Agenda
Site certification Look back Certification requirements Current status, what’s ahead
CR 470 Widening Corridor plan Leesburg segment Current Status, what’s ahead
Site Certification
Duke Energy Site Readiness Program McCallum Sweeney Consulting (MSC)
Great site – lots of strengths, few weaknesses Pursue “Site Certification”
Growing trend in Economic Development Lets developers know site is shovel ready State Program or 3rd party certifier
Site Certification with MSC - $29,500
Site certification (Cont)
Site certification requirements Extensive list of requirements
3 page summarized list 10 page detailed list
Acceptable size, 100 acre minimum Immediately available, properly zoned Utilities available now or within 6 months Approved master plan, protective covenants Boundary survey Preliminary land sale or lease agreement
Site certification (Cont)
Site certification requirements (cont) Environmental Due Diligence
Wetland delineation Endangered species certification Historical/Archaeological survey Phase I, Environmental Site Assessment Geotechnical/soil suitability evaluation
CR 470 Site Certification Cost
PARCEL 323 AC 513 AC 596 AC 719 AC
GEOTECH
Andreyev Engr $10,970 $16,345 $20,150 $25,525
ARCHAEOLOGICAL
SouthArc, Inc $8,375 $14,500 $17,265 $23,750
HRP $16,830 $28,315 $35,056 $43,149
ESA Assoc $1,800 $3,600 $5,400 $7,200 withdrew
WETLANDS DELINEATION
HRP $36,410 $69,021 $69,021 $127,214
ESA Assoc $16,460 $34,020 $51,580 $48,030
Bio-Tech $9,200 $7,800 $14,100 $18,100
ENDANGERED SPECIES
HRP $7,877 $13,914 $18,686 $23,069
ESA Assoc $8,640 $15,840 $20,880 $23,940
Bio-Tech $8,700 $12,200 $13,700 $15,200
PHASE I ESA
HRP $3,550 $6,186 $7,736 $10,136
ESA Assoc
Bio-Tech
TOTAL $36,435 $60,671 $80,131 $104,151
Site certification (Cont)
Endangered Species Survey – Documented habitat areas Field investigations
Site certification requirement – Clearance letters from FF&WL and USF&WL Mitigation plan executed within 6 months
concerns Gopher tortoise, indigo snakes, eagles, sand
skink, scrub jay
Site certification (Cont)
Sand skink survey – Plan A 2’x2’ cover boards, 40/ac, checked 2/week for 4
weeks, estimated cost for 323 ac -$94,075
Sand Skink survey – Plan B Visual pedestrian survey, submit results Cost - $7,877
Mitigation cost- $30,000 -$60,000/ac Place all other work on hold pending results
Site certification (Cont)
Sand Skink Survey Opted for Plan B Visual survey completed – May No skink sightings Reports to FF&WL and USF&WL Positive indications from FF&WL No response from USF&WL
CR 470 Widening
Leesburg segment – Co line to SR 33 Approximately 4 miles, R/W - $6m, Construction - $21m County project, unfunded Bridge Widening - $8m SR 48 widening -SR 33 to Bridge - $13m
CR 470 Widening
Current Status FDOT-Sumter Co road swap Bridge widening $$ moved by MPO Split Lake County segment Move 2nd segment to construction
CR 470 Widening
What’s ahead TAC approved move to construction Final R/W acquisitions - ~ 2 acres Push for FDOT funding