Upload
mohamaddanielbinyaacob
View
25
Download
7
Embed Size (px)
DESCRIPTION
Cost Estimation Lecture Notes
Citation preview
3 PPM Cost Estimating
1
Cost Estimating o A project cost estimate
– Is a prediction of the final cost. – Informs the Project Sponsor, stakeholders, and participants of the
approximate scope and / or final cost of the project. – Compares predicted final project cost with the projected benefits to
help decide if the project should proceed. – To obtain preliminary or final funding for the project. – Is a control tool to track actual/ forecast costs against an agreed
budget – Helps evaluate alternative designs, processes, delivery strategies,
technologies, sites, etc. o Understand philosophy behind acceptance of cost estimates:
– GSK policy : projects should have an equal probability of over/ under run.
– DO NOT RELY ON OVERSPEND GOVERNANCE RULES !!
The total investment in a project will be significantly higher than the capital cost of the equipment alone.
1. Determine the plant and equipment cost, including costs of direct engineering (you!), procurement and delivery to site.
2. Determine the total erected and installed cost (TEC) – the cost of the completed plant erected and ready to operate – includes constructional engineering, labour and materials, services, buildings and other infrastructure (roads, etc.) and so on. Use a Factorial approach (see example tables below).
3. Determine the total capital employed (TCE) which also includes working capital (to cover the period between paying for supplies and receiving income for product) and financing charges.
Estimate accuracy vs cost Recommended nomenclature
Probable range of Accuracy
Cost as % of project expenditure
Order of magnitude estimate (Guestimate, ballpark, seat of the pants estimate)
±30 to ±50 % 0 to 0.1 %
Study estimate (Evaluation or predesign estimate)
±20 to ±30 % 0.1 to 0.2 %
Preliminary estimate (Sanction, funding or authorization estimate)
±10 to ±25 % 0.4 to 0.8 %
Definitive estimate (Control estimate)
±5 to ±15 % 1 to 3 %
Detailed estimate (Tender or contractor’s final cost estimate)
±2 to ±5 % 5 to 10 %
Estimations of Plant cost 1. Step count estimating (1)
Main plant item basis Capital cost of plant C = f x N x AUC x FM x FP x FT where f = Investment factor (Figure 4.1 in the “Guide”)
N = Number of all main plant items (not pumps) AUC = Average cost of main plant items = 21V0.675 where V = plant output in tonnes per
year FM = Factor for material of construction (see table
4.1 in “Guide”) FP = Factor for design pressure FT = Factor for design temperature (see figure 4.3
in “Guide”) Crude but often works as a first shot.
Investment Factor
7
Temperature Factor
9
Estimations of Plant cost 1. Step count estimating (2) Functional unit basis o Each functional unit (main operating unit) has a capital cost
which is a function of Capacity, Temperature, Pressure and Material of Construction. There are a number of different methods (see the “Guide” pp 26-31) for estimating the cost. Most are based on expressions of the type:
o C = A constant x N x Capacity (an exponent) x Factors for P
and T (with exponents) o where N = the number of functional units
11
Estimations of Plant cost Power Law or exponential estimating
C = ( S )n Cr ( Sr)n
where C = Capital cost of a plant (or an item) processing S units per year and Cr and Sr are reference (i.e. known) values. The units are those that are appropriate (could be mass, volume, number, etc.)
n is often quoted as 0.6 (the six-tenths rule) but it can vary with the type of plant and equipment (see example in table 4.3)
This can be applied (crudely on an “overall basis” to complete plants) or (in a more sophisticated way) on a simple breakdown of the plant into main cost areas.
Factorial estimation Factorial methods are used to estimate a TEC (and
TCE) when you have already obtained the costs of plant and equipment as delivered.
Installation factors (often called Lang factors) are used as
multipliers of plant/equipment costs to account for erection, piping, instrumentation, electrical services, civil works, structures and buildings, and lagging.
They may be applied to the whole plant or (more accurately)
to plant areas.
Estimate Factors
15
Updating estimates – cost indices Inflationary effects have to be compensated for. This is done
by applying cost indices:
Cost at time B = cost at time A x Index at time B Index at time A
Sources of indices: UK: The PREDICT index (monthly) in Process Engineering (also
available on-line) Association of Cost Engineers in The Cost Engineer
USA: The Chemical Engineering (CE) Plant Cost Index published monthly in the (American) journal of that name
M&S (Marshall and Swift) Index for various industries also published in Chemical Engineering
Other countries: Also published in Process Engineering Note that the time base of Indices may change from time to time. e.g. The PREDICT Index was rebased (to 100) in January 2000
Typical Estimate Classifications
PPrroojjeecctt SSttaaggee EEssttiimmaattee
CCllaassssiiffiiccaattiioonn aanndd TTiittllee
TTyyppiiccaall CCoonnttiinnggeennccyy
LLeevveell
TTyyppiiccaall SSttaatteedd
EEssttiimmaattee AAccccuurraaccyy
No. Description
1 Inception Class 1 25-50% 50%
2 Feasibility Study Class 2 20-25% 20-25%
3 Concept Design Class 3 15-20% 15-20%
4 Scheme Design Class 4 10% 10%
Estimate Classifications
o As the design proceeds, more information on which to base the estimate is available.
o Estimating methods must become more detailed, and the resulting estimate becomes more accurate.
o Not all project stages and estimates are required for every project.
o Projects typically require a Class 4 Estimate (+/-10%) for the final/ full funding
Who Prepares Cost Estimates and How They Are Prepared
Class 1- 2 Estimates, Stages 1-2 o Class 1 and some Class 2 Estimates are often produced
internally by the client. o External consultants can often produce estimates from historical
& other data o Building costs are usually estimated by multiplying a cost per-
unit area o Manufacturing projects may be estimated by adjusting a cost
estimate or final cost from a similar project. o Typical country cost factors compare local project costs vs. a
baseline (typically USA).
Class 1 & 2 Estimating Techniques
o Earliest – ETCM tool using historic project data o Capacity factors
Cost 2 = (C2/C1)n x Cost 1 where: C1 = known capacity or size Cost 1 = known facility
cost C2 = new capacity or size Cost 2 = new facility cost n = cost capacity factor
o Equipment factors Cost 2 = Eq x factor where: Eq = Cost of all major pieces of equipment
factor = historical empirical data o Area
Cost 2 = m2. required x /m2 Rate where: m2. required = m2. of new building
/m2. Rate = historical average cost per m2.
Who Prepares Cost Estimates and How They Are Prepared
Class 3 Estimate, Stages 3 o Class 3 Estimates are typically developed by client engaged
Engineering or Construction Management contractors. o The estimating approach must be consistent with the level of
design information available. – Detailed estimating techniques such as material take offs and vendor
quotes should be used. when suitable documentation is available. – Concept style estimating techniques such as cost/ m2a can be used when
detail information is not available – introduces risk
o An Estimate Basis Document (EBD) helps the PM’s understanding of the estimate and facilitate further development.
o Estimates should be compared & reconciled to previous class estimates, and significant differences understood & explained.
Who Prepares Cost Estimates and How They Are Prepared Class 4 Estimates, Stage 4 o Class 4 Estimates set the amount of the final funding and
become the control budget for the rest of the project. – Accuracy is critical. – Require a well-planned, detailed, quantity-based approach. – Require material take-offs from the scheme design drawings and
current unit prices for the project location. – Responsibility to develop the cost estimate is with the contractor. – Capability in this area is a key criteria for contractor selection. – GSK PM is responsible for including GSK items in Class 4
Estimate. o EBD (estimate basis document) is required to ensure PM and
others understand how estimate has been prepared.
Estimate Basis Document (EBD) o EBD should cover:
– Design documents used – Key exclusions, what others need to estimate – Who will actually do material take-offs? - potential subcontractors
and if so, how will the contractor ensure quality? (Will this affect the schedule)
– The Work Breakdown Structure to be used. – The economic/ time basis for all unit costs (present day or future). – Currency assumptions – Assumptions for use of growth & other estimating allowances – Contingency included – Risk Allowances – Other estimating instructions including labour and schedule and
escalation assumptions. – Area factors (using past project information from other international
locations).
Cost Estimate Summary
Template Tool 11B
Standardized format
Source data to align with major headings
Aligns to cost report 11E
COST ESTIMATE SUMMARYProject Name
Project No. : 1234Classification : 4 (+/-10%)
Date : 16-Jan-02Currency
CAPITALDirect Costs
Equipment 43.0Bulk Materials 32.0
Installation Subcontracts 76.0Automation 5.5
Subtotal Directs 156.5Professional Services
Engineering and Procurement 22.0Construction Management 11.0
Subtotal Professional Services 33.0GSK Costs
GSK Staff 5.0GSK Consultants 4.0Other GSK Costs 2.0
Subtotal GSK Costs 11.0Preliminaries
Contractor 11.0GSK 11.0
Subtotal Preliminaries 22.0
Escalation 0.0Contingency 22.5
Total Capital Costs 245.0
REVENUE EXPENSEDemolition 5.5
Asset Write-off 5.5Lease Costs 5.5
Other Project Expense 11.0Subtotal Revenue Expense Components 27.5
Escalation 0.0Contingency 2.5
Total Revenue Expense Costs 30.0
Total Project Costs 275.0
Risk Allowance 0.0
Project Leader: NamePrepared by: Name
Cost Estimating Lessons Learned Causes of Poor Estimating o Lack of clear estimate preparation plan. o Information (database) content or accuracy inadequate. o Incomplete reflection of basic constraints, influences or
assumptions. o Insensitive to change. o Level of detail too high -- too low. o Material specifications definition hazy, inconsistent (pricing
errors). o Participant respect and full commitment lacking - patronisation. o Inadequate cross-checking of calculations. o Not used in regular decision-making process. o Not relatable to activities. o Accounts lack clear definition. o Updating cycle slow -- data not timely / useful. o Format complicated and inconvenient.
Cost Estimating Lessons Learned Causes of Poor Estimating (Continued) o Inadequate site survey. o Does not reflect specific project characteristics or
circumstances. o Interfaces with schedule, WBS not clear, specific or consistent. o No/weak subcontracting plan. o Slighting of logistics problems. o Failure to “sample check” data. o No critical procurement program. o No definition construction strategy. o Does not include allowances, contingency or retreat
considerations. o Distorted to cover-up resource deficiencies or fit conveniences. o Estimate data (costs, escalations) - unrealistic /
undemonstrated.
o Developed too late to provide pro-active tool for management. o Inadequate ability of estimators. o Not consistent with subordinate level “time” and “cost” control
techniques staffing. o Failure to consider local regulations, union rules, assessments,
and customs. o Incomplete / inadequate future economic trends. o Inadequate analysis of contract bid/specification closure. o Omission / inadequate treatment of taxes, benefit burdens,
depreciation insurance. o Omission or commission errors / oversights.
Cost Estimating Lessons Learned Causes of Poor Estimating (Continued)
Doublespeak?
“..there are known knowns; there are things we know we know. We also
know there are known unknowns; that is to say we know there are some
things we do not know. But there are also unknown unknowns -- the ones
we don't know we don't know."
28
Cost Estimate Conditioning
o Growth Allowances o Escalation o Currency o Risk Allowances o Contingency
Growth Allowances o Are not contingencies o For ‘known unknowns’ o The GSK project team must ensure that Class 4 Cost
Estimates include appropriate growth allowances for each of the following types of growth described below: – ‘Natural’ design development – Design quantity “creep” – Equipment cost growth
o Productivity and/or unit rate cost used by EPCM should reflect actual project experience.
• Conveyers, Air-handlers, Filter, Towers with Specialized Internals and Driers
6% to 8%
• Drums, Fillers, Reactors, Tublet Presses, Heat Exchangers
5% to 6%
• Pumps and Minor Compressors, Chillers, Boilers and Furnaces
3% to 5%
• Specialized Vendor Designs, includes GSK Standard Designs
2%
Typical Growth Allowances
• Civil • Structural Steel • Piping
10 % to 15 % Allowance
• Instrumentation • Electrical • Painting • Insulation
7 % to 10 % Allowance
Equipment
Works Packages
Escalation
o An allowance for inflation in equipment, material, works packages pricing & professional fees
o Based on market conditions, commodity & raw material pricing, political environment etc.
o Should be based on the anticipated project schedule & cash flow – Don’t just apply x% per year to the entire cost
Currency Fluctuations
o Many different approaches o Agree approach with finance/ governance rules
– Fixed/ plan rate assumptions – Buying forward cover/ hedging
33
$ £ € ¥
Risk Allowances o Defined Risk allowances may be added for high
impact/ high probability risks – Refurbishment projects – Technology projects – Regulatory risks – One off project risks
o Risk workshop to identify whether any key risk allowances are required
o Should be held as a separate risk budget and returned if not required – Don’t use to fund other parts of the project (overspends,
changes)!
Contingency o Contingency must be added to an estimate to cover
costs due to changes as the project moves to completion. (‘known unknowns’).
o Not for: – Changes in the fundamental delivery basis. – Significant changes in fundamental scope of the project. – Cost fluctuations outside agreed governance – Labour disputes, Major new governmental regulations &
external events (force majeure).
o If a significant change as above occurs, the PM must request additional funds for approval by the original approving authority.
o Don’t make your own job impossible by being too accommodating !!
Contingency - continued o Contingency should cover:
– Minor scope changes – Design changes – Minor Project Plan changes – Significant field developments – Design errors and omissions – Estimating errors and omissions
o Contingency is intended to cover costs associated with future events that are expected to occur but cannot be identified at the time the estimate is prepared (‘known unknowns’)
o Increased contingency is justified for ‘risky’ projects – e.g. refurbishment, new technologies.
JD Science of Contingency & Communicating estimates Slides
o Right shifting to get 50:50 outcome o Lessons in communicating estimates o Impact of contract strategy
37
Basis of Early Estimates
o What you know – Broad objective – Location – Capacity / size
o What you don’t know – Future options – Other strategic impacts – Aspirations – Details of locality – Condition of existing assets – Complexity of product range – Actual capacity – Details of process, safety and technical requirements
P50 Estimating (Equal chance of under/overspend)
Early Estimates • Most likely cost estimated against the known • 50/50 cost is significantly higher due to unknown • Difference=contingency • 25-50%
Final Approval Estimates • Most likely cost estimated against the known • 50/50 cost is only marginally higher due to engineering • Difference=contingency • 10-15%
Consistent methodology for What You Know o EarliEst o Structured & Inclusive
Page 17John DysonJanuary 2005
GSK EngineeringEarly Cost Estimate Tool
Estimate Model
Boiler
HVAC
Equip
BuildingBoiler
Road
Pipe Bridge
Process Modules
Buildings
Shell
Fit-Out
Utilities
Infrastructure
Security, Fencing & Landscaping
DIRECT COST INDIRECT COSTPreliminaries
All Temporary Equipment, Structures, Accommodation and others works used to execute the project.
GSK Cost
Cross Charge of GSK personnel onto the project.
Includes project management, project support and VALIDATION. (Assumed)
Professional Services
All Engineering, Procurement, QS, Management and supervisory costs bought in. (Assumed)
Includes Material & Labour
Equipment Buildings Shell / Fitout
Services Indirects Prompts
Contingency
Business Requirements Scope unknowns
Execution unknowns
Typical Contingency Allocations
Action
All Business Case / Strategic Estimates to o Follow EarliEst methodology o Basis and assumptions clearly documented o Apply appropriate Contingency based upon Stage o Be Peer Reviewed by GCP leadership team member