training Group.

    Crane operators must renew their training every three years, and must be medically

    recertified every three years.

    Work Process D. Restricted Operations

    High-Consequence/High-Value Lifts and Moves

    The customer (i.e., the manager who requires the items to be moved) or a program

    organization designates parts, components, assemblies, or lifting operations as high-

    consequence/high-value lifts/moves, because the effect of those items falling from the

    crane, or colliding with other objects, could:

    Cause damage in excess of $500,000o This requirement does not apply to routine movements of shielding blocks

    performed by members of the professional rigging crew.

    Cause significant work delay or programmatic impact Cause undetectable damage resulting in future operational or safety problems Result in significant release of radioactivity or other undesirable conditions Present a potentially unacceptable risk of personnel injury or property damage

    In addition, any lift/move that requires the simultaneous use of both the main and auxiliaryhoists of a given crane or the simultaneous use of two cranes must be considered a high-

    consequence/high-value lift/move.

    High-Consequence/High-Value Lift/Move Requirements

    A detailed, step-by-step procedure in the form of an Engineering Note must be prepared for

    each high-consequence/high-value lift/move. This requirement covers lifts and moves

    performed with forklifts or cranes. An Engineering Note template may be obtained from the

    Engineering Division athttps://dcc.lbl.gov/dcc/EngNotes.php. While high-

    consequence/high-value lift procedures are customarily prepared for one-time use, general

    high-consequence/high-value lift procedures may be employed to accomplish routine,

    recurrent high-consequence/high-value lift operations. For example, a general high-

    consequence/high-value lift procedure may be applied to lift shielding blocks or a frequently

    lifted item. Examples can be found through the search page of the Berkeley Lab Engineering

    https://dcc.lbl.gov/dcc/EngNotes.phphttps://dcc.lbl.gov/dcc/EngNotes.phphttps://dcc.lbl.gov/dcc/EngNotes.phphttps://dcc.lbl.gov/dcc/EngNotes.php
  • 7/29/2019 Cranes Hoisting and Rigging

    14/25

    Note Repository athttps://dcc.lbl.gov/dcc/EngNotes.php(enter the keywords high value

    in the Title 3 field).

    The customer, i.e., the Laboratory manager who requires the item to be moved, is

    responsible for preparing the high-consequence/high-value lift/move Safety EngineeringNote. The customer can discharge this responsibility by indicating on the Facilities Work

    Request that the scope of work should include preparation of the Engineering Safety Note

    and management of the move. It is the responsibility of the customer to notify all personnel

    whose approval is required early in the process. See High-Consequence/High-Value Move

    Lift/Move Approval below.

    Approvers have special expertise and are available to provide guidance during the design of

    the lifting procedure. Please allow sufficient time for the review-and-approval process. There

    is no charge for the review-and-approval process.

    The procedure must contain the following:

    Identification of the item to be moved Identification of the Laboratory manager or engineer who is responsible for planning

    the lift

    Identification of the rigging supervisor or designated qualified rigger (other than theequipment operator) who will be the Person In Charge (PIC) of all aspects of the lift

    while the load is suspended

    Special precautions Weight of the item Total hook load (all component parts of the item plus tackle and load-measuring

    devices)

    Determination of the center of gravity A list of each piece of equipment and each accessory (e.g., slings, spreader bars,

    yokes) to be used in the lift

    Each accessory must be identified by type and rated capacity If a portable item to be used has no manufacturers serial number, a Berkeley Lab

    identification number must be assigned and affixed to the item

    Surveillance procedures, checkpoints, and estimated instrument readings (if used)must be listed to enable confirmation that the lift is proceeding as planned

    Calculation of stresses to be generated in the item during lifting and determination ofthe adequacy and proper labeling of the attachment points of the item to be lifted.

    A rigging sketch or sketches that include the following:

    https://dcc.lbl.gov/dcc/EngNotes.phphttps://dcc.lbl.gov/dcc/EngNotes.phphttps://dcc.lbl.gov/dcc/EngNotes.phphttps://dcc.lbl.gov/dcc/EngNotes.php
  • 7/29/2019 Cranes Hoisting and Rigging

    15/25

    o Lifting pointso Load vectors at all stages of the lift/moveo Sling angles at all stages of the lift/moveo Accessories usedo Method(s) of attachmento Method of rotating about either horizontal axis, if applicableo Other factors affecting the capacity of the equipment or accessorieso Identification of the capacity (or limit) of equipment and loado Identification of the expected load in each item of equipment and each

    accessory

    A load-path sketch of the load path with the expected height of the load at eachpoint in the lift

    Where appropriate, floor loading diagrams are to be included to provide for settingthe load down at any point in the path if that should be necessary.

    A travel sketch, either as a part of the load-path sketch or a separate sketch,indicating the planned travel path, and lifting and travel speeds

    Where clearances are an issue, a detailed drawing with verified dimensions thatdemonstrates the lift can be accomplished as planned

    An assessment of wind loading and weather concerns for all outdoor work Obtain assistance from the Facilities Division Structural Engineering Group for wind

    loading concerns.

    A checklist detailing each step of the procedure, with each step initialed by theLaboratory manager or engineer responsible for the planning of the lift

    A sign-off sheet where all personnel involved in the lift verify that they are familiarwith the contents of the procedure

    Load tests and practice lifts, if required Verification that all primary and secondary hoisting equipment is within the current

    inspection and test time requirements as specified in this chapter (for example,

    yearly periodic inspections and certification)

    High-Consequence/High-Value Lift/Move Approval

    The procedure must be reviewed and approved by:

    Customer management The Engineering Division Mechanical Engineering Department Designee The Facilities Department Structural Engineering Group The Facilities Department Rigging Supervisor

  • 7/29/2019 Cranes Hoisting and Rigging

    16/25

    The EH&S Division DesigneeAll reviewers should be consulted early in the process to ensure their concerns are

    addressed, avoiding the need for later revisions to the procedure.

    Unanticipated conditions may require on-the-spot changes of the lift procedure. Approvers

    of the lift procedure should be present during the lift or at least immediately available to

    approve changes. Changes must be recorded on the procedure and initialed by all available

    approvers before they are implemented.

    Personnel Participating in High-Consequence/High-Value Lifts/Moves

    Each person involved in a high-consequence/high-value lift/move must be familiar with the

    procedure before beginning work. A pre-lift meeting with all participating personnel must be

    held before the lift. All participating personnel must initial the procedure sign-off sheet to

    verify that they are familiar with the procedure.

    Cab-Operated Cranes

    Operation of cranes from a cab is restricted to professional riggers. The following rules apply

    to cab-operated cranes:

    Do not store personal belongings (including necessary clothing) in a manner thatinterferes with operations.

    Store other necessary equipment (tools, oil cans, waste, extra fuses, etc.) in thetoolbox. Do not store equipment loosely in or about the cab.

    Heavy Lifts

    Heavy lifts should be made by the professional rigging crew that performs such work

    routinely. Where there is a need for other personnel to lift loads over 10,000 lb., and lifts

    exceeding 75% of the cranes maximum capacity, the proposed lift must be reviewed with

    and approved informally by the supervisor of the professional rigging crew or his or her

    designee.

    Tilting Loads

    Using a crane to tilt a load (standing up a load that is lying down or vice versa) carries a

    significant risk of shock-loading the crane or losing control of the load. When such

    operations involve loads that exceed 50% of the rated capacity of the crane, they must be

  • 7/29/2019 Cranes Hoisting and Rigging

    17/25

    reviewed by and may be performed only with the informal approval of the supervisor of the

    professional rigging crew or his or her designee. If two hooks are required to tilt the load,

    follow the high-consequence/high-value lift procedures listed above.

    Work Process E. Mobile Cranes

    The operation of mobile cranes is restricted to those who have been certified as competent

    and qualified mobile crane operators by an independent certification agency. The Facilities

    Division Riggers have authorized and qualified mobile crane operators.

    Mobile crane operations for construction have additional requirements, which are found in

    PUB-3000, Chapter 10. For the purpose of the Berkeley Lab Cranes, Hoisting, and Rigging

    Program, small truck-mounted jib cranes with capacities of less than 2 tons are not

    considered mobile cranes. Mobile crane operations are conducted in accordance with all

    applicable Occupational Safety and Health Administration (OSHA) (and Cal/OSHA for

    construction) requirements.

    Any mobile crane, when not attended by a qualified operator during an entire shift or during

    off-hours, must be secured by locked controls or equivalent means to prevent access to the

    crane, such as locking the doors or locking up radio controls. Only the Crane Manager or

    another qualified and authorized user of the secured crane may have control of the locking

    mechanism.

    Work Process F. Crane Inspections

    Each crane or hoist must be inspected by a qualified crane operator before use, during any

    given work shift. The inspection can be documented either on a tag attached to the crane

    controls or in a log that is kept with the key to the crane controls. If the crane is not used

    during any shift, it does not need to be inspected. However, each crane must be given a

    documented operator inspection at least once a month whether or not it is used during the

    month of the inspection. Inspection tags will be collected by the Facilities Division Crane and

    Hoist Services Contractor and kept on record. Where applicable, crane inspection logs will

    be reviewed by the Crane and Hoist Services Contractor. Typical crane inspection checklistsare shown inAppendix Aof this PUB-3000 chapter.

    All other required equipment inspections and tests are performed by the Facilities Division

    Crane and Hoist Services Contractor. Equipment and the frequency of equipment

    inspections and tests are listed in a Facilities Division database as required by applicable

    http://www.lbl.gov/ehs/pub3000/CH10.htmlhttp://www.lbl.gov/ehs/pub3000/CH10.htmlhttp://www.lbl.gov/ehs/pub3000/CH27.html#27.ahttp://www.lbl.gov/ehs/pub3000/CH27.html#27.ahttp://www.lbl.gov/ehs/pub3000/CH27.html#27.ahttp://www.lbl.gov/ehs/pub3000/CH27.html#27.ahttp://www.lbl.gov/ehs/pub3000/CH10.html
  • 7/29/2019 Cranes Hoisting and Rigging

    18/25

    regulations and/or standards. Facilities Division Crane Maintenance Vendor work orders are

    automatically generated monthly and are based on information in the database.

    Work Process G. Rigging and Other Below-the-Hook Devices and Fixtures

    The crane operator is responsible for verifying that the load is properly rigged. The crane

    operator must also take the following precautions when performing work:

    Thoroughly inspect rigging before use (document the inspection on the Daily CraneInspection Tag).

    Remove defective rigging from service. DO NOT USE and DO NOT REPAIR defectiverigging.

    All other required rigging inspections and tests are performed by the FacilitiesDivision Crane and Hoist Services Contractor. The frequency of these various

    inspections and tests are detailed in Facilities Division work orders.

    Only use slings in accordance with the manufacturers recommendations. Use engineered attachment points and standard hardware (swivel lift rings, shackles,

    and nylon slings) wherever possible.

    Verify that all slings and hardware are rated for more than the expected load and areappropriate for the intended type of load and configuration.

    Verify that all slings and special lifting hardware have current Berkeley Labinspection tags.

    Never shorten slings with knots, bolts, or other makeshift devices. Never load rigging in excess of its rated capacities. Use padding to protect natural fiber or synthetic slings from damage (e.g., contact

    with sharp edges).

    Verify loads are balanced to prevent slippage (e.g., when using a basket hitch). Remove slings from a load when the load is not resting on the sling. Contact the EH&S Crane and Hoist Subject Matter Expert ([email protected]) or

    the Facilities Division Crane Maintenance Vendor (ext. 7667) before rigging is used in

    any manner or environment (e.g., used in close proximity with corrosives or

    degrading chemicals, operated in temperature extremes of20F or +180F, etc.)

    that may compromise its construction or strength.

    Inspection and Testing of Lifting Devices

    Each division is responsible for the safety and pre-use inspection of its lifting devices

    (such as screw pin shackles, hoist rings, commercial equipment, etc.) and for its lifting

    fixtures (such as spreader bars, special slings, equipment designed at Berkeley Lab, etc.).

    mailto:[email protected]:[email protected]:[email protected]
  • 7/29/2019 Cranes Hoisting and Rigging

    19/25

    Berkeley Lab proof-load tags and inspection stickers must be current, where

    applicable. Special-purpose lifting fixtures must be marked with a Laboratory equipment

    number and labeled to identify applicable Engineering Safety Notes for fixture design and/or

    high-consequence/high-value lifts/moves.

    All lifting fixtures designed at the Laboratory must be proof-tested to twice their maximum

    rated loads before being placed in service. A Non-Destructive Examination (NDE) is required

    after the proof test. The exact type of NDE must be specified in the Engineering Safety Note

    for the lifting fixture. The rated capacity must be marked on the lifting fixture so that it is

    clearly visible to the equipment operator.

    Order commercially available lifting fixtures through the Facilities Division Maintenance

    Manager or Designee to assure they are ordered with a certificate of proof load testing. For

    commercial lifting fixtures without certified load ratings, an Engineering Safety Note must

    be written to determine the safe load capacity and furnish guidance for load testing.

    Where the lifting fixture cannot be proof-tested because it is an integral part or component

    of the experimental device, equivalent alternative safety precautions acceptable to the

    Mechanical Engineering designee must be described in the Engineering Safety Note, which

    delineates the lift procedure.

    All lifting device pins of 5 cm (2 in.) in diameter or larger must have a magnetic-particle

    inspection before they are placed in service. These pins are always part of a lifting device or

    fixture. Make arrangements with the Facilities Division Crane Maintenance Vendor, ext.

    7667, or theWork Request Center, ext. 6274, to have lifting fixtures inspected.

    Active lifting devices and fixtures must be examined by an NDE at least once every four

    years (or upon request), using magnetic-particle detection or other appropriate methods.

    Make arrangements to have lifting fixtures inspected with the Facilities Division Crane

    Maintenance Vendor, ext. 7667, or contact theWork Request Center, ext. 6274. Records

    must be maintained by the Facilities Division and NDE organizations. Inactive lifting devices

    and fixtures must be clearly marked STOP: DO NOT USE, and must be load tested and

    certified prior to renewed use.

    The Responsible User must ensure that:

    Proof-testing is performed by the Facilities Division on all lifting fixtures designed atthe Laboratory, before they are placed in service

    Adequate test records are kept

    http://fac.lbl.gov/Facilities/http://fac.lbl.gov/Facilities/http://fac.lbl.gov/Facilities/http://fac.lbl.gov/Facilities/http://fac.lbl.gov/Facilities/http://fac.lbl.gov/Facilities/http://fac.lbl.gov/Facilities/http://fac.lbl.gov/Facilities/
  • 7/29/2019 Cranes Hoisting and Rigging

    20/25

    Lifting devices and fixtures are used and maintained correctlyThe Responsible Designer must obtain design approval by means of an Engineering Safety

    Note, as described below. For equipment designed at the Laboratory, the Responsible

    Designer must provide the user with the information required to operate the lifting device orfixture safely. The Facilities Division will provide a test report to the user upon request.

    Design of Lifting Fixtures

    A qualified engineer must be designated to be responsible for the design, fabrication, and

    testing of lifting fixtures not purchased commercially. The actual physical testing usually will

    be performed by the Facilities Division in accordance with the written test procedure

    specified by the Project Engineer.

    All lifting fixtures designed or fabricated at the Laboratory must be covered by an

    Engineering Safety Note. The Engineering Safety Note must include the calculation of lifting

    fixture stresses and deflections, and must be reviewed and approved by:

    The Responsible Designer Customer Management The Engineering Division Mechanical Engineering Department designee The Facilities Division Planning, Design & Construction Department, Structural

    Engineering Group designee

    The Facilities Division Plant Operations Department Rigging Supervisor The EH&S Division designee

    The design stress for lifting fixtures or lifting attachment points must not exceed one-fifth

    the ultimate strength of the material at its operating temperature. If welded fabrication is

    used, the design stress must take into consideration any weakening effects of welding, such

    as those that occur in aluminum alloys.

    If practical, avoid welding in the fabrication of lifting fixtures. If welding must be used,

    design and fabrication in conformance with the latest standards of the American WeldingSociety (AWS) are required. Careful, thoughtful design and follow-up are required.

    Follow these rules for all lifting fixtures:

    All welds in lifting fixtures must be certified welds, performed by certified welders,and inspected and certified by certified weld inspectors.

  • 7/29/2019 Cranes Hoisting and Rigging

    21/25

    If at all possible, do not allow welds to be subjected to tearing loads. Stresses inwelds must be substantially uniform.

    Where possible, design lifting fixtures so that the main loads are carried only bystructural members, plates, or shear pins rather than by welds. Examine this

    possibility carefully. Proof-test lifting fixtures to twice the maximum rated load. Follow by a

    nondestructive examination. X-ray primary load-carrying welds and welds in

    tension, or perform other suitable subsurface crack-detection examinations.

    The screw-thread engagement required for conservative development of the fullstrength of a screw fastener depends upon the screw-fastener material and the

    material of the threaded member.

    o If the fastener is made of the same material as the female threaded member e.g., a low-carbon steel bolt and a hole threaded into low-carbon steel

    an engagement of at least 1 diameters is required.o A hardened steel screw (Allen screw) in mild steel requires at least 2

    diameters of engagement.

    o A low-carbon screw fastener, threaded into a tapped hole in aluminum alloy,copper, or cast iron must have a threaded engagement of 1 diameters.

    o Other material combinations must be approved by the Mechanical EngineeringDepartment designee.

    Safety hoist rings may be used to make lifts up to their rated load whenscrewed 2 hoist-ring bolt diameters into materials such as aluminum alloy,

    copper, or cast iron. When special high-strength bolts are required, test any bolt used as part of

    Laboratory-designed lifting fixtures or pickup devices to two times its rated load. A

    crack-detection inspection must be performed after the load test to ensure integrity.

    Try to maintain a supply of tested bolts in the event that one is lost, or better yet, to

    have the bolt on a permanent lanyard. Once a lifting device or fixture has been

    delivered to the user, the user is responsible for ensuring that the proper bolt is

    inserted to the proper depth and correctly torqued.

    When the lifting fixture also serves as a shipping container or frame holding theexperimental device during transport, specify tie-down requirements and otherspecial shipping requirements to ensure the integrity of the experimental device,

    e.g., anticipate flexing of the truck bed, acceleration due to bumps and potholes,

    and/or vibration.

    Label lifting attachment points adequately to ensure proper and safe use of thefixture.

  • 7/29/2019 Cranes Hoisting and Rigging

    22/25

    Any deviation from these rules requires equivalent alternative safety measures that have

    been explicitly approved by the Mechanical Engineering Department designee.

    Single-Bolt Pickup Devices

    When equipment is designed to be crane-lifted at a single point with a single-bolt pickup

    device, the vertical lifting load through the screw thread of the bolt must be in line with the

    axis of the bolt so the load will remain level when it is lifted. With this bolt alignment, the lift

    will be through the center of gravity and will be safer, since the load will not tilt or kick out

    when it is lifted. A single-bolt pickup device must be used, such as a safety hoist ring or an

    equivalent in-house device that is carefully designed and maintained. The threaded

    engagement must comply with the requirements in the Design of Lifting Fixtures section,

    above.

    When a load is to be crane-lifted by slings from a crane hook through two, three, or four

    pickup points located at the corners of the load, and without the use of a spreader bar, the

    forces at the lift points are nonvertical. Again, a single-bolt pickup device, such as a safety

    hoist ring or an equivalent in-house device that is carefully designed and maintained must

    be used at each pickup point.

    Eyebolts without shoulders are not allowed for use in lifting any load. Eyebolts with

    shoulders are permitted for lifting loads when the following conditions are met:

    These devices shall be rated for the load and approved for the application, e.g., acarbon steel eyebolt rated at 1,500 lb. Threaded into a carbon steel block.

    The load is in line with the axis of the eyebolt, and side loads are minimal (aspreader bar may be required).

    The thread engagement is at least 2 bolt diameters. The eyebolts are torqued to amanufacturers recommendations, if given, or another reasonable torque

    substantially greater than finger tight. Angled sling usage is allowable if a

    manufacturers recommendations for load reduction are given.

    The use of unrated eyebolts or eyebolts in applications not specifically approved by themanufacturer must be specifically approved by an Engineering Safety Note.

    27.7 Standards

    29 CFR 1910, Occupational Safety and Health Standards for General Industry, Subpart N

    Materials Handling and Storage, Paragraphs:

  • 7/29/2019 Cranes Hoisting and Rigging

    23/25

    1910.179, Overhead and Gantry Crane

    1910.180, Crawler, Locomotive and Truck Cranes

    1910.184, Slings

    29 CFR 1926, Occupational Safety and Health Standards for Construction, 1926 Subpart CC,

    Paragraph 1926.251, Rigging Equipment for Material Handling

    California Code of Regulations, Title 8, Subchapter 4, Construction Safety Orders (as it

    pertains to cranes used in construction work)

    27.8 Related PUB-3000 Chapters

    Chapter 24, Environment, Health and Safety (EH&S) Training Chapter 10,Appendix A, Code of Safe Practices

    27.9 References

    ASME HST-1M, PerformanceStandard for Electric Chain Hoists ASME HST-2M, Performance Standard for Hand Chain Manually Operated Chain

    Hoists

    ASME HST-3M, Performance Standard for Manual Lever Operated Chain Hoists

    ASME HST-4M, Performance Standard for Electric Overhead Wire Rope Hoists ASME HST-5M, Performance Standard for Air Chain Hoists ASME HST-6M, Performance Standard for Air Wire Rope Hoists Crane Manufacturers Association of America, Inc. (CMAA) Specification No. 61,

    Electric Overhead Traveling (EOT) Cranes

    CMAA Specification No. 70, Specifications for Top Riding Bridge and Gantry TypeMultiple Girder Electric Overhead Traveling Cranes

    CMAA Specification No. 74, Specification for Top Running and Under Running SingleGirder Electric Traveling Cranes Utilizing Under Running Trolley Hoists

    DOE-STD-1090-2004, Hoisting & Rigging

    Appendix A. Typical Pre-use Inspection Tag

    http://www.lbl.gov/ehs/pub3000/CH24.htmlhttp://www.lbl.gov/ehs/pub3000/CH24.htmlhttp://www.lbl.gov/ehs/pub3000/CH24.htmlhttp://www.lbl.gov/ehs/pub3000/CH10-AppA.htmlhttp://www.lbl.gov/ehs/pub3000/CH10-AppA.htmlhttp://www.lbl.gov/ehs/pub3000/CH10-AppA.htmlhttp://www.lbl.gov/ehs/pub3000/CH10-AppA.htmlhttp://www.lbl.gov/ehs/pub3000/CH24.html
  • 7/29/2019 Cranes Hoisting and Rigging

    24/25

    Figure A-1. Front of Daily Crane Inspection Tag

  • 7/29/2019 Cranes Hoisting and Rigging

    25/25

    Figure A-2. Back of Daily Crane Inspection Tag

    _____________________

    >

    http://www.lbl.gov/ehs/pub3000/CH26.htmlhttp://www.lbl.gov/ehs/pub3000/CH26.htmlhttp://www.lbl.gov/ehs/pub3000/pub3000c.htmlhttp://www.lbl.gov/ehs/pub3000/pub3000c.htmlhttp://www.lbl.gov/ehs/pub3000/pub3000c.htmlhttp://www.lbl.gov/ehs/pub3000/CH28.htmlhttp://www.lbl.gov/ehs/pub3000/CH28.htmlhttp://www.lbl.gov/ehs/pub3000/CH28.htmlhttp://www.lbl.gov/ehs/pub3000/pub3000c.htmlhttp://www.lbl.gov/ehs/pub3000/CH26.html