Upload
loren-todd
View
215
Download
1
Embed Size (px)
Citation preview
Copyright ©2015. University of North Florida. All rights reserved.
Cost Estimation
Managerial Accounting
Prepared by Diane TannerUniversity of North Florida
Chapter 5
Cost Estimation Methods
Used by managers to Enable the creation of a cost function so that
costs can be predicted at various activity levels Useful when fixed and variable costs are
grouped together Four common methods
1. Account analysis2. Scattergraph3. High-low4. Linear regression
2
The Goal of Cost Estimation
Goal is to create a total cost equationTotal cost = Variable cost/unit * # of units + Total fixed cost
TC = VCx + TFC
Y = mx + bWhere:TC = Y = total costsTFC = b = total fixed costs = y-interceptVC = m = variable cost per unit = slope of function x = units produced/sold
3
Both equations serve the same
purpose
Account Analysis Method Used to estimate fixed and variable costs Step 1: Classify costs as variable or fixed
Separate the list of costs into two piles—fixed costs versus variable costs
Requires professional judgment
Step 2: Determine variable costs per unit
Step 3: Determine total fixed costs Add the costs in the fixed cost pile from step 1
Total Variable CostsActivity Level Achieved
Total Variable CostsActivity Level Achieved
Cost function (equation) =TC = VCx + TFC
4
Scattergraph Approach
Used to estimate fixed and variable costs to determine how costs and activity levels changeStep 1: Acquire cost information over activity levels Step 2: Graph the data points Step 3 : Eyeball a linear relationship and draw a ‘trend’ line through
the data pointsStep 4: Determine where the line crosses the y-axisi.e., y-intercept = total fixed costsStep 5: Determine the slope (rise over run), i.e., variable cost per unitStep 6: Write the cost equation
5
If you have forgotten how to graph data points, this will help. .http://www.studyzone.org/testprep/math4/d/linegraph4l.cfmSource www.studyzone.org Grade 4 Math Lessons
High-Low Method
Used to estimate fixed and variable costs at various levels of activity
Uses two data points, the high and low levels of activity and their related total costs
Results:• Variable cost = Line slope • Total fixed costs = Y-intercept
Results:• Variable cost = Line slope • Total fixed costs = Y-intercept
6
High-Low Method
Step 1: Select the high and low data activity pointsStep 2: Subtract the smallest from the largest cost and
the smallest from the largest activity and use the changes in the following formula
= Variable cost per unitChange in Cost
Change in Activity
First select the high and low amounts from the activity column. Then use the costs related to those activity points.
7
Step 3: Pick one point—either the high or low:Plug the total cost and the activity of the point you selected in the cost equation: TC = VCx + TFC
High-Low Method Continued
Step 5: Solve for fixed costs “TFC”Step 6: Replace the VC with the variable cost per unit
you calculated and the TFC with the fixed costs you calculated, into the following formula:
TC= VC x + TFC
Only two variables will be displayed in the formula: X and TC. The other components: VC and TFC, should
be replaced by the respective amounts.
8
Step 4: Substitute the number of activity units for the data point chosen in step 3 for “x”
9
The End