The presentation explains some of the controls and compliance issues related to public sector procurement in Singapore
Citation preview
Public Sector Procurement Asia 201017-18 August 2010g
Yoong Ee Chuan, CIA, CPA, CISA, CISM
1
Evolution of public sector procurement Evolution of public sector procurement Procurement risks
Managing procurement risks Managing procurement risks Control and compliance issues
2
Paper to Digital Paper to Digital Centralisation to de-centralisation
IM3B to IM on procurement IM3B to IM on procurement Snapshot of procurement ecosystem
3
4
5
Principles remain similar i e open and fair Principles remain similar i.e. open and fair competition, transparency and value-for-money (or previously “lowest cost meeting
ifi i ”)specifications”) Procurement processes were very manual
IM3B Government Instruction Manual on IM3B – Government Instruction Manual on Procurement prescriptive rules for manual handling of procurement exercisesg p
Rules for quotations vs tenders Estimated procurement value (EPV)◦ >=$3,000 < $30,000 – quotations◦ > $70,000- tenders
6
7
Quotations Quotations◦ Less onerous compliance wise to tenders◦ Confidentiality of quotations
l d◦ Fax quotations vs mailed quotations◦ Dedicated fax, officer opening etc.◦ Posting of quotations on notice boardg q
◦ Finance Circular No 3/2010 [11 August 2010] Changes to the Quotation Processto the Quotation Process Minimum Conditions of Contract for Quotation Publication of Quotation Schedule and Corrigendum Changes
P bli i f R f Q i h “C ll d” Publication of Reasons for Quotations that are “Cancelled” or “No Award”
8
Tenders Tenders◦ Offer by vendors – more legal documentation as it
is bindingis binding◦ Confidentiality and integrity important Tender boxes system with dual key Tender opening committee Tender witnessing officers
E l i b i Evaluation by committee Award by approving authorities based on value◦ Posting of bids on notice boards◦ Posting of bids on notice boards
9
Centralisation to de-centralisation Centralisation to de-centralisation◦ THEN Central procurement office (CPO)Central procurement office (CPO) Stationeries e.g. pens obtained via CPO Savings from bulk purchases but spoilage from stock
obsolescence, matching demand/supply◦ NOW
Decentralised Decentralised E.g. e-Catalogue buy, bulk tender, GeBIZ You buy what you need, block budget aproachYou buy what you need, block budget aproach
10
IM3B to IM on procurement IM3B to IM on procurement◦ THEN Instruction manuals came in paper filesInstruction manuals came in paper files Updating was a pain, manually cross out super-ceded
paras, paste over new paras etc. People were more controls & rules conscious◦ NOW
Web based Web-based Ease of reference and ease of forgetting (in some
cases))
11
Inherent Risks Inherent Risks◦ Procurement is susceptible to corruption (in
general)general)◦ E.g. vendors gifts, ang-pows, free samples◦ Non-compliances can threaten openness, fairness
and transparency occur◦ Laxity in contract management can result in loss of
al e for monevalue-for-money◦ Report of the Auditor-General highlights cases of
non-compliancenon compliance
12
In the past: In the past:◦ AG’s Report 1994/1995 Audit of Purchases under United States Foreign MilitaryAudit of Purchases under United States Foreign Military
Sales Programme Review of Financial Systems of Singapore Armed Forces
S A i iSports Association Compliance with Government Procurement Procedures
by Statutory Boardsby Statutory Boards
13
14
15
16
Recently – Report of the Auditor-General Recently – Report of the Auditor-General FY2008/09, Auditor-General’s Overview
Areas of concern Areas of concern◦ Laxity in procurement and contract management◦ Lack of financial prudence in procurement and poorLack of financial prudence in procurement and poor
management of contracts and agreements◦ Resulting in higher expenditure for goods and g g g
services
17
Areas of concern (cont’d) Areas of concern (cont d)◦ Under-performance not detected◦ Penalties for non-performance not imposedPenalties for non performance not imposed◦ Revenues due not collected◦ Little or no assurance of value-for-money in y
projects carried out
18
19
20
21
22
People People◦ Clear from AGO report that lapses are due to the
way people interpret and enforce the rules as wellway people interpret and enforce the rules as well as implementing the procedures◦ IM3B now more principles-based, i.e. more room
for people to interpret hence critical to educate staff handling procedure about how to apply the principlesprinciples◦ IM3B now provides case studies to help us◦ But still need to inculcate controls consciousnessBut still need to inculcate controls consciousness
23
People People◦ Segregation of responsibilities Not one person do everythingNot one person do everything GeBIZ – different roles, e.g. goods received and goods
inspection must be different officers, purchasing ffi l b iofficer also cannot be approving etc.
Previously can circumvent if manual, now with GeBIZ roles, more difficultroles, more difficult
Evaluation team for tenders shouldn’t all be from the same dept/team
◦ Education and awareness of IM 3B (and 3G)◦ Trade-off between controls and efficiency
24
System of procurement System of procurement◦ Implement systems and processes that adhere to
IM3◦ But public agencies do vary in implementation E.g. of SBs that had dubious quotations◦ Get internal audit to review◦ Get internal audit to review◦ Perhaps external audit may review However, does not focus too much on internal controls
over procurement, i.e. more concerned about validity and authorisation, completeness of recording of purchasing and payment transactions then procurement principles: openness, fairness and transparency
25
GeBIZ: A game changer GeBIZ: A game changer◦ Controls are built into the procurement process◦ More difficult (but not impossible!) to circumvent
relative to manual processes◦ Examples Openness of web invitations to quotes and invitations Openness of web invitations to quotes and invitations
to tenders and request for proposals (global) Routing for approvals
f Publication of awards◦ Make full use of GeBIZ Because you HAVE to (SBs MUST follow IM3)Because you HAVE to (SBs MUST follow IM3) Because it’s good for your agency
26
Some issues for procurement managers to Some issues for procurement managers to consider:◦ To what extent does your agency adhere to IM3B/G?◦ To what extent does your agency adhere to IM3B/G?◦ To what extent is your standard operating
procedures for procurement in line with IM3B/G?p p◦ How familiar are your people with IM3B/G principles
and procedures (i.e. GeBIZ use)d d f◦ Have you set-up assurance and audit of
procurement Get your internal audit to look into it Get your internal audit to look into it Ask your external auditor to look into it
27
Understand your own control and compliance Understand your own control and compliance issues first
Auditor General’s Office will carry out audits Auditor-General s Office will carry out audits on a rotational basis◦ Your turn for procurement or contracts audit by◦ Your turn for procurement or contracts audit by
AGO will (eventually!) come ◦ At least minimise or reduce number of findings by g y
AGO (or your agency will be featured in Report of the Auditor-General FY 20XX/XX
28
Questions? Questions? Contact◦ Yoong Ee Chuan Director/Internal Audit Office◦ Yoong Ee Chuan, Director/Internal Audit Office◦ 535 Clementi Road, Singapore 599489◦ Ngee Ann Polytechnic (www np edu sg)Ngee Ann Polytechnic (www.np.edu.sg) [email protected] DID: 6460-6275 Twitter: @eechuan LinkedIn: http://sg.linkedin.com/in/eechuan