Contract Strategies Light Rail 2

Embed Size (px)

Citation preview

  • 7/29/2019 Contract Strategies Light Rail 2

    1/14

    7202ENG

    PROJECT CONTROLAND EVALUATION

    GOLD COAST LIGHT RAIL

    CONTRACT STRATEGIES

    ALMTHAMI, KHEDHER S2187371

    MARISSA ADRAINCEM S2850497

    FRIDAY 25/05/2012

  • 7/29/2019 Contract Strategies Light Rail 2

    2/14

  • 7/29/2019 Contract Strategies Light Rail 2

    3/14

    OUTLINE

    DESIGN

    BUILD DESIGN-BID-BUILD

    DESIGN-BUILD-OPERATE-TRANSFER

    CHOSEN CONTRACT STRATEGY

    COMMENTS & QUESTION

  • 7/29/2019 Contract Strategies Light Rail 2

    4/14

    CONTRACT STRATEGIESThere are several contract strategies that could beadapted to best suit the rapid transit project, the

    following three strategies will be assessed to

    determine the most suitable strategy.

    1) DESIGNBUILD

    2) DESIGN-BID-BUILD

    3) DESIGN-BUILD-OPERATE-TRANSFER

  • 7/29/2019 Contract Strategies Light Rail 2

    5/14

    1. DESIGN

    BUILDDesign-build can be considered a two-step contract in this strategy1. The design

    2. Construction of a project

    Both are completed by a single company.

  • 7/29/2019 Contract Strategies Light Rail 2

    6/14

    1. DESIGN

    BUILDTHESIGNIFICANTDIFFERENCEBETWEENDESIGNBIDBUILD

    is also the one problem that can plague the project, due

    to the one company designing the project then

    completing construction of the project there is a greatamount of trust that is placed in the company from the

    client.

    ADVANTAGE

    Reduced delivery time from a design bid build contract,due to the nil effects of putting the construction element

    out to tender.

  • 7/29/2019 Contract Strategies Light Rail 2

    7/14

    2. DESIGN-BID-BUILD

    DESIGN-BID-BUILDCONTRACTSAPPOINTACOMPANYTO

    1. Complete the design

    2. and then following a tender

    3. and approval process an additional contract is

    awarded to a second company to complete the

    construction aspect of the project of the project.

  • 7/29/2019 Contract Strategies Light Rail 2

    8/14

    2. DESIGN-BID-BUILDTHISPROCESSALLOWSTHECLIENTTOHAVEa second company check the work practices of

    the other and therefore this will REDUCE THE

    RISK of poor workmanship and short-cuts

    devaluing the final product.

    DIFFERENCEBETWEEN DB & DBB

    Design bid build carries a SIGNIFICANTLY LONGER

    PROCESSTHANdesign build as the additional bid

    step in the program. This step can be

    summarised as the tender stage and has the

    potential to add months to the projectspractical completion date.

  • 7/29/2019 Contract Strategies Light Rail 2

    9/14

    3. DESIGN-BUILD-OPERATE-TRANSFERThe Design-Build-Operate-Transfer has the ability

    to reduce construction time, therefore,

    maintaining the clients cash flow.

  • 7/29/2019 Contract Strategies Light Rail 2

    10/14

    3. DESIGN-BUILD-OPERATE-TRANSFERTHISSYSTEMISSIMILARTOTHEDESIGNBUILDSTRATEGYhowever, prior to the project being transferred to

    the client it is operated by the contractor to produce

    revenue as part of the contract payment.

  • 7/29/2019 Contract Strategies Light Rail 2

    11/14

    3. DESIGN-BUILD-OPERATE-

    TRANSFERThis allows the design company to

    reduce their tendered price and

    attempt to make up this difference at

    the completion of the project.

    THIS STRATEGY CARRIES THE MOST

    AMOUNTOFrisk for the contractor, as it is reducing

    the number of consumers the rail

    system has and reducing the incomefor the contractor.

  • 7/29/2019 Contract Strategies Light Rail 2

    12/14

    CHOSEN CONTRACT STRATEGYTHEMOSTAPPROPRIATECONTRACTSTRATEGYFORTHELIGHTRAILPROJECTWOULDBE

    The design build operate transfer.

  • 7/29/2019 Contract Strategies Light Rail 2

    13/14

    CHOSEN CONTRACT STRATEGYSEVERALFACTORSINFLUENCETHISDECISION

    1.The risk of loss in profits following completion is

    transferred to the contractor.

    2.The current global debt crisis, this also maintainsgovernment revenue as the principle construction

    expenses are shared with the contractor.

    3. The deliver time of the project will be a top

    priority of the contractor as they seek to deliver the

    project earlier to eliminate potential costs associatedlengthy loan period

  • 7/29/2019 Contract Strategies Light Rail 2

    14/14