Upload
ngonhi
View
232
Download
5
Embed Size (px)
Citation preview
Presented by :
Hany Ismail, MSc, PMP
CONSTRUCTION CLAIMS MANAGEMENT
&
EOT DELAYS ANALYSIS
Contract Module
Part 1
CONTRACT MODULE
CONSTRUCTION CLAIMS MANAGEMENT
EOT DELAYS ANALYSIS
WWW.PLANNINGENGINEER.NET
CONTRACT IS ONE OF THE MOST IMPORTANT REFERENCES
AND DOCUMENTS FOR ANY CLAIM , YOU HAVE TO REFER
FOR EVERY ENTITLEMENT YOU ASKING FOR IN YOUR CLAIM
WITH THE CONTRACT REFERENCE AND ITS CLAUSE.
IN CONTRACT MODULE AND ITS LECTURES WE WILL FOCUS
ON SOME OF THE MOST IMPORTANT CONCEPTS AND
ESSENTIAL INFORMATION , YOU HAVE TO KNOW DURING
YOUR CLAIM PREPARATION FORM THE CONTRACT
ADMINISTRATION POINT OF VIEW.
PART 1
INTRODUCTION ABOUT CONTACTS &
CONTRACTS TYPES
CONSTRUCTION CLAIMS MANAGEMENT
EOT DELAYS ANALYSIS
WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )
Agenda • Introduction
• Construction Industry Parties
• What is Contract ?
• Contract Strategy
• Contract Need
• Contract Documents
• Contract Documents Priorities
• Construction Contract Forms
• Contracting Process
• Types of Contract
• Conditions of Contract
• Legal Laws WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Construction Industry Parties
The key parties involved in most construction projects
and considers what each of their roles are and how
they are linked to one another i.e. the contracts that are
entered into between them.
Employer
Contractor
Professional Team ( Engineer )
Sub-Contractors
Employer's Agent/Project Manager
Funder / Sponsor
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Construction Industry Parties
The relationship between all the parties differs
according to the contract type ,form and conditions.
Contractor
Engineer
Employer
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
What is a Contract
A contract is defined as: “An agreement made
between two or more parties which is enforceable by
law to provide something in return for something
else from a second party".
The two parties are expected to perform the various
obligations they have undertaken, as expressed in a
mutually agreed set of contract documents.
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Contract Strategy
Contract strategy means selecting organizational
and contractual policies required for the execution
of a specific project.
The development of the contract strategy comprises
a complete assessment of the choices available for
the management of design and construction to
maximize the probability of achieving project
objectives.
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Contract Strategy
A proper contract strategy for a project involves Four
key decisions:
Setting the project objectives and constraints.
Selecting a proper project delivery method.
Selecting a proper contract form / type.
Contract administration practices.
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Do you think …
All Agreements are Contracts ??
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Competent (legal standing) Parties
For an agreement to be a contract, there must be two or
more competent parties. In order to be considered
competent, a part must have a certain legal standing.
Proper Subject Matter
For the subject matter of a contract to be proper, the first
requirement is that it was be clearly defined as to the
rights and obligations of each party. Second, the
purpose of the contract must not violate the law.
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Consideration
There must be a lawful and valuable consideration given
to both parties. A consideration often called "Something
for Something." A consideration must, also, be possible.
Agreement
For valid contract, there must be a mutual agreement.
An agreement is considered to have been reached
when an offer made by one party is accepted by the
second party. Both parties must wish and intend their
bargain to be enforceable by law.
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Proper Form
The terms of a contract must be written so that both
parties are very sure of what their rights and
responsibilities are.
Consent (agreement) of the Parties
The agreement must be free from Misrepresentation or
Duress (by force) , ..etc.
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Contract Need
Contracts provide a description of responsibilities and
liabilities.
Contracts bind parties to their duties.
Contracts can establish a time frame for duties.
Contracts can secure payment.
Contracts can provide resources.
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
What are the …
Contract Documents??
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Contract Documents
The contract is defined by the contract documents,
which are developed from the tender documents.
Contract
Documents
Agreement Form
General Conditions
Special Conditions
Additional
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Contract Documents
1- Contract Agreement.
Which represent the final agreement document that is signed by both
parties and contains the full detailed information about them.
2- Letter of Tender.
Letter of Tender is the letter which is completed by the contractor and
contains the signed offer to the Employer.
3- Letter of Acceptance.
Letter of Acceptance” is the letter sent from the Employer to the
contractor including any annexed attached agreed between both parties.
If the Letter of Acceptance is not available it will be referred to the
Contract Agreement and related dates.
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Contract Documents
4- Conditions of Contract.
1. Special Conditions.
2. General Conditions
Which represents the rights and obligations for both parties
5- Specifications.
Which should contain a detailed description on design and material used
in execution.
6- Drawings.
Which Indicates to the drawings specified in the Specification Document
and any drawing modifications written by the Consultant.
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Contract Documents
7- Programme
Means the document(s) entitled schedules, completed by the
Contractor and submitted with the Letter of Tender, as included in
the Contract. Such document may include the Bill of Quantities,
data, lists, and schedules of rates and/or prices.
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Contract Documents Power??
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Contract Documents - Priorities
In the Case of any differences arising between the contract
documents, What is the order of documents power?
For Example :
1.The Contract Agreement 5.Drawings
2. Letter of Acceptance 6. Specifications
3. The Particular Conditions 7.B.O.Q
4. The General Conditions
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Construction Contract Forms
They are forms guide the drafting of documents on civil
engineering and construction projects for the purpose of
obtaining tenders, awarding and administering Contracts.
As such they legally define the responsibilities and duties
of Employers (who commission work) and Contractors
(who carry out work) in the Works Information such as
( Fidic Contract Forms , NEC Form , …etc.).
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Contracting Process
Prepare Tender Documents
Identify Project
Prepare Scope
Select Contract
Invite Tenders
Tender Meetings
Tender Evaluation
Place Contract
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Types of Contracts
Contract
Cost based
Cost Plus
Target Cost
Price based
Unit Price
Lump Sum
Unit Price contract
Construction Claims Management & EOT Delay Analysis – Part 1
Contract Value: Tender price is usually increased by
variations and claims.
Payment : Payment is paid monthly for all work
completed during the month or any duration agreed .
Design Changes : Offers a facility for the client to
introduce changes in the work defined in the tender
documents.
Additional Payments : Additional payments for any
changes in the work content of the contract.
Unit Price contract
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis – Part 1
Using : This contract is best suitable for repetitive
works.
Variations : Not limited
Additional Payments : For variations or quantity
increase of the items in the BOQ
Lump-sum contract
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis – Part 1
Contract Value: Single tendered price is given for the
completion of specified work by a certain date.
Payment : May be staged at intervals on the completion.
Design Changes : Contract has a very limited flexibility
for design changes.
Contract Final Price : Final price is known at tender.
Contractor Risk : High Level of Risk.
Employer Risks : Low Level of Risks, transfer risks to
the contractors.
Lump-sum contract
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis – Part 1
Using : This contract may be used for a turn key
construction
Important Risk : An important risk t the client is that of
not receiving competitive bids from desirable
contractors who may avoid a high-risk lump-sum
contract.
Variations : limited variations are expected
Additional Payments : For variations Only.
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Construction Claims Reference
to the Contract
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Construction Claims
• A construction claim is a request for payment or
time extension to which the contractor considers
him/herself entitled under the contract conditions
and terms . There are three types under which
claims are required:
Extension of time only.
Additional cost.
Both extensions of time and additional cost.
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Legal systems
Legal Systems
Civil Law
(القانون المكتوب )
Common Law
(السوابق القضائية)
Construction Claims Management ( Contract Module – Part 1 )
WWW.PLANNINGENGINEER.NET
Egypt Applicable Law
Egypt Applicable Law
Civil Law
(« القانون المدنى»القانون الخاص )
Administrative Law
(« القانون اإلدارى»القانون العام )
Law 89 and its Amendments
Law 119 year 2008 ( (قانون البناء الموحد
Arbitration Law (Law 27 year 1997)
قانون )
(التحكيم
Construction Claims Management & EOT Delay Analysis – Part 1
WWW.PLANNINGENGINEER.NET
Thank You …
Contact InfoWWW.PLANNINGENGINEER.NET
Mobile : +20 1277767728 /PlanningEngineerDotNet
We hope you enjoy our lecture today
Hope to receive your feedback and recommendations
/groups/4809645