11
CPA A group of workers is involved in a building project. The table shows the activities involved. Each worker can perform any of the given activities. Activi ty Preceding activity Duration (days) Number of workers A - 3 5 B A 8 2 C A 7 3 D B, C 8 4 E C 10 2 F C 3 3 G D, E 3 4 H F 6 1 I G, H 2 3

CPA A group of workers is involved in a building project. The table shows the activities involved. Each worker can perform any of the given activities

Embed Size (px)

Citation preview

Page 1: CPA A group of workers is involved in a building project. The table shows the activities involved. Each worker can perform any of the given activities

CPAA group of workers is involved in a building project. The table shows the activities involved. Each worker can perform any of the given activities.

Activity Preceding activity

Duration (days) Number of workers

A - 3 5B A 8 2C A 7 3D B, C 8 4E C 10 2F C 3 3G D, E 3 4H F 6 1I G, H 2 3

Page 2: CPA A group of workers is involved in a building project. The table shows the activities involved. Each worker can perform any of the given activities

CPAComplete the activity network for the project.

8D

10E

3F

3G

2I

8

7C

B

3A

6H

Activity Preceding activity

Duration (days)

Number of workers

A - 3 5

B A 8 2

C A 7 3

D B, C 8 4

E C 10 2

F C 3 3

G D, E 3 4

H F 6 1

I G, H 2 3

Page 3: CPA A group of workers is involved in a building project. The table shows the activities involved. Each worker can perform any of the given activities

CPAFind the earliest start time and the latest finish time and insert their values in the appropriate boxes.

Duration

3

8 8 3

3 6

210

7C

D

E

F

GB

IA

H

Earliest start time Latest finish time

0

3

3

11

10

10

20

13

23 25

23

23

20

20

1710

12

3

Page 4: CPA A group of workers is involved in a building project. The table shows the activities involved. Each worker can perform any of the given activities

CPAFind the critical path and state the minimum completion time

Duration

3

8 8 3

3 6

210

7C

D

E

F

GB

IA

H

Earliest start time Latest finish time

0

3

3

11

10

10

20

13

23 25

23

23

20

20

1710

12

3

Critical Path: A C E G I and the minimum completion time is: 25 days

Page 5: CPA A group of workers is involved in a building project. The table shows the activities involved. Each worker can perform any of the given activities

CPA

3

8 8 3

3 6

210

7

C

D

E

F

GB

IA

H

0

3

3

11

10

10

20

13

23 25

23

23

20

20

1710

12

3

Activity FloatB 1

D 1

F 4

H 4

Activities A, C, E, G and I are “critical” – they must start on time and end on time for the minimum completion time to be 25 days.

Some activities do not have to start exactly on time and finish exactly on time without affecting the minimum finish time. They have a "float".

Now we can draw a Gantt Chart or Cascade Diagram. This gives us another way of displaying how the activities can be completed. In addition, the diagram can help us to figure out how many workers may be needed to complete the project within the minimum time of 25 days.

Page 6: CPA A group of workers is involved in a building project. The table shows the activities involved. Each worker can perform any of the given activities

CPA

3

8 8 3

3 6

210

7

C

D

E

F

GB

IA

H

0

3

3

11

10

10

20

13

23 25

23

23

20

20

1710

12

3

A C E G I

B

F

D

H

We can draw a Gantt Chart or Cascade Diagram

First set down the Critical Path

Now set down each activityIncluding the float

Page 7: CPA A group of workers is involved in a building project. The table shows the activities involved. Each worker can perform any of the given activities

CPA

3

8 8 3

3 6

210

7

C

D

E

F

GB

IA

H

0

3

3

11

10

10

20

13

23 25

23

23

20

20

1710

12

3

A C E G I

B

F

D

H

We can “shuffle” the activities to determine how many workers are needed to complete the project.

Activity Number of workers

A 5

B 2

C 3

D 4

E 2

F 3

G 4

H 1

I 3

D

H

Page 8: CPA A group of workers is involved in a building project. The table shows the activities involved. Each worker can perform any of the given activities

CPA

3

8 8 3

3 6

210

7

C

D

E

F

GB

IA

H

0

3

3

11

10

10

20

13

23 25

23

23

20

20

1710

12

3

A C E G I

B

F

D

H

This is for D2, but some UoM students might find it interesting. Add in the number of workers for each activity.

Activity Number of workers

A 5

B 2

C 3

D 4

E 2

F 3

G 4

H 1

I 35

42

3 2

3

4

1

3

Can you see that in order to complete the project on time at least 2 and at most 9 workers are needed.

Page 9: CPA A group of workers is involved in a building project. The table shows the activities involved. Each worker can perform any of the given activities

CPA

3

8 8 3

3 6

210

7

C

D

E

F

GB

IA

H

0

3

3

11

10

10

20

13

23 25

23

23

20

20

1710

12

3

B D 42

F H3 1

A C E G I5 3 2 4 3

D2: We could draw a “Resource Histogram” to show exactly how many workers are needed on each day

Page 10: CPA A group of workers is involved in a building project. The table shows the activities involved. Each worker can perform any of the given activities

CPA

3

8 8 3

3 6

210

7

C

D

E

F

GB

IA

H

0

3

3

11

10

10

20

13

23 25

23

23

20

20

1710

12

3

D2: So this is what the resource histogram looks like. It’s a handy diagram to show haw many worker are needed throughout the duration of the project.

Page 11: CPA A group of workers is involved in a building project. The table shows the activities involved. Each worker can perform any of the given activities

CPA

3

8 8 3

3 6

210

7

C

D

E

F

GB

IA

H

0

3

3

11

10

10

20

13

23 25

23

23

20

20

1710

12

3

For D2 only. Use “resource levelling” to explain why the project will overrun if there are only 7 workers available at any one time. Which activities need to be delayed so that the project will be delayed with the minimum extra time. What is the minimum completion time now.

A B

CD

E

F

G

H

IB

E E

F

E

Activity F is the problem at day 11. Delay the start of D by 2 days, but because there a 1 day of float, this means that G and I are only delayed by 1 day. The new minimum completion time is 26 days. Activity Number of

workers

A 5

B 2

C 3

D 4

E 2

F 3

G 4

H 1

I 3