36
Mitglied der Helmholtz-Gemeinschaft Cooling Experiments at COSY in preparation for HESR COOL 09, August 30 th to September 4 th , 2009 Dieter Prasuhn

Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

Mitg

lied

der H

elm

holtz

-Gem

eins

chaf

t

Cooling Experiments at COSYin preparation for HESR

COOL 09, August 30th to September 4th, 2009

Dieter Prasuhn

Page 2: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 2COOL 09 in Lanzhou

Outline

Introduction to the COSY Facility

The HESR

Recent Cooling Experiments at COSY

Future Developments

Page 3: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 3COOL 09 in Lanzhou

The Accelerator Facility

COSY accelerates (polarized) protons and deuterons between 300/600 and 3700 MeV/c

4 internal and 3 external experimental areas

Electron cooling at low momentaStochastic cooling at high momenta

Page 4: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 4COOL 09 in Lanzhou

The Electron Cooler

Design Values

Electron energy up to 100 kV

Electron current up to 3 A

Page 5: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 5COOL 09 in Lanzhou

Stochastic CoolingHardware

2 Pickup-Tanks, 4m long, cooled to 20 K2 Kicker-Tanks, 2 m long

Frequency range: 1.0-1.8 GHz1.8-3.0 GHz

Adjustable delays for different ion velocities above β=0.85

Longitudinal Notch FilterCooling with the vertical system in „Sum-Mode“

Page 6: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

Mitg

lied

der H

elm

holtz

-Gem

eins

chaf

t

The HESR at FAIR

Page 7: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 7COOL 09 in Lanzhou

Artist’s view of

High Energy Storage RingHESR

Page 8: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 8COOL 09 in Lanzhou

Basic Data of HESR

Circumference 574 mMomentum (energy) range1.5 to 15 GeV/c (0.8-14.1 GeV)Injection of (anti-)protons from RESR at 3.8 GeV/cMaximum dipole field: 1.7 TDipole field at injection: 0.4 TDipole field ramp: 0.025 T/sAcceleration rate 0.2 (GeV/c)/s

Page 9: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 9COOL 09 in Lanzhou

Electron cooling

Electron energy range: 450 keV to 4.5 MeVElectron current up to 1 A

Allows cooling of anti-protons between1.5 GeV/c and 8.9 GeV/c

Beam Cooling in the HESR

Page 10: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 10COOL 09 in Lanzhou

Stochastic cooling(optimized for momenta above 3.8 GeV/c)

2 systems with 2-4 GHz and 4-6 GHzSeparate systems for radial, vertical and longitudinal phase spaceIndependent cooling per plane to adjust beam properties to the experimental requirements

Page 11: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 11COOL 09 in Lanzhou

Main common features of COSY and HESR

Electron coolingStochastic coolingInternal targets

Page 12: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 12COOL 09 in Lanzhou

Page 13: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 13COOL 09 in Lanzhou

Internal Target Experiments at COSY

ANKE:

• Dipol spectrometer• Polarized target• Cluster target• Solid state target

WASA:

• Solenoidal field• Pellet target

Page 14: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 14COOL 09 in Lanzhou

Internal Target Experiments at HESR

PANDA

• Solenoidal field• Forward dipol magnet• Pellet target• Cluster target

Page 15: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 15COOL 09 in Lanzhou

Studies at COSY for HESR

Prototype hardware tests

Beam – Target interaction- With stochastic cooling- With barrier bucket- Combination of barrier bucket and stochastic cooling

Electron cooling- Phase space density limits- Beam feed-back- Phase space manipulation

Page 16: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 16COOL 09 in Lanzhou

Prototype hardware tests at COSY

Barrier Bucket tests in COSY

One cavity one gapFilled with VitroPerm 500F Very compact design (length of cavity without gap: 28 cm). The length form flange to flange including the COSY gap: 50cm.

• Single sinus 5*f0 (2.5MHz) generated by 20 harmonics -> ~20% gap in antiproton beam

• Standing bucket• Voltage: 600V

1. Barrier bucket cavity

Page 17: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 17COOL 09 in Lanzhou

The principle of the Barrier Bucket

-0.1-0.08-0.06-0.04-0.02

00.020.040.060.080.1

0.0 0.5 1.0 1.5 2.0 2.5

Phasensonde mitBBAWG Signal

Barrier Bucket voltage

-0.1

-0.08

-0.06

-0.04

-0.02

0

0.02

0.04

0.06

0.08

0.1

0 0.5 1 1.5 2

time / µs

a.u.

beam-phase monitor with BBbeam-phase monitor with RF

Page 18: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 18COOL 09 in Lanzhou

2. Stochastic cooling electrodes

Page 19: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 19COOL 09 in Lanzhou

Inner part with coupling structures

Printed loop couplersSlot couplers

Page 20: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 20COOL 09 in Lanzhou

Longitudinal pickup (protons, 1.69 GeV/c, 5E10)

1958. Harmonics 1959. Harmonics

Page 21: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 21COOL 09 in Lanzhou

Slot coupler as transversal pickup:Beam centered / out of center

Betatron sidebands

only low beta-functions atinstallation point

Page 22: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 22COOL 09 in Lanzhou

Slot ring coupler as BPM

long. Spectrum vs BPM 5

02468

101214

-30 -20 -10 0 10 20

Position [mm]

Am

plitu

de [µ

V]

Noise level

Page 23: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 23COOL 09 in Lanzhou

Studies of Beam Target Interaction

• Only with stochastic cooling

• Only with RF or barrier bucket

• With the combination of stochastic cooling and RF

Page 24: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 24COOL 09 in Lanzhou

Page 25: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 25COOL 09 in Lanzhou

Page 26: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 26COOL 09 in Lanzhou

Page 27: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 27COOL 09 in Lanzhou

Advantage of the barrier bucket

Page 28: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

Mitg

lied

der H

elm

holtz

-Gem

eins

chaf

t

Electron Cooling Experiments at COSY• At low energies• Beam life time studies• Dynamic aperture calculations

Page 29: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 29COOL 09 in Lanzhou

PAX at COSYThe beam time for beam acceptance studies gaveus new insight into loss mechanisms within COSY

The electron beam size limits the dynamicacceptance of COSYThe beam lifetime (dynamic aperture) is stronglytune dependantInitial losses due to the electron cooling can bereduced by slowly increasing the electron current

Page 30: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 30COOL 09 in Lanzhou

Initial losses

Beam Intensity vs. Time

00.10.20.30.40.50.60.70.80.9

1

0 5 10 15 20

time / s

BC

T / V

BCT (20 ms injection)BCT (10 ms injection)

H_0-rate vs time

0123456789

10

0 5 10 15 20time / s

H_0

rate

/ ar

b. u

nits

H_0-Rate (20 ms injection)

H_0-Rate (10 ms injection)

Initial losses disappear at smaller injected proton beam emittance

Explanation:Protons outside the electron beam see a non-linear focussing by the electron beam

Page 31: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 31COOL 09 in Lanzhou

Recent studies to overcome initial losses:

Electron cooled beam

0.00

0.05

0.10

0.15

0.20

0.25

0.30

0 20 40 60 80 100time / sec

Beam

Inte

nsity

/arb

. uni

ts

0.0

0.5

1.0

1.5

2.0

2.5

3.0

H_0

sig

nal /

arb

. uni

ts

Page 32: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 32COOL 09 in Lanzhou

Electron cooled beam

0.00

0.05

0.10

0.15

0.20

0.25

0.30

0 20 40 60 80 100time / sec

Beam

Inte

nsity

/arb

. uni

ts

0.0

0.5

1.0

1.5

2.0

2.5

3.0

H_0

sig

nal /

arb

. uni

ts

Page 33: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 33COOL 09 in Lanzhou

Electron cooled beam

0.00

0.05

0.10

0.15

0.20

0.25

0.30

0 20 40 60 80 100time / sec

Beam

Inte

nsity

/arb

. uni

ts

0.0

0.5

1.0

1.5

2.0

2.5

3.0

H_0

sig

nal /

arb

. uni

ts

Page 34: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 34COOL 09 in Lanzhou

Beam life time in the presence of a cluster target (1014 cm-2)

beam lifetime vs. ecool current

0.0200.0400.0600.0800.0

1000.01200.01400.01600.01800.02000.0

0 50 100 150 200 250 300 350 400 450 500e_cool current / mA

1/e-

beam

life

time

/ s

lifetime target on / s

Page 35: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 35COOL 09 in Lanzhou

Explanation for the life time results

• Without electron beam the measured beam life time is consistentwith the full geometrical acceptance of COSY and the targetrelated loss rates

• The electron beam is smaller than the proton beam. Now thebeam life time can only be explained with a reduced dynamicacceptance

• The dynamic acceptance corresponds to the acceptance of theelectron beam.

• The non linear space charge of the electron beam excitesresonances of higher order and reduces the dynamic acceptance.

Page 36: Cooling Experiments at COSY in preparation for HESR · 2010. 11. 6. · August 31st, 2009 COOL 09 in Lanzhou 16 Prototype hardware tests at COSY Barrier Bucket tests in COSY One cavity

August 31st, 2009 36COOL 09 in Lanzhou

Future Developments at COSY

• Investigations of Time-of-Flight stochastic coolingTalk on Tuesday morning

• Installation of the proposed 2 MeV electron coolerTalk by Juergen Dietrich on Friday morning