Cooling Tower Inspection Checklist

Embed Size (px)

Citation preview

  • 7/27/2019 Cooling Tower Inspection Checklist

    1/9

    Kharafi National

    Project : 1670 - Ministy of Education South Surra

    Pre-shipment Inscpection Checklist

    LPO#40081610, Supply of Cooling Tower

    Vendor: Atlas Blue Co.

    Equipment Discription

    Cooling Tower Type Counter Flow

    Manufacturer Tower Engineering - USA

    Qty 2 Cooling Towers x 3 Cells (each)

    Capacity per Cell 3300 GPM

    HWT 100oF

    CWT 90oF

    EwbT 85oF

    Items to be Inspected Inspection Results

    A- Exterior

    1-Steel Support Grillage

    2-Cold Water Collection Basin

    Material Stainless Steel AISI Type 316 L

    Components / Connections Equalizer Opening

    Drain / Clean-out

    Outlet Fange drilled 125 psing 16"

    Anit-Vortex Hood

    Stainless Steel Debris Screen

    2 1/2" Make-up Connection

    4" Over Flow Stand Pipe

    Basin Depth 1 feet

    Drop Sump Depth below basin f 3 feet

    3-FibreGlass Structure

    Structural Members Pultuded FRP, Type:I, II, IV

    with synthitic polyster fiber-

    Structural Hardware 300 series Stainless Steel

    Inspected By:

    Name: Name: Name:

    Company: Company: Company:

    Signature Signature Signature

    Date: Date: Date:

    Page

  • 7/27/2019 Cooling Tower Inspection Checklist

    2/9

    Kharafi National

    Project : 1670 - Ministy of Education South Surra

    Pre-shipment Inscpection Checklist

    LPO#40081610, Supply of Cooling Tower

    Vendor: Atlas Blue Co.

    Items to be Inspected Inspection Results

    4-Air Inlet Louvers

    Casing FRP 12 oz.

    Structural Hardware Stainless Steel

    5-UV and Corrosion Protection

    outer Layer 10-15 mil thick synthetic or

    polyster fiber sufacing veil

    Second Layer 30 mils thickness polymric veil

    6-Exterior Casing

    Material 1 3/4" Pultuded FRP double wall construction panels

    Panels Color Light grey

    Hardware SS series 300 screws and heads

    neoprene washers

    7-Wind Walls 22'-3" & 22'-0" shipment length

    Material 1 3/4" Pultuded FRP double wall construction panels

    Panels Color Light grey

    Hardware SS series 300 screws and heads

    neoprene washers

    8-Partition Walls 20'-6" shipment length

    Material 1 3/4" Pultuded FRP double wall construction panels

    Panels Color Light grey

    Hardware SS series 300 screws and heads

    neoprene washers

    Inspected By:

    Name: Name: Name:

    Company: Company: Company:

    Signature Signature Signature

    Date: Date: Date:

    Page

  • 7/27/2019 Cooling Tower Inspection Checklist

    3/9

    Kharafi National

    Project : 1670 - Ministy of Education South Surra

    Pre-shipment Inscpection Checklist

    LPO#40081610, Supply of Cooling Tower

    Vendor: Atlas Blue Co.

    Items to be Inspected Inspection Results

    9-End Walls 20'-6" shipment length

    Material 1 3/4" Pultuded FRP double wall construction panels

    Panels Color Light grey

    Hardware SS series 300 screws and heads

    neoprene washers

    10-Parapet Wall

    Material 1 3/4" Pultuded FRP double wall construction panels

    Panels Color Light grey

    Hardware SS series 300 screws and heads

    neoprene washers

    11-Fan Deck

    Material Pultuded FRP deck panels + UV protection

    Hardware SS 304 fasteners

    12-Fan Stack

    Material High quality handlaid FRP + 17 mils UV gel coat protection

    Profile Curved bell inlet and velocity recovery exit

    Bolted in-place removable access panel

    Hardware SS series 300

    Bolts spans 18" centers maximum

    13-Posts /HandRail including SS

    Inspected By:

    Name: Name: Name:

    Company: Company: Company:

    Signature Signature Signature

    Date: Date: Date:

    Page

  • 7/27/2019 Cooling Tower Inspection Checklist

    4/9

    Kharafi National

    Project : 1670 - Ministy of Education South Surra

    Pre-shipment Inscpection Checklist

    LPO#40081610, Supply of Cooling Tower

    Vendor: Atlas Blue Co.

    Items to be Inspected Inspection Results

    B- Internals

    1-Fill Media Brentwood OF21MA

    Material PVC - cellular type

    Sheets Wave formed 20 mils thickness

    Flute Height 0.818 inch

    Flutes Arrangement cross-corrugated with vertical offset

    2-Hot Water Distribution FRP Header, PVC SDR-35 Laterals, ABS Nozzles

    Side Wall Entry Header

    Side Laterals PVC SDR-35

    fittings

    Nozzles Screw in type, orifice 0.81 color Pink QTY 120/Cell

    Distribution Header FRP pipe with 16" flange connection clas 150

    Hardware SS

    3-Drift Eliminator Brentwood Industries CF150 MAX-15

    3 pass design / senusoidal-shaped corrugation

    Cellular Material PVC corrugated sheet 15 mil (0.38mm)

    Stiffener Sheet Thickness 15 mil (0.38mm)

    FRP Hatch

    Max. Drift Rate 0.0015% of tower flow rate

    Inspected By:

    Name: Name: Name:

    Company: Company: Company:

    Signature Signature Signature

    Date: Date: Date:

    Page

  • 7/27/2019 Cooling Tower Inspection Checklist

    5/9

    Kharafi National

    Project : 1670 - Ministy of Education South Surra

    Pre-shipment Inscpection Checklist

    LPO#40081610, Supply of Cooling Tower

    Vendor: Atlas Blue Co.

    Items to be Inspected Inspection Results

    4-Fan Motor

    Manufacturer Siemens

    Horsepower 50/12.5 HP

    Frame 365T

    Volts/Phase/Freq. 415V/3PH/50Hz

    Speeds 1485 / 740 RPM

    Windings Single

    Enclosure TEFC - Severe Duty

    Service Factor 1.0 @ 65oC ambient

    Insulation H

    Weather Proof elect. Connection boxes

    epoxy coating

    Neoprene rubber mounts vibration isolators

    Inspected By:

    Name: Name: Name:

    Company: Company: Company:

    Signature Signature Signature

    Date: Date: Date:

    Page

  • 7/27/2019 Cooling Tower Inspection Checklist

    6/9

    Kharafi National

    Project : 1670 - Ministy of Education South Surra

    Pre-shipment Inscpection Checklist

    LPO#40081610, Supply of Cooling Tower

    Vendor: Atlas Blue Co.

    Items to be Inspected Inspection Results

    5-Speed Reducer

    Manufacturer Amarillo Gear Co.

    Model 135

    Gear Ratio 6 to 1

    Reduction Type Single

    Rated HP 54 (S.F. =2)

    Type right angle gear

    grey iron casting

    Oil fill line SS

    Vent line SS

    Oil Level Sight Glass gage

    Epoxy Coating

    Gears Spiral bevel/helical -nikel alloy steel

    Gear Housing grey iron casting

    Thrust Bearing Life 200,000 hours

    Lubrication System Splash

    input and output shafts seals dual spring loaded, double lipped

    Labyrinth plate for out put shaft also

    Oil Charge for every 6 month changing(---Litres)

    Inspected By:

    Name: Name: Name:

    Company: Company: Company:

    Signature Signature Signature

    Date: Date: Date:

    Page

  • 7/27/2019 Cooling Tower Inspection Checklist

    7/9

    Kharafi National

    Project : 1670 - Ministy of Education South Surra

    Pre-shipment Inscpection Checklist

    LPO#40081610, Supply of Cooling Tower

    Vendor: Atlas Blue Co.

    Items to be Inspected Inspection Results

    6-Mechanical Equipmet Support

    Material Single piece welded steel

    assembly, hot dipped

    7-Drive Connection

    Manufacturer Rexonord / Addax

    Model LR375.275SS

    Rated HP 79.8 (S.F. = 2)

    Torque Tube Material Composite Fiberglass

    Hubs Material 316 Stainless Steel

    Driver Shaft Guards at gear End SS

    Driver Shaft Guards at Motor E FRP

    8-Fan Assembly

    Manufacturer Cofimco

    Model 4572-8-31N/B6T

    Fan Diameter 15 feet

    No. of Blades 8

    Tip Speed 11663.2 fpm

    Fan Speed 247.5 rpm

    Type propeller

    Manual adjustable pitch

    Material Cast Aluminum Alloy

    Air Seal Disc FRP

    Harware 304 SS

    non corrosive spacer sleeve

    Inspected By:

    Name: Name: Name:

    Company: Company: Company:

    Signature Signature Signature

    Date: Date: Date:

    Page

  • 7/27/2019 Cooling Tower Inspection Checklist

    8/9

    Kharafi National

    Project : 1670 - Ministy of Education South Surra

    Pre-shipment Inscpection Checklist

    LPO#40081610, Supply of Cooling Tower

    Vendor: Atlas Blue Co.

    Items to be Inspected Inspection Results

    9-Controls

    Electronic vibration switch Metrix Model 440SR

    Power Supply 230 Volt

    Oil Level Switch Murphy EL-150-EX

    Factory installed on gear reducer

    10-External Caged Ladders 6 Nos

    Material SS (AISI Type 316)

    Flat bar with 450mm min. width

    main rail 63.5mm X 9.5mm flat bar

    rungs 1"

    Base plates 100x100x10 mm

    Safety Cages 25 x 3 mm SS flats for ladder

    11-Internal Ladders 6 Nos

    Material FRP

    12-Plenum Access 3 x 3 ft FRP each cell + 3x3 ft grating

    13-Hardware Series 300 SS

    14-Water Level Sensor Flowline "Smart-Trak" sensor with stilling well

    15-Float Valve for makeup

    line

    6 Nos

    16-Speciality Connectors/ discharge chute extension

    Inspected By:

    Name: Name: Name:

    Company: Company: Company:

    Signature Signature Signature

    Date: Date: Date:

    Page

  • 7/27/2019 Cooling Tower Inspection Checklist

    9/9

    Kharafi National

    Project : 1670 - Ministy of Education South Surra

    Pre-shipment Inscpection Checklist

    LPO#40081610, Supply of Cooling Tower

    Vendor: Atlas Blue Co.

    Items to be Inspected Inspection Results

    C-Spare Parts

    Fan motor bearing 1 Set

    full charge gear Lubrication oil 1 each gear

    Fan Blade Assembly 1 No.

    Gear Box 2 Nos.

    Shaft 1 Set

    D-Warranty

    2 years from subatantial completion date June 2014

    five years for the geares speed reducer

    15 years for PVC elements

    E-L/C Documents

    Packing List 3 copies

    Test Certificate for CT componeone original + 2 copies

    Bill of Lading triplicate Original

    Certificate of origin in

    duplicate (issued by the

    Chamber of Commerce)

    Ivoice one original + 2 copies

    Inspect ion Realease Note original

    Inspected By:

    Name: Name: Name:

    Company: Company: Company:

    Signature Signature Signature

    Date: Date: Date:

    Page