Correcting SPT Blow Counts to N 60 Values Correcting SPT Blow Counts to N 60 Values Roger A. Failmezger, P.E. In-Situ Soil Testing, L.C.

Correcting SPT Blow Counts to N60 Values

Embed Size (px)

Citation preview

Page 1: Correcting SPT Blow Counts to N60 Values

Correcting SPT Blow Counts to N60 ValuesCorrecting SPT Blow Counts to N60 Values

Roger A. Failmezger, P.E.In-Situ Soil Testing, L.C.

Page 2: Correcting SPT Blow Counts to N60 Values

WHY IS IT IMPORTANT ?WHY IS IT IMPORTANT ?

When SPT empirical design correlations were developed (1940s-1960s), experts believe that N60 values represent what those earlier researchers used.SPT method has changed since the 1960s.Uncorrected “N” values can vary by a factor of 3.

Page 3: Correcting SPT Blow Counts to N60 Values

Earlier Research MethodsEarlier Research Methods

Mud rotary drilling was used instead of augers. Reduces the geostatic stress release. ID of barrel was same as tip.Only safety and donut hammers were used.

Page 4: Correcting SPT Blow Counts to N60 Values

Although N60 Corrections are easy to perform, they are only rarely performed in practice.

Although N60 Corrections are easy to perform, they are only rarely performed in practice.

Page 5: Correcting SPT Blow Counts to N60 Values

N60 FormulaN60 Formula

(After Coduto, 1994)

Page 6: Correcting SPT Blow Counts to N60 Values

SPT Hammer TypesSPT Hammer Types

(After Coduto, 1994)

Page 7: Correcting SPT Blow Counts to N60 Values

SPT Hammer Energy CalibrationSPT Hammer Energy Calibration

Page 8: Correcting SPT Blow Counts to N60 Values

Typical Hammer EfficienciesTypical Hammer Efficiencies

Theoretical Energy = (30in)(140lbs) = 4200 ft-lbsDonut -- 0.45Safety -- 0.60Automatic (CME) – 0.95

Consult Manufacturer

Page 9: Correcting SPT Blow Counts to N60 Values

N60 Correction FactorsN60 Correction Factors

(After Coduto 1994)

Page 10: Correcting SPT Blow Counts to N60 Values

Today’s SPT SamplerToday’s SPT Sampler

(After Coduto, 1994)

Page 11: Correcting SPT Blow Counts to N60 Values

Borehole DiameterBorehole Diameter

Large inside diameters of boreholes reduce confinement making it easier for spoon to penetrate soilOnly important when I.D. is 6 inches or more

Page 12: Correcting SPT Blow Counts to N60 Values

Rod Length CorrectionRod Length Correction

When the hammer strikes the rods, a compression wave travels down the rods and is reflected as a tension wave after is reaches the bottom of the split spoon.When the tension wave travels back to the hammer, the hammer is lifted and energy transfer essentially stops.Incomplete hammer energy is transferred when rod lengths are less than 30 feet.

Page 13: Correcting SPT Blow Counts to N60 Values
Page 14: Correcting SPT Blow Counts to N60 Values

ConclusionsConclusions

N60 values are needed for more accurate design analyses.N60 values have less variability or scatter due to test method. {Standardization of field procedures}Contractor fees may be reduced from consistent data reporting.Consider revising geotechnical report guidelines to require N60 values on all boring logs

Page 15: Correcting SPT Blow Counts to N60 Values

Worked ExamplesWorked Examples