Page 1: Contract Year 1 Review IMT

Contract Year 1 ReviewIMT

Tilt Thompkins

MOS - NCSA

15 May 2002

Page 2: Contract Year 1 Review IMT

13-17 May 2002 Contract Year 1 Review 2

Program Development Approach

• Major Issues Addressed As NCSA Core Lead– Classified contract– Updating UI financial system after late start

date– Performance and Hiring as impacted by IL

State budget crisis

Page 3: Contract Year 1 Review IMT

13-17 May 2002 Contract Year 1 Review 3

Program Development Approach

• Major Issues Addressed As FAPOC– Engaging T&E Community

• Who, where, what• Level of HPC expertise

– On-site performance and security– Program development barriers

• T&E Community has limited HPC expertise• Sense that HPC/PET is trying to “tell them how to do their job”• In general, 50% of the funding for a T&E center is yearly

customer funds, and as a result, their time horizon is short (3 to 6 months)

– Projects are of limited interest given the relatively long development time

Page 4: Contract Year 1 Review IMT

13-17 May 2002 Contract Year 1 Review 4

• Top priorities: Application of HPC software tools and techniques with

live tests and hardware-in-the-loop simulations for test and evaluation.

Tools for collecting, organizing, and combining diverse information sets to optimally guide T&E decision making.

• Concentrate on: High-fidelity component and process models Real-time model execution Integration of information from disparate sources Test data repositories Optimal Test Strategy Planning Building IMT Communities of practice Training in new software tools & methodologies (Core)

Strategic Goals for IMT

Page 5: Contract Year 1 Review IMT

13-17 May 2002 Contract Year 1 Review 5

1. High-fidelity component and process models

2. Real-time models

3. Information Integration

3. Test data repositories

4. Optimal test planning

5. Building IMT communities of practice

FY02 FY03 FY04 FY05FY06IMT 002

CORE

IMT 002

CROSS-FA PROGRAMS

IMT 006

R-T INTEROPERABILITY MODEL DATA REDUCTION

FY03 PROJECT PLANNING: IMT

OPT. T&E DECISION MAKING

CORE TRANINING STATISTICSDATA REPOSITORIES

OPT. T&E DECISION MAKING

OPT. T&E DECISION MAKING

OPT. T&E DECISION MAKING

DATA REPOSITORIES

DATA REPOSITORIES

Page 6: Contract Year 1 Review IMT

13-17 May 2002 Contract Year 1 Review 6

Technical (Metrics)

• User Codes Impacted by PET

Logistics Common Model

Deployment planning and system acquisition analysis tool

TENA - Test and Training Enabling Architecture

Logical Range Enabler, see Joint Test and Training Range Roadmap (JTTRR)

Page 7: Contract Year 1 Review IMT

13-17 May 2002 Contract Year 1 Review 7

Technical (Metrics)

• User Contacts and Assistance

HPC Users: 3. Total of 9 months duration

Direct Contact:

T&E working staff: 19

T&E Management: 11

Page 8: Contract Year 1 Review IMT

13-17 May 2002 Contract Year 1 Review 8

Technical (Metrics)

• Tools introduced to community

– Parallel LCOM

Users have low HPC skills

Intensive use by 3 to 5 DoD staff

Logistics tail a major DoD expense and system evaluation criteria

Page 9: Contract Year 1 Review IMT

13-17 May 2002 Contract Year 1 Review 9

Technical (Metrics)

• Presentations Given: 5

• Conferences Held: NTR

• Workshops Held: NTR

• Seminars Held: NTR

• Training Held: In progress: WSMC intro to parallel programming, ATC datamining and data warehousing introduction

Page 10: Contract Year 1 Review IMT

13-17 May 2002 Contract Year 1 Review 10

Technical (Metrics)

• Technical Reports and Articles

– None

Page 11: Contract Year 1 Review IMT

13-17 May 2002 Contract Year 1 Review 11

IMT 002 Deployment Logistics Planning

• Objective: Implement the infrastructure needed to bring PET-1 capabilities into general DoD use

DeliverablesGreen: Generic Simulation Wrapping and convert to handle new LCOM version

Green: Improved HPC back-end and response surface generation capability

Green: Final Project Technical Report, 1 Oct 02

Yellow: Simplified User interface, 15 March 02

Yellow: Training Package – 15 April 02

Yellow: Demonstrate Mission Capable Rate Optimization– 31 May 02

• Budget - $75,000 • Period of Performance:

10/01 to 10/02

• PI: Tilt Thompkins

Yellow: Delayed for early focus on HPC back-end

Page 12: Contract Year 1 Review IMT

13-17 May 2002 Contract Year 1 Review 12

IMT 006 Training and User-Focused Workshops

• Objective: develop and deliver a user-centric training and problem development program

Deliverables

Yellow: Develop base training materials

Yellow: Deliver four four day workshops

Yellow: Deliver four, two day, training classes

• Budget - $100,000 • Period of Performance:

10/01 to 10/02

• PI: Tilt Thompkins

Developing requirements proved much more difficult than expected. Workshops now being scheduled for June and July

Page 13: Contract Year 1 Review IMT

13-17 May 2002 Contract Year 1 Review 13

IMT Invoice StatusCLIN 1 CLIN 1 CUM CLIN 4 CLIN 4 CUM

JUN 0 0

JUL 0 0

AUG 0 0

SEP 0 0

OCT 0 0 0 0

NOV 0 0 0 0

DEC 0 0 0 0

JAN 0 0 0 0

FEB 0 0 0 0

MAR 0 0 0 0

APR $141,502 $141,502 $50,966 $50,966

Page 14: Contract Year 1 Review IMT

13-17 May 2002 Contract Year 1 Review 14

IMT Budget

Project Expense ($000)

$0$20$40$60$80

$100$120$140$160$180$200

O N D J F M A M J J A S

Actual

Forecast

Plan

March - 68% of PlanForecast 90% of Plan

Page 15: Contract Year 1 Review IMT

13-17 May 2002 Contract Year 1 Review 15

IMT Budget

Core Expense ($000)

$0

$50

$100

$150

$200

$250

$300

$350

$400

$450

Actual

Forecast

Plan

March - 61% of PlanForecast 66% of Plan

Page 16: Contract Year 1 Review IMT

13-17 May 2002 Contract Year 1 Review 16

Staffing

• 2 On-Sites, ARL and AEDC

• 1 New Hire for AEDC

• 1 departed due to performance issues, ARL

• AEDC Position required 5 months to fill, security clearance issues have delayed arrival at AEDC

• ARL position now open

Page 17: Contract Year 1 Review IMT

13-17 May 2002 Contract Year 1 Review 17

Summary

• University billing mistakes resolved and invoices should reflect close to estimated.

• On-Sites– Open slot at ARL– Security issues remain at AEDC