Upload
ngodang
View
225
Download
0
Embed Size (px)
Citation preview
COUNTRY REPORT ECID 8 TRAININGCOUNTRY REPORT ECID 8 TRAINING
AOTS, TOKYO KENSHU CENTREAOTS, TOKYO KENSHU CENTRE
TOKYO, JAPANTOKYO, JAPAN
DIRECTORATE GENERAL OF ELECTRICITY
MINISTRY OF ENERGY AND MINERAL RESOURCES
OUTLINE
� Overview of National Electricity Conditions (Current Status)
� Need for Private Power Participation
� Indonesian Power Sector Infrastructure
� Power Generation Current Condition
� Power Generation Development Planning
� Target of Energy Mix for Power Generation
� Opportunity of Investment
Overview of National Electricity Conditions
(Current Status)
� Total installed capacity (2012): 38,063 MW (PLN 76%, IPP 20%, and PPU 4%)
� Current electrification ratio: 72,95%.
� Several areas are facing critical condition (demand > supply)
� Energy mix in power generation: Coal 46%, Gas 26%, Oil 19%, Hydro 7%, Geothermal 2%.
� Power plants under construction (based on RUPTL 2011 – 2020) : PLN 5,372 MW and IPP:
1,505 MW
� Total investment in Power Sector (2011):
– Power Generation : USD 1,644 Million
– Transmission : USD 1,089 Million
– Distribution : USD 317 Million.
SUPPLY CHALLENGES
� Mismatch between primary energy resources versus population
density:
- 80% population located in Java-Bali;
- majority source of primary energy in other islands.
� Dependency on oil as primary energy for electricity generation :
- abundance coal reserve, but many electricity generations still use fuel
oil.
� Lack of supporting infrastructures:
- gas pipe networks;
- coal transportation and distribution;
- electricity transmission networks, especially in outer islands.
� Limited financial budget to develop electricity sector:
- Electrification ratio is still low;
- Funding is needed for the development of additional generation
capacity (crash programs), transmission and distribution networks.
POLICY ON POWER SECTOR DEVELOPMENT
� The electricity business is basically conducted by State and
carried out by state own enterprise (PLN).
� State Own Enterprise should has first right of refusal in
electricity supply.
� Other enterprises (e.g. Regional Own Enterprise (BUMD),
Private sector, Cooperation and Society) could participate
in electricity supply business.
� Electricity business could be conducted for own use or for
public use.
� Continually increase electrification ratio.
� Continuously increase new and renewable energy usage in
primary energy composition for electricity generation.
� Increase the ratio of electrification, 80% in 2014 (currently
67.2%) and continuously implementing short term, medium
and long term programs to overcome the electricity crises in
the provinces
� Improve the investment climate in the power sector. Promote
private power investment in the power sector
� Improve efficiency in the electricity demand and supply side
� Increase the local content (TKDN) in the power sector
� Enforce safety regulations in the power sector
� Encourage energy diversification program shifting away from
oil based sources and the utilization of renewable and more
environmentally friendly energy sources
POLICY ON POWER SECTOR DEVELOPMENT (2)
ELECTRICITY DEVELOPMENT PLAN MEDIUM & LONG TERM
� Transmission
- Java – Sumatera Interconnected;
- Transmission Development in Sumatera, Kalimantan and Sulawesi;
- Interconnection of Sumatera and Malaysia Peninsula;
- Interconnection of West Kalimantan and Serawak.
� Electric Power Generation
- Increase Gas Supply for Power Generation;
- Low Rank Coal Utilization for Power Generation;
- Replacement of Oil Power Plant with Non-Oil Power Plant;
� Increase Electrification Ratio (to reach 93% in 2025).
Need for Private Power Participation
� Growth rate of demand for electricity is still
high (9.5% p.a up to 2029).
� Electrification ratio is still low (72.95% in 2011).
� Lack of electricity supply in some
areas/regions.
NEED A HUGE OF ADDITIONAL CAPACITY (estimated of 7,800
MW p.a during 20 years), investment required approx. USD 11.4
billion p.a)
BUT
� PLN’s investment capability is limited (around 20%)
� The Government budget for infrastructure is very limited.
THEREFORE� Privates sector participation are required:
• Engineering, Procurement and Construction (EPC) Project => 33 projects under the FTP-1 and 26 projects under the FTP-2
• Independent Power Producer (IPP) Project => 72 projects under the FTP-2 and other IPP projects are listed in RUPTL PT
PLN (Persero) 2010-2019
• Public Private Partnership (PPP) Project => 7 projects
0
100
200
300
400
500
600
700
800 TWh
Jamali
Outside Jamali
INDONESIA
Electricity Demand (based on draft RUKN 2010-2029)
0
20
40
60
80
100
120
140
160
180
GWAdditional Power Generation
(based on draft RUKN 2010-2029)
Infrastructure JAMALI Outside JAMALI Total
Generation 121,217 79,607 200,824
Transmission Line and
Substation9,180 5,844 15,024
Distribution Line 6,546 4,728 11,275
Total 136,944 90,179 227,122
Investment Requirement(based on draft RUKN 2010-2029)
Million USD
Note: RUKN : National Electricity General Plan
FTP-1 : Fast Track Program 10,000 MW Phase I
FTP-2 : Fast Track Program 10,000 MW Phase II
Indonesian Power Sector Infrastructure
(Current Status) : Transmisi yang sudah ada
: Transmisi yang direncanakan
: Pembangkit Listrik
•• POWER GENERATION CAPACITYPOWER GENERATION CAPACITY : : 338.063 8.063 MWMW•• TRANSMISSION LENGTH :TRANSMISSION LENGTH :-- 500 KV : 500 KV : 4.923 kms4.923 kms-- 275 KV : 275 KV : 9.5059.505 kms kms -- 150 KV : 150 KV : 24.38024.380 kmskms-- 70 KV : 70 KV : 4.7244.724 kmskms
•• DISTRIBUTION LENGTHDISTRIBUTION LENGTH::-- JTM : 2JTM : 2775.613 kms5.613 kms-- JTR : JTR : 406.149 406.149 kmskms
SUMATERA : • Pembangkit: 5.909 MW (16%)• 275 kV : 1.011 kms• 150 kV : 8.382 kms• 70 kV : 332 kms• JTM : 75.382 kms• JTR : 83.827 kms
JAMALI : • Pembangkit: 28.101 MW (74%)• 500 kV : 4.923 kms• 275 kV : 8.494 kms• 150 kV : 12.126 kms• 70 kV : 3.437 kms• JTM : 137.354 kms• JTR : 256.156 kms
Nusa Tenggara:• Pembangkit: 282 MW (1%)• JTM : 7.836 kms• JTR : 7.794 kms
KALIMANTAN : • Pembangkit: 1.602 MW (4%)• 150 kV : 1.568 kms• 70 kV : 123 kms• JTM: 23.487 kms• JTR : 22.540 kms
SULAWESI : • Pembangkit: 1.625 MW (4%)• 150 kV : 2.304 kms• 70 kV : 833 kms• JTM : 24.482 kms• JTR : 29.722 kms
MALUKU :• Pembangkit:233 MW (1%)• JTM : 4.722 kms• JTR : 2.717 kms
PAPUA : • Pembangkit: 311 MW (1%)• JTM : 2.351 kms• JTR : 3.393 kms
10
Oil share in electricity production is still high, because:
� DPP that should be operated in peak load period, is operated in
base load period to fulfill the demand (mostly happened in Outside
Java-Bali system)
� Several CCPP and GTPP in the Java-Bali system are operated
utilizing oil as primary energy because of lack of gas supply.
Total installed capacity is about 38,063 MW,
which consist of those owned by PLN’s (29,132 MW), IPP’s (7,551
MW) and PPU’s (1,380 MW).
POWER GENERATION CURRENT CONDITIONPOWER GENERATION CURRENT CONDITION
Power Generation by Owner
Power Generation by Type
Electricity Production
by Energy Mix
Power generation is dominated by CFPP, then followed by
CCPP, DPP, HEPP, GTPP, Geo PP, MHPP, GEPP and WTPP.
Note:
CFPP : Coal Fired Power
Plant
CCPP : Combine Cycle
Power Plant
HEPP : Hydro Electric Power Plant
GTPP : Gas Turbine Power Plant
GeoPP : Geothermal Power Plant
MHPP : Mini Hydro Power Plant
GEPP : Gas Engine Power Plant
WTPP : Wind Turbine Power Plant
SCPP: Solar Cell Power Plant
IPP : Independent Power Producer
PPU : Private Power Utility
PLN
29,132 MW
76 %
IPP
7,551 MW
20 %
PPU
1,380 MW
4 %
� Total power generation that will be developed from 2012 -2020 is about of 50 GW or in
average 5.5GW p.a
� PLN will develop about of 54% of the total capacity and the rest (46%) will be developed by
IPP/private
� Diesel Power Plant will still be developed, but only dedicated to isolated/remote area.
POWER GENERATION DEVELOPMENT PLANING (MW)POWER GENERATION DEVELOPMENT PLANING (MW)
2011 2019
Target Of Energy Mix For Power Generation
Coal46%
Oil19%
Geothermal2%
Gas26%
Hydro7%
Coal58%
Oil3%
Geothermal13%
Gas21%
Hydro5%
� Electricity efficiency effort is conducted through diversification of primary energy in power
generation (supply side) by optimizing utilization of gas, replacement of HSD to MFO,
increasing coal utilization, and developing renewable power generation
� Oil utilization is dedicated to isolated/remote areas with a higher priority for renewable
energy resources
� Gas and coal are given priority to reduce dependence on oil in power generation.
OPPORTUNITY OF INVESTMENT
POWER 2012 2013 2014 2015 2016 2017 2018 2019 2020
Total
(MILLION
USD)
Generation 6.087,7 8.784,4 10.146,7 9.089,9 7.338,9 7.194,1 6.474,4 4.842,7 3.371,3 67.815,7
Transmission 2.531,4 1.701,2 1.907,8 2.389,3 1.375,1 717,6 480,7 331,0 79,8 14.928,0
Distribution 1.269,5 1.172,1 1.253,3 1.166,8 1.320,5 1.395,0 1.477,4 1.539,3 1.605,5 13.461,0
Grand Total 9.888,6 11.657,7 13.307,8 12.646,0 10.034,5 9.306,7 8.432,5 6.713,0 5.056,6 96.204,7
� The establishing of more efficient and transparent investment
climate.
� Private Investments should comply with Indonesian’s law and
regulations.
� The achievement of self-financing power sector development.
� Providing fiscal and non-fiscal incentives for investors to accelerate
electricity development, such as:
- Free import tax for power plant’s capital goods that producing
energy for public use and additional Income Tax & VAT facilities for
renewable power plant.
- Attractive energy sale price generated from geothermal or other
renewable power plant.
- Simplifying power purchase mechanism by PLN from IPP for certain
terms and conditions.
INVESTMENT POLICY
� Phase I
– Accelerated Program Phase I consist of 10.000 MW Coal Fired
Power Plant (37 projects) and approximately 1817 kms
transmission project as PLN’s projects, introduced in 2007.
– As PLN’s project, private sector participation as EPC contractor.
� Phase II
– Government has launched Accelerated Program Phase II (total
capacity approximately 10.000 MW) in the early 2010, consist of
93 power plant projects, with composition based on primary
energy: Hydro 11%, Geothermal 34% , Coal 40%, and , Gas
15%.
– PLN and Private could participate (through EPC or IPP as
well) in the development program.
ACCELERATED PROGRAM
16
Energy Conservation Program
on Electricity Sector 1)
NO PROGRAM DESCRIPTION / PROGRESS
1. Improving transmission and distribution system
� To reduce technical losses
� Currently, total electricity losses is more than 9%
2. Switch off fuel oil for power plant from HSD to MFO, natural gas, coal, geothermal and hydro,
� To reduce production cost of electricity
� To reduce dependency of oil
� To reduce CO2 emission
3 Utilization of advanced technology (cogeneration, clean coal technology, etc)
� To reduce energy consumption
� To reduce CO2 emission
4. Utilization of excess power from captive
Excess power from captive can be sold to PT.PLN
Supply Side
17
Energy Conservation Program
on Electricity Sector 2)
NO PROGRAM DESCRIPTION
1. Creating Public
Awareness
� “Energy Saving” campaign through seminar/workshop and public
advertisement.
2. Labeling program � Providing information to consumers the energy efficiency level of an
electrical appliances
� The program is focused on electrical appliances
3. Partnership
Program on
Energy
Conservation
� Providing free energy audit for industries and buildings
4. Energy Manager
Program
� To plans, conducts, monitors and evaluates energy consumption in
industries and building.
5. Electricity Tariff � Implementing blocking tariff
Demand Side