Copy of Methodology

Embed Size (px)

Citation preview

  • 8/22/2019 Copy of Methodology

    1/33

    GIGATECH INC.

    METHOD STATEMENT

    ELECTRICAL RACEWAYS INSTALLATION WORKS

    A. Scope of Works

    This method statement describes the work execution plan for the installation of

    raceways and their accessories in conjunction with the Electrical Boxes

    installation. Raceway types include the following:

    1. Rigid Steel Conduit (RSC)

    2. Intermediate Metallic Conduit (IMC)

    3. Unplasticized Polyvinylchloride Conduit (PVC)

    4. Flexible Metallic conduit (FMC)

    5. Liquid tight flexible Metallic conduit (LFMC)

    6. Cable Trays, Cable Ladders, Wire ways and Wire Gutters

    B. Preparatory Works

    Materials intended for use shall have been submitted and approved. Coordinated

    shop drawings and have been approved for implementation. Necessary work

    permits shall have been applied for and approved including requisite Job Hazard

    Analysis. Equipment intended for used shall have been expected and tagged safe

    for use. The skilled and labourer doing the installation work shall have undergone

    safety orientation and shall have been familiarized with the procedures related to

    their works.

    C. Procedure for Installation

    1. Examination

    1.1 Examine surfaces to receive raceways, boxes and enclosures for

    compliance with installation tolerances and other conditions affecting

    performance of raceway installation.

    1.2 Do not proceed with installation until unsatisfactory conditions have

    been corrected.

    2. Delivery and Storage

    2.1 Non-metallic conduits stored on site prior to installation shall be placedon a flat surface off the ground and shall be protected from

    construction debris and direct rays of the sun.

    2.2 Damaged, oxidized, warped, improperly stored material or with

    excessive amounts of foreign debris will be removed from the project

    site and replaced with new materials.

    3. Sleeving and Block Out works

    3.1 Sleeving and block out work shall be implemented during setting up of

    formworks.

    3.2 Prepare all sleeves and block outs and ensure the use of proper

    materials.3.3 Coordinated with the general contractor and set the sleeves/block outs.

    METHODOLOGY Page 1

  • 8/22/2019 Copy of Methodology

    2/33

    GIGATECH INC.

    4. Site Fabrication

    4.1 All raceways shall be properly cut square and reamed smooth at the

    ends and all joint made tight. Cut ends of conduit with hand or power saw.

    4.2 Threads cut on job shall have same effective lengths, thread

    dimensions and taper as factory-cut threads.

    4.3 Threads cut on job shall have same effective lengths, threaddimensions and taped as factory-cut threads.

    4.4 Used raceway fittings compatible with raceways and suitable for use

    and location

    4.5 Make bends and offset will be skilfully done so that the inside diameter

    will not be reduced.

    4.6 Field-made bends and offsets shall be made with hickey or conduit-

    bending machine.

    5. Meeting

    5.1 Coordinate and confirm schedule and sequence of work with other

    trades.

    5.2 Coordinate and confirm installation procedure

    5.3 Prepare and secure necessary permits (installation permit, hot works

    permit, etc.) before actual start of installation work.

    6. Marking

    Mark anchor locations in accordance with the specified spacing requirement.

    Check actual condition of anchors.

    7. Hangers/Supports

    7.1 Hangers and supports installation is to be implemented upon strippingof formworks.

    7.2 Install hangers/supports according to specified material, size, type and

    spacing.

    7.3 Where raceway support members are welded to structural building

    framing, scrape, brush, clean and apply one coat of zinc rich primer to

    welding.

    8. Raceway Installation

    8.1 Installation of raceway is to be implemented upon completion of

    hangers and supports installation and will not coincide with the wet

    work stage (partition, topping, etc.)8.2 For overhead installations beyond the comfortable and safe reach of

    workers, provide approved ladders or erect sufficient and safe

    scaffolds

    8.3 Install and seal raceways in accordance with approved shop drawings.

    8.4 Surface of the raceways shall be checked for any dents prior to

    installation.

    8.5 Keep raceways at least 150mm away from parallel runs of flues and

    steam or hot-water pipes. Install horizontal raceway runs above water

    and steam piping.

    8.6 Install raceways level and balance and at proper elevations. Provide

    adequate headroom.

    METHODOLOGY Page 2

  • 8/22/2019 Copy of Methodology

    3/33

    GIGATECH INC.

    8.7 During construction provide temporary closures of taped polyethylene

    on open raceway to prevent foreign matter from entering the raceway

    system. Conduits shall be capped during construction and shall remain

    closed until ready for use.

    8.8 In all cases, where conduits rise from concrete slab or footings, they

    shall be accurately held in place during concrete application andfinishing by means of suitable templates or spacer protector caps.

    8.9 Penetrations of raceways through fire-rated vertical (walls/partitions)

    and horizontal (floor/ceiling assemblies) barriers shall be filled with

    approved firestop material.

    8.10 Protect stub-ups from damage where conduits rise through the

    floor slab. Arrange so box or enclosure where the stub-ups terminate

    may be positioned with sufficient height above finished floor surface

    is indicated in drawings.

    8.11 Support pull boxes independent.

    8.12 Run concealed raceways with a minimum of bends, in the

    shortest practical distance considering the type of building

    construction and obstructions, unless otherwise indicated.

    8.13 Install exposed raceways parallel to or at right angles to nearby

    surfaces of structural members and follow the surface contours as

    much as practical.

    8.13.1 Run parallel or banked raceways together on common

    supports where practical.

    8.13.2 Make bends in parallel or banked runs from the same

    centreline to make bends parallel. Use factory elbows where

    elbows can be installed parallel. Otherwise, provide field bends

    for parallel raceways.8.14 Apply coat of protective paint to conduits where protective

    coating is damaged. Do not paint conduit threads.

    8.15 Join raceway fittings designed and approved for the purpose

    and make joint tights

    8.15.1 Make raceway termination tight. Used bonding bushings

    or wedges at connections subject to variation. Used bonding

    jumpers where joints cannot be made tight.

    8.15.2 Use insulating bushings to protect conductors.

    8.16 Unplasticized polyvinylchloride conduits (PVC) shall be

    jointed using approved PVC cement. Ensure that joints are properly

    bonded/made to prevent intrusion of dust or liquid.8.17 Terminations: Where raceways are terminated with locknuts

    and bushings, align raceways to enter squarely and install locknuts

    with dished part against the box. Where terminations are not secure

    with 1 locknut, use 2 locknuts: inside and 1 outside the box.

    8.18 Install pull wires with empty raceways. Use no. 14 AWG zinc-

    coated steel or monofilament plastic line with not less than 200-lb

    (90.9 kg) tensile strength. Leave at least 300mm slack at each end of

    the pull wire.

    METHODOLOGY Page 3

  • 8/22/2019 Copy of Methodology

    4/33

    GIGATECH INC.

    8.19 Flexible connections: Use maximum of 1800mm flexible

    conduit for recessed and semi-recessed lighting fixtures; for

    equipment subject to vibration, noise transmission, or movement; and

    for all motors. Install separate ground conductor across flexible

    connections.

    8.20 Complete raceway installation before starting conductorinstallation.

    9. Cleaning

    9.1 On completion of installation, including outlet fittings and devices,

    inspect exposed finish. Remove burrs, dirt and construction debris

    and repair damaged finish, including chips, scratches and abrasions.

    9.2 Clean inside of conduits by mechanical means to remove all foreign

    materials, burrs, dirt, construction debris and moisture before pulling

    wires or cables.

    10. As-built Drawings

    10.1 As-built drawings shall be progressively prepared as installation

    proceeds.

    D. Equipment and Tools

    1. Hickey

    2. Hydraulic puncher

    3. Electric drill

    4. Blow torch

    5. Threading machine

    6. Grinder7. Hand tools

    E. Materials

    Materials to be used shall be approved brands. Similarly, fittings and accessories

    shall be of approved brands. Submittals and samples shall be submitted for

    approval following the technical specifications.

    F. Personnel Responsibilities and Supervision

    Gigatech Inc. shall provide direct labor or sub-contractors to carry out the actual

    installation works. GTC shall ensure that sufficient manpower is available for the

    timely progress and completion of the works. GTC shall provide supervision to itsworkers and shall prepare coordinated shop drawings for the services installation.

    GTC shall prepare and follow schedule in line with the Master Construction

    Programme.

    G. Inspection

    Inspection procedures to ensure compliance in installation shall be carried out by

    GTC prior to the Engineers inspection and approval. Adjustments/rectifications

    shall be undertaken as required.

    H. Health and Safety

    METHODOLOGY Page 4

  • 8/22/2019 Copy of Methodology

    5/33

    GIGATECH INC.

    GTC shall carry out its works in the safest manner possible. Job hazard analysis

    shall be prepared and approved prior to setting out with specific tasks to be

    performed. The health of its workers shall be a paramount concern of GTC.

    I. Conformance Criteria and Standards

    Industry reference standards indicated in the technical specifications andconstruction contract shall be followed and complied with.

    ELECTRICAL BOXES INSTALLATION WORKS

    A. Scope of works

    This method statement describes the work execution plan for the installation of

    electrical boxes and their accessories in conjunction with the Raceways Systems

    installation. Types of electrical boxes and fittings include the following:

    1. Outlet boxes

    2. Junction boxes

    3. Splice boxes

    4. Pull boxes

    5. Floor boxes

    6. Conduit bodies

    7. Bushings

    8. Locknuts

    9. Knock out closures

    B. Preparatory Works

    Materials intended for use shall have been submitted and approved. Coordinated shop

    drawings and shall have been approved for implementation. Necessary work permits

    shall have been applied for and approved including requisite Job Hazard Analyses.

    Equipment intended for use shall have been inspected and tagged safe for use. The

    labor force doing the installation work shall have undergone safety orientation and

    shall have been familiarized with the procedures related to their work.

    C. Procedures for Installation

    1. Examination

    1.1 Examine surfaces to receive raceways, boxes and enclosures forcompliance with installation tolerances and other conditions affecting

    performance of raceway installation.

    1.2 Do not proceed with installation until unsatisfactory conditions have

    been corrected.

    1.3 Review all approved shop drawings to avoid conflicting interferences

    and minimize site adjustments.

    1.4 Outlet boxes to be provided shall not be smaller that required and

    shall be larger if required by Code for the number and size of

    conductors to be installed.

    2. Block Out Work2.1 Block out work shall be implemented during setting up of formworks.

    METHODOLOGY Page 5

  • 8/22/2019 Copy of Methodology

    6/33

    GIGATECH INC.

    2.2 Prepare all block outs and ensure the use of proper materials.

    2.3 Coordinate with the general contractor and set the sleeves/block outs.

    2.4 Where embedded raceways terminate to embedded boxes, electrical

    boxes should be accurately installed to form as the blocking-out work

    itself.

    2.5 Outlet boxes installed in poured concrete or cast in place shall beconcrete-tight type. The box depth shall allow 50mm minimum on

    concrete cover.

    3. Meeting

    3.1 Coordinate and confirm schedule and sequence of work with other

    trades.

    3.2 Coordinate and confirm installation procedure

    3.3 Prepare and secure necessary permits (installation permit, hot works

    permits, etc.) before actual start of installation work.

    4. Marking

    4.1 Mark another locations in accordance with the specified spacing

    requirement

    4.2 Check actual condition of anchors.

    5. Hangers/supports

    5.1 Hangers and supports installation is to be implemented upon stripping

    of formworks.

    5.2 Install hangers/supports according to specified material, size, type and

    spacing.

    5.3 Where support members are welded to structural building framing,scrape, brush, clean and apply one coat of zinc rich primer to welding.

    5.4 Support every box from structure as follows:

    5.4.1 Secure to wood screws

    5.4.2 Secure to hallow masonry with toggle bolts

    5.4.3 Secure to metal with sheet metal screws, machine bolts

    or clamps

    5.4.4 Anchors for solid masonry and concrete shall be

    expansion shields or lead shields with machine bolts.

    Power actuated pin stud may be used.

    5.4.5 Secure outlet boxes to metal studs with spring steel

    clamp which wraps around entire face of stud and digsinto both sides of stud. Clamp shall be screwed to stud.

    5.4.6 Where box is supported/suspended below structure,

    support from structure with threaded steel rod. Secures

    rod directly to outlet boxes with double nuts. For boxes

    larger than 450mmx450mmx150mm, construct

    40mmx40mmx14 gauge metal channel frame and

    secured by bolts to box. The frame is secured to

    threaded rod at each corner.

    5.4.7 Boxes directly attached to structure shall be supported

    in conformance with the code.

    METHODOLOGY Page 6

  • 8/22/2019 Copy of Methodology

    7/33

    GIGATECH INC.

    6. Electrical Boxes Installation

    6.1 All electrical boxes shall be complete accessible as required by Code.

    Provide access panels in any non-accessible spaces to allow access to

    boxes installed.6.2 Installation of electrical boxes is to be implemented upon completion

    of hangers and supports installation and will coincide with the wet

    works stage (partition, topping, etc.)

    6.3 Install and seal electrical boxes in accordance with approved shop

    drawings.

    6.4 Provide an outlet box for each lighting fixtures or as indicated on the

    drawings.

    6.5 Outlet boxes for flush mounted lighting fixtures shall be accessible.

    Where fixture installation is in non-accessible ceiling or box stud

    mounted, outlet box shall be accessible when fixture is removed.

    6.6 Set outlet for flush mounted devices to within 4mm of finished wall.

    Box extension rings will be used as necessary.

    6.7 Supports pull boxes independently. Do not put support from conduit.

    6.8 Remove required knockouts only and plug all unused openings. Use

    threaded plugs for cast boxes and snap-in metal plugs for sheet metal

    boxes.

    6.9 Outlet boxes in the same wall shall not be mounted back-to-back.

    Offset 150mm minimum.

    6.10Install pull boxes only in unfinished spaces or concealed above

    ceilings, except when indicated on the drawings or approved by the

    Consultant.6.11Install pull boxes when any of the following conditions apply:

    6.11.1 Where indicated on the drawings

    6.11.2 Where conduit runs exceed 45m, or as prescribed in the

    specifications, from box to box from box to terminal.

    6.11.3 Where a conduit run contains more than 4-90 degree

    bends or the equivalent of offsets.

    6.11.4 To facilitate conductor installation or to ensure that the

    manufacturers maximum pulling tension is not

    exceeded.

    6.11.5 As described in the raceway system section of the

    specifications for crossing expansion joints.6.12 Junction boxes/pull boxes installed in finished spaces shall be flush

    mounted cabinets provided with trim; hinged door and flush latch and

    lock to match panel trim for flush mounted electrical panelboards.

    6.13Conductors shall not be spliced in pull boxes except when approved in

    writing by the Engineer or where shown in drawings using approved

    splicing methods.

    6.14Where a pull box is required, one shall be installed for each individual

    branch circuit conduit or each feeder. It shall contain only the feeder

    conductors or those conductors in the conduit. A combined pull box

    for multiple branch conduits or feeders is not permitted unless

    approved by the Engineer or indicated in the drawings. Wheremultiple circuits are permitted within a pull box, circuit conductors

    METHODOLOGY Page 7

  • 8/22/2019 Copy of Methodology

    8/33

    GIGATECH INC.

    and feeders shall be individually laced with nylon tie straps with the

    identification tabs to permit identification of each circuit feeder within

    the pull box.

    6.15Box covers shall be in place and completely secured to the box.

    7. Cleaning

    On completion of installation, including outlet fittings and devices, inspect exposed

    finish. Remove burrs, dirt and construction debris and repair damaged finish,

    including chips, scratches and abrasions.

    8. As-built drawings

    8.1 As-built drawings shall be progressively prepared as installation

    proceeds.

    D. Equipment and tools

    1. Hydraulic puncher

    2. Electric drill

    3. Power jigsaw

    4. Grinder

    5. Hand tools

    E. Materials

    Materials to be used shall be approved brands. Similarly fittings and accessories

    shall be approved brands. Submittals and samples shall be submitted for approvalfollowing the technical specifications.

    F. Personnel Responsibilities and Supervision

    Gigatech Inc. shall provide direct labor or sub-contractors to carry out the actual

    installation works. GTC shall ensure that sufficient manpower is available for the

    timely progress and completion of the works. GTC shall provide supervision to its

    workers and shall prepare coordinated shop drawings for the services installation.

    GTC shall prepare and follow a schedule in line with the Master Construction

    Programme.

    G. Inspection

    Inspection procedures to ensure compliance in installation shall be carried out by

    the GTC prior to the Engineers inspection and approval.

    Adjustments/rectifications shall be undertaken as required.

    H. Health and Safety

    GTC shall carry out its works in the safest manner possible. Job hazard analyses

    shall be prepared and approved prior to setting out with specific tasks to be

    performed. The health of its workers shall be a paramount concern of GTC.

    METHODOLOGY Page 8

  • 8/22/2019 Copy of Methodology

    9/33

    GIGATECH INC.

    I. Conformance Criteria and Standards

    Industry reference standards indicated in the technical specifications and

    construction contract shall be followed and complied with.

    WIRES AND CABLES (600V & Below) INSTALLATION WORKS

    A. Scope of works

    This method statement describes the work execution plan for installation of wires

    and cables for power, control, communication and signal systems.

    B. Preparatory Works

    Materials intended for use shall have been submitted and approved. Coordinated

    shop drawings and shall have been approved for implementation. Necessary work

    permits shall have been applied for and approved including requisite Job Hazard

    Analysis. Equipment intended for used shall have been inspected and tagged safe

    for use the labor force doing the installation work shall have undergone safety

    orientation and shall have been familiarized with the procedures related to their

    work.

    C. Procedure for Installation

    1. Examination

    1.1 Examine raceways, boxes and enclosures to receive wires and cables

    for compliance with installation tolerances and other conditionsaffecting performance of installation.

    1.2 Do not proceed with installation until satisfactory conditions have

    been corrected.

    1.3 Do not pull wires and cables in raceways unless the raceway run is

    complete.

    1.4 Do not install more conductors in a raceway other than indicated on

    the drawings.

    2. Delivery and Storage

    2.1 Deliver wires and cables in undamaged factory packaging

    2.2 Stores wires and cables on elevated platforms in a clean, dry location.Protect from dirt, fumes, water and construction debris and traffic.

    3. Meeting

    3.1 Coordinate and confirm schedule and sequence of work with other

    trades.

    3.2 Coordinate and confirm installation procedure.

    3.3 Prepares and secure necessary permits (Installation permit, hot works

    permit, etc.) before actual start of installation work.

    4. Installation

    METHODOLOGY Page 9

  • 8/22/2019 Copy of Methodology

    10/33

    GIGATECH INC.

    4.1 Pull the wires/cables using prescribed pull wires except where

    conductors are indicated or specified to be installed other than in a

    raceway.

    4.2 Conductors within all pull boxes and/or enclosures shall be grouped

    and identified with nylon tie straps with circuit identification tag.

    4.3 Provide identification on each control conductor at its terminal pointswith wrap-around tape wire/cable markers. ID to indicate terminal

    block and point designation per control diagrams.

    4.4 Color code all secondary service, feeder and branch circuit conductors

    4.5 When connecting conductors, torque each terminal connection to the

    manufacturers recommended torque value. A calibrated torqueing

    tool shall be used to insure proper torque application.

    4.6 Approved compression-type lugs and connectors shall be used for

    termination as prescribed per conductor size.

    4.7 Maintain phase sequence on all three-phase circuits as established

    from the service equipment throughout the entire project.

    4.8 Group and lace with nylon tie straps all conductors within enclosures,

    e.g. panels, motor controllers, motor control center, switchboards,

    terminal cabinets and fire alarm cabinets.

    4.9 Make splices with conductors only within junction/splice boxes,

    wiring troughs and other enclosures as permitted by Code. Do not

    splice conductors in pull boxes, panel boards, safety switches,

    switchboard and motor controllers or motor control centers.

    4.10 Support conductors installed in vertical raceways at intervals

    not exceeding distances as prescribed by Code

    4.11 Control, communications or signal conductors shall be installed

    in separate raceway systems.

    5. Testing and Commissioning

    5.1 Perform inspection and test procedures as prescribed in the

    specifications.

    5.2 Conduct in-house prescribed wires/cable tests.

    5.3 If the in-house wires/cable tests pass or meet the requirements,

    conduct witnessed tests with the presence of the Third Party testing

    entity and the Owners representative

    5.4 Record the results in prescribed/approved forms. The completed test

    forms shall be signed by the Third Party testing entity and the

    Owners representative.5.5 Prior to energization of wires and bales rated 600V, the following tests

    and inspections shall be carried out.

    5.5.1 Confirm that all terminations are tight and that all wires

    and cables are correctly identified and adequately

    protected against mechanical damage and abrasion.

    5.5.2 Test polarity to ensure that all single pole and protective

    devices are connected in the phase conductor only and

    that all multi-pole devices are connected with correct

    phase sequence.

    5.6 Completed test report forms shall be submitted to the Engineer.

    6. As-Built Drawings

    METHODOLOGY Page 10

  • 8/22/2019 Copy of Methodology

    11/33

    GIGATECH INC.

    6.1 As built-drawings shall be progressively prepared and installation

    proceeds.

    D. Equipment and Tools

    1. Hydraulic cable cutter2. Hydraulic crimping tool

    3. Megger Insulation Resistance Tester

    4. Phase sequence tester

    5. Torque wrench

    6. Cable basket

    7. Voltmeter

    8. Multi tester

    9. Clamp ampere-meter

    10. Hand tools

    E. Materials

    Materials to be sued shall be approved brands. Similarly, fittings and accessories

    shall be of approved brands. Submittals and samples shall be submitted for

    approval following the technical specifications.

    F. Personnel Responsibilities and Supervision

    Gigatech Inc. shall provide direct labor or sub-contractors to carry out the actual

    installation works. GTC shall ensure that sufficient manpower is available for thetimely progress and completion of the works. GTC shall provide supervision to its

    workers and shall prepare coordinated shop drawings for the services installation.

    GTC shall prepare and follow a schedule in line with the Master Construction

    Programme.

    G. Inspection

    Inspection procedures to ensure compliance in installation shall be carried out by

    GTC prior to the Engineers inspection and approval. Adjustments/rectifications

    shall be undertaken as required.

    H. Health and Safety

    GTC shall carry out its works in the safest manner possible. Job hazard analysis

    shall be prepared and approved prior to setting out with specific tasks to be

    performed. The health of its worker shall be a paramount concert of GTC.

    I. Conformance Criteria and Standards

    Industry reference standards indicated in the technical specifications and

    construction contract shall be followed and complied with.

    METHODOLOGY Page 11

  • 8/22/2019 Copy of Methodology

    12/33

    GIGATECH INC.

    WIRING DEVICES INSTALLATION WORKS

    A. Scope of works

    This method statement describes the work execution plan for the installation of

    interior and exterior wiring devices with references to Raceways, Electrical Boxes

    and wires and cables installation methodologies. The term wiring devices shall

    include:

    1. Switches

    2. Dimmer Switches

    3. Receptacle outlets

    4. Plugs and connectors

    5. Cover plates

    B. Preparatory Works

    Materials intended for use shall have been submitted and approved. Coordinated

    shop drawings and shall have been approved for implementation. Necessary work

    permits shall have been applied for and approved including requisite Job Hazard

    Analyses. Equipment intended for used shall have been inspected and tagged safe

    for use. The labor force doing the installation work shall have undergone safety

    orientation and shall have been familiarized with the procedures related to their

    work.

    C. Procedure for Installation

    1. Examination

    1.1 Examine surfaces where the wiring devices are going to be mounted

    for compliance with installation tolerances and other conditions

    affecting performance of installation.

    1.2 Ensure that switches and wall dimmers shall located on the strike side

    of the door.

    1.3 Do not proceed with installation until satisfactory conditions have been

    corrected.

    1.4 Do not terminate the wires unless the circuit has passed the prescribedtest and accepted by the Engineer.

    1.5 Architectural and structural features shall be coordinated with wiring

    devices installation

    1.6 Review Architectural and Interior drawings for wiring devices

    requiring specific locations.

    2. Delivery and Storage

    2.1 Deliver and store wiring devices in undamaged factory packaging

    2.2 Store wiring devices on elevated platforms in a clean, dry location.

    Protect from dirt, fumes, water and construction debris and traffic.

    3. Meeting

    METHODOLOGY Page 12

  • 8/22/2019 Copy of Methodology

    13/33

    GIGATECH INC.

    3.1 Coordinate and confirm schedule and sequence of work with other

    trades

    3.2 Coordinate and confirm installation procedure

    3.3 Prepare and secure necessary permits (installation permit, hot works

    permit, etc.) before actual start of installation work.

    4. Marking

    4.1 Mark the prescribed mounting heights of the wiring devices, from the

    centreline of the wiring devices vertically measured, prior to

    positioning the outlet boxes. The vertical centreline of outlet boxes

    shall be measured as accurately as possible as if the wiring device is

    already installed.

    4.2 Mounting heights shall be based on the reference or benchmarks as

    predetermined and provided conspicuously by the structural or civil

    contractor.

    4.3 Actual surface finishes shall be obtained from the Architect to

    predetermine mounting heights.

    5. Supports and Fittings

    Ensure that supports or fixing areas according to specified materials, size, type and

    spacing.

    Ensure that supports and fixings are complete per manufacturers recommendation.

    Each wiring device shall be fixed in place, levelled and square with Architectural

    lines and finishes.

    6. Installation

    6.1 Wiring devices shall be installed in accordance with themanufacturers recommendation.

    6.2 Installation of wiring devices shall be done after completion of

    Architectural finishes

    6.3 Utmost care should be observed and practiced at all times to ensure

    neat and clean installation of wiring devices

    6.4 Approved gloves shall be worn by workers to at all times during

    installation in order to avoid marks on the finished ceiling or adjacent

    surface finishes as well as on the wiring device itself.

    6.5 For overhead installations beyond the comfortable and safe reach of

    workers, provide approved ladders.

    6.6 Local switches which are shown near doors shall be located at thestrike side of the doors as finally hung.

    6.7 Receptacles installed with major axis horizontal above the backsplash.

    6.8 Mount all wiring devices within outlet boxes to allow cover plate to be

    in contact with wall on all sides.

    6.9 Align devices with major axis of wiring device parallel to adjacent

    predominate building feature, e.g. door frames or countertops.

    6.10 Connect the grounding terminal or each wiring device to the

    equipment grounding conductor of the circuit, or where no

    equipment grounding conductor is installed, connect to the metallic

    outlet box grounding lug with a bonding jumper conductor.

    METHODOLOGY Page 13

  • 8/22/2019 Copy of Methodology

    14/33

    GIGATECH INC.

    6.11 Grounding conductors connection to wiring devices shall be made

    such that removal of the device will not interrupt the ground

    continuity of the downstream devices.

    6.12 Where outlet boxes for wiring devices are not within 4mm of

    finished wall surface, install extension ring to bring it within the

    tolerance in order to secure support for the wiring device6.13 Protect all wiring devices and cover plates from paint and

    construction debris/material. All devices and cover plates shall be

    clean, undamaged and unscratched. Delay installation of wiring

    devices until wiring work and painting or wall paper works are

    completed.

    7. Testing and commissioning

    Perform inspection and test procedure as prescribed in the specifications.

    Prior to energizing circuitry, test wiring devices for electrical continuity and correct

    polarity connections.

    After energizing circuitry, test wiring devices to demonstrate compliance with

    requirements.

    Conduct in-house prescribed tests. If the in-house tests pass or meet the requirements,

    conduct witnessed test with the present of the Third Party testing and the Owners

    representative.

    Record the results in prescribed/approved forms. The completed tests forms shall be

    signed by the Third Party testing entity and the Owners Representative.

    Completed test reports forms shall be submitted to the Engineer.

    8. As-Built Drawings

    8.1 As-built drawings shall be progressively prepared as installationproceeds.

    D. Equipment & Tools

    1. Hydraulic cable cutter

    2. Hydraulic crimping tools

    3. Megger Insulation Resistance Tower

    4. Phase sequence Tester

    5. Torque wrench

    6. Cable basket

    7. Voltmeter

    8. Multi-tester9. Clamp amper-meter

    10. Hand-tools

    E. Materials

    Materials to be used shall be approved brands. Similarly, fittings and accessories

    shall be approved brands. Submittals and samples shall be submitted for approval

    following the technical specifications.

    F. Personnel Responsibilities and Supervision

    METHODOLOGY Page 14

  • 8/22/2019 Copy of Methodology

    15/33

    GIGATECH INC.

    Gigatech Inc. shall provide direct labor or sub-contractors to carry out the actual

    installation works. GTC shall ensure that sufficient manpower is available for the

    timely progress and completion of the works. GTC shall provide supervision to its

    workers and shall prepare coordinated shop drawings for the services installation.

    GTC shall prepare and follow a schedule in line with the Master Construction

    Programme.

    G. Inspection

    Inspection procedures to ensure compliance in installation shall be carried out by

    GTC prior to Engineers inspection and approval adjustment/rectifications shall be

    undertaken as required.

    H. Health and Safety

    GTC shall carry out its works in the safest manner possible. Job hazard analyses

    shall be prepared and approved prior to setting out with specific tasks to be

    performed. The health of its workers shall be a paramount concern of GTC.

    I. Conformance Criteria and Standards

    Industry reference standards indicated in the technical specifications and

    construction contracts shall be followed and complied with.

    LIGHTING FIXTURES INSTALLATION WORKS

    A. Scope of Works

    This method statement describes the work execution plan for the installation of

    interior and exterior lighting fixtures.

    B. Preparatory Works

    Materials intended for use shall have been submitted and approved. Coordinated

    shop drawings and shall have been approved for implementation. Necessary work

    permits shall have been applied for and approved including requisite Job Hazard

    Analyses. Equipment intended for use shall have been inspected and tagged safefor use. The labour force doing the installation work shall have undergone safety

    orientation and shall have been familiarized with the procedures related to their

    work.

    C. Procedure for Installation

    1. Examination

    1.1 Examine surfaces where the lighting fixtures and/ or their supports are

    going to be mounted for compliance with installation tolerances and

    other conditions affecting performance of installation.

    METHODOLOGY Page 15

  • 8/22/2019 Copy of Methodology

    16/33

    GIGATECH INC.

    1.2 Do not proceed with installation until unsatisfactory conditions have

    been corrected.

    1.3 Do not terminate the wires unless the circuit has passed the prescribed

    test and accepted by the Engineer.

    1.4 Do not install lighting unless the supporting system for each unit is

    completed.1.5 For mounting on drop ceiling, lighting fixtures shall not be installed

    until such time the ceiling suspension systems are complete.

    2. Delivery and Storage

    2.1 Deliver and store lighting fixtures and their associated equipment in

    undamaged factory packaging.

    2.2 Store lighting fixtures with and their associated equipment on elevated

    platforms in a clean, dry location. Protect from dirt, fumes, water and

    construction debris and traffic.

    2.3 Stack lighting fixtures in undamaged factory packaging per

    manufacturers recommendation. Do not stack lighting fixtures more

    than what is allowed.

    2.4 Do not stack unpacked lighting fixtures.

    3. Meeting

    3.1 Coordinate and confirm schedule and sequence and sequence of work

    with other trades.

    3.2 Coordinate and confirm installation procedure.

    3.3 Prepare and secure necessary permits (installation permit, hot workspermit, etc.) before actual starts of installation work.

    4. Marking

    4.1 Mark anchor locations in accordance with the specified spacing

    requirement.

    4.2 Check actual condition of anchors.

    5. Hangers/Supports

    5.1 Hangers and supports installation is to be implemented upon strippingof formworks.

    5.2 Install hangers/supports according to specified materials, size, type and

    spacing.

    5.3 Where support members are welded to structural building framing,

    scrape, brush, clean and apply one coat of zinc rich primer to welding.

    5.4 All lighting fixtures shall be supported fro the building structure.

    5.5 Support all lighting fixture as recommended by manufacturer.

    5.6 Ensure that each lighting fixture weight is equally distributed to the

    support system in order to maintain a level and stable position.

    6. Installation

    METHODOLOGY Page 16

  • 8/22/2019 Copy of Methodology

    17/33

    GIGATECH INC.

    6.1 Lighting fixtures shall be installed in accordance with the

    manufacturers recommendation. Do not remove protective plastic

    covering over the fixture as delivered.

    6.2 Approved gloves shall be worn by workers to all times during

    installation in order to avoid marks on the finished ceiling or adjacent

    surface finishes as well as on the fixture itself.6.3 For overhead installations beyond the comfortable and safe reach of

    workers, provide approved ladders or erect sufficient and safe

    scaffolds. Do not place any fixture on the ladder.

    6.4 Install flush mounted fixtures in suspension system type acoustical tile

    or plaster, stucco or sheet rock ceiling with adjustable brackets integral

    with the fixture. Brackets shall be adjustable from the inside of the

    fixture.

    6.5 Install surface mounted fixtures on suspended ceilings with a light

    weight channel above the ceiling attached by nylon tie straps to two

    members of the ceiling suspension system. Two support channels are

    required for each 1.2m fixture.

    6.6 Surface and wall mounted incandescent fixtures shall be mounted on

    fixture stud in outlet box.

    6.7 Approved solder less connectors such as wire nuts shall be used for

    termination and as prescribed.

    6.8 All fixtures with lamp positions, tilt, shutter rotation or other types of

    adjustment shall be roughly adjusted at the time of installation. The

    Architect will determine the final aiming and/or adjustments of all

    adjustable fixtures during the final inspection. Fixtures serving areas

    where daylight is predominant will be adjusted after sunset.

    7. Testing and Commissioning

    7.1 Perform inspection and test procedures as prescribed in the

    specifications.

    7.2 Do not remove protective plastic covering over fixture louvers unto the

    final

    inspection. All installed fixtures shall be free from dirt or fingerprints

    prior to

    acceptance.

    7.3 All lamps shall be illuminated and operational at the time of the final

    inspection. Lamps not providing 100% output shall be replaced.7.4 Conduct in house prescribed tests. If the inhouse tests pass or meet the

    requirements, conduct witnessed tests with the presence of the Third

    Party testing entity and the Owners representative.

    7.5 Record the results in prescribed/approved forms. The completed test

    forms shall be signed by the Third Party testing entity and the Owners

    representative.

    7.6 Completed test report forms shall be submitted to the Engineer.

    8. As-Built Drawings

    8.1 As-built drawings shall be progressively prepared as installationproceeds.

    METHODOLOGY Page 17

  • 8/22/2019 Copy of Methodology

    18/33

    GIGATECH INC.

    D. Equipment & Tools

    1. Megger Insulation Resistance Tester2. Lux Meter

    3. Voltmeter

    4. Multi- Tester

    5. Clamp ampere-meter

    6. Hand tools

    E. Materials

    Materials to be used shall be approved brands. Similarly, fittings and accessories

    shall be of approved brands. Submittals and samples shall be submitted for approved

    following the technical specifications.

    F. Personnel Responsibilities and Supervision

    Gigatech Inc. shall provide direct labor or sub-contractors to carry out the actual

    installation works. GTC shall ensure that sufficient manpower is available for the

    timely progress and completion of the works. GTC shall provide supervision to its

    workers and shall prepare coordinated shop drawings for the services installation.

    GTC shall prepare and follow a schedule in line with the Master Construction

    Programme.

    G. Inspection

    Inspection procedures to ensure compliance in installation shall be carried out by

    GTC prior to the Engineers inspection and approval. Adjustments/rectifications shall

    be undertaken as required.

    H. Health and Safety

    GTC shall carry out its works in the safest manner possible. Job hazard analyses shall

    be prepared and approved prior to setting out with specific tasks to be performed. The

    health of its workers shall be a paramount concern of GTC.

    I. Conformance Criteria and Standards

    Industry reference standards indicated in the technical specifications and construction

    contract shall be followed and complied with.

    METHODOLOGY Page 18

  • 8/22/2019 Copy of Methodology

    19/33

    GIGATECH INC.

    MAIN POWER DISTRIBUTION WORKS

    A. Scope of Works

    This method statement describes the work execution plan for the installation of main

    power distribution system with references to Raceways, Electrical Boxes, Electrical

    Connections and Wires and Cables installation methodologies. The work shall

    include (applicable to and including Owner-supplied where installation shall be done

    by GTC):

    1. Main Low Voltage Switchboards

    2. Feeders

    3. Distribution panels

    4. Panel boards5. Meter Centers

    6. Motor Control Centers

    B. Preparatory Works

    Materials intended for use shall have been submitted and approved. Coordinated shop

    drawings and shall have been approved for implementation. Necessary work permits

    shall have been applied for and approved including requisite Job Hazard Analyses.

    Equipment intended for use shall have been inspected and tagged safe for use. The

    labor force doing the installation work shall have undergone safely orientation and

    shall have been familiarized with the procedures related to their work.

    All legworks and arrangements with the Power Company shall be executed for the

    permanent electrical service on behalf of the Owner. Application charges shall be to

    the account of the Owner in the event that they are not included or not available

    during tender.

    C. Procedure for Installation

    1. Examination

    1.1 Examine locations for compliance with installation tolerances and otherconditions affecting performance of installation.

    1.2 Review all details and installation particulars pertaining to Owner-

    supplied equipment.

    1.3 Do not proceed with installation until unsatisfactory conditions have been

    corrected.

    2. Delivery and Storage

    2.1 Deliver distribution equipment in undamaged factory packaging.

    2.2 Store equipment on elevated platforms in a clean, dry location. Protect

    from dirt, fumes, water and construction debris and traffic

    METHODOLOGY Page 19

  • 8/22/2019 Copy of Methodology

    20/33

    GIGATECH INC.

    2.3 As much as practicable, the equipment should be delivered and brought

    up to its actual mounting location.

    2.4 Approved hauling machinery shall be utilized.

    2.5 Do not stack distribution equipments.

    3. Meeting

    3.1 Coordinate and confirm schedule and sequence of work with other trades.3.2 Coordinate and confirm installation procedure.

    3.3 Prepare and secure necessary permits (installation permits, hot works

    permits, etc.) before actual start of installation work.

    4. Marking

    4.1 Mark anchor locations in accordance with the specified spacing requirement.

    4.2 Check actual condition of anchors.

    4.3 Mark the prescribed mounting heights of surface mounted equipment.

    Mounting heights shall be based on the references or benchmarks as

    predetermined and provided conspicuously by the structural or civil

    contractor. Actual surface finished shall be obtained from the Architect to

    predetermine mounting heights.

    5. Supports and Fixings

    5.1 Ensures that supports or fixing are according to specified material, size,

    type and spacing.

    5.2 Ensures that supports and fixing are complete per manufacturers

    recommendation.

    5.3 Each equipment shall be fixed in place, levelled and square withArchitectural lines and finishes.

    6. Installation

    6.1 Where the delivery of the equipment to its actual mounting location is not

    practical, approved system of moving the equipment shall be employed.

    6.2 Where construction elevators cannot accommodate the weight of the

    equipment and hauling crew, crane shall be used. Provide wood planks

    sufficient to support the equipment on the space where it will be placed.

    6.3 Manufacturers recommended maximum angle of tilt for certain equipment

    shall be strictly observed. Do not tilt equipment beyond what is allowed.6.4 Approved pipes shall be used as rollers to facilitate horizontal movement

    of distribution equipment where cranes and hoists are not suitable. The

    diameters of pipes together with temporary steel plate ramps shall be

    chosen so as to match the thickness of the pad where they shall be

    mounted onto.

    6.5 Utmost care and attention shall be observed when moving equipment to its

    final location so that damage to structures or the equipment itself is

    avoided.

    6.6 During hauling of equipment, prescribed security procedures shall be

    implemented to avoid personnel injury.

    6.7 Approved hardware shall be utilized to ensure levelling of equipment asrequired.

    METHODOLOGY Page 20

  • 8/22/2019 Copy of Methodology

    21/33

    GIGATECH INC.

    6.8 Surface-mounted panels shall be secured to the structure by a minimum of

    four fastening devices. Panel boards 600 amperes and higher shall be

    secured by a minimum of eight fastening devices.

    6.9 Enclosures shall be mounted where indicated on the drawings. Install

    supports to the structure with specified fastening devices.

    6.10 Flushed mounted panels in concrete structures shall be cast-in place whereconstruction is by casting. Approved fixing materials and methods shall

    be employed per case. As much as practicable, the actual panel should

    terminated to the raceway system and shall be casted in place to minimize

    removal and adjustment works.

    6.11 Attach enclosure directly to masonry, concrete or wood surfaces except in

    exterior or moist locations where 40mm stand off steel channel shall be

    provided.

    6.12 Power circuit conduits, cable and bus ways shall terminate in the respective

    section that the circuit breaker is located.

    6.13 Nylon tie straps shall be used to group conductors. Only one conductor

    shall be terminated at each terminal. Conductors shall be arranged neatly

    in the wiring space.

    6.14 Splicing conductors in equipment enclosure shall not be allowed.

    6.15 Conductors not terminating in an enclosure section or unit shall not be

    extend or pass that section or unit.

    6.16 No termination shall be allowed unless respective conductors pass the

    prescribed test and accepted by the Engineer.

    6.17 Protect all wiring distribution equipment from paint and construction

    debris/materials. All equipments shall be clean, undamaged and

    unscratched.

    7. Testing and Commissioning

    7.1 Perform inspection and test procedures as prescribed in the specifications

    and in accordance with the manufacturer recommendation.

    7.2 Prior to energizing circuitry, test equipment foe electrical continuity and

    correct polarity connections.

    7.3 After energizing circuitry, test equipment to demonstrate compliance with

    requirements.

    7.4 Conduct in-house prescribed tests. If the in-house tests pass or meet the

    requirements, conduct witnessed tests with the presence of the Third Party

    testing entity and the Owners representative.7.5 Record the results in prescribed/approved forms. The completed test

    forms shall be signed by the Third Party testing entity and the Owners

    representative.

    7.6 Completed test report forms shall be submitted to the Engineer.

    8. Field Quality Control

    8.1 Visual and Management Inspection

    8.1.1 Verify that equipment enclosure interiors are clean and free from

    accumulated dust, films, moist and other foreign material.8.1.2 Inspect and clean all bus and support insulators.

    METHODOLOGY Page 21

  • 8/22/2019 Copy of Methodology

    22/33

    GIGATECH INC.

    8.1.3 Inspect all electrical and mechanical components for condition and

    any evidence of unseated/disconnected circuit breakers.

    8.1.4 Check circuit breaker connection integrity to bus.

    8.1.5 Inspect bolted connections. Torque wrench tightens or remake

    questionable connections.

    8.1.6 Inspect for missing or loose hardware or accessories.8.1.7 Inspect ground bus connection.

    8.1.8 Operate key and door interlock devices to ensure proper operation.

    8.1.9 Protective Relays: remove relay from base. Visually inspect each

    relay and base from damage and or broken parts. Check contacts

    clearances. Check electrical connections for proper contact. Make

    adjustments as necessary.

    8.2 Electrical Tests:

    8.2.1 Insulation Resistance Test: test main secondary bus and feeder

    circuits phase-to-phase and phase to ground with all

    instrumentation and control wiring disconnected.

    8.2.2 Energize any space heater circuits to ensure proper operation.

    8.2.3 Protective Relays: Megger each relay circuit to relay frame.

    Perform operational tests as prescribed in the specifications.

    8.3 Instruments and Meter Tests: inspect panel-mounted instruments and

    meters. Clean and check for calibration accuracy. Make minor

    adjustments as necessary.

    9. As-Built Drawings

    9.1 As-built drawings shall be progressively prepared as installation proceeds.

    D. Equipment & Tools

    1. Crane

    2. Rollers

    3. Hydraulic cable cutter

    4. Hydraulic crimping tool

    5. Megger Insulation Resistance Tester6. Phase sequence tester

    7. Torque wrench

    8. Cable basket

    9. Voltmeter

    10. Multi-Tester

    11. Clamp ampere-meter

    12. Hand tools

    E. Materials

    METHODOLOGY Page 22

  • 8/22/2019 Copy of Methodology

    23/33

    GIGATECH INC.

    Materials to be used shall be approved brands. Similarly, fittings and accessories

    shall be of approved brands. Submittals and samples shall be submitted for approval

    following the technical specifications.

    F. Personnel Responsibilities and Supervision

    Gigatech Inc. shall provide direct labor or sub-contractors to carry out the actual

    installation works. GTC shall ensure that sufficient manpower is available for the

    timely progress and completion of the works. GTC shall provide supervision to its

    workers and shall prepare coordinated shop drawings for the services installation.

    GTC shall prepare and follow in line with the Master Construction Programme.

    G. Inspection

    Inspection procedures to ensure compliance in installation shall be carried out by

    GTC prior to the Engineers inspection and approval. Adjustments/rectifications shall

    be undertaken as required.

    H. Health and Safety

    GTC shall carry out its works in the safest manner possible. Job hazard analyses shall

    be prepared and approved prior to setting out with specific tasks to be performed. The

    health of its workers shall be a paramount concern of GTC.

    I. Conformance Criteria and Standards

    Industry reference standards indicated in the technical specifications and construction

    contract shall be followed and complied with.

    ELECTRICAL CONNECTIONS FOR EQUIPMENT

    A. Scope of works

    This method statement describes the work execution plan for the electrical

    connections for equipment with references to Raceways, Electrical Boxes and Wires

    and Cables, Lighting Fixtures and wiring Devices installation methodology. The typesof connections shall include the following:

    1. To switchgear and switchboards

    2. To panel boards and distribution boards

    3. To motor controllers/motor control centers

    4. To emergency generator system

    5. To busways/busducts

    6. To meter center

    7. to elevators

    8. To communications and data, controls and signalling systems

    9. To MVAC, plumbing and fire protection systems

    10. To packaged sets of mechanical equipment such as fans, pumps, compressors,etc.

    METHODOLOGY Page 23

  • 8/22/2019 Copy of Methodology

    24/33

    GIGATECH INC.

    11. To lighting fixtures and lighting controls

    12. To wiring devices

    13. To master units of FDAS, telecommunication systems, BMS, Security

    Systems and Public Address Systems

    B. Preparatory Works

    Materials intended for use shall have been submitted and approved. Coordinated shop

    drawings and shall have been approved for implementation. Necessary work permits

    shall have been applied for and approved including requisite Job Hazard Analyses.

    Equipment intended for use shall have been inspected and tagged safe for use. The

    labor force doing the installation work shall have undergone safely orientation and

    shall have been familiarized with the procedures related to their work.

    C. Procedure for Installation.

    1. Examination

    Examine all associated electrical connections for compliance with installation

    tolerances and other conditions affecting performance of installation.

    Do not proceed with installation until unsatisfactory conditions have been corrected.

    2. Meeting

    Coordinate and confirm schedule and sequence of work with other trades.

    Coordinate and confirm installation procedure.

    Prepare and secure necessary permits (installation permit, hot works permit, etc.)before actual start of installation work.

    3. Installation

    Electrical Connections shall be made in accordance with the requirements of the

    manufacturers written instructions, the Code and Industry practices.

    Equipment installation work shall be coordinated with the electrical connection work

    Electrical power connections shall be in accordance with the manufacturers written

    instructions and wiring diagrams.

    Sizes of wires and connectors shall be compatibly selected to ensure sound interfacing

    between the electrical power supply and the equipment.Wires and cables shall be prepared for termination by stripping the covering armor,

    jacket, insulation and/or shielding properly to ensure a uniform and neat appearance.

    Wires and cables shall be cut to lengths as practical as possible to allow ease of

    arrangement as well as facilitate inspection, testing and maintenance. Sufficient slack

    should be provided to allow future reconnections.

    Conductor terminations, terminal lugs, terminals as well as conductors, shall be rated

    for the operating temperature of the circuit.

    Splices shall be covered with electrical insulations equivalent to or of higher rating

    than the insulations of the conductors being spliced.

    Flexible conduits suitable to application shall be provided for motor connections and

    for other connections that will be subject for movements or vibrations.

    METHODOLOGY Page 24

  • 8/22/2019 Copy of Methodology

    25/33

    GIGATECH INC.

    4. Testing and commissioning

    Perform inspection and test procedures as prescribed in the specifications.

    Terminations shall be tightened firmly. Tightening of connections to switchgears,switchboards, transformers, panel boards, motor control centers, meter centers, and

    other power connections shall be done in the presence of the Engineer and prior to

    energization of t he equipment.

    5. As-Built Drawings

    As built drawings shall be progressively prepared as installation proceeds.

    D. Equipment and Tools

    1. Hydraulic cable cutter

    2. Hydraulic crimping tool

    3. Megger Insulation Resistance Tester

    4. Phase sequence tester

    5. Torque wrench

    6. Cable basket

    7. Voltmeter

    8. Multi-tester

    9. Clamp ampere-meter

    10. Hand tools

    E. Materials

    Materials to be used shall be approved brands. Similarly, fittings and accessories shall

    be approved brands. Submittals and samples shall be submitted for approval following

    the technical specifications.

    F. Personnel Responsibilities and Supervision

    Gigatech Inc. shall provide direct labor or sub-contractors to carry out the actual

    installation works. GTC shall ensure that sufficient manpower is available for the

    timely progress and completion of the works. GTC shall provide supervision to itsworkers and shall prepare coordinated shop drawings for the services installation.

    GTC shall prepare and follow a schedule in line with the Master Construction

    Programme.

    G. Inspection

    Inspection procedures to ensure compliance in installation shall be carried out by

    GTC prior to Engineers inspection and approval adjustment/rectifications shall be

    undertaken as required.

    H. Health and Safety

    METHODOLOGY Page 25

  • 8/22/2019 Copy of Methodology

    26/33

    GIGATECH INC.

    GTC shall carry out its works in the safest manner possible. Job hazard analyses shall

    be prepared and approved prior to setting out with specific tasks to be performed. The

    health of its workers shall be a paramount concern of GTC.

    I. Conformance Criteria and Standards

    Industry reference standards indicated in the technical specifications and construction

    contracts shall be followed and complied with.

    GROUNDING SYSTEM INSTALLATION WORKS

    A. Scope of Works

    This method statement describes the work execution plan for the installation of

    grounding system with reference to raceways, electrical boxes, wires and cables, main

    distribution and lightning protection system installation methodologies.

    B. Preparatory Works

    Materials intended for use shall have been submitted and approved. Coordinated shop

    drawings and shall have been approved for implementation. Necessary work permits

    shall have been applied for and approved including requisite Job Hazard Analyses.

    Equipment intended for used shall have been inspected and tagged safe for use. The

    labor force doing the installation work shall have undergone safety orientation and

    shall have been familiarized with the procedures related to their work.

    C. Procedure for Installation

    1. Examination

    Examine electrical system components to be connected to the grounding

    system for compliance with installation tolerances and other conditions

    affecting performance of installation.

    Do not proceed with installation until unsatisfactory conditions have been

    corrected.

    2. Meeting

    Coordinate and confirm schedule and sequence of work with other trades

    Coordinate and confirm installation procedure

    Prepares and secure necessary permits (installation permit, hot works permit,

    etc.) before actual start of installation work.

    3. Installation

    All metallic non-current carrying parts of the electrical system including

    raceways, electrical boxes, equipment enclosures, machine frames, wire

    ways and all other conductive system components in close proximitywith electrical circuits shall be grounded

    METHODOLOGY Page 26

  • 8/22/2019 Copy of Methodology

    27/33

    GIGATECH INC.

    For the utility service entrance, the star point (or neutral) of the secondary

    winding at each sub station transformer shall be solidly

    grounded/connected to ground via associated main low voltage

    switchgear ground bus.

    For separately derived system (Generator set), the frame and alternator

    winding star point ( or neutral) shall be connected solidly, separately anddirectly to ground.

    There shall be no solid connection between the utility neutral and the neutral

    of the separately derived system. There shall be no connection between

    neutral and ground other than as specified in the preceding paragraphs.

    Install grounding conductors from the main substation ground bus to the

    ground grid network.

    Bond the main water line entering the buildings as shown in the drawings.

    The following systems will be bonded to the grounding installation at the main

    sub-station ground bus as shown in the drawings:

    Cold Water piping system

    Lightning protection system

    Building steel

    Communications grounding systems

    Connections to building steel shall be made to the reinforcing steel of vertical

    columns by exothermic welding. Exothermic connections shall be of

    suitable type for each application.

    Grounding conductors for feeders and branch circuits as shown on the

    drawings shall be properly and electrically connected to their

    corresponding terminals such as ground bus and ground terminals.Attach equipment grounding conductor to the equipment to be grounded with

    bolt or sheet metal screw dedicated as grounding connection only.

    Each telephone cabinet shall be provided with separate grounding conductor

    as shown on drawings. The MDF grounding shall be connected to the

    main grounding bus as indicated.

    For each building expansion joints, a flexible copper bonding jumper shall be

    connected to the building steel by suitable from physical abuse.

    Bonding jumpers shall be installed in concealed locations away from physical

    abuse.

    Auxiliary riser closets shall be provided with separate ground riser conductor

    as shown on the drawings.Lighting fixtures shall be grounded with a green insulated ground wire secured

    to the fixture with a bond lug, screw or clip intended for the purpose.

    Approved compression-type lugs and connectors shall be used for termination

    as prescribed per conductor size.

    4. Testing and commissioning

    METHODOLOGY Page 27

  • 8/22/2019 Copy of Methodology

    28/33

    GIGATECH INC.

    Perform inspection and test procedures as prescribed in the specifications.

    Inspect wiring system junction point locations for proper grounding

    Verify connections of grounds and connection types, e.g. mechanical,

    exothermic or hydraulic

    Verify proper connection to all components of building service entrancegrounding system.

    Note all system components that are interconnected and the type of connection

    Upon completion of installation of grounding system, tests the resistance-to-

    ground of the ground grid network.

    If the in-house wire/cable tests pass or meet the requirements, conduct

    witnessed tests with the presence of the Third Party testing entity and the

    Owners representative.

    Record the results in prescribed/approved forms. The completed test forms

    shall be signed by the Third Party testing entity and the Owners

    representative.

    Completed test report forms shall be submitted to the Engineer.

    5. As-Built Drawings

    As-built drawings shall be progressively prepared as installation proceeds.

    D. Equipment and Tools

    1. Hydraulic cable cutter

    2. Hydraulic crimping tool

    3. Earth resistance tester

    4. Megger Insulation Resistance tester5. Torque wrench

    6. Multi-tester

    7. Hand tools

    GROUNDING SYSTEM INSTALLATION WORKS

    A. Scope of works

    This method statement describes the work execution plan for the installation of

    grounding system with reference to raceways, electrical boxes, wires and cables, maindistribution and lightning protection system installation methodologies.

    B. Preparatory Works

    Materials intended for use shall have been submitted and approved. Coordinated shop

    drawing and shall have been approved for implementation. Necessary work permits

    shall have been applied for approved including requisite Job Hazard Analyses.

    Equipment intended for use shall have been inspected and tagged safe for use.

    The labor force doing the installation work shall have undergone safety orientation

    and shall have been familiarized with the procedures related to their work.

    C. Procedure for Installation

    METHODOLOGY Page 28

  • 8/22/2019 Copy of Methodology

    29/33

    GIGATECH INC.

    1. Examination

    1.1 Examine electrical system components to be connected to the

    grounding system for compliance with installation tolerances and

    other conditions affecting performance of installation.

    1.2 Do not proceed with installation until unsatisfactory conditions havebeen corrected.

    2. Meeting

    2.1 Coordinate and confirm schedule and sequence of work with other

    trades.

    2.2 Coordinate and confirm installation procedure.

    2.3 Prepare and secure necessary permits (installation permit, hot works

    permit, etc.) before actual start of installation works.

    2.4

    3. Installation

    3.1 All metallic non-current carrying parts of the electrical system

    including raceways, electrical boxes, equipment enclosures, machine

    frames, wireways and all other conductive system components in

    close proximity with electrical circuits shall be grounded.

    3.2 For the utility service entrance, the star point (or neutral) of the

    secondary winding at each substation transformer shall be solidly

    grounded/connected to ground via associated main low voltage

    switchboard ground bus.

    3.3 For separately derived system (Generator set), the frame and

    alternator windings star point (or neutral shall be connected solidly,separately and directly to ground.

    3.4 There shall be no solid connection between the utility neutral and

    neutral of the separately derived system. There shall be no

    connection between neutral and ground other than as specified in the

    preceding paragraphs.

    3.5 Install grounding conductors from the main substation ground bus to

    the ground grid network.

    3.6 Bond the main water line entering the building as shown in the

    drawings.

    3.7 The following systems will be bonded to the grounding installation

    at the main sub-station ground by as shown in the drawings.3.7.1 Cold water piping system

    3.7.2 Lightning protection system

    3.7.3 Building steel

    3.7.4 Communication grounding system

    3.8 Connections to buildings steel shall be made to the reinforcing steel

    of vertical columns by exothermic welding. Exothermic connections

    shall be of suitable type for each application.

    3.9 Grounding conductors for feeders and branch circuits as shown on

    the drawings shall be properly and electrically connected to their

    corresponding terminals such as ground bus and ground terminals.

    METHODOLOGY Page 29

  • 8/22/2019 Copy of Methodology

    30/33

    GIGATECH INC.

    3.10 Attach equipment grounding conductor to the equipment to be

    grounded with bolt or sheet metal screw dedicated as grounding

    connection only.

    3.11 Each telephone cabinet shall be provided with separate grounding

    conductor as shown on the drawings. The MDF grounding shall be

    connected to the main grounding bus as indicated.3.12 For each building expansion joints, a flexible copper bonding

    jumper shall be connected to the buildings steel by suitable

    exothermic welding.

    3.13 Bonding jumpers shall be installed in concealed locations away from

    physical abuse.

    3.14 Auxiliary riser closets shall be provided with separate ground riser

    conductor as shown on the drawings.

    3.15 Lighting fixtures shall be grounded with a green insulated ground

    wire secured to the fixture with a bond lug, screw or clip intended

    for the purpose.

    3.16 Approved compression-type lugs and connectors shall be used for

    termination as prescribed per conductor size.

    4. Testing and commissioning

    4.1 Perform inspection and test procedures as prescribed in the

    specifications.

    4.2 Inspect wiring system junction point locations for proper grounding

    4.3 Verify proper connections of ground and connection types, e.g.

    mechanical, exothermic, or hydraulic

    4.4 Verify proper connection to all components of building service

    entrance grounding system.4.5 Note all system components that are interconnected and the type of

    connection.

    4.6 Upon completion of installation of grounding systems, test the

    resistance-to-ground of the ground grid network.

    4.7 If the in-house wire/cable tests pass or meet the requirements,

    conduct witnessed test with the presence of the Third Party testing

    entity and the Owners representative.

    4.8 Record the results in prescribed/approved forms. The completed test

    forms shall be signed by the Third Party testing entity and the

    Owners representative.

    4.9 Completed test report forms shall be submitted to the Engineer.

    5. As-built drawings

    As-built drawings shall be progressively prepared as installation proceeds.

    D. Equipment and Tools

    1. Hydraulic Cable Cutter

    2. Hydraulic crimping tool

    3. Earth Resistance Tester

    4. Megger Insulation Resistance Tester

    5. Torque Wrench6. Multi-tester

    METHODOLOGY Page 30

  • 8/22/2019 Copy of Methodology

    31/33

    GIGATECH INC.

    7. Hand tools

    LIGHTNING PROTECTION SYSTEM INSTALLATION WORKS

    A. Scope of Works

    This method statement describes the work execution plan for the installation

    of grounding system with references to raceways, wires and cable, main

    distribution and grounding system installation methodologies.

    B. Preparatory Works

    Materials intended for use shall have been submitted and approved.

    Coordinated shop drawings and shall have been approved for implementation.

    Necessary work permits shall have been applied for and approved including

    requisite Job Hazard Analyses. Equipment intended for use shall have been

    inspected and tagged safe for use. The labor force doing the installation work

    shall have undergone safety orientation and shall have been familiarized with

    the procedures related to their work.

    C. Procedure for Installation

    1. Examination

    1.1 Examine electrical system components to be protected by the system

    for compliance with installation tolerances and other conditions

    affecting performance of installation.1.2 Do not proceed with installation until unsatisfactory conditions have

    been corrected.

    2. Meeting

    2.1 Coordinate and confirm schedule and sequence of work with other

    trades.

    2.2 Coordinate and confirm installation procedure.

    2.3 Prepare and secure necessary permits (installation permits, hot works

    permits, etc.) before actual start of installation work.

    3. Installation

    3.1 Install lightning protection system as indicated in the drawings in

    accordance with equipment manufacturers written instructions and

    in compliance with applicable requirements of the Code and

    Standards.

    3.2 Coordinate with other work including electrical wiring and roofing

    work as necessary to interface installation of lightning protection

    system.

    3.3 Conduits intended for the down conductor from air terminals shall be

    installed maintaining a downward course and minimizing bends ofthe downward conductor as recommended by manufacturer.

    METHODOLOGY Page 31

  • 8/22/2019 Copy of Methodology

    32/33

    GIGATECH INC.

    3.4 Approved bimetallic connectors/connections suitable for the purpose

    shall be used with dissimilar metals connection.

    3.5 Bonding of metal objects and systems at roof level and elsewhere on

    the structure shall be complete as required and specified.

    3.6 Connect each down conductor independently to a ground to a ground

    rod and the grounding resistance loop.3.7 Provide equipment grounding and bonding connections sufficiently

    tight to assure permanent and affective grounds and bonds for

    specified connections.

    4. Testing and Commissioning

    4.1 Perform inspection and test procedures as prescribed in the

    specifications.

    4.2 Inspect wiring system junction point locations for proper grounding.

    4.3 Verify connections of grounds and connection types, e.g.

    mechanical, exothermic or hydraulic.

    4.4 Verify proper connection to all components of building service

    entrance grounding system.

    4.5 Note all system components that are interconnected and the type of

    connection.

    4.6 Upon completion of installation of grounding system, test the

    resistance-to-ground of the ground grid network.

    4.7 If the in-house wire/cable tests pass or meet the requirements,

    conduct witnessed tests with the presence of the Third Party testing

    entity and the Owners representative.

    4.8 Record the result in prescribed/approved forms. The completed testforms shall be signed by the Third Party testing entity and the

    Owners representative.

    4.9 Completed test report forms shall be submitted to the Engineer.

    5. As-Built Drawing

    5.1 As-built drawings shall be progressively prepared as installation

    proceeds.

    D. Equipment & Tools

    1. Hydraulic cable cutter

    2. Hydraulic crimping tool

    3. Earth Resistance Tester

    4. Megger Insulation Resistance Tester

    5. Torque wrench

    6. Multi-Tester

    7. Hand tools

    E. Materials

    METHODOLOGY Page 32

  • 8/22/2019 Copy of Methodology

    33/33

    GIGATECH INC.

    Materials to be used shall be approved brands. Similarly, fittings and

    accessories shall be of approved brands. Submittals and sample shall be

    submitted for approval following the technical specifications.

    F. Personnel Responsibilities and Supervision

    Gigatech Inc. shall provide direct labor or sub-contractors to carry out the

    actual installation works. GTC shall ensure that sufficient manpower is

    available for the timely progress and completion of the works. GTC shall

    provide supervision to its worker and shall prepare coordinated shop drawings

    for the services installation. GTC shall prepare and follow a schedule in line

    with the Master Construction Programme.

    G. Inspection

    Inspection procedures to ensure compliance in installation shall be carried out

    by GTC prior to the Engineers inspection and approval.

    Adjustments/rectifications shall be undertaken as required.

    H. Health and Safety

    GTC shall carry out its works in the safest manner possible. Job hazard

    analyses shall be prepared and approved prior to setting out with specific tasks

    to be performed. The health of its workers shall be a paramount concern of

    GTC.

    I. Conformance Criteria and Standards

    Industry reference standards indicated in the technical specifications and

    construction contract shall be followed and complied with.