Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Phase 1 Response
4 broad actions during March & April
1. Prioritised and reduced elective work programme
2. ITU surge plan to accommodate rapid demand for ventilated beds
3. Re-design of inpatient management (24/7 rotas)
4. ED divert to load balance downstream ITU demand
Phase 1 Response
Enabled by
• Vastly reduced non-covid clinical activity
• Re-purposed clinical and admin teams
• Staff welfare and well-being efforts
Surgical Capacity Elective (OP and IP) activity currently at 25% of normal levels
OP referrals 1/3rd of normal
Successful IS collaboration over three weeks
National contract for 14 weeks
Currently utilising:
• Parkway, Little Aston, Dolan Park, Priory, Westbourne
• approx 5 theatres per day
Internal capacity severely constrained
• GHH & BHH CEPOD, QEHB 5 theatres daily
Phase 2 Response
May onwards – priorities:
• Implement 18 month plan – adaptability is key
– Maintaining ITU access for covid management
– Patient cohorting - bed occupancy
– Revised model of Acute Care
• Increasing elective access – graduated & flexible
How? Build on what we’ve learnt so far:
1. Re-purposing of hospitals and staffed to meet their core purposes
2. Resilient ITU staffing to sustain covid access for the duration
3. Benefit of generalist v specialist model
Other major considerations
Staff health and well-being support via prolonged interventions
Maintaining access to IS and other NHS facilities
Model for delivery of outpatients
Access to diagnostics
Pre-op assessment and screening
ITU is the critical dependency
Options
• Amb care
• 7 theatres
• 2 procedure rooms
• 24 beds
• 56 trolley spaces
• Consultation / assessment rooms / OPD access
• Clean access separate to main access
• Close to imaging, cath lab, IR rooms
• Must maintain Level 3 services
QEHB
Options • Solihull
– Can be a ‘clean site’
– 7 theatres
– Cath lab
– Imaging
– In patient beds - 238
– HDU / ITU could be expanded
• AMU and Medical Inpatient Wards
– 2 week phase down from present use
– Transfer take to BHH
• Good Hope DCU
• BHH hybrid theatre
Phase 2 – Repurposing Hospital Inpatient Care
BHH
• ITU NEL Covid & non-covid.
• Revised model of Acute Care
GHH
• ITU NEL Covid & non-Covid.
• Revised model of Acute Care
QEHB
• ITU NEL Covid & non-covid.
• Revised model of Acute Care
• Level 2 & 3 elective care
SOL
• Level 1+ / 2 elective theatres
• Elective wards
• Non-ward based services
Front door and inpatient management teams at hospital level for NEL – ‘hot teams’
Elective inpatient management - ‘cold teams’
Increased ITU capacity for covid and non-covid / NEL and EL patients
Plan
• Max out IS capacity May and June
– Support with UHB staff as and where possible
– Could increase capacity by 75-100%
• Develop and implement phase two changes
– Aim for 1st June to be fully operational
– Allow staff recovery time and ongoing support