1 Cost Estimating & Cost Management Florida DOT Approach Phillip “Greg” Davis, P.E. State Estimates Engineer Florida Department of Transportation Specifications & Estimates Office August 11-13, 2010 Cost Estimating & Cost Management Capacity Building Workshop Peer Exchange FHWA/AASHTO/MnDOT Minneapolis, Minnesota

Cost Estimating & Cost Management Florida DOT Approach

Embed Size (px)

Citation preview

1

Cost Estimating & Cost ManagementFlorida DOT Approach

Phillip “Greg” Davis, P.E.State Estimates EngineerFlorida Department of Transportation

Specifications & Estimates OfficeAugust 11-13, 2010

Cost Estimating & Cost Management Capacity Building Workshop

Peer ExchangeFHWA/AASHTO/MnDOTMinneapolis, Minnesota

2

OVERVIEW

Construction Cost

Bid Competition

Work Program (STIP)

FDOT Mitigation Strategies

3

Construction Cost

4

Construction Cost

5

Bid Competition

6

Bid Competition

7

Work Program (STIP)

Budget vs Awards

FiscalYear

Budget(Million $)

Awarded(Million $)

Percent Difference

2004/2005 2,578.9 2,890.6 12.0%

2005/2006 1,714.3 2,076.7 21.1%

2006/2007 3,231.4 3,230.4 0.0%

2007/2008 3,009.3 2,757.4 8.4%

2008/2009 3,424.6 2,449.6 28.5%

2009/2010 3,126.4 2,270.4 27.4%

8

9

FY05/06 Impacts Rejected 71 contracts because of

high bids These were advertised at $600M and

bids came in at $977M 28 of these were re-let. 43 contracts were moved into FY

06/07

Impacts to Florida’s Program

10

FY06/07 Impact Rejected 11 contracts because of high

bids These were advertised at $23.1M and

bids came in at $37.3M 2 of these were re-let. 9 projects were deferred to 07/08

Impacts to Florida’s Program

11

FY07/08 to present Budget surplus Identify additional Projects to consume

excess budget

Impacts to Florida’s Program

12

FDOT Mitigation Strategies

13

Draft Guidebook

14

FDOT Cost Increases Summit

February 2006

15

Nearly 200 Attendees

Brainstorm Strategies

Short/Long Term Strategies

FDOT Cost Increases Summit

16

Bid Options

Scope Alternates

Pavement Alternates

Alternative Contracting

17

Specification

Contractor Feedback

Results

Maximum Budget

18

Design what can be build easilyrather than build what can be designed easily

Do not design everything to federal-aid standards

Flexible Design & Engineering

19

Refine Awards Criteria

Normal Criteria

Additional Criteria

Rejected Contracts

20

Cost Estimate Study

August 2006

21

Purpose of Cost Estimate Study

Improve Cost Estimating Processes

Enhance Tracking of Project Cost Changes

SAVE MONEY $$$ Manage Project Cost Stabilize Work Program

22

RECOMMENDATIONS

23

DOCUMENTING/APPROVING SCOPE OF WORK AND COST ESTIMATES

• Develop a statewide Estimates Tracking System that extracts data from existing Department systems. This system will be used to document scope of work and cost estimate changes from project inception to contract award.

• Every project scope of work and cost estimate should be reviewed by the appropriate Department Head(s) and approved by the Director of Transportation Development. Each District/TPE should decide what level of approval is required based on the size of the change.

• Central Office Estimates working with the Districts/TPE shall develop a sample electronic form for documenting these changes to be used by the Districts/TPE as they deem appropriate.

24

SCOPE OF WORK & COST ESTIMATE COMMUNICATION

• Program Manager, Project Manager or EOR/Designer should be responsible for communicating the approved scope of work including changes to the District Estimates Office.

• District/TPE Estimates Office should be responsible for communicating all construction cost estimates including updates and reasons for cost changes to the District/TPE Work Program Office. District Work Program Office should only accept cost information from the District/TPE Estimates Office.

• A representative from the District/TPE Work Program Office should attend all Production Meetings.

25

HANDLING REQUESTS FROM OUTSIDE GROUPS FOR ADDED WORK TO A PROJECT

• Each District/TPE shall establish an approval process for all requests. Included in this directive should be guidance when an outside group will be required to pay for the enhancements.

• Enhancement requests affecting project cost shall require District Secretary approval.

26

PROJECT DEVELOPMENT AND ENVIRONMENTAL

(PD&E) PHASE COST ESTIMATES

• Prior to entering a project that has gone through a PD&E study into the Work Program, a detailed LRE shall be done on the preferred alternative.

• All projects in the Five Year Plan shall be entered into the LRE system.

27

Construction Cost Performance Measures

28

Construction Cost Performance Measures Adopted vs Low Bid

Official Estimate vs Low Bid

Initial Cost Estimate vs Phase II

Initial Cost Estimate vs Adopted

29

ERTS was developed to support cost estimate performance measures

Contains 5 years of cost estimates Data refreshed every night

Estimates Report Tracking System (ERTS)

30

Implementation of Cost Risk Analysis

Cost Risk Analysis Team

Team Members

Mission/Vision/Goals/Objectives

Team Activities

Team Members

Greg Davis – State Estimates Engineer

Kurt Lieblong – State Value Engineer Alan Autry– State Alternative

Contracting Engr Tim Brock – D4 Value & Utilities

Engineer Jose Theiler – D4 Program Service

Administrator

Mission Statement

“Manage/control the quality of construction cost & schedule estimates to ensure they are reasonable, defendable and

reliable.”

Vision Statement

“Risk Management…the way FDOT controls project unknowns and manages their impacts to cost and schedule by incorporating those risks into the decision process.”

Goals

Develop and Implement Cost Risk Analysis Program

Conduct Cost Risk Analysis Workshops on major projects

Develop a mentoring/succession/ training plan

Objectives

•To conduct cost risk analysis workshops for projects between $100M and $500M

•To manage a consultant contract for cost risk analysis workshops on projects greater than $500M

•To develop training program for cost risk analysis

Team Activities

Draft Procedures

Identify List of Projects

Software Selection

Consultant Contract Scope of Services

Training and Culture Change

Pilot Workshops

I-4 Lee Roy Selman Expressway & Tampa Port Connector

CSX Commuter Rail

I-595 Corridor Improvements

First Coast Outer Beltway

I-75 Corridor Improvements

39

Thank You and Any Questions!

40

CONTACT INFORMATION

Greg Davis, P.E.State Estimates [email protected]

(850) 414-4170