Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 1
Contents
1. INTRODUCTION ...............................................................................................................................................3
2. CONFIRMATION OF THE MINUTES OF THE 33rd MEETING OF SRPC ...............................................................7
3. SUPPORT OF RE GENERATORS FOR REACTIVE COMPENSATION ....................................................................7
4. RAMP RATES ................................................................................................................................................. 11
5. PROCUREMENT OF POC SOFTWARE FOR DISCOMS .................................................................................... 13
6. TERMS OF REFERENCE FOR RENEWABLE INTEGRATION – TASK FORCE ...................................................... 13
7. MONITORING OF SCHEMES FUNDED FROM PSDF ....................................................................................... 14
8 TRANSMISSION CHARGES / SHARING RELATED ISSUES ............................................................................... 16
9 OPTIMUM HARNESSING OF RE IN SOUTHERN REGION ............................................................................... 21
10 ISSUES WITH OA CONSUMERS ..................................................................................................................... 23
11 PREPARATION FOR MEETING REVISED ENVIRONMENT NORMS AS PER ENVIRONMENT
(PROTECTION) AMENDMENT RULES, 2015 .................................................................................................. 25
12 COAL ISSUES ................................................................................................................................................. 27
13 STATUS OF DC/GENERATION IN ISGS ........................................................................................................... 37
14 ROADMAP TO OPERATIONALISE RESERVES IN THE COUNTRY .................................................................... 38
15 TTC/ATC ........................................................................................................................................................ 41
16 ISSUE OF PREVAILING OVER VOLTAGES IN SR GRID .................................................................................... 42
17 ISSUES IN RESPECT OF NPCIL ........................................................................................................................ 44
18 UPCOMING TRANSMISSION SYSTEM ........................................................................................................... 51
19 SCHEDULING OF MACHKUND AND TB DAM ................................................................................................ 67
20 NEW PROJECTS OF NTPC, NLC, NPCIL, JOINT VENTURE & UMPP ................................................................ 67
21 NEW PROJECTS OF STATE SECTOR & IPP ..................................................................................................... 71
22 REVIEW OF ULDC / SCADA/COMMUNICATION ............................................................................................ 72
23 URTDSM (PMU) PROJECT IN SOUTHERN REGION ........................................................................................ 75
24 EMERGENCY RESTORATION SYSTEM (ERS) .................................................................................................. 75
25 ADOPTION OF UNIFORM PROCEDURE TO PREPARE MERIT ORDER DESPATCH LIST ................................... 76
26 PROGRESS OF BUS/LINE REACTORS TO BE COMMISSIONED IN SR ............................................................. 76
27 NON-AVAILING OF OCC APPROVED SHUTDOWN ........................................................................................ 82
28 COMPLIANCE STATUS OF PHASE-I AND PHASE-II OF PROTECTION AUDIT RECOMMENDATIONS .............. 84
29 IMPLEMENTATION OF PROTECTION SUITE / PROTECTION MANAGEMENT SYSTEM (PMS) FOR
SOUTHERN REGION ...................................................................................................................................... 85
30 COMPLIANCE STATUS OF NEW PROTECTION AUDIT RECOMMENDATIONS ............................................... 87
31 AUTO-RECLOSURE IMPLEMENTATION ON ALL 220 KV & ABOVE TRANSMISSION LINES OF
SOUTHERN REGION ...................................................................................................................................... 88
32 COMPLIANCE STATUS OF PCSC RECOMMENDATIONS ................................................................................ 89
33 COMMERCIAL COMMITTEE ISSUES .............................................................................................................. 90
34 IEGC RELATED ISSUES REQUIRING ATTENTION/ACTION.............................................................................. 96
35 COMPLIANCE OF ORDER OF HON’BLE CERC IN PETITION NO. 420/MP/2014 – IN RESPECT OF LVRT
AND OTHER PROVISIONS OF CEA/CERC REGULATIONS ............................................................................. 107
36 GRID OPERATION ....................................................................................................................................... 108
37 CERTIFICATION OF NON-ISTS LINE CARRYING INTER-STATE POWER FOR THE YEAR 2018-19 .................. 115
38 EFFECT ON POC CHARGES ON ACCOUNT OF SCHEDULING WIND AND SOLAR STATIONS BY RLDC .......... 116
39 MEMBERSHIP OF TRADER IN SRPC FOR THE YEAR 2018-19 ...................................................................... 116
40 REIMBURSEMENT OF SRPC EXPENDITURE ................................................................................................. 116
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 2
41 OPERATION OF HYDRO POWER PROJECTS IN PEAKING MODE ................................................................. 116
42 RSD & TECHNICAL MINIMUM .................................................................................................................... 116
43 FREQUENT REVISION OF OUAGE PLAN BY ISG STATIONS .......................................................................... 117
44 COMPLIANCE OF CEA REGULATIONS FOR GRID CONNECTIVITY OF RENEWABLE ENERGY SOURCES ..... 117
45 SCHEDULING OF ANANTHAPURAMU ULTRA MEGA SOLAR PARK / RAMAGUNDAM SOLAR PROJECT ..... 119
46 KARAIKAL DRAWAL .................................................................................................................................... 120
47 GRID STUDY COMMITTEE (GSC) MEETINGS ON PACKAGE-A & PACKAGE-B .............................................. 120
48 OVR Grading of 400 kV and 765 kV Transmission Lines of Southern Region ............................................. 122
49 COMPLIANCE OF CERC (COMMUNICATION SYSTEM FOR INTER-STATE TRANSMISSION OF
ELECTRICITY), REGULATIONS 2017 ............................................................................................................. 122
50 SPECIAL MEETING ON THE TRIPPINGS OF POLES - 1 & 2 AT HVDC GAJUWAKA SS OF POWERGRID
(SRTS-I) ....................................................................................................................................................... 122
51 SPECIAL MEETING ON THE PENDING PROTECTION ISSUES OF PUDUCHERRY SUBSTATIONS ................... 123
52 UPCOMING RENEWABLE PROJECTS AND THEIR INTEGRATION WITH TRANSMISSION NETWORK ........... 123
53 PATROLLING / MAINTENANCE OF CRITICAL LINES AND SUBSTATIONS ..................................................... 124
54 ROSTER FOR HOSTING THE SRPC MEETINGS ............................................................................................. 124
55 CONLCUSION .............................................................................................................................................. 125
56 DATE & VENUE OF THE NEXT MEETING OF SRPC....................................................................................... 125
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 3
SOUTHERN REGIONAL POWER COMMITTEE
BENGALURU
MINUTES OF THE 34th
MEETING OF SRPC HELD ON 11
th AUGUST 2018 AT
COIMBATORE
1. INTRODUCTION
1.1 The 34th
Meeting of Southern Regional Power Committee was conducted on 11th
August
2018 at Coimbatore. The list of participants is enclosed at (Annexure-I).
1.2 On behalf of POWERGRID, Ms Seema Gupta, Director (O&P) extended a very warm
welcome to all Members to the SRPC meeting. She especially welcomed Shri K
Vijayanand, Chairperson SRPC & CMD, APTRANSCO, Shri P S Mhaske, Member
(GO&D), CEA and all other CMDs of various utilities present here. She stated it was a
proud moment for PGCIL to organize this SRPC Meeting. Being the first SRPC Meeting
after her assuming charge as Director, it becomes all the more special to her. PGCIL team
has taken all efforts for the smooth conduct of the Meeting.
Director (O&P) stated that POWERGRID requires no particular introduction since it is
keeping the flag of India high as far as technological advances are concerned, be it a 800 kV
HVDC or 765 kV lines (which are one of the highest in the world). India can boast about
one of the largest synchronous grid with all the five regions in the country connected. One
of the proud moments was when in December 2013, SR grid was connected synchronously
with the rest of the grid. Though SR was earlier connected through HVDC links, with 765
KV Raichur- Sholapur link, it got connected to NEW grid synchronously. She stated that
during the last SRPC Meeting that she attended, Raigarh-Pugalur HVDC link had been
conceived. At that time SR was facing acute shortage of power, market used to get split and
price of electricity in SR was more compared to price in other regions. Though situation had
improved with Raichur-Sholapur, but more was required to be done and in this context
Raigarh-Pugalur HVDC link was formulated. With the active support of all SR constituents
it is going to be commissioned. SRPC is on the forefront in adopting new technologies. One
example is that the first STATCOM in India had been commissioned in SR. All Members of
SRPC need to be congratulated on being progressive and visionary as to the needs of SR. As
far as POWERGRID is concerned, there is lot of feeling and importance for Southern
Region. In SR around 50 Sub stations were being operated by POWERGRID, out of which
around 10 high capacity substations had been commissioned in the last one year. The
available power transfer inter regional capacity which was around 3,450 MW in 2013 had
increased to 9,500 MW after commissioning of Raichur-Sholapur, Angul-Srikakulam,
Wardha-Nizamabad-Hyderabad and other links. For Wardha –Hyderabad, the Planning
team as well as SR team had taken lot of efforts to commission it ahead of schedule. This
enabled lower price power being available to SR constituents. Strengthening of transmission
had led to overall reduction of power prices in the country. This forum should continue to
approve schemes which are progressive and visionary. Transmission cost in the entire value
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 4
chain of production to consumption is quite minimal. The type of benefits that adequate
transmission can accrue to the system is immense. This has been witnessed in Southern
Region with saving in cost of power purchase. This was the main reason that 6,000 MW
HVDC link from Raigarh to Pugalur & 2000 MW link to Trichur were approved. Lot of
generation is available in Raigarh and thus SR constituents are certainly going to benefit.
VSC technology from Pugalur to Trichur is first of its kind in India and proudly it is in
Southern Region. There were certain ROW issues but full support is being extended by
constituent states, CEA & MoP. This is helping enable POWEGRID to complete those lines
in an effective and timely manner. There was a period when number of lines were stuck in
SR but now the situation had improved and she extended heartfelt thanks to SR constituents,
CEA & MoP for extending timely help. It had been informed that discussions in the TCC
Meeting had been fruitful and hoped that all the points would get concluded today. She
wished all the best for this 34th
SRPC Meeting, and hoped that SR would continue to come
out with new ideas to meet the challenges ahead.
1.3 PGCIL presented a shot film in which the following was highlighted:
POWERGRID a Central Navrathna PSU is one of the world‟s largest Electric Power
Transmission Company. It has been rated „Excellent‟ under MoP since 1993-94.
It has grown from 22,228 ckm (1989) to 1,45,650 ckm of transmission lines. From
35 substations to 230 substations and transformation capacity from 12,201 MVA to
3,24,244 MVA.
POWERGRID has established global presence in constructing and operating State of
the Art power transmission network in several countries.
GoI has an objective of One Nation- One Grid-One Price and POWERGRID is the
prime mover in this regard.
In April 2001, SR-I & SR-II were bifurcated for efficient operation and
management.
SR-II was established with responsibility of transmission system in TN, Karnataka,
Kerala and Puducherry.
SR-II had increased from 3,017 ckm to 32,000 ckm, 8 substations to 34 substations
and 2,890 MVA to 25,785 MVA.
SR-II had been adjudged best performing region in POWERGRID for past several
years.
SR-II is a pioneer in Hot Line maintenance techniques avoiding outage with
improved system availability. A State of the Art Unified Load Dispatch and
Communication System ensures hassle free operation of the grid.
Kalvindapattu substation is the first completely unmanned remotely operated
substation in POWERGRID. Presently, all substations in SR-II are remotely
operated.
NTAMC had been established at Manesar for remote operation and monitoring by
experts on 24x7 basis. Back up RTAMC is located at SR-II, RHQ in Bengaluru
monitors 31 substations by deploying State of the Art monitoring, visualising and
diagnostic tools. It consists of three distinct areas SCADA, RASP & VMS.
Journey to reach the objective had been overwhelmingly satisfying. As per the
MOU, 98.5 % was the target availability assigned but subsequently it has
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 5
outperformed with transmission availability of more than 99.9 % with no grid
disturbance in SR-II since 2001.
Before 2000 there were repeated blackouts in SR but establishing HVDC Talcher-
Kolar in 2003 had brought out immense stability in SR.
Kolar HVDC has achieved 100 % availability for two years at a stretch which is a
world record.
Employ Development Centre (EDC) at Hosur is established to enhance and update
employees at par with current trends in profession.
Research & development is also carried out at Research Testing and Development
Centre (RTDC) for insulating oil testing and field test.
Pavagada, a 2,000 MW Solar Power Park is being developed by KSPDCL and SR-II
is responsible for evacuation of this power.
As a Green Corridor service TN is expected to add 7,300 MW of renewable
generation through wind mills. For this SR-II had established 400/230 kV Tuticorin
GIS.
SR-II has taken pioneering steps in bringing Smart Grid technology to all facets of
power supply value chain with development of Smart Grid Pilot Project at
Puducherry through open collaboration covering all attributes of Smart Grid in
distribution system. Battery Storage System with latest technologies is installed and
already under operation.
Upcoming power transmission of HVDC link from Raigarh in Chhattisgarh to
Pugalur in Tamil Nadu in SR-II has a capacity of 6,000 MW. HVDC link from
Pugalur in Tamil Nadu to Trichur in Kerala has a capacity of 2,000 MW further
enhancing the success story of Kolar.
Business Development Department (BDD) has been successful in providing services
for State Government clients by providing inputs through consultancy works.
PowerTel network under SRTCC has crossed 10,000 kM and poised to grow further
with commencement of new projects. It has presence in thirty major cities across the
Region.
Turnover had grown from Rs. 136.7 Crores to Rs. 2047.37 Crores while profit had
grown from Rs. 72.36 (2001-)Crores to Rs. 741.41 (2017-18).
HRD, SR-II is also highly active motivating the manpower. SR-II HQ building has
been accredited 4 stars rating under GRIHA.
1.4 Shri S R Bhat, Member Secretary, SRPC extended a hearty welcome to all esteemed
Members to the 34th
Meeting of SRPC. He extended special welcome to Chairperson
SRPC & CMD, APTRANSCO & also Member (GO&D), CEA. He thanked Director,
PGCIL, ED, SR-II and the entire team for making wonderful arrangements for conduct of
the Meeting.
1.5 Shri K Vijayanand, Chairperson SRPC & CMD, APTRANSCO welcomed Shri P S
Mhaske ,Member ( GO&D) , CEA, , Director, PGCIL, MS, SRPC , MDs, Directors and
senior officers from different utilities of Southern States, SCCL, MCL, Railways,
PGCIL, NPCIL to the 34th
Meeting of SRPC. He stated that SRPC forum, over a period
of time, has immensely helped all constituent states to sort various regional issues and
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 6
created a framework to develop the power sector within the region. In the PGCIL
presentation, different works carried out by SR-I & SR-II had been highlighted. In
similar manner each and every state had grown in leaps and bound in providing quality
power to consumers of the respective states. Other organizations such as Railways, Coal
Companies, ISGS and IPPs had also helped SR in growth. It has been informed that
majority of the issues in the TCC had been discussed; deliberated and broad
understanding had been achieved. Therefore, the SRPC Agenda could now be completed
in a meaningful manner. He thanked PGCIL for making excellent arrangement for
conduct of the Meeting.
1.6 SRPC welcomed the following new Members:
Shri P S Mhaske, Member (GO & D), CEA
Shri Y Adam, Director (Grid & Tr. Mgmt), APTRANSCO, Vijayawada
Shri H Y Dora, CMD, APEPDCL, Visakhapatnam
Dr S Selvakumar, MD, KPTCL, Bengaluru
Shri K V Shivakumar, Director (Transmission), KPTCL, Bengaluru
Shri K V C Ramanajaneyalu, Chief Engineer (E), SLDC, KPTCL, Bengaluru
Shri V Bharatheesha Rao, MD I/c, PCKL, Bengaluru
Shri Vikram Kapur, Chairman, TNEB, Chennai
Shri T Senthilvelan, Director (Transmission Projects), TANTRANSCO, Chennai
Shri G Raghuma Reddy, CMD, TSSPDCL, Hyderabad
Shri Tarsem Kumar, Secretary (Power), Govt. of Puducherry, Puducherry
Ms Seema Gupta, Director (Operations), PGCIL, Gurgaon
Shri P K Agarwal, Director (Market Operation), POSOCO, New Delhi
Shri Shaji John, CEO, NTPL, Tuticorin
Shri Kulbhushan Mittal, MD, Mittal Processors Pvt Ltd., New Delhi
SRPC also welcomed Shri D S Choudhary, Station Director, KKNPP who would be taking
over shortly as Director (O), NPCIL
SRPC placed on record the excellent services rendered by the following outgoing Members:
Shri R K Verma, Member (GO & D), CEA
Shri Jawaid Akhtar, MD, KPTCL, Bengaluru
Shri H Nagesh, Director (Transmission), KPTCL, Bengaluru
Shri R V Dilip Kumar, Chief Engineer (E), SLDC, KPTCL, Bengaluru
Shri T H M Kumar, MD, PCKL, Bengaluru
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 7
Dr M Saikumar, Chairman, TNEB, Chennai
Shri M M Nayak, CMD, APSPDCL, Tirupati
Shri A Gopal Rao, CMD, TSNPDCL, Warangal
Shri Prashant Kumar Panda, Secretary (Power), Govt. of Puducherry, Puducherry
Shri K V S Baba, CMD, POSOCO, New Delhi
Shri M Prabhagar, CEO, NTPL, Tuticorin
SRPC welcomed the following Special Invitees to this Meeting:
Shri H S Bajwa, Executive Director (Coal), Railway Board
Shri Rajesh Mishra, HOD (M&S), MCL
Shri B Krishna Rao, ED, SCCL
Dr K. Balraman, Director General, NIWE
Dr K Kasthurirangaian Chairman, IWPA
Since there were a number of issues in respect of coal supply & coal transport, MCL, SCCL
& Railways had been invited by Chairperson, SRPC to attend the Meeting as Special Invitee.
1.7 The Agenda was taken up for deliberations.
2. CONFIRMATION OF THE MINUTES OF THE 33rd
MEETING OF SRPC
2.1 Minutes of the 33rd
SRPC Meeting held on 17th
February 2018 at Puducherry had been
circulated vide letter dated 13th
April 2018.
2.2 Minutes of the Meeting were confirmed.
3. SUPPORT OF RE GENERATORS FOR REACTIVE COMPENSATION
3.1 In earlier Meetings, the following had been noted:
Solar / Wind generators have controllable reactive injection / absorption capability,
which are not getting utilized fully on account of PPA commitment / penalties.
It had been suggested that SLDCs / STUs may approach their Regulator for flexible set
points as per direction of SLDCs.
In the 32nd
Meeting, TCC had opined that details could be shared by the states and the
matter could be examined to arrive at some commonality in SR.
Subsequently, the following was noted:
In the Meeting held at NIWE on 28th
April 2018, NIWE had explained that support from
RE generators for MVAR interchange was very much possible.
SRPC vide letter dated 24th
May 2018 (Annexure-II) had circulated a Note regarding
MVAR power restrictions/support from RE generators. It was felt that suitable penal
rates/incentives may need to be in place for RE generators for their contribution, in the
interest of smooth grid operation.
It was noted that reactive support was required from grid operation / reliability
perspective and the same needed to be internally discussed by the SLDC / TRANSCO /
DISCOMs / Commercial sections and then it could be taken up with the RE generators.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 8
All states had been requested to give their comments in this regard so as to help in to
arrive at consensus on this matter in Southern Region and to take the matter further.
KSEBL had informed that RE generators are not being penalized (charges suspended) on
injection or absorption of MVAR in case the same is as per SLDC instruction.
In the Special Meeting held on 09.07.2018 to discuss pending issues in respect of
Karnataka, KPTCL had informed that a Sub Committee has been agreed to be constituted
in KEGC Review meeting held on 04.07.2018 to review these aspects.
3.2 SRPC vide letter dated 24.05.2018 (Annexure-III) had taken up the issue of reactive power
support by the generating stations including RE with Hon‟ble CERC.
3.3 It may kindly be noted, that 400 kV lines connected to 400 kV Uravakonda S/S are tripping
frequently on account of persisting high voltage. Voltages at 400 kV Uravakonda S/S and
400 kV Jammalmadugu S/S were persistently very high. There were two instances of
complete outage of 400 kV Uravakonda S/S and 400 kV Jammalmadugu S/S during the
month of June 2018. This matter had also been discussed in the 75th
Meeting of Protection
Sub Committee on 28th
June 2018. It had been proposed to constitute a Group of Officers
from SRLDC, SRPC and the States who would visit major RE nodes facing high voltage
and suggest any improvement in the Operating Procedure.
3.4 The following had been deliberated in the TCC Meeting:
Contribution of RE generation towards active and reactive power support cannot be
overlooked especially since they are contributing significantly towards the demand met.
In Karnataka for instance, about 80% of the demand was met through RE sources at one
instant of time.
Billing mechanism, PPA provisions, ERC Orders etc with regard to RE reactive energy
needs to align with system grid operation requirements. Since Charges were for drawal of
reactive energy, reactive energy was always being injected into the grid irrespective of
the voltage level. Details of reactive power billing adopted in SR states for Wind and
Solar is furnished as Annexure-IV.
Circular dated 17.07.2017 of KPTCL classifying valid and invalid VAR was in line with
grid operation requirements. SRPC Secretariat vide letter dated 03.08.2018 (Annexure-
V) had taken up certain issues in this regard with KPTCL.
To verify the technical capability of RE generators, MVAR capability testing had been
carried out at Urvakonda (Wind Pooling Station) in AP on 25th
and 26th
July 2018 and at
Pavagada (Solar Pooling Station) in Karnataka on 2nd
and 3rd
August 2018. Minutes of
the meeting dated 25.07.2018 on high voltage issues at Urvakonda and Jammalmadugu
(Meeting held on 23.07.2018) are available at SRPC website. Valuable support extended
by APTRANSCO, KPTCL and also the efforts of SRLDC and SRPC Secretariat were
placed on record. KSPDCL, M/s Suzlon (Urvakonda) and M/s Adani (Pavagada) had
actively participated in the exercise which was also appreciated by the forum. Reactive
charges had been suspended on these days to faithfully measure and verify technical
capability of the turbines / inverters. Similar exercise had also been planned at Kamuthi
(Solar) for which M/s Adani and TANTRANSCO had kindly agreed.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 9
At Urvakonda there was MVAR absorption upto 400 MVAR and the voltage had touched
around 400 kV. This was an achievement because since its commissioning, the sub-
station had never recorded voltage of 400 kV. Around 8 kV voltage improvement was
attained. Technically, it had been demonstrated that reactive support was possible from
WTGs, provided commercial conditions are made favorable. Two reports had been made
by SRPC Secretariat and SRLDC which had been circulated. Urvakonda had faced two
grid disturbances in the recent past which had led to loss of generation. It was noted that
lines were getting tripped or being tripped on account of high voltage. Certain changes in
over voltage settings had been suggested for implementation in that area. Capability of
WTGs could be used to control the voltages during wind season and thus more lines can
be kept in service improving the reliability. Thus generation reliability would enhance,
during off season when reactive support would be limited , operator may be required to
take out few lines to control over voltages.
At Pavagada it was noted that each 50 MW SPD could support with 15 MVAR (though
the technical capability is more) absorption at night. During day time, 250 MVAR had
been tested against normal absorption level of around 50 MVAR (at 400 kV).
The way forward suggested is as follows:
Policy intervention for appropriate reactive energy billing to aid system operation.
Classification by KPTCL of invalid VAR (injection during high voltage and
absorption during low voltage) is in line with grid operation requirements. However,
MVAR interchange should solely be dependent on voltages and not on power factor
alone.
Billing of reactive interchange presently is only with respect to drawal of MVAR,
irrespective of Voltage/ grid requirement.
Surcharge for injection of VAR at voltages greater than 103 % and drawal of VAR
when voltages are less than 97 % needs to be implemented.
Incentivization for absorption of VAR at voltages greater than 105 % and injection of
VAR at voltages less than 95 % may need to be considered.
SPDs/Wind Developers to be advised to absorb during night time also ( as also
demonstrated by M/s Adani).
Transformer Tap position to be optimized to help improve voltages at 400 kV.
Centralized SCADA operational control needs to be in place for reactive / scheduling
requirements.
SPDs/Wind Developers should support the grid as per set points advised by
SLDC/RLDC.
All states of SR (except Karnataka) have no tariff provisions for VAR exchange by
SPDs. Voltage based tariff provisions for VAR exchange needs to be introduced.
SRLDC had stated that earlier voltages were very low and it made sense to charge for
reactive drawl. Connectivity Agreement also states that at interface point there should not
be any reactive interchange. Injecting MVAR at high voltages was undesirable from grid
operation point of view. It is high time that this forum recommended to Regulators at
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 10
Central and State that reactive interchange should be as per voltage profile. Charges for
injection of VAR at voltages greater than 103 % and drawal of VAR when voltages are
less than 97% needs to be implemented.
APTRANSCO had thanked SRPC Secretariat and SRLDC for taking the initiative to
conduct trial test at Urvakonda and stated that their reports would strengthen their case in
the plea before Hon‟ble APERC. It is being proposed to waive off reactive charges
between 0.95 lag to 0.95 lead for wind and solar generators. Before proposing to APERC
it would be put up to APPCC (Discoms Board) on 13.08.2018 and after one week, they
would approach APERC.
It was pointed out that power factor based MVAR interchange may not bring out the
desired results (issues during night and during low RE generation). Therefore, voltage
based MVAR interchange coupled with specific powers to SLDC to direct MVAR
interchange as per grid requirement was needed.
NPC had informed that MVAR interchange in the grid should be on voltage basis and the
same is as per power system principles. This has been built into the Planning Criteria of
CEA. The same is specified in clause 14.2.2, „It shall be the responsibility of the
respective utility to bring the load power factor as close to unity as possible by providing
shunt capacitors at appropriate places in their system. Reactive power flow through
400/220 kV or 400/132 kV or 220/132 (or 66) kV ICTs, shall be minimal. Wherever
voltage on HV side of such an ICT is less than 0.975 pu no reactive power shall flow
down through the ICT. Similarly, wherever voltage on HV side of the ICT is more than
1.025 pu no reactive power shall flow up through the ICT. These criteria shall apply
under the „N-0‟ conditions‟.
APTRANSCO had agreed to consider and recommend MVAR interchange, based on
voltage.
KPTCL is planning to take up the recommendation to GoK to issue directions to KERC
to ensure that PPA / billing is in line with provisions of Grid Code (voltage based MVAR
interchange). Further, as per the Hon‟ble Supreme Court Order, PPA has to be aligned in
line with provisions of the Regulations.
TANTRANSCO had informed that testing at Kamuthi had been taken up on 09.08.2018.
On account of issues in inverter settings, there was improvement of around 1 kV only,
but retesting would be taken up.
NLDC had strongly recommended for voltage based MVAR interchange since it would
improve high voltage situation and enable keeping more lines in service. This would
improve reliability for RE evacuation and would avoid stress on switchyard equipment.
The same needs to be implemented at national level also.
CEA had informed that for 500 MW and above RE generators, active and reactive power
control as per the directions of the system operators is likely to come up in the
Amendment to Connectivity Regulations of CEA.
TSTRANSCO had informed that they are already taken up the requirements to be
incorporated in the State Grid Code (as had been suggested by SRPC Secretariat) with
TSERC.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 11
TANTRANSCO and KSEBL had agreed in principle, and stated that they would take up
the issue with SERC appropriately.
Way forward in this regard was agreed in principle by all the constituents.
3.5 The following was noted in the SRPC Meeting:
Director General, NIWE informed that both Wind and Solar generators have a
capability of around 30 % of capacity as MVAR support. Tariff and commercial
mechanism is inhibiting their possible support. Further, the Regulations also talk
about active power control. NIWE is establishing testing facility for LVRT, HVRT,
active & reactive power control. All modern WTGs and inverters are capable of
supporting the grid in all respect. Only enabling Regulations as well as commercial
framework need to be in established. SRPC can take kindly note of it .
MS, SRPC informed the exercises carried out were without compromising with active
power. Technical capability had been established and with enabling regulations, PPA
conditions, ERC directions, MVAR support up to good extent could be achieved.
4. RAMP RATES
4.1 Ramp up and ramp down rates are assuming significance with higher level of RE
penetration, sudden changes in load, sudden PX schedules etc. Details of ramp rates of
RRAS stations are enclosed at Annexure-VI.
Regulation 7(4) of CEA (Technical Standard for Construction of Electrical Plant and
Electrical Lines states, „the design shall cover adequate provision for quick start up and
loading of the unit to full load at a fast rate. The unit shall have minimum rate of loading or
unloading of 3% per minute above the control load (i.e. 50% MCR)‟.
4.2 This issue had been discussed in the Meetings of OCC, wherein NTPC had pointed out that
for different make, same capacity units will be having different parameters. Also even for
same make of machines, the year of manufacturing also matters.
It was noted that Kudgi, NTPL and NTECL units had had come after 2010 and in case any
issue is being faced by generators in adhering to the Regulations, they may need to approach
CEA/Regulators. NTPC, NLC, NTPL and NTECL had agreed to discuss the matter with
their engineering division and try to improve the ramp percentages.
4.3 ISG stations under RRAS have started giving at least a ramp of 0.5%/minute which was
implemented from 16.06.2018. This had resulted in an increase in ramp of around 262
MW/block. SRPC vide letter dated 03.07.2018 (Annexure-VII) had taken up the issue of
providing ramps in the range of 1% to 1.5% /minute with NTPC, Ramagundam.
4.4 SLDCs should also ensure the enhanced ramp rates from the state generators. All units
irrespective of control area jurisdiction/ownership need to contribute with higher ramp rates.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 12
4.5 The following had been deliberated in the TCC Meeting:
NTPC had informed that at Ramagundam as per data available 0.66% was possible and it
would be implemented. Higher ramps would be tested and may be adopted in future,
since it may require more controlled operation. For other NTPC stations like Simhadri,
Kudgi and Talcher, the matter would be considered appropriately. 0.66 % would be
tested at Simhadri also.
NLCIL had stated that due to technology issues, they were constrained to restrict the
ramps. At TS-II Expn for ramping down, there was an issue since heat content remains
even after tripping of the boiler as 40-50 MW can be generated. However, they would
take up the issue with OEMs for increasing of the ramp rates.
CEA had informed that both in technical specifications as well as Regulations, it has been
mentioned that ramp rates of 3% needs to be ensured. CEA‟s Regulations were
applicable to units of Central and State and also the IPPs.
NPC had pointed out that units need to meet requirements specified for TE clearance and
also specified in the Regulations subsequently. Further, forum could consider possibility
of a mechanism that could be in place for self-improvement in ramp rates by generators.
NLDC had informed that ramps as informed by generators were being implemented
under RRAS. Ramp rate being furnished by generators needs to be examined wrt design
ramp rate as per CEA‟s Regulation. NLDC had assured that this issue would be taken up
with ISG stations at all India level.
SRLDC had pointed out that the demand rates and the RE injection/withdrawal was
within 3,000 MW/block. But as per estimate, once SR touches 4,000 MW
variation/block, present ramp rates would not suffice. Higher ramp rates in both the
direction were very much required.
PCKL had pointed out that more clarity on the ramps was required since there were
certain discrepancies in the Regulations / Technical Specifications. Higher ramp rates
were very essential in the present high RE scenario.
TCC had concluded that the ramp rates needed to be increased considering high
level of RE penetration. State sector / IPP generators were requested to kindly
improve ramp rates and SLDCs were kindly requested to implement the same.
NTECL, NTPL and NLCIL had agreed to consider increasing the ramp rates in both the
directions.
TCC had suggested that a Committee may look into provisions with regard to ramp
requirement as specified in various Regulations / specifications and expert advice of
CEA/NLDC may also be sought.
4.6 The following was deliberated in the SRPC Meeting:
SRPC agreed on TCC‟s suggestion that provisions with regard to ramp requirement as
specified in various Regulations / specifications could be looked into by a Committee.
Chairperson, SRPC suggested that advice and guidance from CEA could also be
sought.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 13
Member (GO&D), CEA kindly agreed to appraise the concerned Division, in this
regard.
SRPC noted the TCC observation that ramp rates need to be increased,
considering high level of RE penetration. State sector / IPP generators were
requested to kindly improve ramp rates. SLDCs were also kindly requested to
examine and implement the same.
5. PROCUREMENT OF POC SOFTWARE FOR DISCOMS
5.1 TANGEDCO vide letter dated 24.05.2018/22.06.2018 had informed that in the 4th
Meeting
of the Task Force on „Review of PoC in ISTS‟, it had been decided that PoC software may
be purchased at RPC level for states (extract copy enclosed as Annexure-VIII) SRPC vide
letter dated 04.06.2018 had informed TANGEDCO that the matter regarding procurement of
software at RPC level would be taken up in the next meeting of SRPC. In the 38th
Meeting
of Commercial Sub Committee held on 29th
June 2018, it was agreed that the matter would
be discussed in the ensuing meetings of TCC and SRPC.
5.2 IIT Mumbai is the developer of the PoC software identified by Hon‟ble Commission. IIT
Mumbai had informed that they will provide software for computation of sharing of inter-
state transmission charges and losses, delivered as a web-service from PowerAnser Labs
(PAL), Department of Electrical Engineering, IIT Bombay for one year. The web-service
will be in compliance with the CERC (Sharing of Interstate Transmission Charges and
Losses) Regulations, 2010, L-1/44/2010- CERC, dated 15th
June 2010 and amendments
thereof. The fee for one year usage of one (1) Institutional Licenses which will include ten
(10) user logins each will be as follows:
One Year usage fee: Rs. 32,20,000/- (Rupees Thirty Two Lakhs Twenty Thousand Only)
plus applicable GST
Ninety (90%) percent + applicable GST to be paid in advance
Balance ten (10%) percent + applicable GST to be paid at the end of the year.
5.3 The following had been concluded in the TCC Meeting after deliberations:
Chairperson, TCC had stated that at present the data provided by NLDC appears to be
adequate. However, states may take a call individually, in case they so desire, and
approach IIT, Mumbai in this regard.
5.4 SRPC noted the above.
6. TERMS OF REFERENCE FOR RENEWABLE INTEGRATION – TASK FORCE
6.1 In line with the decision taken in the 30th
Meeting of SRPC, Terms of Reference (TOR)
were finalized after consultation with stakeholders in the Subcommittee/Special Meetings.
The objective was to have a Study/Report on the TOR, by means of engaging a Consultant.
Constituent states of SRPC had agreed to share the financial commitment equally.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 14
6.2 Subsequently, Chairperson, SRPC vide letter dated 12.12.2017 addressed to MNRE had
proposed that certain specific studies could get initiated under IGEN – GEC Project being
implemented by GIZ in India on behalf of the German Federal Ministry of Economic
Cooperation and Development (BMZ).
6.3 Based on further discussion with M/s GIZ, the TOR had been refined and following scope
was agreed:
Control Reserve Dimensioning for States in Southern Region
Ancillary Services from RE and controlling RE generation during grid contingency
6.4 Further, M/s GIZ vide mail dated 03.07.2018 had informed that they had started the
procurement process. As they had to go for competitive tendering it would take about 3
months before they could sign contract with the Consultant.
6.5 SRPC noted the above.
7. MONITORING OF SCHEMES FUNDED FROM PSDF
7.1 In the 7th
Meeting of NPC held on 08.09.2017, RPCs had been further requested to examine
the implementation of PSDF funded schemes in OCC & TCC meetings and intimate NPC
about any bottlenecks.
7.2 In the 6th
Meeting of the Monitoring Group of PSDF held on 05th
January 2018 at Kochi, it
was observed that the overall progress was not very satisfactory. It had been emphasized in
that Meeting that better utilization was highly essential, especially since progress was also
being monitored by MoP.
7.3 The following had been deliberated in the TCC Meeting:
Overall status of schemes in SR as on 31st July 2018 is as given below:
S.
N
o.
State /
Entity
Total
No
of
prop
osals
Under
Approval
Not
eligible
San
ctio
ned
Grant
sanctioned
(Rs.
Crores)
Grant
Disburse
d
(Rs.
Crores)
Recen
tly
receiv
ed
Input
sought
1 Andhra
Pradesh
8 2 1 1 4 314.53 29.55
2 Karnataka 6 0 3 0 3 205.06 44.97
3 Kerala 7 0 0 1 6 581.8 166.15
4 Tamil Nadu 16 2 10 0 4 459.39 41.03
5 Telangana 12 0 6 1 5 247.72 49.93
6 Puducherry 2 0 0 0 2 13.19 0.95
7 PGCIL-SR 1 0 0 0 1 378.04 37.80
8 SRPC 2 0 0 0 2 30.59 19.01
Total 54 4 20 3 27 2230.32 389.39
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 15
In the OCC Meeting, Director, NPC had stated that there had been delays in signing of
Agreements and availing first 10 % installment, while subsequent releases had been
meager. Approved projects getting delayed beyond one year may not be eligible for
PSDF funding.
NPC had informed that at time of Kochi meeting the total disbursement was Rs. 161.8
crores while presently it was around Rs. 389.4 Crores and thus SR has certainly
progressed. This is around 17% of the grant sanctioned to SR. Kerala is progressing well
while other states need to put more efforts. Even 10% amount was not being availed by
some entities. In October/November, another round of follow up/review meeting is being
planned for SR constituents. Due to non-availing of the earlier sanctioned funds, MoP
was not releasing funds as per budget demand.
KPCL was requested to revert back on clarifications sought on DPR of Rs 156 Crores for
Modernization and Up-gradation of Control and Protection System at their Generating
Stations.
APTRANSCO had informed that PO has been placed for Reliable Communication
scheme (Rs 144 Crores) and the amount would be claimed soon. For other schemes also,
PO is under process.
TANTRANSCO had pointed that only after erection, balance 60 % is being released.
Orders for all the proposals had been placed and 20 % grant has been received. About Rs
90 crores of work is under commissioning and Rs 41 Crores would be availed within 2
months. PO for Reliable Communication scheme of Rs 139 crores is going to be placed
shortly.
KPTCL had informed that OPGW scheme was recently sanctioned, SAMAST scheme
observations would be replied back. NPC had informed that certain inputs had been
sought for SCADA scheme and the reply could be expedited by KPTCL.
KSEBL had informed that work has been nearly completed for the first scheme, but
extension was granted upto July 2018 which may need to be further extended by 3
months due to severe floods in the state. Rs. 30 Crore claim had been made which is to
be disbursed and the final claim of (Total Rs 47 Crores balance) would be made after the
works are completed, as and when water recedes. For the ADMS scheme, second claim
of 20% was pending for disbursement. Other schemes are also in the pipeline.
NLDC had stated that once the LOA had been placed, schedule needed to be followed up
vigorously. Time schedules are getting extended and extension approval getting delayed
since Appraisal Committee was not meeting frequently, resulting in delay in payments.
Getting the funds released from MoP takes around 3-4 months. Inputs sought by Techno
Economic Group also needed to be expedited for early sanctioning of DPRs.
NPC had informed that time extension approval was pending for a number of schemes. A
week before, procedure had been finalized to handle and process requests for time
extension. The procedure is for helping and facilitating the time extension requests. All
entities were requested to kindly furnish any time extension request within 15 days as per
this procedure.
SRPC had suggested that a senior Officer in each state may act as a Nodal Officer and
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 16
monitor the progress of PSDF funded schemes regularly, for better and effective
implementation.
It was agreed that periodical monitoring of PSDF funded schemes would be undertaken
at Senior Management level in each state.
7.4 SRPC noted that periodical monitoring of PSDF funded schemes would be undertaken at
Senior Management level in each state.
8 TRANSMISSION CHARGES / SHARING RELATED ISSUES
8.1 The issue of Transmission charges / sharing had been discussed in the Commercial Sub
Committee Meeting. Chairperson, SRPC vide letter dated 03.07.2018 (Annexure-IX) had
taken up the following issues with Chairperson, CERC:
a) Determination of Relinquishment Charges
Early resolution of Standard Capacity and relinquishment charges which are already
under kind consideration of Hon‟ble Commission in Petition No 92/MP/2015 would
help relieve the financial stress on DICs.
b) Transmission charges related with RE projects
The issues involved in implementation of policy regarding waiver of transmission
charges for solar evacuation under POC mechanism had been earlier taken up vide
letter dated 23.08.2017. The issue had been referred to the Task Force.
c) Recovery of Transmission Charges for delay in commissioning of SPDs
It was noted that there was a time gap between issuance of provision of Tariff Order
and Final Tariff Order. During this interim period, the charges are recovered through
POC mechanism from existing DICs, thus, causing upfront financial burden.
8.2 TANGEDCO vide letter dated 02.07.2018 (Annexure-X) had raised the following issues:
a) Issues associates with sharing of transmission charges by IPPs
It had been pointed out that Hon‟ble CERC in every tariff order directs to recover the
transmission charges as per the provisions of Sharing Regulation. The Clause (5) of
Regulation 8 of the Sharing Regulations stipulates as under:-
“(5) Where the Approved Withdrawal or Approval Injection in case of a DIC is not
materializing either partly or fully for any reason whatsoever the concerned DIC
shall be obliged to pay the transmission charges allocated under these regulations:
Provided that in case the commissioning of a generating station or unit thereof is
delayed, the generator shall be liable to pay Withdrawal Charges corresponding to
its Long term Access from the date the Long Term Access granted by CTU becomes
effective. The Withdrawal Charges shall be at the average withdrawal rate of the rate
of the target region:
In the referred case the defaulting DICs are the IPPs. Hence, the implementing
agency (NLDC) being responsible to implement the tariff orders and make PoC
computation is accountable to make the following points clear to the DICs for the
benefit of all concerned:
i. Whether the entire LTA quantum of the IPPs is considered for the purpose of
PoC calculation?
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 17
ii. Whether any clarification is obtained from Hon‟ble Commission with regard
to difficulties in implementing the orders related to the above IPPs?
iii. Any specific observation and comments of the validation committee on the
difficulties in implementing the orders.
iv. The details assets / LTA quantum to be considered for bilateral billing
furnished to SRPC.
Implementing Agency (NLDC) / CTU had been kindly requested to present their views.
b) Issues associated with transmission charges to be recovered from entities procuring
RE power and not qualified for waiver of transmission charges
MoP in its Order dated 13.02.2018 had communicated the waiver of inter-state
transmission charges and losses on transmission of the electricity generated from solar
and wind sources of energy under para 6.4(6) of the revised Tariff Policy, 2016. It had
been stated that in supersession of Ministry of Power‟s earlier order No.23/12/2016-
R&R dated 30th
September, 2016 and Order No.23/12/2016-R&R dated 14th
June,
2017, it is hereby notified that –
For generation projects based on solar and wind resources, no interstate transmission
charges and losses will be levied on transmission of the electricity through the inter-
state transmission system for sale of power by such projects commissioned till 31st
March 2022.
Provided that the above waiver will be available for a period of 25 years from the date
of commissioning till 31st March 2022.
Provided further that the above waiver will be available for solar and wind projects
entering into PPAs with all entities, including Distribution Companies for sale of
power from solar and wind power projects for compliance of their renewable
purchase obligation.
Provided further that the above waiver will be allowed only to those solar and wind
projects that are awarded through competitive bidding process in accordance with the
guidelines issued by Central Government.
This Order, irrespective of the purchasing entity, shall be applied prospectively ie from the
date of issue of Order.
CTU/NLDC had been kindly requested to elucidate on how this is being implemented.
c) Issues associated with recovery of transmission charges in respect of ultra mega solar
project at NP Kunta, Ananthapuram District, Andhra Pradesh
TANGEDCO has stated that the direction of Hon‟ble Commission in Order dated
30.06.2016 in petition No.26/TT/2016 should have been compiled by CTU and the IA.
The relevant portion of the order is extracted below:
51…………………….Accordingly the transmission tariff for the instant assets from the
date of commercial operation till the commissioning of solar generation shall be
borne by Andhra Pradesh Solar Power Corporation Pvt Ltd in line with the
Commission‟s order dated 06.05.2015 in Petition No.29/MP/2015. The relevant
portion of the order is extracted hereunder:-
„33…………….that transmission charges for delay in commissioning of solar power
generators are required to be paid by such solar generators/SPPD on the same line
as the liability for payment by the thermal and hydro generating stations in
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 18
accordance with the Central Electricity Regulatory Commission (Terms and
Conditions of Tariff) Regulations, 2014…………….‟
Subsequently Hon‟ble CERC in Petition No. 133/TT/2017 in the matter of Approval of
transmission tariff for ±100 MVAR STATCOM at NP Kunta Pooling Station under
“Transmission System for Ultra Mega Solar Park in Anantpur District, Andhra Pradesh-
Part A (Phase-I)…….” had passed Order dated 29.06.2018 wherein the following was
stated,
60. The Commission observed that as per the minutes of the 38th
SCM held on7.3.2015,
the CTU was to obtain clarification on the eligibility for LTA, connectivity, issue of
multiple injections, whether the sub-station which is in the premises of the solar park
should be under the scope of park developer or in STU/CTU and whether LTA should be
applied by actual generation developers who may sign PPA with AP DISCOMS or the
APSPCL and directed the petitioner to submit action taken and the clarifications
received.
61. In response, the petitioner vide affidavit dated 12.12.2017 has submitted that as per
CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in Inter-
State Transmission and related matters) Regulations, 2009 any company authorized by
the central government as Solar Power park developer (SPPD) can apply for
Connectivity/Long Term Access (LTA) in ISTS. MNRE vide its letter dated3.6.2015
authorized APSPCL as a SPPD to apply for connectivity/LTA in ISTS for its NP Kunta
Solar Park (1500 MW). As regards multiple injections, the petitioner submitted that
according to the Statement of Reasons to the above said regulations, in a solar power
park there may be multiple generation developers who may be injecting at various
points within the solar park and ultimately inject at interface with ISTS. Hence, it will
be treated as single injection at the interface point with ISTS. On the issue of whether
the sub-station within the solar park should be under the scope of park developer or
STU/CTU, the petitioner submitted that as per the Government of India (MNRE) letter
dated 12.12.2014, the responsibility of setting up a sub-station near solar park will lie
with the CTU or the STU taking into consideration the technical and commercial
requirement stipulated by the State and Central Commission.
62. TANGEDCO has submitted that in case of State specific solar projects there are no
identified beneficiaries outside the host State and there is no inter-State flow of power as
there is no firmed-up beneficiary outside the State. Further, the regulations do not permit
the socialization of the PoC charges among the beneficiaries of ISTS. TANGEDCO has
submitted that it has raised the issue of ambiguous procedure for implementation of the
waiver of the transmission charges for the solar and wind power under PoC mechanism.
63. TANGEDCO has submitted that the CERC (sharing of inter-State Transmission
Charges and Losses) Regulations, 2010 (2010 Sharing Regulations) did not account for
solar power injections into grid due to the capacity limitations and dispersal at
distribution level. As per the SOR of the 2010 Tariff Regulations, the 2010 sharing
Regulations facilitate solar based generation by allowing zero transmission access
charge for use of ISTS and allocating no transmission loss to solar based generation.
Solar power generators shall be benefited in event of use of the ISTS. Since such
generation would normally be connected at 33 kV, the power generated by such
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 19
generators would most likely be absorbed locally. This would cause no / minimal use of
400 kV ISTS network and might also lead to reduction of losses in the 400 kV network by
obviating the need for power from distant generators. TANGEDCO has submitted that in
contrast to the SOR, the present scenario is different as the solar power has attained grid
parity and the capacity is of the order of 1000 MW and above. This peculiar situation
necessitates revisiting the methodology for determining the PoC charges and the Sharing
Regulation. The sharing Regulations in the present form will only pass on financial
burden on account of the inefficiencies/inaccuracies in allocating the charges on to the
existing DICs irrespective of whether they are beneficial user or not. TANGEDCO is in
no way connected with the sharing of the transmission charges since it is neither the
beneficiary of the State specific solar project nor using the transmission lines. The power
generated and consumed within the State of Andhra Pradesh does not entitle levy of
transmission charges on TANGEDCO and hence the claim of the petitioner is not
maintainable.
64. In response, the petitioner in its rejoinder dated 28.12.2017 has submitted that
Ministry of Power, Govt. of India vide its letter No. 11/64/2014-PG dated 8.1.2015 while
dealing with the evacuation of power from nine solar parks (7020 MW capacity) being
set up in seven States including Andhra Pradesh Solar Ultra Mega Park observed that
the transmission line connecting solar parks to ISTS are to be declared part of ISTS and
PGCIL is assigned to take up construction of transmission line including pooling station
from solar generating parks on compressed time schedule basis. Further, the issue of
implementation of the transmission line for connecting the Solar Power Parks to the ISTS
was discussed in the 38th
meeting of the Standing Committee on Power System Planning
of Southern Region held on 7.3.2015 and it was agreed that the proposal was technically
in order and could be firmed up subject to resolving the regulatory issues. The scheme
was technically validated in the 38th
SCM and at Para 21.21 of the 38th
SCM following
submissions were made with respect to scheme and STATCOM. The scheme was also
deliberated in 27th
meeting of SRPC held on 12.05.2015 in presence of all Southern
region constituents. The Commission in order dated 6.8.2015 in Petition No. 29/MP/2015
accorded the regulatory approval for execution of the instant transmission. The petitioner
has submitted that the sharing of transmission charges for Solar Park at Ananthpur
district, Andhra Pradesh has already been decided by the Commission wherein it was
held that billing, collection and disbursement of transmission charges shall be governed
by the 2010 Sharing Regulations.
65. TANGEDCO has submitted that it has filed an appeal against the Commission’s
order dated 16.5.2016 in Petition No.26/TT/2016 before the Hon’ble Appellate
Tribunal for Electricity and it is pending disposal.
66. We have considered the submissions of the petitioner and TANGEDCO. We are not
able to agree with TANGEDCO that waiver of ISTS charges for solar and wind
generation is not in order. We are of the view that the waiver of transmission charges
for solar and wind generation is as per provisions of Sharing Regulations 2010 and is
in line with government policy to encourage renewable energy in the country.
Therefore, the billing, collection and disbursement of the transmission charges approved
for the instant asset shall be governed by the provisions of CERC (Sharing of Inter-State
Transmission Charges and Losses) Regulations, 2010, as amended from time to time, as
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 20
provided in Regulation 43 of the 2014 Tariff Regulations, subject to the outcome of the
Appeal filed by TANGEDCO before APTEL.
8.3 SRPC vide letter dated 04.07.2018 (Annexure-XI) had taken up the issue with CTU.
Implementing Agency (NLDC) / CTU had been kindly requested to furnish the views.
8.4 The following had been deliberated in the TCC Meeting:
MS, SRPC had appraised the TCC about the issues taken up by Chairperson, SRPC
with Chairperson, CERC based on deliberations of Commercial Committee.
TANGEDCO had been raising these issues in various forums and had also gone in
appeal before Hon‟ble APTEL and thus matter is sub judice. Further the matter
regarding LTA operationalization of SPDs in accordance with Order for Petition No
26/TT/2016 had been taken up by SRPC Secretariat with CTU. CTU vide letter dated
09.08.2018 (Annexure-XII) had informed that LTA would be made effective with
commissioning of associated elements at NP Kunta, in phases. In case of NP Kunta, all
elements except NP Kunta – Hindupur were nearing completion. Operationalization of
part LTA/full LTA needs to be carried out periodically and possibly in consultation
with RPC constituents. This periodic exercise would help allay any apprehensions and
also instill confidence among these entities.
TANGEDCO had pointed out that NP Kunta issue had been raised by TANGEDCO in
CC Meeting and the billing needs to be carried out bilaterally as per CERC Order.
Further there was no provision for blanket waiver of transmission charges and losses for
wind and solar generators. The checks (in respect of three conditions) being carried out
by CTU/NLDC in this regard, needs more clarity. Implementing Agency needs to issue
guideline regarding sharing of charges by SPDs for delay in commissioning of
generating units. Regarding relinquishment, presently there were no clear guidelines
from Hon‟ble CERC with regard to recovery of these charges.
CTU had stated that it is a rolling exercise as and when generation and transmission
elements are added to the grid, and results would be shared with the RPC. All decisions
are being taken fully complying with the CERC Regulations and CERC Orders. There
are a number of similar cases and generators are paying the charges, as applicable.
Hon‟ble CERC is also reviewing status of LTA/part LTA operationalization.
TSTRANSCO had stated that there was a need for assessing that commercial activities
are in line with prevailing Regulations.
SR-I, PGCIL had observed that transmission elements for NP Kunta had been brought
after thorough consultation with APSPCL and NTPC and also discussion in SRPC
forum. Line from NP Kunta to Hindupur (including reactor at Hindupur) was ready
since February 2018 but APTRANSCO was facing certain ROW issues in completing
line from Urvakonda to Hindupur, because of which commissioning is getting delayed.
CTU had informed that for the delay in commissioning of the generation projects, the
cost would be recovered from SPDs/ SPPDs in accordance with CERC Order in
Petition no: 26/TT/2016.
It was agreed that a Special Meeting would be held with CTU, NLDC & SR-
Constituents to discuss the above issues. Issue regarding operationalization of LTA/
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 21
part-LTA would be discussed and would be supported with studies. Criterion in place
for waiver of transmission charges for RE-generators would also be discussed.
TCC recommended that Chairperson, SRPC may kindly be requested to take up the
issues again with Chairperson, CERC for addressing the concerns raised.
8.5 The following was noted in the SRPC Meeting:
Chairperson, SRPC suggested that the Committee may deliberate and come out with
some recommendations in consultation with PGCIL, and also the matter may need to be
taken up with Hon‟ble CERC.
9 OPTIMUM HARNESSING OF RE IN SOUTHERN REGION
9.1 Follow up of MoP/SRZC meeting
9.1.1 In earlier SRPC Meetings Tamil Nadu had been requested to kindly sign the Overarching
Agreement. SRPC vide letter dated 24.01.2018 had requested Chairperson, TNEB that
necessary directions may kindly be arranged be given to TANGEDCO for signing the
Overarching Agreement. In the 33rd
Meeting of SRPC, TANTRANSCO had stated that
before the next SRPC Meeting, the Overarching Agreement was likely to be signed for
Banking/Swap option.
9.1.2 MoP vide letter dated 18.06.2018 (Annexure-XIII) had sought update in respect of
„Optimum harnessing of renewable energy available in Southern States without
endangering the security‟ as noted in the 10th
meeting of the Standing Committee of
Southern Zonal Council held on 28.11.2017 at Bengaluru. It had been recorded,
„Government of Tamil Nadu stated that balancing of demand can be made with mutual
agreement among member States to (i) Standalone export: By which power could be
transferred from surplus State to deficit State without any obligation to return the power;
and (ii) Banking/Swapping of Power to deficit States on „Give and Take mode‟, returnable
to installments at a mutually agreed quantum, duration and time. It was stated that TN is
also considering signing an agreement after considering the issue of pricing‟.
9.1.3 SRPC Secretariat vide letter dated 27.06.2018 had furnished the update to CEA wherein it
was noted that the Overarching Agreement had been utilized as follows:
Date Seller Buyer MW and duration
28.02.2018 Karnataka Kerala 150 MW – 2.5 hrs
01.03.2018 Karnataka Kerala 200 MW – 04 hrs
21.05.2018 Karnataka Andhra Pradesh 300 MW – 03 hrs
9.1.4 MS, SRPC vide letter dated 27.06.2018 (Annexure-XIV) to Chairman, TNEB had
requested to kindly consider signing the Overarching Agreement and to avail opportunities
in real time operation and this also enclosed in the letter to CEA.
TCC deliberations
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 22
9.1.5 TANTRANSCO informed that they were considering signing of the Overarching
Agreement after obtaining necessary approval.
TN has entered for 900 MU of swap power exchange with other states.
9.1.6 SRPC noted the above
9.1.7 The following was noted in earlier Meetings with regard to SAMAST, while update in
TCC is given in italics:
APTRANSCO had informed that they had prepared a Report and submitted it to
CERC and to NLDC for funding.
APTRANSCO had informed that sanction has been received.
TSTRANSCO had informed that DPR for Rs. 87 Crores had been submitted.
TSTRANSCO had informed that the matter was being followed up.
TANTRANSCO had informed that PO had been placed on 13.12.2017; and the
project was likely to be completed by 25.05.2018.
TANTRANSCO had informed that it was moving ahead.
KPTCL had informed that they had placed the Order for meters which are adjustable
to 0-60 minutes. DPR for Rs. 43.3 Crores had been submitted on 08.12.2017.
KPTCL had informed that reply to observations would be furnished.
NPC had stated that as per ToR, the need for 5 minute scheduling was to be examined.
The same was needed to be simulated and validated w.r.t. 15-Minute scheduling
before recommending the same to FOR. It needs to be ascertained whether there
would be huge variation between 3 blocks of 5 minutes wrt 15 minute block, for the
new scheme to be in place with operational / economic justification, without AGC in
place. Pros and cons of the two options are not highlighted in the draft report. NPC
also informed that the SAMAST schemes are being considered favorably for enhanced
approvals, (50 % for communication and >50 % for other project aspects).
9.2 Pump Storage Plants
9.2.1 The following is the status of upcoming Pump Storage Plants in SR:
State PSP Scheme Status
Andhra Pradesh Sileru (6 x150 MW) Recommended to
MoEF&CC for granting
Environmental Clearance
Tamil Nadu Kundah (4 x125 = 500 MW) 42nd
SCPSPSR : 2020-21
33rd
TCC: All the statutory clearances required for the
project have been obtained. EPC contracts for
establishment of packages I & II of phase I of this project
relating to Civil and Hydro mechanical works have been
awarded on 15.02.2018. Due to no response for the tenders
floated for Package-III of Phase-I, Phase II & Phase III
(E & M works) retendering is being processed. This Project
is expected to be commissioned in 2021-22.
Sillahalla-I (4x250 = 1000
MW)
42nd
SCPSPSR : 2023
onwards
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 23
33rd
TCC: The First Stage (1000 MW) with the proposed
Sillahalla reservoir as upper Reservoir and a new
reservoir below the existing Kundah Paalam & Kundah
Power House I as lower reservoir is to be taken up. Tender
for Consultancy services towards preparation of DPR for
the Stage –I of this project has been floated.
Preliminary works are under progress. The project is
expected to be commissioned in the year 2024.
Sillahalla-II (4x250 = 1000
MW)
42nd
SCPSPSR : 2023
onwards
33rd
TCC: To be taken up later.
4 projects on existing sites
33rd
TCC: Manalar PSHEP (500 MW) and Kodayar
PSHEP (500 MW) are in preliminary investigation stage.
The other two PSHEPs are found to be not much suitable.
Further investigations are under progress.
Karnataka Sharavathy (2000 MW) PFR submitted to MoEF
Varahi
Kerala Sholayar-I (810 MW) Survey and investigation
(S&I)/implementation could
not be taken up for want of
forest clearance
Sholayar-II (390 MW)
Poringalkuthu(80 MW)
9.2.2 APGENCO vide letter dated 03.08.2018 (Annexure-XV) had requested for
recommending 6 x 150 MW Pumped Storage Sileru Basin to MoEF&CC for granting
Environmental Clearance on priority basis.
9.2.3 The following had been noted in the TCC meeting:
TCC had recommended that MoEF&CC be kindly approached for granting
Environmental Clearance on priority basis to 6x150 MW Pumped Storage Sileru
Basin.
TCC had requested the entities to expedite the identified pumped storage schemes on
priority.
9.2.4 SRPC noted the above.
10 ISSUES WITH OA CONSUMERS
10.1 In the OCC Meetings, it was noted that some OA consumers are directly approaching Power
Exchange for short duration of time when PX rates are less and during other times they were
availing power from the DISCOMs.
10.2 During last year KSEBL had suspended NOC of such consumers but OA consumers had
approached KERC and High Court with the prayer that NOC cannot be rejected on account
of lower demand. High Court had directed KERC to give a solution and Commission had
stated that NOC can be rejected only if there are transmission constraints.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 24
10.3 OCC Members had informed that the following modalities / procedure for granting OA to
consumers in states like Gujarat, Rajasthan and Himachal Pradesh to mitigate this problem
as given below:
OA is granted on RTC basis and not for few blocks during the day.
Once consent is granted for OA, the consumers have to compulsorily purchase
through OA.
For taking consent for OA for any particular day, the application filed by the
consumers two days in advance. For taking OA for the whole month, the consumers
have to file the O.A. application by the 15th
of the previous month.
Such conditions have helped the Discoms to assess the demand supply in a more
efficient manner.
It was suggested that the best practices of different states could be studied for further
finalizing a procedure / guideline which could be implemented in the states after due
approval of the SERCs.
10.4 The following had been deliberated in the TCC Meeting:
SRPC had presented the practices being followed in this regard in Rajasthan &
Gujarat (Annexure-XVI). Crux was that OA was permitted for the whole day and not
for intermittent blocks. For 8 hours, uniform schedule was to be maintained and
minimum schedule was to be at least 75 % of the max schedule. This was required so
that supply planning by the Escoms is carried out in a more efficient manner.
KSEBL had informed that Kerala faces typical problem that whenever demand is
crashing, OA consumers are going to the market for large quantum and for that huge
generation backing down is to be resorted to. SLDC was forced to curtail OA during
such exigencies. OA consumers had gone to SERC & High Court and the SERC had
passed the Order that low demand cannot be a reason for OA curtailment. Gujarat OA
conditions were informed to SERC, but SERC is waiting for OA quantum to increase
to consider any amendment.
APTRANSCO had observed that whether any tweaking of OA Regulations would be
violation of the EA provisions. Only two conditions are to be satisfied - metering and
transmission capacity.
It was opined that non-discrimination means that the utility should not discriminate
among OA consumers but it does not mean that certain reasonable conditions cannot
be imposed. OA in its present form affects the planning process of Discoms to meet
the demand since OA demand is already considered by them. Subsequently, it may get
replaced and thus that much margin is always to be maintained by the Discoms.
TSTRANSCO had opined that there should be advance intimation by OA consumers
on the quantum being availed through state utilities.
PCKL had pointed out that Distribution Licensee & OA consumers are to be viewed
on different parameters and whether different DS Mechanism is required for OA
consumers‟ needs to be examined.
It was agreed that Chairperson, SRPC would be kindly requested to take up the issues
raised by Constituents with MOP.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 25
10.5 SRPC requested Chairperson, SRPC to kindly to take up the issues raised by Constituents
with MOP.
11 PREPARATION FOR MEETING REVISED ENVIRONMENT NORMS AS PER
ENVIRONMENT (PROTECTION) AMENDMENT RULES, 2015
11.1 Revised water consumption and emission norms for existing as well as new thermal units (to
be installed from 01.01.2017 onwards) as per Environment (Protection) Amendment Rules,
2015 had been notified by Ministry of Environment, Forest & Climate Change (MOEF &
CC) (Gazette Notification dated 07.12.2015). MOEF guidelines had classified thermal
generators into three categories with different norms. The three classes were - prior to 31st
December 2003, 1st Jan 2004 to 31
st December 2016 and beyond 1
st January 2017. Existing
as well as new plants were required to meet standards by the stipulated time lines.
Preparedness and action plan in order to comply with revised norms had been discussed in
SRPC as well as Subcommittee Meetings
11.2 The following had been noted in earlier Meetings:
SRPC had noted the requirements for necessary compliance.
Chairperson, SRPC vide letters dated 24th
May 2017 & 28th
August 2017 addressed to
Secretary-Power, MoP had brought to kind attention of MoP, the issue regarding funding
either from PSDF or any other fund to meet stipulated revised environmental norms.
In view of the time bound nature and its criticality Chairperson, SRPC vide letter dated
04.10.2017 had requested Chairperson, CERC that the concerns expressed by the
generators may kindly be arranged to be examined.
11.3 As discussed in the 33rd
Meeting of SRPC held on 17.02.2018, Chairperson, SRPC vide
letter dated 02.03.2018 (Annexure-XVII) had requested that MoP to bestow its kind
attention on the matter regarding funding; either from PSDF or any other fund, to meet the
stipulated revised environmental norms.
11.4 A Special Meeting had been convened at SRPC Bangalore on 23.02.2018 (Minutes
available on SRPC website) to discuss on incentive to TTPS for early installation of
Pollution Control Equipment.
11.5 MoP vide letter dated 30.05.2018 (Annexure-XVIII) had finalized „Mechanism for
implementation of New Environment Norms for Thermal Power Plants (TPP) supplying
Power to distribution licensees under concluded long term and medium term Power
Purchase Agreement (PPA)‟. In the Mechanism, it has been stated, „After considering all
aspects and with due regard to the need for safeguards against environmental hazards and
accordingly to ensure timely implementation of new environment norms, the Central
Government has declared that –
5.1 The MoEFCC Notification requiring compliance of Environment (Protection)
Amendment Rules, 2015 dated 7th
December, 2015 is of the nature of Change in Law
event except in following cases:
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 26
a) Power Purchase Agreements of such TPPs whose tariff is determined under Section
63 of the Electricity Act, 2003 having bid deadline on or after 7th
December 2015, or
b) TPPs where such requirement of pollutions control system was mandated under the
environment clearance of the plant or envisaged otherwise before the notification of
amendment rules.
5.2 The additional cost implication due to installation or up-gradation of various emission
control systems and its operational cost to meet the new environment norms, after
award of bid or signing of PPA as the case may be, shall be considered for being made
pass through in tariff by Commission in accordance with the law.
5.3 The respective TPPs may approach the Appropriate Commission for approval of
additional capital expenditure and compensation for additional cost on account of this
Change in Law event in respect of the Power Purchase Agreement entered under
Section 62 or Section 63 of the Electricity Act, 2003
5.4 For the TPPs that are under the purview of the Central Commission, the Commission
shall develop appropriate regulatory mechanism to address the impact on tariff and
certainty in cost recovery on account of additional capital and operational cost, under
concluded long term and medium term PPAs for this purpose.
11.6 SRPC Secretariat vide letter dated 25.06.2018 (Annexure-XIX) had forwarded CEA‟s
letter seeking updated information in respect of status of implementation of the revised
FGD installation / ESP upgradation plan to comply with the new environment norms.
Updated information is to be communicated periodically (initial update was to be
furnished by 30.06.2018).
11.7 The following had been deliberated in the TCC Meeting:
TANGEDCO had stated that they had already furnished their comments that
expenditure towards compliance of MoEF rules may be decided on average PLF, age
and benchmark norms to be finalized by CEA. It is seen that many old Thermal Plants
are in service beyond the life span. Therefore compliance in all cases may not be
necessary considering level of RE penetration in TN and also shortage of domestic coal.
It was noted that units need to necessarily comply with the norms as per the CPCB
timelines.
Generators had noted the MOP directive dated 30.05.2018 on „Mechanism for
implementation of New Environment Norms for Thermal Power Plants (TPP) supplying
Power to distribution licensees under concluded long term and medium term Power
Purchase Agreement (PPA)‟.
CPCB timelines for the compliance of environmental norms were also noted by the
generators (enclosed as Annexure-XX).
PCKL had pointed out that there has to be some measure and check on the pass
through, commensurate to the environmental concept and the same is being suggested
to KERC.
It was noted that this is a monitored activity by Hon‟ble Supreme Court and by
Government through CEA and hence regular updates need to be communicated. The
timelines of CPCB need to be strictly adhered.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 27
11.8 SRPC noted the above.
12 COAL ISSUES
12.1 Number of thermal power stations in the Region had faced critical coal stock situation in
the past few months. The following had been noted in earlier Meetings:
Chairperson, SRPC vide letters dated 25th
September 2017 and 13th
November 2017
had taken up the issue regarding critical coal stock and availability of sufficient rakes
with Ministry of Power.
SRPC vide letter dated 22nd
November 2017 had raised energy security concerns with
Hon‟ble CERC and had requested that the matter regarding maintenance of low coal
stock by CGS station whose tariff is approved by Hon‟ble Commission may kindly be
examined.
As agreed in the Secunderabad Meeting held on 21st December, Chairperson, SRPC
vide letter dated 28th
December 2017 had taken up the issue regarding „Consent of
original beneficiaries‟ for diversion of coal with Chairperson, CEA.
CEA had informed that CEA and NTPC, with active help of Railways and Ministry of
Coal are developing an IT application which would help in monitoring of coal stock
available at each Railway siding, with daily receipts and dispatch of coal, rake
allocation for coal supply to generating stations. This along with stock, consumption
and receipt of coal at generating station as available in NPP Portal, would help in
effective monitoring of coal supply. This would help ensure that coal movement is
monitored from source to consumption.
APGENCO had requested for minimum 2 rakes/day at Balram siding. Moreover,
sufficient rakes were required at Talcher (3 rakes/day) and Ib (5 rakes/day) sidings to
improve the coal at Vijayawada TPS and Rayalaseema TPS which was less than 5
days on sustained basis. For Unit 6 at Rayalaseema (Stage IV) additional 2 rakes/day
were required for movement of raw coal from MCL for this purpose.
KPCL had informed that around 18 rakes/day would be required for FY 2018-19.
Additionally around 2-3 rakes were required for fly ash movement. KPCL had
requested to ensure adequate availability of valid rakes for movement of allocated coal
through ARR.
The logistic constraints between Sambalpur-Rayagada and the congestion between
Vizianagaram and Vizag were noted.
MCL had pointed out that Availability of BOXN rakes (in ECR and ECOR) for long
distance linkage power plants are to be improved. Availability of Box N rakes for
maximizing long distance linkage power plants to be improved. Presently, Box N
rakes are not sufficient with Zonal Railways. Congestion in ECO Railways, for rakes
going to Paradip and through Sambalpur – Titlagarh route was affecting rake
materialization for plants location in Southern Region. Also BOB rakes need to be
allowed over long distance for power plants such as Simhadri and other plants with
BOB rakes unloading facilities. To Paradip port, BOBR rakes were being supplied,
and Gencos may need to avail RSR route also instead of All Rail Route to reduce
congestion. There had been no shortfall in offer by MCL while problem was mainly
with regard to availability of rakes by Railways. MCL had requested Gencos for
clearing of the dues to MCL in a timely manner.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 28
12.2 As agreed in 33rd
Meeting of SRPC, Chairperson, SRPC vide letter dated 20.02.2018
(Annexure-XXI) had taken up the concerns of SR Thermal generators with Chairman,
Railway Board.
12.3 MD, APGENCO vide letter dated 08.06.2018 (Annexure-XXII) had taken up the issues of
transportation of raw / washed coal from MCL to APGENCO power plants by ARR with
Railways. The daily requirement has been specified as 2 rakes/day from BBMT siding &
3.2 rakes/day for Dr NTTPS, 1.33 rakes/day for RyTPP and 2 rakes/day for RyTPP stage-
4.
12.4 NTPL vide letter dated 31.05.2018 (Annexure-XXIII) had requested CEA to review the
criteria of criticality for NTPL coal stock position as 20 days for critical and 9 days for
super critical so as to improve the allocation of coal companies and rakes by railways.
12.5 NTECL vide mail informed that around 233 MU had been lost (in DC Declaration) from
01.04.2018 to 21.05.2018) (Annexure-XXIV).
12.6 SRLDC had prepared a link where the details of coal were to be uploaded
(https://goo.gl/y3LL4n). This information needs to be furnished before 06:00 hours every
day (critical since information is shared with MoP).
12.7 APGENCO vide letter dated 5th
July 2018 (Annexure-XXV) had informed that they are
getting 2 to 3 grade slippages particularly in case of coal received from Manuguru and
Rudrampur mines for RTPP and Dr NTTPS stations. This is despite constant pursuance
with SCCL and CIMFR.
12.8 The following had been deliberated in the TCC Meeting:
It was noted that there was loss in DC of around 394 MW during July 2018 out of
which 323 MW was from Talcher-II station, alone.
NTPC had informed that the loss in DC was due to issues at MCL (strikes etc) and
prominently due to very poor quality of coal. The issue had been taken up with MCL
and officials had been stationed at mines to ensure that coal quality improves.
KSEBL had pointed out that for Talcher II, DC during peak hour was less than other
hours on some of the days.
APTRANSCO had stated that monsoon would recede by mid-September and adequate
DC availability needs to be ensured by generators.
PCKL had stated that the coal stock position also needs to be considered in Merit Order
Despatch.
It was noted that OCC had suggested that less than three days of coal stock could be
considered as fuel shortage conditions. ISGS need to ensure that in case average DC is
less than ex-bus (normative) over a day, then DC would need to be maximized during
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 29
6-9 hours and also during 18-21:30 hours, while appropriately reducing DC during
other hours. TCC observed that the same needs to be followed.
It was noted that the issues would be discussed further in the SRPC Meeting where ED
(Coal), Railways, HOD (M&S), MCL & ED (CM), SCCL had confirmed their
participation.
12.9 Coal Supply Issues
MCL stated they were maintaining overall materialization of coal at 79 % in FY 2018-
19. For South bound power plants it had been 64.6 % in 2016-17 and 71.5 % in 2017-18
while upto July 2018 (FY 2018-19) it was 77 %. There has been a continuous growth in
materialization of South bound power plants. Some of the plants of MAHAGENCO and
RGHPGCL were getting coal only up to 65 %. MCL had to optimize supply to all the
link plants and not just to specific plants.
NTPC-Talcher stage-II
MCL stated that upto 08.08.2018 in this FY, around 98 % contracted capacity had been
supplied to Talcher Kaniha plant. Since Talcher had been supplied the linkage quantity,
the remarks on coal supply may need to be reviewed.
NTPC informed that in the month of July 2018 for around 25 days, the quality of coal
supplied was quite poor and the specific coal was in the range of 1 kg/kwh. There had
been reported strikes and instances of rain water entering the mines during that period.
On 23rd
, 24th
, 27th
and 30th
, only slurry had been supplied.
MCL informed that there had been heavy rain during 2nd
half of July 2018 which was
622 mm around Sambalpur, Raigad, Cuttack, Bhubaneshwar & Paradip. Even some of
the mines had been submerged. Despite these constraints, the supply had been ensured.
In the month of August 2018 the materialization was 108% in respect of NTPC, Kaniha.
It was assured that the coal would be supplied as per the requirement. MCL had been
requesting NTPC to avail coal from Ib sidings. Earlier NTPC was picking 2 rakes from
Ib siding which had been stopped in July 2018. NTPC needs to supplement by taking
additional rakes from ECL, and this would ensure higher generation levels also. This
suggestion had also been made to NTPC in the Sub-group meeting. Earlier additional
coal was being given to Talcher; Kaniha for getting performance incentive. But from
2017-18, NTPC has rationalized incentive for overall FSA, adversely affecting MCL‟s
incentive. Incentive on supplying coal to local plants needs to be relooked by NTPC.
NTPC informed that NTPC had not questioned the quantity of the coal but there were
issues in the quality. In the coming months, with depletion of rain the situation was
likely to improve. Other issues of availing coal from ECL / Ib would be examined as
there were cost implication also (ECL cost high) and same would be communicated to
the concerned division in NTPC Corporate.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 30
APGENCO
MCL / APGENCO informed that FSA for 2.778 MTPA for Rayalaseema Stage-IV had
been completed on 20.07.2018 and the coal supply had started.
MCL informed that in April 2018 as part of its initiative (to go to door step of
consumers) they had held a meeting with the APGENCO / APPDCL and AP power
plant along-with Vizag Port and Railway officials at Vizag. Power Stations had been
requested to avail some coal through Vizag Port. Parallel channels need to be utilized so
as to ensure that requirements are met. New Sardega siding at MCL had been added and
around 5-6 rakes/day could also be loaded from there. It is a new siding of South East
Railways. Generators were requested to have agreement with SE Railways (HQ
Kolkata) for enhanced rake movement towards Damra and Haldia Ports.
KPCL
KPCL informed that price structure proposed by SCCL for 4.89 MT is higher compared
to normal mine rates under FSA & CIL price. Offered quantity is less than requirement
of 90 lakh MT per annum (for RTPS and BTPS). Signing of FSA was to be as per
FSA/linkage terms and conditions at notified price (MOC had directed SCCL and KPCL
to sign FSA in its meeting dated 10.4.2018).
SCCL informed that they had already informed KPCL through letters regarding the price
structure and quantity offered as per MoC policy and as per SCCL Board directives.
SCCL had also informed that KPCL is yet to come forward for signing of FSA as per
SCCL proposal.
MCL informed that materialization in respect of Raichur was 103 % in 2016-17 and 109
% in 2017-18 while in 2018-19 (upto July 2018) it was 134 %. Additional coal of
around 2 LT/month was being taken from MCL by KPCL. Proper mix of ARR and RSR
should be ensured by KPCL and it should be practical. It was suggested to take more
coal from Ib field. Most of the stations were requesting more coal from Talcher which
may not be possible and thus other options of getting coal from Ib etc needs to be
exercised.
TANGEDCO
MCL informed that additional supply of coal of 0.5 MTPA (earlier being supplied by
WCL) had been formalized for TANGEDCO.
TANGEDCO observed that some of the MCL coal was being moved to Vizag Port.
However, at Vizag Port there was no mechanical unloading and thus all was under
manual unloading. Cost of unloading at Vizag Port was much higher compared to
Paradip Port so they are not able to divert their coal to Vizag Port.
MCL stated that TANGEDCO was already having multiple avenues; coal was being
taken through ARR for Mettur and through Paradip, Vizag and Haldia Ports. Vizag Port
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 31
in the meeting held in April 2018 had assured of package (merit order benefit, discount
etc) to the power plants which could be availed.
NTECL
MCL informed that they were in touch with NTECL for any additional requirement of
coal in the coming months.
NTECL informed that they were willing to avail more coal from Sardega siding of
MCL, but there were some issues regarding weighment.
NTPL
NTPL informed that they are getting good support from MCL (95 % realization up to
July 2018). From September 2018, additional quantity would be required.
MCL
MCL stated that the utilities (APGENCO, APPDCL and NTPL) availing coal through
Washery mode should ensure that the Washery operators pickup sufficient raw coal in
time. Lifting of coal by Washery has been poor. Utilities can take up the issues with the
Railways for lifting washed coal from Washery.
Most of the South bound stations taking coal through Paradip Port should also consider
increasing off take at Damra and Vizag Ports to improve materialization.
12.10 Grade Slippage Issues
APGENCO had informed that 2 to 3 Grade slippages between loading end of SCCL and
unloading end (from Manuguru and Rudrampur mines) for RyTPP and Dr. NTTPS
(Vijayawada TPS) was an issue of concern. In last two month‟s atleast 2 to 3 Grade
slippages had been observed.
SCCL informed that representatives from Gencos / NTPC were being allowed as per the
Tripartite Agreement and they were extending all necessary facilities to representatives
at the loading points. At the loading point all the three parties were present and hence
SCCL was not responsible for any reported grade slippage at the unloading point.
Specific two areas had been mentioned by APGENCO and SCCL would look into this
issue.
APGENCO observed that officials/representatives of APGENCO were not being
allowed at the loading point.
MD, APGENCO noted that Grade slippages were affecting the generation besides the
cost also. Normally, whatever quality and quantity of coal is loaded only reaches the
plant and hence variations are minimal. In a nutshell, whatever is loaded should be
billed. There is a need for a transparent mechanism to sort out loading / unloading Grade
slippage issues.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 32
SCCL informed that the issue of the Grade slippages between loading and unloading
point also needs to be sorted out by CIMFR.
MCL informed that the Grade slippage was getting addressed and only 27 % of the
supply was getting downgraded while 73% supply was being upgraded. Even the 27%
issue would be looked into and rectified.
NTPC observed that at Ramagundam the loading point is only 8 kms away (15 minutes
delivery time) and that through MGR and even there 2 Grade slippages have been
reported. Representatives and cameras are not being allowed by SCCL. Auto sampler
has not been installed/not working at SCCL. Same CIMFR is doing sampling at both the
ends and still the Grade slippages are being observed. Issues at loading end needs to be
addressed by coal companies and the unloading issues would be taken care by the
stations.
NTPL informed that MCL had resolved the Grade slippage issues and other coal
companies need to fall in line. Grade slippages were being observed in ECL supply also.
They were getting invoice for G11 while the supply was G15.
PCKL pointed that 2 to 3 Grade slippages was having significant impact on GCV and it
translates into about 600-900 Kcal/ Kg loss which has to be borne by the consumers.
TANGEDCO observed that CIMFR was sending the quality reports after 2 months,
CCL & ECL reports were not being received and the payment was made in advance (1st,
11th
and 21st) and subsequently only the quality linked payment (Grade slippage) was
being factored in. Reports by CIMFR needs to be expedited to ensure payment
curtailment in a timely manner. The advance quantum would also get reduced
considerably.
Chairperson, SRPC concluded that in the interest of the consumers, coal companies need
to come out with a transparent mechanism, besides third party sampling. Importance of
Third party sampling at unloading point could also be examined. Cameras and
representatives could be allowed to improve the confidence levels of the stations
towards quality and quantity. SCCL and other coal companies could take the lead from
MCL on addressing the Grade slippage issues which could be discussed in the next
meeting. CIMFR officials could also be invited in the next Meeting.
12.11 Railway issues
Railways
It was informed by Railways that materialization of All Rail Routes (ARR) from
Talcher had been less in the last 3 to 4 months due to the need for higher deployment of
BOXN rakes for carrying coal to power houses in North India and West India. This was
necessitated due to closure of some Port based power plants (run on imported coal) in
Mundra and Essar Ports which had resulted in shortfall of 3,000 to 4,000 Megawatts.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 33
The power plants in Haryana, Gujarat and Rajasthan had been fed extra 20 rakes per
day from CIL sources. The materialization for BOBR circuits from Talcher was
satisfactory. It was also informed that a large number of BOXN wagons were being
inducted (8,000 to 10,000 wagons) in the current financial year which has improved
BOXN rake availability and helped in improving the ARR materialization from
Talcher.
Railways have close coordination with MoP and MoC and they are meeting nearly on a
daily basis. For stations featuring in super critical / critical coal stock, special
arrangements were being made to improve the coal supply. In addition, there was a
fortnightly Meeting between Secretary (P), Secretary(C) and Member (Traffic) and
issues are discussed with Power Plants and Zonal Railways. Critical coal stock stations
come on radar and issue is resolved on priority. Most of the plants in SR are more or
less comfortable except few plants like Kondapalli (Vijayawada) which have come
recently under critical coal stock. Rains have impacted loading all over, WCL and ECL
are badly affected and MCL and Railways‟ mobility were also impacted. Stations don‟t
release the wagons in a timely manner and the issues of sticky coal, CHP getting
jammed etc leads to lesser rake availability.
Railways informed that preferred movement from Sardega siding of MCL was towards
Damra and Haldia and not towards Paradip.
Railways assured the forum that they were in touch with all the utilities on day-to-day
basis and issues are being resolved.
NTPC-Talcher, Kaniha
Railways informed that one rake/day was being moved from ECL and because of rains
the loading at ECL had gone down. Presently around 10 rakes/month were coming, and
as and when ECL loading picks up, the supply would increase.
NTPC - Simhadri
NTPC Simhadri stated that though MCL was offering coal, there were some issues in
allocating higher number of BOBR rakes to Simhadri by the Railways. BOXN rakes
were taking longer time to unload.
Railways clarified that supply to Simhadri would be a combination of BOXN and
BOBR rakes. Simhadri is under advance payment scheme and the program for Simhadri
being submitted by NTPC was in the range of 6-7 rakes. Upto 8 rakes would be ensured.
Loading of 8 rakes/day for Simhadri can be done, provided adequate availability of coal
in sidings is ensured by coal companies.
NTPC-Kudgi
NTPC Kudgi requested Railways to supply 2 rakes/day from SCCL. Though the indent
has been raised supply was not taking place. SCCL / Railways stated that as per NTPC‟s
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 34
request the rakes were being diverted to Sholapur and Mouda. SCCL stated that Kudgi
was Bridge Linkage customer and 2 rakes/day would be ensured.
APGENCO
APGENCO informed that at Dr. NTTPS (Vijayawada TPS) (for the period April – May
2018), 177 rakes were supplied against 244 sanctioned rakes for raw coal and 26 rakes
were supplied against 66 sanctioned rakes for washed coal. At Rayalaseema 42 rakes
were supplied against 72 sanctioned rakes for raw coal. Around 63% supply was
effective with respect to sanctioned rakes. Railway Board (vide letter dated 09.02.2018)
had committed existing linkages through ARR. It was informed that with the
augmentation of BOXN rakes, the rake availability would improve in East Coast
Railway and help in higher materialization of ARR from Talcher in the coming months.
Requirement was of 3.2 rakes/day (2 from BBMT siding) for Dr. NTTPS (Vijayawada
TPS), 1.33 rakes/day for Rayalaseema TPP and 2 rakes/day for Rayalaseema Stage-IV.
Railways assured that materialization would increase to 80 to 90 % which was achieved
earlier in the coming months. In August 2018, the raw coal movement was already more
than 100%. For washed coal for some period the Washery was closed due to some
infrastructure additions but now the coal supply have resumed. Last month, the washed
coal supply was around 90%. Kondapalli (Vijayawada) has added advantage that they
can unload BOBR rakes. At BBMT siding 2 -3 rakes/day were being loaded.
On the request of MCL, APGENCO had requested for transfer of raw coal to some other
Washery also. More number of BOXN wagons was required as at RyTPP the unloading
facility for BOBR wagons was not there.
Railways stated that the complete requirement of washed coal could not be met only
from Spectrum Washery due to capacity constraints in the layout of the siding and hence
movement should be planned for other washery sidings also. Railways assured of higher
availability of rakes for Kondapalli as Kondapalli was good releasing point for
Railways. More number of BOXN rakes had been inducted for movement of coal for
Western and Northern Sectors but slowly the availability to Southern Sector would
improve since loading of BOXN wagons from CCL and BCCL has gone down.
KPCL
KPCL informed that 18 rakes per day were required for FY 2018-19. Additionally, 2 to
3 rakes per day were required for fly ash movement. Railways to ensure valid rakes
availability for movement through ARR. Percentage realization of rakes with reference
to 60 % of FSA quantity was only 70. 61% (for 2017-18). KPCL was also programming
movement of coal through RSR mode. For April 2018, Railways had provided only 21
rakes against requirement of 34 rakes. Less coal was being received at Raichur and
Bellary through ARR mode from MCL and it was around 25 % from WCL. Through
RSR mode the supply was being met. The supply issues were being taken up with CIL
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 35
and CEA (criteria of critical / super critical was affecting them to buildup the coal
stock).
Railways informed that due to the reason cited above the supply via ARR was less but
there was 90-95% materialization on RSR. Because of ARR/RSR options, the supply
from MCL was satisfactory while the supply from WCL was badly affected since last
two months due to less coal on account of rains. For the month of July 2018 the
materialization was around 105 % (100% ARR and 106% RSR).
Railways requested KPCL to furnish the source-wise breakup of 18 rakes/day. It was
informed that KPCL gets significant portion from SCCL. KPCL was requested to
furnish the details of fly ash movement and the type of wagons required, whether
BCCW (special wagon for fly ash) or BOXN.
TANGEDCO
It was noted that coal stock at North Chennai was for one day only (CEA report dated
09.08.2018).
Railways informed that overall supply to TANGEDCO stations was more than trigger
level. Further, as per CEA‟s criteria, North Chennai has not been categorized under
critical/super critical.
TANGEDCO stated that not a single rake had been moved from Ib to Mettur through
ARR though earlier 28 rakes and later 6 rakes had been supplied.
Railways informed that the movement of BOXN rakes to Western and Northern Sector
had affected the rake movement through ARR to Southern Sector.
NTECL
NTECL informed that realization was only around 72-75% and that also at 85% PLF.
Coal movement from Talcher to Paradip Port was quite less than the requirement of 3
rakes/day. Further, there were some issues in coal movement from Ib to Paradip and
Damra and the realization is poor. NTECL was requesting around 25 rakes to Damra
which was not being allocated.
Railways informed that there were no issues for movement between Talcher to Paradip
Port and the allocation would be optimized. As the plant was not featuring in the critical
list, the allocation of rakes could have reduced. Once the consumption increases, rake
allocation would automatically enhance. Railways stated that as per the records 100%
realization was there on Ib to Damra sector based on the submitted program. However,
the issue would be looked into.
NTECL requested Railways to ensure 1 rake/day from SCCL though the indent has been
raised. SCCL stated that the coal supply was under MOU (till now 17 rakes have been
supplied) but due to rains the loading was affected. Now the supply would be improved.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 36
TSGENCO
SCCL informed that TSGENCO was commissioning 800 MW unit and 2 rakes/day were
being supplied to them, as it was under FSA.
MCL
In the 33rd
SRPC meeting, MCL had raised issues on availability of BOXN rakes for
maximizing long distance linkages, congestion in ECO railways (going to Paradip &
through Sambalpur – Titlagarh route) and BOB rakes to be allowed over long distances
for plants such as Simhadri ( having unloading facilities).
Railways informed that these issues are being discussed and resolved on day-to-day
basis with MCL.
MCL informed that these issues are being taken up in the sub-group meeting on daily
basis.
12.12 Unloading facility issues
SCCL pointed out that some of the stations don‟t have facility of unloading BOBR rakes
which needs to be developed to provide flexibility in supply of rakes. This affects coal
supply to Muddanur, Raichur, Bellary, Kudgi etc. Major coal plants should have
multiple type of unloading facility.
12.13 Issues on CEA’s methodology for monitoring coal stock
NTECL
NTECL informed that they were getting coal through RS mode and it was taking more
than 10 days. As per CEA‟s criteria if the coal is available for more than 7 days it is not
categorized under „Critical‟. In case of increased generation level, movement from
„Critical‟ to „Super Critical‟ is very fast. Therefore for RS mode, criticality should be
fixed at least 10 days.
NTPL
NTPL stated that the same issue has been raised by NTPL and the time lines for the
movement of coal were further severe.
KPCL
KPCL stated that the CEA‟s methodology was affecting to build up coal stock.
Computing 30 days stock at 85% PLF they require 7.36 MT while the stock is 3.98 MT
(CEA website showing 27 days) at Raichur TPS. The issue had been taken up by MD,
KPCL with CEA.
TANGEDCO
Most of the power plants are under shutdown/partially running to harvest the wind
power and hence consumption of coal was around 25-30%. CEA is computing the stock
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 37
in number of days based on the past few days consumption pattern. For example for 26th
,
MCL has mentioned that Tuticorin is having coal stock of 25 days (based on running of
only one unit) but actual stock was for 5 days only. TANGEDCO is very badly affected
due to this. On the other side TANGEDCO is being requested to build up stock to 30
days (for full station capacity). CEA‟s computation methodology was not clear.
Conclusion
It was pointed out that computation methodology had been finalized by CEA in
consultation with the stake holders and is available in public domain. The stake
holders had been kept appraised on the methodology.
Member (GO&D), CEA stated that the issue would be examined, in case the same is
referred to CEA.
Chairperson, SRPC stated that since more than one state is having issue in the
calculation, the issue could be taken with CEA. All affected entities were kindly
suggested to provide detailed inputs / reports for further taking up with CEA.
13 STATUS OF DC/GENERATION IN ISGS
13.1 Issue regarding low DC/Generation at NLC TS-II Expansion and NTECL had been
deliberated in earlier Meetings of SRPC. Level of generation of some ISG stations is given
below:
13.2 The following had been noted in earlier Meetings:
MS, SRPC had informed that the loss in DC wrt normative was 956/272/356 MW
during Nov 2017/Dec 2017/Jan 2018 respectively. While scheduling right is with
beneficiary, DC being the sole prerogative of generator should not be less.
NLC had informed that some modification works through OEM had been planned and
full availability was expected during the first quarter of 2018-19.
NTPC & NLC had requested for maximization of consent for trading.
Subsequently it has been noted that NTECL unit-III which was out since 06.06.2017 had
come back on bars on 27.02.2018.
13.3 The following had been deliberated in the TCC Meeting:
Loss in DC was 167/151/117/292/156/394 MW during Feb 2018/March 2018/April
2018/ May 2018/ June 2018/July 2018.
NLC had informed that major modification had been carried out in Unit II of TS II
Expn and unit brought back in June 2018 .Unit I would be brought back by 15th
August
2018 and after that, above 90 % DC was expected.
Station Feb-18 Mar-18 Apr-18 May-18 June-18 July-218
NTECL,
Vallur
DC % 67.19 72.63 98.18 80.23 64.43 73.90
PLF (on Actual)
%
56.43 62.88 85.91 97.57 48.87 46.53
NLC TS II
Exp
DC % 44.14 31.52 25.78 30.62 16.72 45.62
PLF (on Actual) 29.51 32.43 26.34 30.97 17.26 41.91
MAPS PLF (on Actual) 51.24 51.04 50.20 49.03 50.51 48.46
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 38
13.4 SRPC noted the above.
14 ROADMAP TO OPERATIONALISE RESERVES IN THE COUNTRY
14.1 In the 29th
Meeting of SRPC it had been noted that in the matter of Roadmap to
operationalize Reserves in the country, Hon‟ble CERC vide Order dated 13.10.2015 on
Petition No. 11/SM/2015 had directed as follows:
(b) The Commission reiterates the need for mandating Primary Reserves as well as
Automatic Generation Control (AGC) for enabling Secondary Reserves.
(i) All generating stations that are regional entities must plan to operationalize AGC
along with reliable telemetry and communication by 1st April, 2017.
(ii) The Central Commission advises the State Commissions to issue orders for intra-
state generators in line with this timeline as AGC is essential for reliable operation of
India‟s large inter-connected grid.
(c) To start with, a regulated framework in line with the Ancillary Services Regulations
would need be evolved for identification and utilizing of spinning reserves and
implemented with effect from 1st April, 2016. This framework may continue till 31
st
March, 2017.
……………
(d) In the long term, however, a market based framework is required for efficient
provision of secondary reserves from all generators across the country. For this,
NLDC/POSOCO is directed to commission a detailed study through a consultant and
suggest a proposal to the Commission for implementation by 1st April, 2017, giving
due consideration to the experience gained in the implementation of Spinning
Reserves w.e.f. 1st April, 2016.
14.2 In earlier Meetings the following had been noted:
Hon‟ble CERC in Petition No. 79/RC/2017 had passed Order dated 6th
December,
2017 in the matter of „Automatic Generation Control (AGC) pilot project‟.
NLDC had informed that in respect of AGC at Simhadri, offer had been received
from M/s Siemens. They would convene a Meeting with NTPC on 20th
February and
then the Order would be placed with implementation schedule of 5 to 6 months.
Regarding AGC at NP Kunta, M/s USAID had agreed to take the AGC
implementation under GTG project. On 10.02.2018, after assessment it had been
concluded that AGC implementation at NP Kunta was feasible. AP utilities as well
as SERC were required to be consulted in this regard.
14.3 A Meeting on AGC issues had been conducted at SRPC on 28th
March 2018 (MOM
available on SRPC website). The following highlights may be kindly noted:
Better Load Forecasting and RE framework (forecasting, scheduling & settlement)
would naturally result in lesser reserve requirement and needs to be pushed through
FOR.
Scheduling software for unit commitment, meeting the ramps (+)/(-), ramps of
generators, fast start up and shutdowns of generators, errors in load and RE forecast,
technical minimum, meeting peak demand, meeting minimum demand, net load,
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 39
pump operation etc is required for resource optimization and proper decision
support.
Forum opined that there was a need for a Procedure to quantify Secondary/Tertiary
Reserves. Procedure should also include a mechanism to monitor these reserves in
real time manner for replenishment of these reserves.
Sharing of these secondary/tertiary reserves, and including those available with
States, could lead to optimization of reserve requirement. However, the mechanism
of sharing and associated cost needs further analysis and discussions.
While there was lot of focus on positive reserve, during large RE ingress, negative
reserve is also required. This needs to be covered prominently in the reserve ambit.
It was strongly felt that secondary and tertiary reserves should always be available
with system operator and cannot be dynamic with URS availability (diminishing
during peak hours) or with all units are running in Technical Minimum (no negative
reserve). Whether this could be achieved through Market based reserve or through
regulatory mandatory market needs to be studied?
There needs to be a mechanism in place for sharing of secondary/tertiary reserves
available with the states. These reserves are to be made available with the system
operator.
A time bound implementation of ABT in the states is also necessary for AGC
(Secondary)/Tertiary Reserves to take off.
Forum (except NLDC/SRLDC) was of the view that Gate Closure already exists (30
minutes prior to the delivery) as per IEGC. This issue needs to be further examined.
Forum opined that proposed Bias Setting requires further review.
It was noted that in the Report on National Reference Frequency it has been
recommended that the dead band of +/-0.03 Hz (ripple factor in IEGC) may be
gradually phased out as is being done in ERCOT Texas and Europe‟. Generators
strongly opined that the dead band of +/-0.03 Hz (ripple factor in IEGC) may need to
be retained.
For SCADA veracity it was noted that it was joint responsibility of all the entities of
SRPC forum to take proactive and appropriate steps to ensure consistency in data.
The issue needed due attention it deserves as it is critical in grid operation. The
entities needed to have dedicated team with 24x7 support specifically at
SLDC/RLDC/NLDC/CTU/STU.
It was noted that the Optical Fibre Connectivity could be assessed and action plan
could be finalized by CTU/STU.
There is a need to have AGC pilot projects in all the SLDCs. It was thus
recommended that each SLDC could have a AGC standalone infrastructure with one
or two stations wired for AGC as Pilot Project. This approach would enable faster
implementation of AGC upto the state level. This would ensure hands on experience
at State Level at a faster pace along-with the development of infrastructure facility at
SLDCs.
IEGC provision that the schedules should not exceed capacity on bar less Normative
Auxiliary Consumption need to be implemented pan India for all generators- ISGS,
State generators, IPPs, MPPs etc.
The forum strongly advocated for AGC also for RE generators. There would be need
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 40
for both positive and negative reserves provision for RE also. There is need to have a
well laid down procedure including commercial settlement, which could also be a
market based mechanism.
14.4 In the OCC Meetings the following had been noted:
KPCL had informed that M/s Andritz for Varahi and M/s ABB for Sharavathy have
been identified for the AGC implementation by USAID / PRDC for which, KPCL has
given approval. This was expected to be completed by December 2018. Further, AGC
for 10 MW of Solar project at Sivasamudram was also under consideration.
Simhadri, NTPC informed that the infrastructure readiness for AGC was likely to be
in place by August 2018.
A Workshop had been conducted on 15Th
May 2018 at APSLDC by NLDC on AGC
at NP Kunta.
14.5 The following had been deliberated in the TCC Meeting:
APTRANSCO had informed that APGENCO is willing to speed up the AGC activity
since more RE has to be integrated. Some lead by SRLDC & SRPC Secretariat would
expedite the Pilot Projects.
KSEBL had suggested to explore the possibility of obtaining funding for
implementation of AGC for utility owned generators and to create suitable market
mechanism.
NLDC had informed that States need to take action as per the Regulations/Orders.
Simhadri AGC may be in place by mid-September, for Mouda (WR), Barh (ER) &
Bongaigaon (NER) tender specification had been rolled out and tender would be floated
by end of August 2018. Detailed road map for Phase I & Phase II had been submitted to
Hon‟ble CERC. For other Pilot Projects, approval of CERC would be sought shortly.
NLDC SCADA is being upgraded with AGC software to include Stations for which
tariff is determined by the Commission and NLDC would be approaching Commission
for approval.
SRLDC had observed that as per CERC Regulation/Order, the AGC should takeoff in
the state generators also. Considering the high RE penetration in SR, TCC could
suggest on AGC pilot project implementation in each state.
NLDC had informed that stand alone AGC software was available. From existing
system tie line flow and frequency data was an input. A communication link to the
generating station was required along-with the protocol compatibility to be included in
LOA. Hardware and software was available. Licensee cost would increase with number
of units wired for AGC. The protocol between SCADA and AGC software has to be
established.
NPC had opined that stand alone system may be sufficient for all the generators and not
only for those in the Pilot Project.
As noted in Meeting held on 28.03.2018, Pilot Project on AGC was agreed to be
implemented in all the states. States could approach the State Regulators and
commence the Pilot Project.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 41
NLDC had agreed to assist on technical aspects in the AGC implementation.
It was also agreed that a Committee with participation from State SLDCs, GENCOs,
SRLDC and NLDC would be formed to facilitate Pilot Project implementation in the
states.
14.6 SRPC noted the above.
15 TTC/ATC
15.1 ATC/TTC computations by SLDCs
The following had been noted in earlier Meetings:
APSLDC had assured that the system would be in place before the next SRPC Meeting.
KAR-SLDC had informed that the converged case was being furnished, while Nodal
Officer details would be furnished within a week.
The following is the status in this regard:
State 5
months
LGB
Converged
PSSE Base
case
ATC/TTC
Computation
furnished to
SRLDC
ATC/TTC
Computation
posted on SLDC
website
Nodal
Officer
Status
Study
Group
AP Yes No No No No Yes
TS Yes Yes No No Yes Yes
KAR Yes Yes No No No Yes
TN Yes Yes Yes No Yes Yes
KER Yes Yes Yes No Yes Yes
The following had been noted in the OCC Meetings:
APSLDC had constituted a Study Group. While one DE had been posted, supporting
staff was to be posted.
SRLDC had assured of cooperation in training of the officials in this regard.
TCC deliberations
APSLDC informed that from August 2018 onwards, PSSSE base case would be
furnished.
SRPC noted the above.
15.2 Harmonization of Philosophy of Computation of Total Transfer Capability (TTC) by
POSOCO and CTU between ER-SR & WR-SR
In a Special Meeting convened by NPC on 23rd
October 2017, members had agreed for the
approach for preparing base load flow case to compute TTC/ATC for the purpose of
operationalization and grant of MTOA.
SRPC/TCC had requested NPC to similarly kindly finalize procedure for base case
preparation by POSOCO, in respect of STOA.
In line with the decision taken in the 32nd
TCC meeting, SRPC Secretariat had taken up the
issue of finalizing the procedure for base case preparation by POSOCO in respect of
STOA with NPC vide letter dated 05.03.2018 (Annexure-XXVI).
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 42
TCC deliberations
NPC had informed that vide letter dated 12.03.2018, NPC had taken up the issue
with all RPCs seeking opinion/views on base case preparation by POSOCO for
STOA. For LTA/MTOA base case preparation methodology, NR & NER were not
part of deliberations and thus it was felt prudent to consult all the regions.
NPC had agreed to call for a Meeting to finalize the Philosophy for the computation
of TTC for STOA by POSOCO.
SRPC noted the above.
15.3 TTC/ATC enhancement – Operational guidelines issued by NRCE
SRPC vide letters dated 13.11.2017 and 20.11.2017 had requested POSOCO to assess the
possibility of TTC/ATC enhancement as per operational guideline for determination of
TTC, ATC and TRM for short term horizon (0-3 months) issued by NRCE, keeping in
view high demand (Jan-Apr), coal shortage conditions etc.
NPC vide letter dated 13.03.2018 (Annexure-XXVII) had again taken up the issue with
CTU and requested that the required details of terminal equipment be furnished. It was
observed that the same request had been conveyed to CTU vide NPC letters dated
21.11.2017, 19.12.2017 and 16.02.2018.
In the 5th
Meeting of Grid Study Committee (GSC) held on 18.06.2018, Chairperson, CEA
had observed on increasing the TTC through dynamic loading of the line, use of HTLS etc.
CTU had been kindly requested to furnish the information sought by NLDC for TTC/ATC
enhancement as per operational guideline for determination of TTC, ATC and TRM for
short term horizon (0-3 months) issued by NRCE.
TCC deliberations
NPC had informed that CTU vide letter dated 18.04.2018 had furnished the details
for all the regions. Onus was with NLDC/RLDCs to consider the equipment ratings
and revise the TTC/ATC.
CTU had confirmed that all India information had been furnished to POSOCO.
Further they were willing to sit together for additional requirement, clarification etc,
if any.
NLDC had agreed to look into the issue and enhance TTC as per the Operational
Guidelines issued by NRCE.
SRPC noted the above.
16 ISSUE OF PREVAILING OVER VOLTAGES IN SR GRID
16.1 Number of nodes in SR are facing high voltage problems. PGCIL had pointed out that these
over voltages lead to over stress to substation equipment including ICTs, Reactors, CVTs,
CTs etc. Life span of equipment was also affected adversely leading to early failures.
16.2 In the operational feedback, POSOCO for the quarter (April-June 2018) had highlighted
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 43
high voltage nodes (41 nodes at 400 kV & 765 kV). List of lines which were opened by real
time operators to control over voltage in the grid were also displayed.
16.3 Details of nodes of high voltage coupled with MVAR injection during February 2018 to
June 2018 are given below:
Nodes with MVAR injection during V > 103%
AP KAR TN TS
Nellore PG Nelamangala Tiruneveli Maheshwaram
Kurnool Mysore Alamathy Hyderabad
Vijayawada Karaikudi Malkaram
Gazuwaka Pugalur Gajwel
Chittoor Mehaboobnagar
Vemagiri Khammam
Warangal
Dichipally
16.4 The issue of high voltage at 400 kV Uravakonda and 400 kV Jammalamadugu sub-stations
was taken up with APSLDC vide letter dated 03.07.2018 (Annexure-XXVIII) by SRPC. It
had been stated that KSEBL had informed that RE generators are not being penalized
(charges suspended) on injection or absorption of MVAR in case the same is as per SLDC
instructions. It was suggested to consider similar philosophy in AP system to contain the
high voltage scenario. It was also proposed to constitute a group of officers from SRLDC,
SRPC and states who will visit major RE notes facing high voltage and suggest any
improvement in the Operating Procedure.
16.5 PGCIL vide letter dated 26.07.2018 (Annexure-XXIX) had expressed concern on over
voltages above 430 kV in the system observed at Pavagada, Tumkur, Mysore, Hassan,
Hiriyur, Kolar, Karaikudi, Dharmapuri, Salem and Thiruvalam stations. Providing VAR
compensation/STATCOM at few of these stations shall be explored
Further, PGCIL had expressed concern on frequent hand tripping of 765kV Kurnool –
Thiruvalam lines and 765 kV lines connected to Nizamabad and Maheswaram GIS stations.
This issue was deliberated in 33rd
SRPC meeting and it was decided to minimize the number
of switching operations. Same may be discussed as the reduction in frequency of switching
on daily basis is awaited.
16.6 The following had been deliberated in the TCC Meeting:
SRLDC had presented the issues in this regard (refer Operational Feedback available at
NLDC website). Commissioning of the reactors and STATCOM needed to be expedited.
SRLDC informed that the number of lines being taken out to curtail Over voltages
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 44
increases with RE ingress and it had gone up from 10 lines/day average to around 20
lines/day in June.
APTRANSCO had informed that Jammalmadugu reactor would come up by December
2018. After tying Vemagiri (PG) & Vemagiri (AP) the voltages have gone up.
APTRANSCO, KPTCL, TANTRANSCO and TSTRANSCO had agreed to look into
this issue and come out with short term and long term measures to address the same.
SR-II had stated that in some instances when there is a known trend of increase in
voltage, SRLDC is directing to open the lines at voltages around 435 kV which needs to
be avoided. Manual tripping above 430 kV should be avoided. SR-II had requested that
lines may be manually tripped between voltages of 420 - 425 kV to reduce stress on the
equipment.
SRLDC had assured that the lines would be taken out proactively considering N-1
reliability. Further, pro-active action would be considered in case of known trends of
increase in voltages and lines would be opened at voltages less than 430 kV. In case of
double circuit, one line would be taken out on sustained basis (7 days) to avoid frequent
switching operations.
16.7 SRPC noted the above.
17 ISSUES IN RESPECT OF NPCIL
The following are the issues in respect of NPCIL stations:
17.1 Balance dues from Beneficiaries
Issue of outstanding dues to NPCIL of Southern Region beneficiaries had been discussed in
the 32nd
/33rd
Meeting of SRPC. All the beneficiary states had assured of early settlement of
the dues. The issue was regularly followed up by NPCIL stations and MS, SRPC and it was
further discussed in the 38th
CCM. Director (F), NPCIL vide letter dated 31.05.2018
(Annexure-XXX) had expressed concern on significant dues. The outstanding dues to
NPCIL as furnished by NPCIL vide letter dated 26.07.2018 (Annexure-XXXI) are as
follows:
(Figures in Crores)
Sl.
No.
Entity
MAPS
KGS
KKNPP
Bill
Amount
Delayed
payment
charges
1 TNEB 160+78 185+123 157 138
2 HESCOM (Karnataka) 1 205+78 168 25
3 Telangana 6 158+2 0 2
4 GESCOM (Karnataka) 2 65+6 65 4
5 CESCORP (Karnataka) 3 46+4 37 3
6 APTRANSCO 7 59+11 1 1
7 PED (Puducherry) 3 13+0 21 2
8 BESCOM (Karnataka) 1 3
9 KSEBL 7
Further the shortfall in LC amount was also furnished.
TCC deliberations
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 45
NPCIL had expressed concern on dues to the extent of about Rs 1,848 crores (as on
30.06.2018) from SR beneficiaries. Considerable cash flow constraints were being
faced.
SRPC deliberations
SD, KKNPP stressed upon the timely payment of dues by the beneficiaries since it
puts lot of strain on resources and the cash flow is affected severely. He thanked TN
for clearing significant amount of dues in the last month. Dues as on date were also
quite significant and lot of payment was due from Karnataka Discoms. He stated that
NPCIL was a government organization and the fund mobilization was difficult.
PCKL stated that they had held a meeting with Discoms in this regard and a procedure
for timely clearance of the bills has been formulated for implementation.
All beneficiaries were requested to kindly clear the dues and increase the LC amounts
at an early date.
17.2 Part load operation/Reserve shutdown/frequent changes in revival of KKNPP units
In the 32nd
TCC Meeting, it was noted that with higher RE penetration, NPCIL units
need to offer some flexibility (seasonal, part load etc) which was need of the hour.
SR constituents had suggested that only one unit of KKNPP could be in service during
July to September each year and refueling need to be planned accordingly.
SR constituents had pointed out that during peak demand months (Feb to Apr) both the
units at KKNPP need to be in service. The 1000 MW size of KKNPP units has
significant impact on the LGB and even affects the power market price also.
Frequent changes in revival were completely distorting the purchase planning and their
LGB of the control area. TN as a major beneficiary was impacted by around 550 MW
for any delay in revival of the unit.
To achieve the above requirements part load operation / reserve shutdown needed to be
contemplated by NPCIL.
Chairperson, SRPC vide letter dated 11.04.2018 (Annexure-XXXII) had taken up the
pertinent issues with CMD, NPCIL.
TANTRANSCO vide letter dated 11.06.2018 (Annexure-XXXIII) had taken up the
issues like bringing back the unit II in service till July end ie till availing shutdown of
Unit I, availing AOH of Unit I once Unit II is brought into service, consider either only
one unit in service till September 2018 end and both the units to be available from
October 2018.
Director (F), NPCIL vide letter dated 31.05.2018 (refer Annexure-XXX) had requested
that the beneficiaries may surrender surplus power on long term basis so that MoP may
be approached by NPCIL for allocation of the same to other beneficiaries in need of the
same. Further, it had been pointed out that in view of the defaults in payments of more
than 6 months and in most cases 4 to 5 months, it was requested to reduce the
entitlement of these beneficiaries from Kudankulam power of NPCIL to the extent of
surplus power available even if it is more than 15% which will enable NPCIL to sale it
to others for cash and the serve the purpose of both the ends, energy consumers and
producers, NPCIL.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 46
TCC deliberations
Unit 1 had been taken out on 1.08.2108 and would come back on 05.11.2018. Unit 2 is
under forced outage since 02.08.2018 and is likely to come back on 01.10.2018.
With reference to revival of Unit 2, OCC had concluded that injection upto 1,000 MW
(corresponding to one unit) could be maintained during the short period of around 10
days since huge RE was being injected into the grid, hydro generation was significant
and number of units had been taken under NLD/RSD (4,000 MW under RSD &
13,000 MW under various outages). Daily flexibility had been categorically refused
by KKNPP, on technical considerations. However, OCC was of the opinion that at
least seasonal flexibility could be offered by the NPCIL units. SRPC letter dated
18.07.2018 in this regard is enclosed at Annexure-XXXIV. KNNPP letters dated
18.07.2018; 19.07.2018 & 20.07.2018 addressed to SRPC/SRLDC are enclosed at
Annexure-XXXV.
NPCIL had pointed out that discussion in OCC forum was not in line with nuclear
power policy. NPCIL units are of base load nature and are not governed by ABT. For
part load/RSD there is no compensation mechanism available and it is direct loss to
the Company. Clause 3.2 of PPA (15 years) clearly states that the beneficiary shall at
all times endeavor to take all the power, which the power plant is in a position to send
out. Frequency cannot be predicted by OCC two months in advance. Further, OCC
discussions were not communicated to appropriate level at Stations/HQ and thus
proper reply was not communicated by NPCIL.
It was pointed out that PPA also mentions that, „However in the event of over
frequency conditions, the SRLDC would regulate their generation/drawal as per the
SRPC/SRLDC guidelines to maintain frequency.‟ Inputs to decide high frequency
conditions can be decided by OCC.
SRLDC had stated that excess injection could lead to undesired U/D and overall grid
conditions have to be considered. KKNPP being part of grid needs to comply with
provision of EA/ Grid Code. Bypassing operational requirements citing PPA clauses
and commercial grounds is against the grid operation principles.
PCKL had stated that at times, generation from NPCIL units is not as per requirement
of the states. As per EA, SRLDC & SLDC are empowered to give suitable directions
in the interest of security of the grid. Grid security, operational efficiency etc has to be
ensured by RLDCs as per Grid Code. In single part tariff, full charges would be
recoverable at some defined PLF.
KSEBL had stated that CMD KSEBL had directed to communicate that all Discoms
are under financial crunch while NPCIL is a profitable organization and these are
factors to be considered when decisions are taken on commercial principles. Request
had been made to restrict injection upto 1,000 MW. Reactor should have been
powered accordingly. KSEBL vide letter dated 21.07.2018 (Annexure-XXXVI) had
taken up the issue with SD, KKNPP with a copy to CMD & Director (O) NPCIL, for
which no prompt reply was given and some reply had been received, couple of days
back. On one part tariff issue, some compensation can be worked out for RSD of the
unit, but for that NPCIL should have come forward. KSEBL vide letter dated
03.08.2018 (Annexure-XXXVII) had suggested to revise the REA indicating energy
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 47
injected without consent by NPCIL, separately. This has gone against the principle of
most economic operation of the grid as envisaged in the Act. As per provisions of
PPA, KKNPP should be ready to reduce the generation in case frequency is high.
TANTRANSCO had stated that 6,000 MW of RE is injected into grid coupled with
around 1,000 MW of KKNPP power (fixed with no flexibility) making it a difficult
task for the system operator to maintain LGB. Part load operation should also be
considered by NPCIL units.
TSTRANSCO had stated commercial issues as suggested by Kerala could be worked
upon. When grid is under stress, generators also need to cooperate.
After discussions, it was agreed that PPA may need to be revisited and
TANTRANSCO would kindly take the lead in this regard. Flexibility, two part
tariff, compensation for backing down etc were issues to be discussed.
It was agreed that the injection beyond 1,000 MW from 21st July 2018 to 2
nd August
2018 would be shown separately in the REA.
KSEBL had stated that the payments for this additional injection would not be made
by them. KPTCL also had stated that they would take appropriate call in this regard.
SRLDC had stated that allocating some quantum of power to other states could be
considered which may be useful in absorbing KKNPP power. Further it could come
under RRAS. It was pointed out that presently, nuclear generating stations are not in
the scheduling ambit.
It was noted that flexibility could be considered in future PPAs of NPCIL units.
NPCIL had reiterated that there was no compensation for backing down/reserve shut
down and as per PPA entire power is required to be absorbed by beneficiaries. The
units are base load stations and daily flexibility cannot be provided. On daily basis,
update of revival of unit is reviewed by CMD, NPCIL and Chairman, Atomic Energy
Commission.
It was noted that there was provision for curtailing the generation as per RLDC
directions in case of high frequency. It was suggested that the same could be
implemented by SRLDC as per any communication received from the beneficiaries.
However NPCIL stated that any directions in this regard would need to be adequately
justified by SRLDC.
Beneficiaries had strongly recommended that the shutdown of NPCIL units of
SR should be availed only during June to December each year.
It was agreed that Chairperson SRPC would be requested to take up the pertinent
issues with MoP.
SRPC deliberations
SD, KKNPP stated that suggestion of the states that nuclear generating stations should
adjust its generation keeping in mind generation from renewable energy sources is a
challenge to the basic design concept of nuclear power station itself. Even though
there may be deliberations but the same may not be feasible. PPAs are signed for 15
years and revisiting of the PPAs may not be practical. As far as scheduling of outages
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 48
is concerned, it is well known that the KKNPP units require refueling after every 300
days of full load operation. As soon as 300 days of full load operation is over,
operators cannot extend the running of the unit even for one day. There is a difference
between PLWR and PHWR technologies. The reactors at MAPS and Kaiga GS have
online refueling possibilities and in these stations, little bit of rescheduling is possible.
It was agreed that there had been more number of unscheduled outages. Unit-1 was
made commercial in the year 2014 and year after year the performance is improving.
This reactor had undergone two refueling cycles and performance of the unit after
second refueling (capacity factor) was about 92.5%. Unit-II has undergone only one
refueling cycle and they were hopeful that after sorting out the teething problems the
performance of Unit-II would be at par with Unit-I. Before PPAs were signed, the
same had been deliberated at length in MoP, wherein it was noted that nuclear stations
were expected to be base load stations. KKNPP installed capacity is hardly 2% of the
installed capacity in SR and not absorbing the power cannot be appreciated.
Sometimes NPCIL also suffer losses when the payments are not received and the
moneys have to be borrowed from banks in addition to the expenditure incurred on
interest. NPCIL has also reached a stage where further money cannot be borrowed
since limit has been reached. These views from NPCIL should also be taken into
account and constituents should not expect some things which are impractical due to
the limitations in the design not only for NPCIL but for nuclear reactors all over the
world. World over nuclear stations are operating as base load stations. Improving the
performance and reliability was NPCIL‟s responsibility and shortly they would
overcome the constraints. For KKNPP units the refueling cycle cannot be altered as
per the requirement of the beneficiaries. He hoped that Electricity Boards would
appreciate and understand these concerns.
It was pointed out as NPCIL was a commercial organization states were also running
under commercial principles. Any deviation beyond limits attracts penalties. If
underdrawal increases there are no payments receivable and beyond certain frequency
even penal rates are applicable. In this case, the beneficiaries had only requested only
some minimum response from NPCIL (to avoid injection beyond 1,000 MW) since
there was underdrawal and high frequency conditions were prevailing.
SD, KKNPP stated that it was in the interest of nuclear station that it operates at stable
power level. Request from states is varying and when KKNPP units were coming up
the state has requested for higher share. Concerns of the state electricity board are well
understood and appreciated, however nuclear stations are to be operated within certain
limitations. Some adjustment in power level in the long run (not on a daily basis) is
something new and needs to be discussed at length. In case some compensation to
NPCIL could be worked out, it can be thought of. It is in the interest of states to
absorb nuclear power since RE energy was variable.
It was pointed out that earlier there were power shortages but now states have surplus
power. Merit order operation has also kicked in and RSD procedure is in place,
Technical minimum has been introduced and the operating philosophy has undergone
sea change. KSEBL has suggested for some commercial mechanism and NPCIL also
needs to come forward in this regard.
Chairperson, SRPC observed that it is a commercial situation and this is the reason
why some generators are being backed down. Technical difficulties of NPCIL units
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 49
are well appreciated but NPCIL could consider the request of the beneficiaries
regarding the outage plans. The outages of the units are to be planned between June to
December for SR as in monsoon SR demand is lean. All electricity boards in the
country are suggesting that the nuclear stations should be operational during summer
and winter. Therefore, there is a window to complete the maintenance for all the
NPCIL units in the country.
It was concluded that Kaiga GS and MAPS units shutdown should be planned
between June to December, while KKNPP units shutdown would be endeavored
between June to December.
PCKL pointed out that there was a need for change in the Tariff structure for nuclear
stations. In the new concept paper three part tariff was being considered for thermal
stations. In the changed scenario balancing part has to be managed both at generation
and consumer ends.
As suggested by TCC, it was agreed that PPA may need to be revisited and
TANTRANSCO would kindly take the lead in this regard. Flexibility, two part
tariff, compensation for backing down etc were issues to be discussed.
Beneficiaries strongly recommended that the shutdown of NPCIL units of SR
should be availed only during June to December each year.
Chairperson, SRPC stated that considering all these factors issues could also be taken
up with MoP justifying the requirements of the beneficiaries.
17.3 BSD of KGS units
Kaiga 1 & 2 would inform the extended dates for BSD of Unit 1well in advance to
OCC/SLDC KPTCL for the states to plan their LGB in an economic and secure manner.
Shutdown of unit 1 would not be allowed during Jan to April 2019.
On similar lines Kaiga GS would consider request of OCC for postponement of BSD
scheduled during Jan to April, for any of the units in future.
All units would be planned for BSD during June to December only each year.
17.4 Black Start Mock Drill at Kaiga GS and MAPS
In the Meeting held on 22.06.2018, KGS had informed that Black Start Mock Drill
would be taken up during BSD of the unit-I on similar lines to KKNPP.
MAPS Black Start Mock Drill is to be carried out.
17.5 PSS tuning / SRT
In the Meeting held on 22.06.2018, Kaiga GS agreed for PSS Tuning of unit during BSD
of Unit 1 & III respectively.
MAPS Unit –II PSS tuning/SRT is to be completed.
17.6 MVAR interchange by Kaiga GS units (meeting held on 22.06.2018)
Kaiga GS units 1 & 2 would start absorbing as per Capability Curve above 225 kV and
there would be no injection at voltages in the range 220-225 kV.
Kaiga GS/NPCIL would take all steps to ensure commissioning of first 125 MVAR by
December 2019. Kaiga GS/NPCIL would also initiate the tendering activities of second
125 MVAR reactor and same needed to be confirmed with the detailed commissioning
plan in the 33rd
TCC/34th
SRPC scheduled in August 2018.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 50
During testing activities of generator 3 & 4 with respect to MVAR absorption, Kaiga GS
would involve SRPC/SRLDC.
Kaiga GS would endeavor to support the grid within the mandated provisions of
IEGC/CEA & CERC Regulations.
17.7 2x125 MVAR Reactor commissioning at Kaiga GS (meeting held on 22.06.2018)
In Kaiga GS/NPCIL informed that technical bid had been opened for the first 125
MVAR reactor on 20.06.2018. The reactor was planned to be commissioned by
December 2019.
Kaiga GS/NPCIL assured that bidding activities for second 125 MVAR reactor would
be initiated.
As discussed in the Special Meeting held 22.06.2018 held at Kaiga GS, Chairperson,
SRPC vide letter dated 26.06.2018 (Annexure-XXXVIII) had taken up the issue with
CMD, NPCIL.
CMD, NPCIL vide letter dated 02.08.2018 (Annexure-XXXIX) had replied to
Chairperson, SRPC‟s letter and had stated that tender had already been floated for
supply and commissioning of one 125 MVAR reactor for which technical bids had been
opened. Engineering details and estimates for replacement of existing 63 MVAR reactor
are being worked out and it would be replaced with 125 MVAR reactor soon after
commissioning of first reactor. All efforts were being made to expedite early
commissioning of these reactors.
17.8 Other issues as noted in the Meeting held on 22.06.2018 and other Meetings
Kaiga GS/NPCIL agreed for providing Differential and REF protection in different
relays in ICT-1&2. This would be complied by December 2018 by procuring additional
relays.
LBB time setting for lines is 0.25 sec and for ICTs - 0.2 sec. Kaiga GS informed that the
settings have been reviewed and it has been decided to keep settings as 200 msec for all.
Approval letter from HQ has been received and it would be completed during Bus
Shutdown at the time of BSD of Unit 1.
KGS agreed to disable sending of DT to remote ends upon 86 X operations for any line
protection operation at its 400 kV KGS within one month.
KGS agreed to ensure time-synchronization of all protection relays with GPS in their
400 kV switchyard by December 2018.
KGS agreed to use stipulated formats for furnishing FIR and TR.
KGS agreed to include line backup protections in Main I & Main II within 2 months,
and configure DR‟s & EL‟s of Main I & II for recording all mandated protections.
Kaiga GS would extend support for insulator replacement in Kaiga complex. Once
concurrence is received from Kaiga GS by SR-II, the works would be completed within
3-4 months as new work order had to be placed.
SRPC/SRLDC had pointed out that as User it was responsibility of Kaiga GS to ensure
data availability to SRLDC. RTU has been handed over to Kaiga GS and Kaiga GS
needed to have a backup arrangement for RTU maintenance. It was agreed that Kaiga
GS would formally take up the RTU related issues with SR-II, PGCIL with a copy to
SRLDC/SRPC. SRLDC would try to facilitate the works through SR-II, however the
onus of SCADA compliance rested with Kaiga GS.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 51
Kaiga GS agreed to extend the digital status under URTDSM within a month.
KKNPP had informed that the rectification for the other reactor would be taken up in
April/May 2018 and expected to be completed by December 2018.
With regard to A/R implementation on MAPS lines, NPCIL had informed that
procurement of required line CVTs was under progress. Commissioning of CVTs and
A/R enabling on all the four 220 kV lines was targeted to be completed by September
2018. MAPS had informed that PO for A/R facility was released for procurement of the
CVTs. A/R for the lines would be implemented after receiving the CVTs.
SRPC noted the above and suggested NPCIL to close the pending issues in a time bound
manner.
18 UPCOMING TRANSMISSION SYSTEM
18.1 42nd
Standing Committee on PSPSR
18.1.1 Minutes of Meeting of 42nd
Meeting of Standing Committee on Power System Planning
in SR (meeting held on 27.04.2018) had been issued on 15th
June 2018 (available on CEA
web site).
SRPC noted the above.
18.1.2 Joint System Study Meeting of SR was conducted on 10th
& 11th
May 2018 at SRPC,
Bengaluru. The MoM is enclosed as Annexure-XL. The following issues were
discussed:-
Evacuation of power from RE sources in Southern Region (proposed Wind Energy
Zone by MNRE )
Intra-state transmission projects proposed for Green Energy Corridor Phase-II in
Karnataka.
High flow on 400 kV KKNPP – Tirunelveli D/C line after commissioning of 400 kV
KKNPP-Tuticorin PS D/C line.
Providing additional feed to 3 x 500 MVA, 400/220 kV Sub-station at Mylasandra
(Electronic City) and establishment of 2 x 500 MVA, 400/220 kV S/S at
Dommasandra, Bengaluru.
SRPC noted the above.
18.2 Operationalization of LTA
In Petition No. 12/SM/2017 along-with I.A. No. 54/2017, in the ROP for date of hearing
15.05.2018 (Annexure-XLI) it was noted, „….the representative of CTU further
submitted that there are certain regulatory issues in operationalization of LTA as under:
(a)Non-opening of LC ………..(b)Relinquishment en-masse (specially on HCPTC
corridor) ……….(c)Abandonment of Generation Project / Adverse Progress…. After
hearing the representative of CTU, the commission reserved orders in the petition.‟
SRPC noted that the above could be discussed in the Meeting planned with CTU & SR
constituents to discuss sharing of transmission charges/ operationalization of LTA etc.
18.3 Upcoming inter-regional transmission schemes
18.3.1 Updated status is furnished below please:
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 52
S S.No. Transmission Element Remarks
a) WR-SR 6000 MW HVDC Bipole Link
[Raigarh (Chhatisgarh) - Pugalur-
Trichur (TN/KER)]
Apr’ 2020
32nd TCC: 800 kV December 2018. 320 kV: September 2019.
CEA (May 2018): Work held up in Tamil Nadu due to severe ROW -Critical.
Huge forest involvement (432 Ha.) in WR portion incl. Wildlife Sanctuary
clearance. Critical.
320 kV: Feb 2020 - Progress affected due to severe ROW problem in Tamil Nadu
area.
33rd TCC: Progress in Tamil Nadu very slow due to RoW issues. Issue taken
up with State administration and project is under review by PMO under
PRAGATI.
b) 765 kV Angul - Srikakulam PS D/C
Corridor
Main corridor commissioned. Other
associated elements by July 2018.
33rd TCC: PGCIL informed that Garividi- Srikakulam PS Trial Operation was
over.
c) Additional inter-Regional AC link for
import to Southern Region, i.e., Warora -
Warangal - Hyderabad- Kurnool 765 kV
link
TBCB, PFCCL- BPC Transmission Licensee : Warora-
Kurnool Transmission Limited
(WKTL)
32nd TCC: There was a Meeting held to consider preponing of Hyderabad-
Kurnool line. It was concluded that further study may be required before
concurring for this preponement. One more Meeting was to be held.
CEA (May 2018): Nov 2019.
d) System strengthening within SR for
transmitting power beyond Vemagiri TBCB- RECTPCL-BPC Project has been awarded to PGCIL
under TBCB, and was expected by
April 2019.
32nd TCC:
Chilkaluripeta – Cuddapah line was stuck up for want of wild life (Tiger
Conservation Reserve) clearance. It requires forest clearance from
AP/TS/Central Govts. They had taken up the issue since Tiger Conservation
Reserve is yet not in public domain, they may not to be obligated to take this
clearance. There were AP lines also stuck up due to the same issue. The line
would come up in Q3 of 2018-19.
Cuddapah – Madhugiri Q2 of 2018 – 19.
POSOCO’s Operational feedback for the quarter April to June 2018
The import capability of Southern Region can only be increased after the
constraint on ICTs at Vemagiri (PG) is relieved. The commissioning of following
765 kV outlets at Vemagiri(PG) need to be expedited in order to relieve the
constraint on Vemagiri ICTs:
a) 765 kV Vemagiri – Chilkaluripeta D/C
b) 765 kV Chilkaluripeta – Cuddapah D/C
c) 400 kV Chilkaluripeta – Narasaraopet D/C
d) 400 kV Cuddapah – Hindupur D/C
e) 400 kV Cuddapah – Madhugiri
18.3.2 Updated detailed status of upcoming inter regional scheme is furnished at Annexure-
XLII.
18.4 Pending transmission elements in WR and SR for proper utilization of 765 kV
Raichur- Sholapur line (Out of planned 18 elements)
18.4.1 Updated status of pending transmission elements in WR and SR for proper utilization of
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 53
765 kV Raichur - Sholapur lines (out of planned 18 elements) is furnished below please:
SRPC noted the above.
18.5 Status of important Transmission Systems
18.5.1 Updated status of associated links is furnished below please:
Transmission Elements
1 765 kV S/C Salem PS (Dharmapuri) - Madhugiri P S line (initially charged at
400 kV) ; 243.23 ckm; PGCIL
CEA (May 2018): Sep 2018, Severe ROW in Karnataka. Obstruction is being
removed progressively with the help of Police protection.
Covered under PRAGATI.
33rd
TCC: Fdn & Erec. Completed; Strg: 233/243 kM, Expected completion:
Sept’18
2 Salem New – Madhugiri 765 kV S/C line; 219 ckm ; (PNMTCL) (A subsidiary of
PGCIL)
CEA (May 2018): Sep 2018; Severe RoW issues being faced in Karnataka, issue
highlighted to PMO level.
33rd
TCC: Fdn: 573/575; Erec: 573/575; Strg.: 188/219 kM, Expected
completion: Sept’18
Sl.
No
Name of Transmission Element
1 400 kV Tumkur-Yelahanka D/C line ; PGCIL (132 Ckm)
CEA (May 2018): Dec 2018; Severe ROW in Karnataka. Balance work re-awarded
in Dec'17. Work under progress.
33rd
TCC : Fdn: 149/178 Erec: 133/178 Strg :10/66 kM, Expected completion:
Dec’18
2 400 kV Nelamangala-Hoody LILO at kV Yelahanka ; PGCIL (20 Ckm)
CEA (May 2018): Charged on 22.03.2018 and COD from 01.04.2018
3 220 kV Tumkur – Antharasana Halli D/C ;KPTCL; LOA placed on 18.03.15 with
18 months completion schedule
Special Meeting (09.07.2018) : KIADB has to procure and hand over the land.
33rd
TCC: Partly commissioned on 12.01.2018. 7 Locations pending. KIADB to
acquire land and hand it over KPTCL.
4 220 kV Tumkur (400 kV) S/S – 220 kV Tumkur S/S D/C; KPTCL; LOA placed
on 18.03.15 with 18 months completion schedule
Special Meeting (09.07.2018): KIADB has to procure and hand over the land.
33rd
TCC: 202/209 stub concreted, 202/209 towers erected, 83.6/88.962 CKms
stringing completed. 7 Locations pending. KIADB to acquire land and hand it
over KPTCL.
5 220 kV Yelahanka (400/220 kV) S/S- 220 kV Yelahanka S/S D/C Cable;
KPTCL (11.75 Ckm)
Special Meeting (09.07.2018): End of August 2018.
33rd
TCC: 17/17 sections (5.9/5.9 km) cable laying completed. 14/16 Cable jointing
work completed. Completion by 20th
August 2018.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 54
3 Transmission evacuation system for HNPCL (1,040 MW) Power Plant
APTRANSCO ; 400 kV TM D/C Kamavarapukota – Vemagiri; 185 ckm
31st TCC: Alternate options being explored, would be taken up with the Standing
Committee.
4 Transmission System required for evacuation of power from Kudgi TPS (3x800
MW in Phase-I) of NTPC Limited
KPTCL : 220 kV D/C line to Vajramatti: 32nd
TCC: 209/267 stub concreted,
141/267 towers erected, 2.292/158.84 CKms stringing completed.
220 kV D/C line to Basavana Bagewadi: 32nd
TCC: Commissioned.
220 kV D/C line to Bijapur:
5
Transmission System for evacuation of power from Singareni Collieries
Generating Project (2 x 600 MW)
TSTRANSCO : STPP, Jaipur – Jagityal; 139 ckm ; 33rd
TCC : August 2018
TSTRANSCO : Jagityal – Nirmal; 148 ckm; 33rd
TCC : August 2018
33rd
TCC: Sub-station is charged on 07.07.2018 with 2 x 315 MVA PTRs. 3rd
PTR is programmed for charging in August'18.
400/11 kV Sundilla LI SS is charged on 18.07.2018 by making LILO of ckt-I of
400 kV STPP,Jaipur - Nirmal QMDC line
STPP-Sundilla Feeder Bay-1 is charged on 18.07.2018 and STPP-Sundilla
Feeder Bay-2 is programmed for charging in August'2018.
6 Damaracherla TPP Evacuation
TSTRANSCO: 400 kV Damacherla TPP – Choutuppal D/C : Sep 2018, 400 kV
Damacherla TPP – Dindi D/C : Sep 2018, 400 kV Damaracherla TPP – Jangaon
D/C : Sep 2018, 400 kV Damaracherla TPP – Maheswaram (TS) D/C : Sep 2018
33rd
TCC: TSTRANSCO have acquired the land acquisition for construction of
400/220/132 kV Choutuppal SS and the survey works of connected 400 kV lines
are under process.
7 Bhadradri TPP (Manuguru) (4x270 MW), TSGENCO
TSTRANSCO: 400 kV Julurupadu SS - Manuguru TPP D/C: 2018-19 (33rd
TCC:
All foundation works completed. Erection and stringing at 3 Nos. locations is
held up due to severe ROW issues).
400 kV Julurupadu (QM) - Suryapet S/S D/C : 2018-19, Julurupadu S/S 2x 315
MVA : Bus I and Bus II charged on 23.12.2017, 33rd
TCC : PTRs are ready for
charging.
8 Kothagudem TPS St-VII (1x800), TSGENCO
TSTRANSCO: 400 kV D/C Julurupadu - KTPS (Stage-VII): 33rd
TCC: charged on
19.05.2018.
400 kV Julurupadu – Jangaon D/C : 33rd
TCC : 69/175 Kms stringing completed
and programmed for charging in Nov'2018
Jangaon SS: 33rd
TCC : Feb 2019
9 Transmission system of KPTCL for evacuation of power from Yermarus TPS
(2 x 800 MW)
KPTCL : Yermarus TPS - Bellary PS 400 kV D/C QM, 33rd
TCC: Commissioned
on 04.05.2018
Gulbarga 400/220 kV substation- 2 x 500 MVA, 33rd
TCC: DPR approved on
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 55
09.03.2018 (to be tendered), Yermarus TPS - Gulbarga 400 kV D/C line (QM), 33rd
TCC: DPR approved on 09.03.2018 (to be tendered)
400 kV SS at Chikkanayakanahalli – 2 x 500 MVA (39th
SC), CEA (May 2018):
Sep 2018, 33rd
TCC: Land identified acquisition of land under progress.
LILO of Nelamangala – Talaguppa 400 kV D/C at CN Halli, 33rd
TCC: Land
identified acquisition of land under progress.
Termination of 400 kV D/C of Hassan from Nelamangala – Talaguppa at CN Halli
400 kV, Bellary PS - C.N.Hally 400 kV D/C line QM, 33rd
TCC: The work is split
into three parts: (a) 400 kV line from BPS to Rampura Limit : Line work
completed, (b) 400 kV line from Rampura limit to Jagalur : Line work is under
progress (c) 400 kV line from Jagalur to Chikkanayakanahalli : To be tendered
De-link 400 kV S/C RTPS-BTPS-JSW-Guttur with JSW Bus
Additional JSW TPS – BPS 400 kV D/C (QM), 33rd
TCC: Commissioned.
400 kV BTPS-Guttur D/C (QM), 33rd
TCC: Estimate under preparation.
10 Transmission System for Rayalaseema TPS (600 MW)
APTRANSCO: 400/220 kV, Kalikiri S/S – 2 x 315 MVA: 2018-19: PO is placed in
Nov-15. Site handed over on 23.06.2016
LILO of Rayalseema IV-Chittoor 400 kV D/C at Kalikiri: 2018-19
11 400 kV Somanahalli- Dharmapuri PS; 244 ckm; PGCIL
CEA (May 2018): Sep 2018 - Severe ROW problem faced in Karnataka. With the
support of state Govt. ROW issues are being resolved.
33rd
TCC: Fdn: 333/336; Erec: 327/336; Strg: 106/122 kM, Expected
completion: Sept’18
12 400 kV Mangalore (UPCL) -Kasargode-Kozhikode; 33rd
TCC: NCT in its 1st
meeting had approved the scheme through TBCB.
13 400 kV Edamon-Kochi; 286 ckm; PGCIL
Being monitored under PRAGATI.
CEA (May 2018): Sep 2018 - Severe ROW problem (long pending). Problem being
addressed progressively as per latest Revised G.O. of 30.07.15 (compensation to be
done on land value, to be finalized by concerned DC with the support of State Govt.).
Works under progress. Site is getting police protection as per requirement from State
Admn. Foundation works affected due to non-availability of aggregate. Matter has
been taken up Secy. level.
33rd
TCC: Fdn: 389/447; Erec: 323/447; Strg: 60/149 kM, Expected completion:
Mar’19, Works under progress. Adverse site conditions & heavy rains affecting
progress. Works being expedited with support of state administration.
14 LILO of 230 kV Neyveli- - Bahour at Karaikal
CEA (May 2018) : NLY- Karaikal – Aug 2018
33rd
TCC: Fdn: completed; Erec: 310/317; Strg : 81/95 kM, Expected
completion: Aug’18
15 400 kV Pavagada – Hiriyur D/C line; PGCIL
CEA (May 2018): Dec 2018- Slow progress due to ROW problem.
33rd
TCC: Fdn: completed; Erec: Completed; Strg: 102/109 kM, Expected
completion: Aug’18
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 56
16 400 kV Hiriyur – Mysore line; PGCIL
CEA (May 2018) : Jan 2019 – severe ROW issues
42nd
SCPSPSR: to be expedited to relieve over loading of Nelamangala-Mysore 400
kV D/C line getting heavily loaded.
33rd
TCC: Fdn: 473/565; Erec: 306/565; Strg: 20/206 kM, Expected completion:
Mar’19 – Slow progress due to ROW issues
17 400 kV Pavagada – Devanahalli D/C line; (139.30 D/C and 13.20 M/C); PGCIL
32nd
TCC: December 2018
CEA (May 2018) : Jan 2019 – severe ROW issues
33rd
TCC: Fdn: 177/436; Erec: 163/436; Strg: 10/152 kM, Expected completion:
Mar’19 – Slow progress due to ROW issues
18 FSC at Pavagada; PGCIL
33rd
TCC: July 2019
SRPC noted the above.
18.6 Associated Transmission Evacuation Schemes in Tamil Nadu
Updated status of the following stations, evacuation schemes finalized in the 37th
SCPSPSR,
which were modified in the following Standing Committee Meetings, is given below:
Generating Station Likely COD Evacuation Status
Ennore TPS Expansion – 1 x
660 MW
33rd
TCC: 2021
Ennore SEZ (NCTPS Stage-
IV) – 2 x 660 MW
33rd
TCC: 2019-20
NCTPS Stage III – 1 x 800
MW
33rd
TCC: 2019-20 41st SCPSPSR: 2019
Ennore TPS Replacement – 1
x 660 MW
33rd
TCC: 2022-23 41st SCPSPSR: 2020
SEPC (1x525) October 2018 41st SCPSPSR: Require
start up power for its
Auxiliaries by April 2018.
SEPC-Thennampatty
400/230/110 kV 41
st SCPSPSR : April 2018 SEPC- Ottapidaram 400kV
(Regular evacuation)
765/400 kV, 2 x 1500 MVA
Ariyalur SS
31.3.2019 Work awarded to M/s BHEL
on 31.03.2017.
765/400 kV, 3 x 1500 MVA
North Chennai PS (GIS) March 2020 Work awarded to M/s
Hyosung Corporation,
Korea on 21.03.18
765/400 kV, 2 x 1500 MVA
Coimbatore SS
2020-21 Administrative approval
accorded. Alternate land is to
be identified.
765 kV Ariyalur – Thiruvalam
(PG) CEA (May 2018): June
2018
Work awarded to M/s
Transrail. Works are
under progress
765 kV North Chennai PS -
Ariyalur CEA (May 2018): Sep
2019
Work under progress.
400 kV Ennore SEZ-North
Chennai PS CEA (May 2018): Sep
2018
Tender opened on 07.06.17.
Price bid opened and
evaluation is under 400 kV Ennore SEZ- Ennore CEA (May 2018): April
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 57
to ETPS Expn 2019 process. Approval of BLTC
to recommend to place
before board.
400 kV ETPS Expn – North
Chennai PS CEA (May 2018): Sep
2018
Interconnection from common
point of SEZ – ETPS Expn to
NCTPS Stage-II and LILO of
NCTPS-II – SV Chatram 400
kV MC between location
No.21 & 22
SRPC noted the above.
18.7 Status of Implementation of downstream network by State utilities associated with
ISTS substation of POWERGRID
Sl.
No
Name of
Substation
MVA
Capacity
220kV
Bays
Expected
Schedule of
Substation
Remarks
1 Tumkur
(Vasantnarsapur)
2 x 500 6 Commissioned Construction of downstream
T/L for 6 Nos 220 kV bays to
be expedited by KPTCL.
Deliberations in 42nd
SCPSPSR : 4 Nos 220kV downstream links i.e. Tumkur-
Anthranasahalli 220kV D/C line & Tumkur- Madhugiri-II 220kV D/C line expected by
Sep‟18. Balance 2 Nos 220 kV downstream links yet to be taken up.
33rd
TCC: Anthranasahalli 220 kV D/C line &Tumkur- Madhugiri-II 220 kV D/C
line expected by Sep’18. Balance 2 Nos 220 kV downstream links yet to be taken
up.
2 Yelahanka 2 x 500 10 Commissioned Construction of downstream
T/L for 10 Nos (6 bays under
ISTS) 220 kV bays to be
expedited by KPTCL.
Deliberations in 42nd
SCPSPSR: 2 Nos 220 kV downstream T/L cable to Yelahanka
DG plant expected by Jun‟18. Balance 4 Nos 220 kV downstream links yet to be
planned.
3 Bidadi 2 x 500 6 Commissioned Construction of downstream
T/L for 4 Nos 220 kV bays to
be expedited by KPTCL.
Deliberations in 42nd
SCPSPSR: 2 Nos 220 kV downstream links i.e Bidadi –
Magadi 220 kV D/C line expected by Mar‟19. 2 Nos 220 kV downstream Link Bidadi-
Kumbalgodu expected by Mar‟20.
4 Hiriyur 2 x 315 6 Commissioned Construction of downstream
T/L for 2 Nos 220 kV bays to
be expedited by KPTCL.
Deliberations in 42nd
SCPSPSR: 2 Nos 220 kV downstream links i.e. Hiriyur-Hiriyur
(KPTCL) 220 kV S/C line & Hiriyur-Chitradurga 220 kV S/C line expected by
Mar‟19.
5 Hassan 2 x 315 6 Commissioned Construction of downstream
T/L for 2 Nos 220 kV bays to
be expedited by KPTCL.
Deliberations in 42nd
SCPSPSR: 2 Nos 220 kV downstream T/L i.e. LILO of
Hassan(KPTCL) – Nittur S/c expected by Mar‟19.
6 Kolar 2 x 500 6 Commissioned Construction of downstream
T/L for 2 Nos 220 kV bays to
be expedited by KPTCL.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 58
PGCIL vide letter dated 26.07.2018 (refer Annexure-XXIX) had requested deliberation on
the above.
SRPC noted the above.
18.8 Operational Feedback
18.8.1 NLDC vide letter dated 30th
April 2018 (available on NLDC website) had highlighted
following transmission constraints as part of Operational Feedback for the quarter
January– March 2018, in respect of SR:
a) Impact on grid operation due to ferro-resonance
Outage of FSC leads to power order reduction in HVDC Gazuwaka block(s) because
high power order without the series capacitive compensation at Jeypore causes low
voltage at Gazuwaka East bus.
Frequent repetition of this phenomenon may affect reliable system operation at Eastern
region and Southern region boundary, and may even cause equipment damage if the FSC
bypass scheme fails to act in case of ferroresonance.
It was necessary to carry out necessary system improvements aimed at damping the
resonant condition.
HVDC links are critical to integrated power system operation, as the operator is able to
gain flexibility in power system operation using HVDC links. It is necessary that
extensive studies are conducted in critical HVDC installations and in cases of
overcompensated AC lines to prevent any such surprises in real-time operation.
NLDC vide letter dated 09th
March 2018 with regard to frequent occurrence of
ferroresonant phenomenon involving Gazuwaka HVDC had communicated the issues to
PGCIL.
TCC deliberations
These issues had been discussed in the Meeting held on 02.04.2018. Tertiary aux
supply issue has been rectified.
Deliberations in 42nd
SCPSPSR: 2 Nos 220 kV downstream links Kolar-Gollahalli
220kV D/C line expected by Mar‟19.
7 Karaikudi 2 x 315 4 Commissioned Construction of downstream
T/L for 1 Nos 230 kV bay to
be expedited by
TANTRANSCO
Deliberations in 42nd
SCPSPSR: 1 Nos 230 kV downstream T/L Karaikudi –
Sembatty 220 kV S/c line expected by May‟18.
8 Hosur 3 x 315 6 Commissioned Construction of downstream
T/L for 2 Nos 230 kV bays to
be expedited by
TANTRANSCO
Deliberations in 42nd
SCPSPSR: 2 Nos 230 kV downstream T/L Hosur -Shoolagiri
220 kV D/C line expected by Jul‟18.
9 Kozhikode 2 × 315
+
1 x 500
4 Commissioned Construction of downstream
T/L for 1 Nos 220 kV bay to
be expedited by KSEBL
Deliberations in 42nd
SCPSPSR: 1 Nos 220 kV downstream T/L to
Kozhikode(KSEB) expected by Mar‟19.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 59
Short term measures (DTPCs commissioning) complied with.
Medium Term measures (STATCOM commissioning at Jeypore) complied with.
PGCIL SR I was also requested to take up implementing Long Term Measures,
viz., refurbishing of controller protection at Jeypore to detect FR and bypass FSC.
SRPC noted the above.
b) Frequent tripping of Talcher-Kolar Bipole
S. o. Name of
Element
Tripping Restoration Remarks
Date Time Date Time
1 Pole 1 8-Jan-18 19:06 9-Jan-18 00:54 Series Reactor in R-Phase of Pole-1
was burnt & faulty at Talcher.
2 Pole 1 9-Jan-18 07:50 9-Jan-18 09:04 Operation of Valve Cooling
Differential Protection at Talcher end.
3 Pole 1 2-Mar-18 16:15 2-Mar-18 19:19 Clogging of the mechanical filter of
Pole-1 valve cooling system at
Talcher.
4 Pole 1 7-Mar-18 09:38 7-Mar-18 10:25 Tripped due to external protection
tripping command as reported by
Talcher end
5 Pole 1 17-Mar-18 15:12 17-Mar-
N18
21:07 DC line differential protection
operated
6 Pole 2 17-Mar-18 20:29 17-Mar-18 21:07 While deblocking Pole-1, Pole 2 went
into ground return mode and power
flow got reduced to 150 MW.
HVDC Talcher-Kolar Related RVO operation January to March 2018
1 Pole 1 17-Mar-18 14:20 Tripped Several transients were observed in
HVDC Talcher –Kolar
2 Pole 1 20-Mar-18 06:32 20-Mar-18 13:43 Due to heavy fog in
Gazuwaka area. Total 6 nos
Transients were observed in
approx 1 hour
3 Pole 2 20-Mar-18 06:20 20-Mar-18 13:52
NLDC had observed Transmission licensees are required to take adequate steps to prevent
undesired outages of this HVDC link. There have been multiple pollution related trippings,
which warrant the replacement of porcelain insulators with appropriate polymer or
composite insulators, which have better resistance to flashovers from prevailing higher
pollution levels. NLDC communication dated 21st March 2018 in regard to frequent
trippings on HVDC Talcher – Kolar bipole had been communicated to PGCIL.
TCC deliberations
PGCIL agreed to look into the issues.
SRPC noted the above.
c) High flow on 400 kV KKNPP-Tirunelveli D/C line after commissioning of 400 kV
KKNPP-Tuticorin PS D/C line
In 42nd
SCPSPSR it was noted that, POSOCO had informed that POWERGRID had
commissioned above transmission system in 1st week of March 2018. But, with the
commissioning of 400 kV Kudankulam - Tuticorin PS D/c line (144 Km), more than 80%
of power generated from KKNPP (with both units in service) is flowing 400 kV
Kudankulam-Tirunelveli D/C section (72.5 km). It was further added that with more
generation at Coastal Energen and NTPL, there would be further uneven distribution of
flow on 400 kV KKNPP Tirunelveli and 400kV KKNPP- Tuticorin PS sections.
Additionally by commissioning of the new 400 kV lines connecting Tirunelveli wind
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 60
station to Tuticorin PS will further aggravate the situation. POSOCO stated that there is a
need to review the evacuation transmission system from KKNPP.
After deliberations, the issue had been referred for joint system study by CEA, CTU,
POSOCO and constituents of Southern Region. The proposal along with study results
would be discussed in next meeting of Standing Committee.
TCC noted the following
This issue had been discussed in the Joint Study Committee Meeting held on 10th
and
11th
May 2018 wherein it was noted that although the line loadings are uneven, there
is no issue regarding power evacuation from KKNPP even under contingency
conditions, as per planning criteria. Uneven loading of lines connected to U 1&2
would be studied while planning the evacuation for U 3&4.
SRPC noted the above.
d) Transmission Line constraints:
400 kV Nellore Pooling Station -Nellore D/C line
33rd
TCC: SRLDC requested SR-I to carry out modification at Nellore 400 kV S/S
as per Standing Committee decision.
400 kV Gooty-Nelamangala line & 400 kV Gooty- Somanahalli line
33rd
TCC: SRLDC informed that with commissioning of Tumkur - Bidadi line
loadings had come down. Downstream at Madhugiri & Yelahanka needs to be
expedited.
KPTCL informed that the prevailing constraint in 400 kV Hiriyur- Nelamangala
DC line with Twin Moose conductor would be reduced after commissioning of the
associated 400 kV transmission scheme of Yeramarus. Further, the newly
commissioned 400 kV Madhugiri-Bidadi D/C line also reduces the loading of 400
kV Hiriyur- Nelamangala D/C line.
400 kV Udumalpet- Palakkad D/C line
KSEBL had stated that there was no constraint on this line. SRLDC stated that
they would examine the matter.
400 kV Hiriyur-Nelamangala D/C line
33rd
TCC: SRLDC informed that line loading is more when wind is more. With
commissioning of Pavagada-Hiriyur, loading may further increase. Hiriyur-
Mysore line needs to be expedited.
220 kV Bangalore Metro Network
33rd
TCC: KPTCL informed that they had planned the following 220 kV sub-stations
and lines which would provide relief to the existing congestion in the transmission
network of Bengaluru:
i. 2x500 MVA, 400/220 kV GIS sub-station at Peenya
ii. 2x500 MVA, 400/220 kV sub-station at Devanahalli(Under 2000 MW Tumkur
ultra-mega solar park scheme)
iii. 2x500 MVA, 400/220 kV sub-station at Mylasandra.
iv. 2x500 MVA, 400/220 kV sub-station at Dommasandra
v. 2x150 MVA, 220/66kV GIS station at ITI
vi. 2x150MVA, 220/66/11kV GIS station at Koramangala
vii. 2x150MVA, 220/66/11kV substation at Kumbalgodu
viii. 2x150MVA, 220/66/11kV GIS substation at Brindavan Alloys
ix. 2x150MVA, 220/66/11kV substation at Exora
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 61
x. 2x150MVA, 220/66/11kV GIS substation at HBR Layout
xi. 2x150MVA, 220/66/11kV GIS substation at Sahakari Nagar
xii. 2x150MVA, 220/66/11kV substation at Manyata Tech Park
xiii. 2x150MVA, 220/66/11kV sub-station at Whitefield.
xiv. 220/66/11kV Sub-Station at Nagarbhavi, Bangalore North Taluk
xv. 2x150MVA, 220/66/11kV substation at Nelamangala.
xvi. 220 kV DC line from Peenya to NRS in the existing corridor of 66 kV line.
xvii. 220 kV DC line from Peenya to Somanahalli in the existing corridor of 220 kV
SC line.
xviii. 220 kV 1000 Sq.mm UG Cable from Bidadi to Vrushabavathi Valley via
proposed 220kV Kumbalgodu.
xix. Construction of 220 kV multi-circuit, multi-voltage line between 400/220 kV
Somanahalli and 220/66 kV Subramanyapura s/s in the existing 66 kV line
corridor.
Overloading of 230 kV Shoolagiri-Hosur (TN)-Yerrandahalli-Somanahalli S/C line
33rd
TCC: KPTCL informed that after commissioning of 400/220 kV Mylasandra, the
loads of 220 kV Yerandanahalli sub-station would be taken on Mylasandra.
Constraints in Nagjheri PH evacuation
Constraints in Chennai 230 kV System
Overloaded 230 kV Lines in Tamil Nadu
220 kV Hyderabad Metro Network
e) ICT Constraints
765/400kV 2x1500 MVA Vemagiri ICTs
400/220 kV 2 x 315 MVA ICTs at Gazuwaka
41st SCPSPSR: After deliberations, members had agreed for an additional
400/220kV, 1x500 MVA ICT at Gazuwaka substation as ISTS.
400/220 kV 3 x 315 MVA ICTs at Vemagiri
41st SCPSPSR: APTRANSCO had to look into the issue and may plan additional
ICTs/ replacement of ICT by higher capacity.
400/220 kV 3 x 500 MVA ICTs at Nelamangala
33rd
TCC: Devanahalli (under 2,000 MW Pavagada scheme) - Relieve loadings
of 400/220 kV ICTs at Nelamangala, Hoody and Hiriyur sub-stations.
Peenya & Huliyurdurga-- Relieve loadings of 400/220 kV ICTs at Nelamangala
sub-station.
400/220 kV 3 x 500 MVA ICTs at Somanahalli
33rd
TCC: Mylasandra - Relieve loadings of 400/220 kV ICTs at Hoody and
Somanahalli sub-stations.
T.K.Halli (Evacuation scheme of additional units of M/s UPCL. Approval yet to
be accorded by CEA) - Relieve loadings of 400/220 kV ICTs at Somanahalli,
Bastipura sub-stations.
400/220 kV 3 x 500 MVA ICTs at Hoody (In the special meeting held on 09.07.2018
to discuss pending issues in respect of Karnataka, KPTCL had informed that with the
commissioning of Yelahanka S/S, the loading was likely to come down)
33rd
TCC: Devanahalli (under 2000 MW Pavagada scheme) - Relieve loadings
of 400/220 kV ICTs at Nelamangala, Hoody and Hiriyur sub-stations.
Mylasandra - Relieve loadings of 400/220 kV ICTs at Hoody and Somanahalli
sub-stations.
400/220 kV 2 x 315 MVA ICTs at Guttur
33rd
TCC: Jagalur- Relieve loadings of 400/220 kV ICTs at Guttur and Hiriyur
sub-stations.
400/220 kV 2 x 315 MVA ICTs at Hiriyur
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 62
33rd
TCC: Devanahalli (under 2000 MW Pavagada scheme) - Relieve loadings
of 400/220 kV ICTs at Nelamangala, Hoody and Hiriyur sub-stations.
Jagalur- Relieve loadings of 400/220 kV ICTs at Guttur and Hiriyur sub-stations.
400/220 kV 1 x 500 MVA + 1x315 MVA ICTs at Narendra
400/220 kV 2 x 315 MVA ICTs at UPCL
400/220 kV 3 x 315MVA ICTs at Shankarapally
41st SCPSPSR: 1 x 500 MVA 400/220 kV transformer (4
th one) at Malkaram
S/S & Shankarpalli S/S approved
f) Other issues:
Vallur TPS (1500 MW) and NCTPS-II (1200 MW) generation is connected at 400 kV
Bus and no 230 kV path is available to give start up supply in case of Blackout. So
there is a need to provide 230 kV path.
National HVDC project of Lower Sileru-Barasoor line right of way has to be used for
New inter connection between SR & NEW Grids.
g) Overloading of 400 kV Nellore PS- Nellore D/C lines
In the 32nd
TCC the following had been noted:
TCC had recommended for SPS during tripping of one of the lines of NPS-Nellore.
TCC had recommended that provision of third ICT at NPS could be planned/studied
as a long-term measure. Other options could also be looked into by CTU as discussed
in earlier Meetings / suggested by POSOCO.
Subsequently, the SPS had been implemented by PGCIL.
In 42nd
SCPSPSR after deliberations, it had been agreed to bypass Nellore PS – Nellore 400
kV D/C (Quad) line and Nellore – Thiruvalam 400 kV D/c (Quad) line at Nellore (PG) for
making Nellore PS – Thiruvalam 400 kV D/c (Quad) line to control loading on Nellore –
Nellore PS 400kV lines and control of short circuit levels.
SRPC noted the above and requested the concerned entities to take short term and
long term measures to overcome identified operational constraints.
18.9 Timely completion of Transmission Assets
PGCIL vide letter dated 26.07.2018 ( refer Annexure XXIX) had updated on transmission
assets which were commissioned /anticipated to be commissioned as discussed in 32nd
meeting of SRPC held on 22.08.2017 as detailed below:
I. Project: Transmission System for Ultra Mega Solar Power Park at Tumkur
(Pavagada), Karnataka -Phase-I
Sl. No. Asset description
Asset-1 LILO of one Circuit of 400 kV Gooty-Tumkur (Vasantnarsapur) D/C
line at Tumkur (Pavagada) pooling station.
Asset-2 New 400/220 kV pooling station at Tumkur (Pavagada) with 1 X
500MVA 400/220 kV ICT along with associated bays & equipment's.
Asset-3 LILO of second Circuit of 400 kV Gooty-Tumkur (Vasantnarsapur) D/C
line at Tumkur (Pavagada) pooling station along with associated bays &
equipment's.
Asset-4 1 X 500 MVA 400/220 kV ICT at 400/220 kV pooling station at
Tumkur (Pavagada) along with associated bays &equipments
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 63
Asset-5 1X 125 MVAR 400 KV Bus Reactor along with its associated bays and
equipments at 400/220 kV Tumkur (Pavagada) pooling station
Asset-6 LILO of 400 kV D/C Bellary -Tumkur (Vasantnarsapur) D/C (Quad
Moose) TL at Tumkur (Pavagada)pooling station along with associated
bays & equipments
Asset-7
(Anticipated)
3rd
500 MVA, 400/220 kV ICT at 400/220 kV pooling station at Tumkur
(Pavagada) along with associated bays &equipments
Asset-8
(Anticipated)
Tumkur (Pavagada) pool - Hiryur 400 kV D/C line along with
associated bays & equipments at both ends
Following are the details of DOCO of above mentioned lines/elements
Sl.
No Particulars
Line
length
(in
Kms)
Investmen
t Approval
date
CERC
qualifying
time
schedules
(in months)
Qualifyi
ng time
for the
project
DOCO
Commission
ed in
months
1 Asset-1 0.45
08.04.16
34
38
06.12.2017 20
2 Asset-2 NA 30 06.12.2017 20
3 Asset-3 0.45 34 01.02.2018 21 months 25
days
4 Asset-4 NA 30 14.02.2018 22 months 8
days
5 Asset-5 NA 30 31.03.2018 23 months 24
days
6 Asset-6 55.76 38 31.03.2018 23 months 24
days
7 Asset-7 NA 30 12.07.2018 27 months 9
days
8 Asset-8 109 34
Anticipated
DOCO
31.07.2018
28 months 24
days
(Anticipated)
Reference had been invited to the 32nd
meeting of SRPC held on 22.08.2017 read with
report of Special Meeting held on 01.09.2017 in SRPC Bangalore with participation from
CTU, SRLDC, states & SRPC. Utilization of these assets had been deliberated in the said
meetings and recommended for commissioning. Since this project is linked with the Ultra
Mega Solar Power Park at Tumkur (Pavagada), Karnataka, timely completion of above
assets was essential for facilitating the generator to commission and evacuate the power.
II. Project: Connectivity for Kudankulam 3 & 4 (2 X 1000 MW) with interstate transmission
system
Particulars: Extension of Kudankulam APP- Tirunelveli 400kV (Quad) D/C line to
Tuticorin pooling station along with associated bays & equipments at Tuticorin pooling
station.
Line
length
(in Kms)
Investment
Approval date
CERC
qualifying
time
schedules
Qualifying
time for the
project
DOCO Commissioned
66.093 12.01.16 38 months 38 months 10.03.18 26 months
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 64
Utilization of the above asset was also deliberated in the said referred Meetings and had
been recommended for commissioning.
III. Project: Green Energy Corridors: Inter-State transmission scheme (ISTS) -Part- A
Particulars: 2 X 400KV D/C (Quad) Tirunelveli Pooling Station -Tuticorin Pooling
station lines along with new 400/230KV (GIS) Tirunelveli Pooling substation with 2X 125
MVAR 400 KV Bus reactors along with associated bays & equipments at 400/230 KV
(GIS) Tirunelveli Pooling Station & associated bays &equipments at 400/230 KV
Tuticorin Pooling station and 2 X 500 MVA, 400/230 KV transformers along with
associated bays &equipments at new 400/230 KV (GIS) Tirunelveli Pooling substation
Line
length
(in
Kms)
Investment
Approval date
CERC
qualifying
time
schedules
Qualifying
time for the
project
DOCO Commissioned
2 X 12.05 17.04.15 38
months
38
months 10.06.18
37 months, 25
days
Utilization of the above asset had also been deliberated in the said meetings and
recommended for commissioning. As regards the utilization of ICTs, they are made ready as
per the timelines committed by Wind generators. Had the generators commissioned as per
the commitment, the ICTs would have been utilized and hence the utilization of ICTs is
beyond the control of POWERGRID. Further, there are no elements under POWERGRID
scope which is pending on account of which utilization is hampered.
TCC deliberations
TANGEDCO had pointed out that few upstream elements are to be completed by
SPPD/SPD and some transmission charges may need to be borne by the respective
SPPD/SPD. CTU should come out with specifics in this regard.
CTU had informed that LTA / part LTA operationalization is as per commissioning of
assets. Tariff is determined by Hon‟ble CERC and the specific billing to generator/DIC is
being clearly mentioned in the Order.
It was noted that this issue would be discussed in the special meeting of CTU and
constituents.
After deliberations, TCC recommended for timely completion of the above mentioned
assets.
SRPC noted the above.
SRPC also approved TCC recommendation for timely completion of the above mentioned
assets.
18.10 Edamon Bays Decapitalization
PGCIL vide letter dated 26.07.2018 (refer Annexure-XXIX) had informed that with
upgradation of POWERGRID bays at 220 kV Edamon/KSEB station with hybrid
equipment, the removed equipment to be de-capitalized and the same to be taken over by
KSEB at depreciated cost. The matter needs deliberation.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 65
TCC deliberations
KSEBL had agreed to take up the asset on depreciated cost after approval of the Board
and SERC. One of the reasons for delay in completing the PSDF project was belated
confirmation by PGCIL in this regard.
SR-II had clarified that would not pay O&M charges to KSEBL neither claim O&M
for this asset.
SRPC noted the above.
18.11 Power transfer reduction in Talcher- Kolar HVDC link
PGCIL vide letter dated 26.07.2018 (refer Annexure-XXIX) had informed that Talcher-
Kolar HVDC link is being operated with extended power transfer capacity up to 2500 MW
for long time. Continuous operation at this rating may affect the performance of the
system. HVDC spares support from OEM M/s Siemens is becoming difficult since they
had declared end of life cycle for few components. Peak power transfer duration issue
needs deliberation for continuous life of link.
TCC deliberations
SRPC Secretariat had presented details of the flow on Talcher-Kolar HVDC link
(Annexure-XLIII). It was noted that the flow was above 2,400 MW for about 5% of
the time and above 2,000 MW for about 9% of time.
SR-II had informed that there was one incident where the pole was loaded beyond
2,400 MW for more than 10 hours. It was requested that the enhanced capacity may
be scheduled in two blocks of 5 hours each. Since there are a number of AC links,
enhanced capacity could be utilized during contingencies.
NLDC had agreed not to schedule at 2,500 MW beyond 10 hours a day. This aspect
was being monitored at NLDC. This capacity was being used during morning peak
hours when SR drawals are high and further when the angle between NR and SR is
exceeding 85 degrees. Generation balancing is also being resorted to.
SRPC noted the above.
18.12 Ratification of re-arrangement of Vemagiri constraint lines
PGCIL vide letter dated 26.07.2018 (refer Annexure-XXIX) had stated that ratification of
rearrangement of Vemagiri constraint lines as given below is required:
a) Vemagiri GIS - Simhadri I and II
b) Vemagiri GIS - Vijayawada II and III
c) Vemagiri – Vemagiri(AP) I and II
As per the request of APTRANSCO, lines at Sl No (c) above were terminated in existing
bays at Vemagiri APTRANSCO to facilitate 400 kV KV Kota lines termination in new bays
constructed by Powergrid. Vemagiri constraint lines were charged on 1st March, 2
nd March
and AP lines on 8th
March respectively and are in service. While issuing trial operation
certificate, SRLDC had advised to ratify the above changes. Concurrence and ratification of
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 66
the same may be requested from SRPC. Copy of trial operation certificate was enclosed.
TCC recommended for ratification.
SRPC ratified the rearrangement.
18.13 250 MVA ICT at Bhadravathi Substation shifted from Moga Substation
PGCIL vide letter dated 26.07.2018 (refer Annexure-XXIX) had informed that out of two
(2) nos. dismantled 250 MVA ICT at Moga S/S, one (1) no. ICT had been diverted to
Bhadravathi S/S. As agreed in 31st SRPC Meeting held on 25.02.2017, the said diverted
ICT was proposed to be provided at Bhadravathi at zero cost. However, in review petition
no. 182/MP/2017, Hon‟ble CERC has denied this ICT as regional spare. Therefore, instead
of zero cost, depreciated cost of diverted ICT and bay equipment cost needs to be shared
by Southern Region beneficiaries.
TCC recommended for approval.
SRPC approved TCC recommendation.
18.14 Utilization of 1 x 500 MVA, 400/220 kV ICT at Trichy S/S
PGCIL vide letter dated 26.07.2018 (refer Annexure-XXIX) had informed that 1 x 500
MVA, 400/220 kV ICT at Trichy S/S is commissioned on 10.06.2017. However,
Extension of 230 kV Main and Transfer Buses in TANTRANSCO Switchyard at Alunder
230 kV Station (Trichy SS) under SRSS-XX are yet to be taken up by TANTRANSCO.
TANTRANSCO informed that the ICT was in service since last year.
18.15 FSC at Cuddapah
In the OCC Meeting, it was noted that FSC at Cuddapah is out from February 2018
onwards. SR-I had informed that few cards were replaced for FSC at Cuddapah to make it
operational. Major rectification would cost a few crores, as per initial estimates.
In the 146th
OCC Meeting SRLDC had presented the study results of flows (Annexure-
XLIV) with FSC and without FSC of N‟Sagar-Cuddapah line. OCC forum had concluded
that major investment was not prudent, considering present flows. The same could be
recommended to TCC/SRPC to decide on future course of action. Further, if the FSC is not
rectified, it would be shown under Prolonged Outage.
TCC deliberations
TCC had recommended that additional major additional expenditure (in Crores) to
rectify the same was not desirable considering the present flows on the line. PGCIL
could take an appropriate call on decapitalization.
SR-I had stated that they would revert back on this matter.
SRPC deliberations
Director (O), PGCIL stated that the issue is being followed up with M/s Siemens to get
it rectified and it can be brought back in service. Other issue was to handle the
commercial implications if the asset is decapitalized. Since this was under 25 years
tariff structure there was some cost which was yet to be recovered. They were planning
a meeting with M/s Siemens and they would revert back.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 67
SRPC observed that additional major expenditure was not recommended and PGCIL
could take same into account while finalizing future course of action.
19 SCHEDULING OF MACHKUND AND TB DAM
19.1 The issue of non-scheduling of Machkund and TB Dam power by APSLDC to Telangana
from 11.06.2017 had been taken up with APTRANSCO vide letter dated 04.07.2018
(Annexure-XLV) by SRPC. In this regard, the letter dated 02.07.2018 received from
TSTRANSCO on the subject was also enclosed.
19.2 The following had been noted in the TCC Meeting:
TSTRANSCO had taken up the issue with Machkund vide letter dated 18.07.2018
(Annexure-XLVI) requesting to suitably advice APSLDC to schedule the 53.89 %
share of power from Machkund to TS Discoms.
APTRANSCO had stated that APGENCO had observed that scheduling from these
stations would be commenced after TSDISCOMs clear the pending dues. They pointed
out that SCCL is not supplying coal if APGENCO stations dues are there.
APGENCO had stated that after bifurcation of AP & TS, Machkund share should be
with AP. Issue of pending dues had been taken up with TSDISCOMs vide letter dated
12.06.2017 and APGENCO had also approached National Company Law Tribunal.
TSTRANSCO had stated that these two projects could be viewed separately being
Inter-state projects and located in states other than AP and Telangana. As per IEGC,
SRLDC can take lead role in scheduling such Inter-state projects.
SRLDC had stated they would schedule the power to comply with IEGC provisions, if
required, but any intermediate solution between AP & TS was also welcome in this
case.
It was agreed that the issue would be discussed further in SRPC Meeting.
SRPC deliberations
CMD, APTRANSCO & MD, APGENCO informed that they are willing to schedule
these inter-state projects. However, TS Discoms should give categorical assurance and
some comfort that payments due for these two stations would be made without linking
with any other payment. For these two projects, there could be some sort of mechanism
to ensure that payment comes on regular basis.
Director (P & GO), TSTRANSCO stated that the CMD, TSTRANSCO would be
appraised in this matter and they would revert back.
20 NEW PROJECTS OF NTPC, NLC, NPCIL, JOINT VENTURE & UMPP
20.1 Schedule of synchronizing/commissioning of the new projects of NTPC, NLC,
NPCIL, and BHAVINI & UMPP is furnished below:
Station Unit
Installed
Capacity
MW
Scheduled date of
synchronizing /
commissioning Remarks
NTPC
Kudgi TPS III 800 August 2018 Unit-III: Trial operation
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 68
Stage-I successfully completed
between 30.04.2018 to
02.05.2018. Hon‟ble CERC
in Petition No.146/MP/2018
had extended the COD upto
31.08.2018.
Telangana STPP
Phase I
2 x 800 33rd
TCC:
U-I CoD August
2020
(Synchronization by
Mar 2020)
U-2 CoD Nov 2020
(Synchronization by
May 2020)
33rd
TCC:
MoP has allocated 85 % to
Telangana and 15%
retained as unallocated
subjected to approval of
competent Authority.
Pudimadaka AP 4 x 1000 52 Months from Zero
Date
85% share to AP.
Zero date yet to be finalized.
AP had requested NTPC to
firm up the zero date at the
earliest.
31st TCC:
NTPC had informed that the domestic coal was yet to be tied up. Within
two months, the status would be communicated.
CTU informed that there was no connectivity / LTA application pending
with them.
33rd
TCC: GoK vide letter dated 19.07.2018 (Annexure-XLVII) had
sought status on share of allocation of power from Pudimadaka and
Ramagundam Stage IV ( rechristened as Telangana STPP Phase-I)
NTPC informed that MoP has allocated 50% to home state (AP) and
balance allocation has to be made.
NLC
New Thermal
Power Project
I 500 33rd
TCC :
Synchronization by
October 2018
II 500 33rd
TCC :
Synchronization by
December 2018
CEA (May 2018): LILO of Neyveli – Puducherry by July 2018, New
Neyveli TPP - Ariyalur (Villupuram) by July 2019.
SRTS-II vide letter dated 26.06.2018 (Annexure-XLVIII) had stated
that the LILO of could not be terminated at NNTPS Switchyard due to
non-readiness of associated bays at NNTPS switchyard which are under
the scope of M/s NLC. The said LILO line has been charged by cross
jumpering at dead end tower in NNTPS switchyard.
PGCIL vide letter dated 26.07.2018 (refer Annexure-XXIX) had
informed that “Zero date” as per the Implementation agreement signed
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 69
between NLC India Ltd & POWERGRID for the subject asset was
01.05.2018. In accordance with the said agreement, POWERGRID has
completed the subject asset in all respects during April 18 and CEA
clearance for Energization of the subject asset was obtained on
27.04.2018, but could not be commissioned due to non-readiness of bays
at NNTPS generation switchyard. Their position and also the concerns
of non- charging of the line was communicated to M/s NLC vide their
letters dated 26.04.2018, 24.05.2018 & 20.06.2018. M/s NLC vide letter
dated 30.04.2018 informed that the bays would be made ready by
23.05.2018, however the bays were not made ready by M/s.NLC as
committed. Hence, as informed vide letter dated 20.06.2018, the subject
LILO line has been charged on 26.06.2018 by cross jumpering at dead
end tower in NNTPS switchyard and notified vide our notification dated
26.06.2018. Further, vide our letter dated.27.06.2018, NLC was again
requested to expedite the work and complete the bays immediately so
that the LILO line can be terminated at the NLC switchyard at the
earliest.
Further, the Status of commissioning of NNTPS Generation was
requested to be confirmed by M/s.NLC.
In view of the above, PGCIL had requested SRPC to recommend for
deemed DOCO of the above asset, please.
33rd
TCC: NLC informed that LILO would be completed by middle
of September 2018. Further these lines were for connectivity and not
for evacuation.
TCC endorsed cross jumpering at dead end tower at NNTPS switch
yard as it was critical line for Puducherry and tripping of lines
would lead to load shedding in Puducherry and TN.
Further it was noted that SRLDC had given for clearance of
charging for antitheft.
CTU stated that the sharing of the transmission charges would be as
per CERC order- most likely it would be borne by NNTPS.
TPS –II 2nd
Expn 1&
2
2 x 660 42nd
SCPSPSR:
Seeking connectivity for
1320 MW w.e.f. 01.04.2021
NPCIL
KKNPP 3 &
4
2 x 1000 32nd
TCC
U3: 2023
U4: 2024
41st SCPSPSR:
CTU had informed that they
had not received any LTA
application from NPCIL for
Kudankulam - 3 & 4 units.
Any system strengthening
would be planned on receipt
of the LTA application based
on proper studies.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 70
BHAVINI
Kalpakkam
(PFBR)
I 500 33rd
TCC: March
2019
PGCIL vide letter dated 26.07.2018 (refer Annexure-XXIX) had
informed that Kalpakkam PFBR - Kanchipuram 230 kV D/C Line of
POWERGRID was commissioned on 01.09.2012 under Transmission
System associated with Kalpakkam PFBR (500 MW) in Southern Region
as per the implementation agreement signed by BHAVINI and as agreed
in SRPC meetings and Standing committee meetings. CERC vide its
Order dated 24.09.2015, declined DOCO of the 230 kV BHAVINI–
Kanchipuram line due to non-readiness of Kanchipuram SS by
TANGEDCO. Kanchipuram SS is yet to be commissioned. During 32nd
TCC, TANTRANSCO informed that the S/S would come up by March
2018.
33rd
TCC : TANTRANSCO informed that the S/S would come up by
September 2018
UMPP
Krishnapatnam 3960
(6 x 660)
32nd
SRPC: CMD, APTRANSCO had informed that
several Meetings had been held with beneficiaries
and coastal UMPP. In the present scenario, the
usefulness of this project for beneficiaries was
limited. In the meeting it had been decided that since
the matter was pending before Delhi High Court, it
was appropriate to file a Petition for Expeditious
Hearing. However after seeking legal opinion, a
SLP before Hon‟ble Supreme Court was
contemplated seeking directions to Delhi High Court
to kindly expedite and pass Orders at the earliest.
32nd
TCC: AP informed that after discussing with the beneficiaries, an
Expeditious Petition was contemplated before Hon‟ble Delhi High Court
(before approaching Hon‟ble Supreme Court). The petition was likely to
be heard in the month of March 2018.
Cheyyur 4000 New bids would be called
33rd
TCC: As per the latest policy of GOI the issues regarding
conversion of the originally envisaged Cheyyur UMPP utilizing
imported coal to domestic coal UMPP is under discussion by MOP/ GOI.
The CEA has indicated a requirement of additional land of 767 acres if
domestic coal is to be utilized. The District / collector Kanchipuram has
been addressed by the Secretary/Energy Department in this regard.
In line with GOI policy for using domestic coal in place of imported
coal, the bidding documents are being revised and the bidding
process will be commenced by Ministry of Power.
SRPC noted the above.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 71
21 NEW PROJECTS OF STATE SECTOR & IPP
21.1 Updated status of new projects of State sector is furnished below:
Sl
No
Name of project Located
in
Capacity
in MW
Commissioning Schedule
/Remarks
1 Rayalaseema TPS ST-IV AP 1 x 600 2018-19
2 Dr. NTTPS, Vijayawada AP 1 x 800 June 2019
3 Krishnapatnam Stage II
(U3)
AP 1 x 800
4 Polaki AP 4000 (5 x
800 MW)
5 Edlapur KAR 1 x 800
6 North Chennai Stage III TN 1 x 800 33rd
TCC: 2019-20
41st SCPSPSR: 2019
7 North Chennai Stage IV TN 2 x 800 33rd
TCC: 2019-20
8 Ennore TPS Exp TN 1 x 660 33rd
TCC: 2021
9 Ennore replacement TN 1 x 660 41st SCPSPSR: 2020
33rd
TCC: 2022-23
10 Udangudi Stage I TN 2 x 660 33rd
TCC: 2021-22
11 Udangudi Stage II TN 2 x 660 33rd
TCC: 2023-24
12 Udangudi Stage III TN 2 x 660 33rd
TCC: 2024-25
11 Uppur TPP (TBCB) TN 2 x 800 33rd
TCC: 2021-22
12 Manuguru PPP Telangana 4 x 270 33rd
TCC :
U1: April 19
U2: June 19
U3: Aug 19
U4: Oct 19
13 Kakatiya TPP Stage III Telangana 1 x 800 Not decided
14 Kothagudem TPS Phase
VII
Telangana 1 x 800 33rd
TCC : Aug 18
15 Damaracherla (Yadadri) Telangana 5x800 U 1 & 2: 33rd
TCC :
Commissioning Oct 2020 U 3 – 5 33
rd TCC :
Commissioning Oct 2021
SRPC noted the above.
21.2 Updated status of new projects of IPPs is furnished below:
Sl
No.
Name of project Located
in
Capacity
in MW
Commissioning Schedule
/Remarks
1 Meenakshi PH-II AP 2 x 350 2018-19
Untied: 640 MW
2 East Coast Energy
Thermal
AP 2 x 660
2018-19
AP : 300 MW
3 Thermal Powertech
(TPCIL) Unit-III
AP 1 x 660
2018-19
5 Godhna TPP, Janjir –
Champa Dist,
Chhattisgarh
For
KAR
2 x 800 2018-19
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 72
22 REVIEW OF ULDC / SCADA/COMMUNICATION
22.1 Status of pending items is as follows:
Update as per Meeting on 13.03.2018 Status update
ICCP link failure/not stable
It was noted that respective Control Center would ensure that M/s GE take pro-active action to renew the licenses before the expiry
Updated communication network diagram to be submitted
by SR-I and SR-II to all SLDCs & SRLDC. Further any
changes done in the communication network needed to be
informed to all.
SR II had informed that
Necessary standby channels
are made available and
updated communication
network is ready.
Data outage after commissioning
Cross checking to be done with site daily values for newly
commissioned elements for a period of two week duration
from commissioning.
SR II : Complied and
SRLDC may check and
intimate any failures
RTU/SAS Maintenance/Upgradation
AMC need to be provided for all RTU/SAS gateways by
CTU/STU.
A life/functional assessment report and action plan by
PGCIL/ISGS on old RTUs would be prepared and
submitted to SRLDC/SRPC.
SR-II does not feel to have
AMC for SAS stations.
However, the conventional
RTUs, commissioned during
2001-02 are proposed to be
upgraded / replaced. The
offer obtained from GE for
upgradation and process to
be initiated
Backup Control Centre
Backup SCADA functionality testing frequency needs to
be done once in 6 months to ensure high availability of
data/preparedness to operate from Back up CC in event of
any contingency. Compliance report may be furnished to
SRLDC.
TN stated that communication network is being
strengthened to Backup CC. Once same is completed, TN
will do the testing.
Periodical testing was being
carried out by SRLDC and
KSEBL.
33rd
TCC: PGCIL would
be floating new combined
Open Tender for Backup
SLDCs for AP (Tirupati),
TS (Warangal) along-with
few other states.
ICCP with NTAMC
PGCIL had confirmed that due to cyber security concerns
data would not be extended to SRLDC from NTAMC
ICCP.
Functional requirement of the requisite data by SRLDC
would remain, which needed to be ensured by PGCIL.
SRLDC would furnish the list of telemetry points that have
to be extended to PGCIL within 10 days, and within 1
month PGCIL would come out with a detailed plan to be
completed within 6 months (October 2018)
SR II : Additional data
points have been received
from SRLDC and action is
being taken to extend the
inputs by Oct 2018
Modification of EMS package
TSTRANSCO had received estimate of Rs 47 lakhs and
the contract was being firmed up.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 73
Sparing of Fibre in Central Sector Project
TANTRANSCO had again requested for sparing of fibre
in Central Sector Project.
SR-II stated that request for
sparing of fibre in new FO
links could be communicated
for consideration.
33rd
TCC: TANTRANSCO
and PGCIL agreed to
deliberate bilaterally.
VC issues
TSTRANSCO Video Conference issue at TSSLDC. There
was disturbance in Video Conference at TS end when
connected to SRLDC.
33rd
TCC: Issue had been
resolved.
Puducherry would take up VC requirement in the financial
year 2017-18.
TCC deliberations
SRLDC had stated that DCPC maintenance was to be carried out diligently.
Tamil Nadu had agreed to compute independent ISTS drawl which could be regularly
verified with SRLDC drawl figures.
SRPC noted the above.
22.2 ICCP links had failed on 07.02.2018, 08.02.2018 and 23.02.2018. To address the issues, an
urgent meeting was called on 13.03.2018 (MOM available at SRPC website). The
actionable points needed to be complied by all the concerned entities. Further, a special
meeting with participation from M/s GE was held on 23.05.2018 (MOM available at SRPC
website). The following had been agreed in the Meeting:
A formal procedure to be followed during ICCP failure would be developed. Timely
renewal of the certificates would also be included in the procedure.
Procedure for database mismatch correction, duration of making changes and
validation of the same to be formulated and made part of procedure such that the
database between control centers are in sync and error logs are cleared in timely
manner.
SR-I & SR-II were requested to check all ICCP links for healthiness through ping
check and testers in consultation with SRLDC and constituents on periodic basis.
It was pointed out that all states need to compute a parallel ISTS drawal on different
philosophy independent of points being used by SRLDC. This will ensure consistent
verification of the ISTS drawal and will be helpful in contingencies. AP & TS
informed that they were following such procedure and independent ISTS drawal was
being computed. Discrepancy needed to be informed to SRLDC for early
rectification.
GE offered to conduct quarterly meetings on AMC and other SCADA related issues
which could be conducted through VC or at a common site.
TCC deliberations
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 74
AP & TS had expressed concern on frequent failure of ICCP links and even the
duration of outages was longer. They stated that they would consider dedicated
leased line from SLDC to SRLDC.
SR-II, PGCIL had informed that besides two OFC connectivity (Somanhalli -
SRLDC, 2nd
connectivity was established 3 months back through HAL) they were
utilizing bandwidth from Powertel (Somanhalli-SRLDC) in which major data was
protected. In addition, fourth connectivity from Hebbal to SRLDC would also come
up within a month. Few issues like license, configuration, architecture, power supply
etc (addressed after the meetings) had also contributed towards ICCP link failures.
Recently the redundancy had been affected due to OFC failure on account of BBMP
works.
SRLDC had stated that they would also examine the connectivity & take appropriate
action.
It was noted that OFC link failures at two locations in KPTCL portion were attended
but the link was yet to come up.
SRPC noted the above.
22.3 Commissioning of alternate communication link to SRLDC through KPTCL
underground fibre link
PGCIL vide letter dated 26.07.2018 (refer Annexure-XXIX) had informed that and placed
on record appreciation of KPTCL that the alternate communication link to SRLDC has
been established and commissioned through KPTCL underground fibre link; HAL – A
Station during April 2018. POWERGRID had extended sincere thanks to KPTCL for
sparing fibres in Bengaluru intra-city underground fibre links for establishing reliable
communication network for effective grid operation of Southern Region.
22.4 Signing of Agreement / MOU between Powergrid and Constituents for
replacement/upgradation of RTUs
With regard to replacement of S-900 RTUs in Northern Region, SRPC vide letter dated
24.05.2018 (Annexure-XLIX) had communicated the concerns to ED (LD & C),
PGCIL and requested that a review exercise on the matter may kindly be taken up for
SR also.
SR-I & SR-II had clarified that the CPU card was to be replaced to handle the present
communication requirements for various applications. The ISG stations requirement of
replacing the CPU card could be covered in the scope of PGCIL works on payment
basis. ISG stations were requested to revert back.
Letter dated 15.06.2018 from PGCIL (LD&C) in this regard is given at Annexure-L,
SR-II vide letter dated 27.06.2018 (Annexure-LI) had informed that it is proposed to
replace the CPU card in all the RTUs of POWERGRID stations (SR-II-13 no, SR-I-09
no) and the estimated cost per station is approximately Rs.6,51,000/- (Supply:
Rs.4,66,000/- & Services: Rs.1,85,000/-) excluding GST @18 %. However, final price
shall be arrived after due negotiations with GE as per POWERGRID standard
procurement policy.
Further, the issue had been taken up by PGCIL vide letter dated 26.07.2018 (refer
Annexure-XXIX)
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 75
TCC deliberations
NLCIL had requested that their requirement may be covered along with SRII, PGCIL
proposal and they would reimburse the amount.
Other ISGS were also requested to kindly furnish their concurrence/ requirement.
SR-II had informed that they were in process of procuring and the requirement to be
communicated at the earliest.
AP & TS had stated that the rates seemed to be on the higher side and subsequently, this
may impact their RTU card procurement.
SRPC deliberations
Director (O), PGCIL informed that the replacement may not serve for long. Since the
replacement of the cards and the new RTU were nearly costing the same, PGCIL would
reconsider replacing the RTU rather than replacing the cards. They would come out
with a proposal shortly.
SRLDC informed that the replacement of RTU has been agreed in WR also. The
transducers would not be replaced.
It was agreed that POWERGRID would take a call on the matter.
23 URTDSM (PMU) PROJECT IN SOUTHERN REGION
23.1 URTDSM Phase-I project is nearing completion. The progress is being reviewed in the
Special Meeting/OCCM. A Special Meeting was conducted on 13.03.2018 to review the
progress. The updated status in this regard is given at Annexure-LII.
23.2 Feedback on currently installed analytical applications (LSE, VADR, Supervised Zone-3
Distance protection) and installation of pending Powergrid analytical application.
23.3 PGCIL had requested all constituents to submit revised PMU requirement, if any, for
Phase-II considering availability of Wide Band nodes. APTRANSCO, TSTRANSCO &
KSEBL vide had submitted PMU requirement for Phase-II.
23.4 SRPC noted the above.
24 EMERGENCY RESTORATION SYSTEM (ERS)
24.1 Requirement of ERS had been outlined in MoP letter dated 05.12.2014. The status was
being monitored by Secretary (Security). Status update is given below please:
Transmission
Utility
Requirement as
per MoP
Existing Status/Remarks
APTRANSCO 3 2 ERS III would be taken up
through own funding.
33rd
TCC: Under process
TSTRANSCO 1 Tender floated; would be taken
up for PSDF funding.
33rd
TCC: Tendering under
progress.
KPTCL 2 2
KSEBL 1 Tenders to be floated. Would be
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 76
taken up for PSDF funding.
33rd
TCC: Agreed to take up
through own funds
TANTRANSCO 2 As per Minutes of BLTC held on
03.01.2017, procurement is put
on hold. Would require PSDF
funding.
33rd
TCC: On clarification from
NPC that PSDF funding would
not be possible and as it was
mandatory as per CEA
regulation, TANTRANSCO
stated that they would also take
up providing ERS through own
funding
PED Nil Nil
PGCIL 4 (2 Nos.
Additional)
4 (SR I
& SR II
is having
2 no.
Each)
765 kV ERS (one each for SR-I
and SR-II)
33rd
TCC: Under inspection.
Expected by January, 2019.
25 ADOPTION OF UNIFORM PROCEDURE TO PREPARE MERIT ORDER
DESPATCH LIST
In the Sub-committee Meetings it was noted that different methods are being followed by
states to prepare Merit Order Despatch List. It was therefore suggested that common
guidelines for preparation of Merit Order Dispatch List may be formulated for the benefit of
all.
This issue had been discussed in 38th
Meeting of Commercial Sub Committee, wherein
some issues like, ISTS loss, incentive, compensation, URS, billed MOD, ERC approved
MOD, EC computation for state vs central generators, flexibility in LTA/MTOA, MOD on
D-3 (non-availing of STOA) etc. It was agreed to discuss the nitty gritty of the issue by a
Sub Group, and then it could be taken up with CEA/NLDC.
SRPC noted that this issue would be discussed further in sub Committee Meeting.
26 PROGRESS OF BUS/LINE REACTORS TO BE COMMISSIONED IN SR
26.1 Status of implementation of Bus / Line Reactors / Dynamic Compensation approved in the
Standing Committee / SRPC pending for commissioning by the SR constituents is furnished
below please:
Entity Bus Name Status REMARKS
KPTCL
Hoody Reactor erected on
platform.
2018-19
Nelamangala Reactor erected on
platform
2018-19
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 77
Entity Bus Name
Capacit
y in
MVAR
Approved
in Type Remarks
PGCIL
Yelahanka 2x63 40th
SC Bus
Deferred as per 40th
SCPSPSR. When
Madhugiri line will come
it will be expedited.
Cuddapah 50 to 125 39th
SC Yet to be awarded
Kurnool 765 kV 2 x 240 42nd
SCPSPSR
Raichur 765 kV 2 x 240 42nd
SCPSPSR
Thiruvalam 765
kV 2 x 240 42
nd SCPSPSR
Pavagada 2 x 125 42nd
SCPSPSR
Nellore (PG) 2 x 50
42
nd SC
Line
to
Bus
Hosur 63 to 125 42nd
SC Bus
Madhugiri 63 to 125 42nd
SC Bus
Dharmapuri 125 42nd
SC Bus
Hiriyur 125 42nd
SC Bus
Pugalur 125 42nd
SC Bus
Pugalur HVDC 2 x 125 42nd
SC Bus
APTRANSC
O
Vemagiri 125
36th
SC
Bus December 2017 – LOA
issued on 18.06.2017
Kurnool 125 Bus December 2017 – LOA
issued on 18.06.2017
Kalpaka 125 Bus March 2018
Chittoor 125 39th
SC APERC approval awaited
Vijayawada 125 39th
SC
It was noted that a
separate reactor at
Vijayawada in scope of
AP had been identified.
The exact location could
be firmed up by
APTRANSCO.
Uravakonda 125 42nd
SC Bus
Uravakonda 80 42nd
SCPSPSR
Jammalmadugu 80 42nd
SCPSPSR
Sattenapalli 125 42nd
SCPSPSR
Rachagunneri 125 42nd
SC Bus
Hindupur 80 to 125 42nd
SC Bus
APGENCO
VTPS Stage IV 125 39th
SC
APGENCO informed that
reactor enquiry was being
taken up.
It was noted that this
reactor was different from
the APTRANSCO reactor.
Polavram HEP 2 x 125 42nd
SC Bus
KPTCL Davanagere 125 39th
SC 41st SCPSPSR:
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 78
Talaguppa 125 39th
SC
Requirement reaffirmed.
Special meeting
09.07.2018 & 33rd
TCC:
Approved in TCCM,
estimate under
preparation.
C N Halli 2 x 125 42nd
SC Bus 42nd
SCPSPSR: KPTCL
stated that they will send
their consent within 15
days of the meeting.
33rd
TCC: C N Halli –
Land identified.
Jagalur – Work under
progress.
Jagalur 2 x 125 42nd
SC Bus
KPCL
Yeramarus 125 42nd
SC Bus
Bellary 2 x 125 42nd
SC Bus
KSEBL Wayanad 125 42nd
SC Bus
TANTRANS
CO
Almathy 125 39th
SC Specification under
process Manali 125 39
th SC
Kayathar 125 39th
SC
Kamuthi 2 x 80 42nd
SCPSPSR
Virudhnagar
(765 kV)
2 x 330 42nd
SC Bus
2 x 330 42nd
SC Line
Coimbatore (765
kV) 2 x 240 42
nd SC Line
Kayathar 125 42nd
SC Bus
Kamuthi 125 42nd
SC Bus
Thappagundu 125 42nd
SC Bus
Kadaladi 125 42nd
SC Bus
Parali 125 42nd
SC Bus
Arni 2 x 125 42nd
SC Bus
Velalividu 125 42nd
SC Bus
TANTRANS
CO/
TANGEDCO
Mettur 125 39th
SC
To be diverted from
Palavadi and works to be
taken up.
TSTRANSC
O
Mamidipally 125 36
th SC
Bus
Commissioned on
23.02.2018
Asupaka 80 42nd
SCPSPSR
Suryapet 125 42nd
SC Bus
42nd
SCPSPSR:
TSTRANSCO stated that
they will send their
consent within 15 days of
the meeting.
Raidurg 2 x 125 42nd
SC Bus
Kamalapuram 125 42nd
SC Bus
Narsapur 125 42nd
SC Bus
Maheshwaram 125 42nd
SC Bus
Tippapur 125 42nd
SC Bus
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 79
Manikonda 125 42nd
SC Bus
Jangaon 125 42nd
SC Bus
Choutuppal 125 42nd
SC Bus
Yellampalli 125 42nd
SC Bus
TSTRANSC
O/
TSGENCO
Srisailam LB 125
39th
SC
42nd
SCPSPSR: CEA
Meeting (06.02.2018)- It
was decided that a team
comprising officers from
CEA, CTU and
TSTRANSCO would visit
SLBHES switchyard to
explore the feasibility to
accommodate the reactor
(125 MVAR).
NPCIL Kaiga 2 x 125
Bus
One reactor by December
2019.
2nd
reactor soon after 1st
reactor.
UPCL
Udupi 2 x 125
39th
SC
41st SCPSPSR: It was
informed that the
requirement was assessed
based on system studies,
therefore, it was decided
that the decision taken in
39th
SC Meeting may be
implemented.
SRPC vide letter dated 09.07.2018 (Annexure-LIII) had taken up with PCKL
the issue of according approval since these reactors had been approved by the
Standing Committee and Karnataka SLDC had also endorsed the urgent
requirement.
KAR SLDC vide letter dated 01.08.2018 (Annexure-LIV) addressed to the
Chief Engineer (E) Planning and Coordination, KPTCL had reaffirmed the need
for 2 x 125 reactors at UPCL for operational requirements.
33rd
TCC:
PCKL had informed that approval may not be essential as UPCL had
already included this asset in their tariff petition filed before CERC. The
requirement would be put upto PCKL Board.
KPTCL has stated that technically the requirement of Reactor was
justified, and they would take pro-active steps in this regard.
UPCL had stated that since 29.09.2017 to 11.07.2018 Unit 1 & 2 had
absorbed in 1,500 blocks and 1,251 blocks respectively and units were
absorbing reactive power up to 80 MVAR and it had gone up to 138
MVAR. As per PPA, there was no obligation on behalf of UPCL to absorb
MVAR beyond 420 kV. In more than 300 cases, voltages were beyond 420
kV at UPCL bus. Approval from PCKL would facilitate early
commissioning.
NLC NLC TPS-II 2
nd
Expansion 125
42nd
SC Bus
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 80
SRPC requested the entities to kindly expedite commissioning of reactor, since high voltage
was being observed on sustained basis.
26.2 Dynamic Compensation (Approved in 36th
SC)
Entity Bus Name
SC
MVA
GVA
/ KA
Dynamic
Compensation
(STATCOM)
Mechanically
Switched
Compensation
(MVAR) Remarks
Reactor Capacitor
PGCIL
Hyderabad 18.4/
26.5
+ 200 MVAR 2x125 1x125 June 2019
Udumalpet 19.4/
28.0
+ 200 MVAR 2x125 1x125 33rd
TCC: 1st
STATCOM
expected at site
by Oct’18 &
2nd
expected by
Nov’18.
Civil works
are in
progress;
commissioning
by Mar’19.
Trichy 12.5/
18.0
+ 200 MVAR 2x125 1x125
26.3 Reactive Power Planning
26.3.1 Status of Capacitor installation in Transco/Discoms is given below:
Utility Reactive Power Planning Voltage
level
Remarks
APTRANS
CO
Kadapa: 244.8 MVAR
Vijayawada: 122.4 MVAR
Visakhapatanam:158 MVAR
On 33
kV side
0 MVAR commissioned
0 MVAR commissioned
0 MVAR commissioned
APSPDCL 640 MVAR 2 MVAR commissioned
APEPDCL 276 MVAR 54 MVAR commissioned.
KPTCL Bengaluru Tr. Zone:784
MVAR
12.1 kV 30 MVAR commissioned
Bagalkot Tr. Zone: 258.1
MVAR
12.1 kV 78.3 MVAR commissioned
Hassan Tr. Zone: 150.8
MVAR
43.5 MVAR commissioned
Mysore Tr. Zone: 60.9
MVAR
60.9 MVAR commissioned
Gulbarga Tr. Zone: 98.60
MVAR
Nil
Tumkur Tr. Zone: 281.3
MVAR
12.1 kV 46.4 MVAR commissioned.
34.8 MVAR EI approval
awaited.
TSNPDCL 288 x 2 MVAR
110 x 1 MVAR
259 x 2 MVAR
105 x 1 MVAR commissioned
TSSPDCL 204 x 2 MVAR
58 x 1 MVAR
Nil
KSEBL 360 MVAR 66 kV Works will be taken up after
approval. 11kV
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 81
TANGEDC
O
34 x 2.4 MVAR 11 kV
16 x 2.4 MVAR 22 kV 16 x 2.4 commissioned
59 x 2.4 MVAR 11 kV IPDS tender to be opened on
30.11.2017
19 x 2.4 MVAR 22 kV IPDS tender to be opened on
30.11.2017
13 x 2.4 MAVR 110 kV PO placed on M/s Shreem
Electric Limited.
53 x 2.4 MAVR 11/22
kV
RAPDRP tender to be floated
101 x 2.4 MAVR – Erode
Region
11/22
kV
Tender to be floated.
32 x 2.4 MAVR – Vellore
Region
11/22
kV
Tender to be floated.
82 x 2.4 MVAR -
Coimbatore Region
11 kV BLTC note for price bid opening
to be submitted
822 MVAR capacitors at
Distribution level had been
commissioned out of 931
MVAR capacitors planned.
Balance 109 MVAR to be
commissioned. However, for
further enhancement of Reactive
Power, Capacitor bank
provisions have to be arranged
by Planning / Transmission
wings.
SRPC requested the entities to kindly expedite the commissioning.
26.4 PSDF – Funding of the schemes of the state utilities for installation of capacitors in
the state network at transmission / distribution network
26.4.1 MS, Appraisal Committee & ED, NLDC vide letter dated 22.06.2016 had earlier stated
that the matter had been deliberated by the Appraisal Committee during the Meeting
held on 31.05.2016 wherein, it was decided that assessment of capacitor requirement be
carried out at regional level by engaging expert agency like CPRI. After due approval,
SRPC vide letter dated 03.05.2017 had placed work order on CPRI for carrying out the
assessment studies for Southern region (except Karnataka).
26.4.2 Base case was modeled by SRLDC & SRPC and submitted to CPRI on 23rd
March
2017. CPRI study report was received on 20.12.2017. SRPC vide letter dated
28.12.2017 had submitted the same to NLDC for further needful action. SRPC vide
letter dated 16.01.2018 had also informed the states that the CPRI Report has been
submitted to NLDC and requested the states for further necessary action at their end.
26.4.3 Convener, TESG & Consultant, NLDC vide letter dated 21.05.2018 (Annexure-LV)
had furnished the extracts of the 38th
Meeting of TESG held on 26.02.2018 and
requested for needful with regard to the observations. With respect to SR it had been
mentioned that the Capacitor Study Report submitted by SRPC prepared by CPRI dealt
only with transmission level (132 kV and 220 kV voltage level) whereas requirement
was also for distribution level (33 kV and 11 kV).
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 82
SRPC vide letter dated 29.05.2018 (Annexure-LVI) had submitted the reply in this
regard to Member Secretary, Appraisal Committee.
SRPC noted the above.
26.5 Low voltages were observed in Bengaluru Area and Central/ North Kerala with
Udumalpet and Arasur areas
A study was undertaken and the following are the recommendations:
Low Voltage in Bangalore Area was likely due to heavy drawl of MVAR to the order
of about 1,000 MVAR. In the Special Meeting held on 09.07.2018, KPTCL had
informed that 784 MVAR capacitors were expected to be commissioned by
December 2018 (153 breakers were expected by Aug 2018). Further KPTCL
confirmed that they would discuss the issue with BESCOM and identify measures to
minimize the impact of MVAR drawal from ISTS grid.
Low Voltage in Kozhikode was due to operational error in switching Capacitor.
KSEBL had assured that in future, while drawing through Kozhikode ICTs, they
would also factor the current voltage situation at Kozhikode Bus.
Low Voltage in other parts of Kerala was due to low short circuit levels. Improvement
in voltage would be possible with commissioning of 400 kV D/C from Tirunelveli to
Cochin. This issue was under deliberation with KSEBL.
Low voltage in Udumalpet and Arasur areas.
TCC deliberations
KPTCL had assured that identified capacitors in Bengaluru area (784 MVAR) would
be commissioned by Dec, 2018.
TCC had suggested KPTCL, KSEBL & TANTRANSCO to take appropriate steps to
address the issue.
SRPC noted the above.
27 NON-AVAILING OF OCC APPROVED SHUTDOWN
27.1 In OCC Meetings, it had been noted with concern that at times, entities were not availing
OCC approved shut downs as per schedule. Details of availed outages against OCC
approved shut downs (furnished by SRLDC) are given below please:
Entity Feb-18 Mar-18 Apr-18 May-18 June-18 July-18
Availed % with respect to the OCC approved outages
AP TRANSCO 35 40 72 75 77 65
KPTCL 83 75 57 60 100 75
KPCL 100 - - - - -
KSEBL 100 100 100 100 100 -
TANTRANSCO 49 - 35 40 70 64
TSTRANSCO 56 100 64 70 70 70
PGCIL, SR1 96 100 64 68 43 92
PGCIL, SR2 45 75 33 80 72 73
NTPC 100 100 100 100 75 0
NLC 100 100 100 50 67 -
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 83
27.2 It was noted that some shutdown proposals were being made even on the day of the OCC
Meeting. Constituents were kindly requested to plan outages more diligently and increase
coordination with the field and project officials.
27.3 In the 141st Meeting of OCC, it was agreed that mid review outages would be approved only
after confirmation from SLDCs of AP, KAR, KER, TN & TS. Proposals would be posted on
outage group and after confirmation of states; the approved shutdowns will be uploaded on
SRPC website.
TCC deliberations
Only outages uploaded on (D-3) in SRLDC portal would be approved.
Only emergency outages would be considered in real time.
SRPC noted the above.
27.4 Delay in restoration of transmission elements
Narendra ICT-II was taken out by SR-II, PGCIL on 05th
March 2018 during the peak
months. The approval of the Senior Management of Karnataka had not been taken for
availing the shutdown. KPTCL had expressed serious concern since a couple of
disturbances involving load loss of about 1,000-1,500 MW had occurred in that area and
there was high loading on the available Narendra ICT. SR-II had restored the ICT on
14.04.2018, though the approved date for revival was 31.03.2018.
Shutdown of 400 kV of Neyveli-Puducherry was also extended beyond the approved dates
(12.04.2018-22.04.2018) by PGCIL (revived on 29.04.2018). During such time the
Puducherry region as well as Cuddalore area in Tamil Nadu was operating under reduced
grid reliability.
It was noted in the OCC Meeting that for any reconfiguration etc, similar procedure as
adopted for new elements needs to be followed by all the concerned entities.
A Meeting in this regard was also held with SR-II, PGCIL on 17th
April 2018. The
actionable points (applicable to all the concerned entities) had been communicated vide
letter dated 18.04.2018 (Annexure-LVII).
NTPL - - - - - -
NPCIL 33 0 - 100 100 -
PNMTL 0 - - - - 50
CEPL 100 - - - - -
MTL 0 - - - - -
RSTCL 0 - - - 0 -
UPCL 0 - - - - 80
MEPL - 0 - - - -
Total 53 66 54 64 68 69
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 84
As noted in the earlier SRPC/TCC meeting, PGCIL / Transmission licensee would
endeavour to deploy ERS for critical outages. Further, PGCIL was to furnish revival
status 2-3 hours prior to scheduled time of revival.
SRPC noted the above.
28 COMPLIANCE STATUS OF PHASE-I AND PHASE-II OF PROTECTION AUDIT
RECOMMENDATIONS
With reference to the Petitions filed by KSEBL (88/MP/2016) and KPTCL (135/MP/2016)
seeking further time-extension for completing their respective Protection Audit
Recommendations (PAR), the final Order of Hon‟ble CERC disposing of petitions was issued
on 15.12.2016. In this Order, the Commission, apart from granting last-chance time-extensions
to various SR-Constituents, had also directed SRPC to monitor the status of completion of
PAR regularly in PCSC meetings and submit bi-monthly report to the Commission confirming
the completion of Phase-I and Phase-II of PAR of the Constituents of Southern Region.
In this regard, based on the information furnished various Constituents, a summary table
showing the compliance status of various SR-Constituents as on 07.08.2018 is given below,
please:
Sl.
No.
Constituent
PAR (Phase-I)
Activities
PAR (Phase-II)
Activities
PAR (Ph-I & Ph-II)
Compliance (%)
Remarks
Stipulated
Completion Date
Stipulated
Completion Date
1 APGENCO
(Hydel)
31.12.2017 31.12.2017 80.00 Based on the status furnished,
timeline for complying with the
remaining pending
recommendations (3 in no.) is
31.08.2018.
2 APGENCO
(Thermal)
30.07.2017 --- 83.33 Based on the status furnished,
timeline for complying with the
remaining pending
recommendations (2 in no.) is
31.08.2018.
3 APTRANSCO 31.03.2017 --- 98.57 Based on the status furnished, the
lone pending recommendation is
expected to be completed by
31.10.2018.
4 TSGENCO
(Hydel)
31.03.2017 31.03.2017 91.18 Based on the status furnished,
timeline for complying with the
remaining pending
recommendations (3 in no.) is
30.09.2018.
5 TSTRANSCO 31.03.2017 31.03.2017 89.77 Based on the status furnished,
timeline for complying with the
remaining pending
recommendations (9 in no.) is
31.08.2018.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 85
6 KPTCL 31.05.2017 31.05.2017 78.87 Based on the status furnished,
timeline for complying with the
remaining pending
recommendations (15 in no.) is
30.09.2018.
7 TANGEDCO 31.12.2017 31.12.2017 80.55 Based on the status furnished,
timeline for complying with the
remaining pending
recommendations (7 in no.) is
30.09.2018.
8 TANTRANSC
O
31.12.2017 31.12.2017 71.21 Based on the status furnished,
timeline for complying with the
remaining pending
recommendations (38 in no.) is
31.12.2018.
9 KSEBL 30.11.2016 31.12.2017 97.4 Based on the status furnished,
timeline for complying with the
remaining pending
recommendations (2 in no.) is
31.08.2018.
10 NPCIL
(MAPS)
31.01.2017 --- 88.89 Based on the status furnished,
timeline for complying with the lone
pending recommendation is
30.09.2018.
All above SR-Constituents (esp. KPTCL & TANTRANSCO) were requested to complete their
respective pending PAR at the earliest. The IPP’s for whom there are pending PAR [viz.,
Spectrum PGL, Konaseema GPL, APGPCL Vijjeswaram (Stage-I & Stage-II), & LANCO-
Kondapalli PL] were also requested to complete them at the earliest.
SRPC deliberations
This being a CERC monitored activity, all the constituents were requested to kindly
complete the pending works at an early date.
MS, SRPC informed that in Western region, WRTS-I & II had gone for third party
protection audits for 8 sub-stations /7 sub-stations respectively through CPRI and same
procedure could be adopted in SRTS-I & II. Though audits are being carried out in SR,
there was a physical limitation on account of manpower constraints. It would therefore be
prudent for PGCIL to go for third party audits in SR.
Director (O), PGCIL informed that internal protection audits are regularly carried out in all
PGCIL sub-stations. However, they would also contemplate third party protection audits for
few of its sub-stations in SR.
29 IMPLEMENTATION OF PROTECTION SUITE / PROTECTION MANAGEMENT
SYSTEM (PMS) FOR SOUTHERN REGION
Based on the approval of SRPC in their 26th
Meeting held on 20th
December, 2014 at
Visakhapatnam, implementation of Protection Management System in Southern Region [Web-
based Management Software and Protection Setting Calculation Tool for Southern Region] had
been undertaken through PSDF funding. The project was awarded through open bidding
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 86
process to M/s PRDC Pvt. Ltd. (PRDC) on 09.08.2017. Execution period for the Project is
about 18 months from the date of placement of LoA (also called “Effective Date”), and is
followed by an Extended Technical Services period of 5 years.
The detail of the project implementation including Milestone-wise status is given at
Annexure – LVIII for kind reference.
In this regard, a protocol on implementing & using Protection Management System and giving
an integrated view of the project had also been circulated to all SR-Constituents vide SRPC
letter dated 20.04.2018. Data collection by physical field visits of the stations in Tamil Nadu,
Puducherry, Kerala, and Telangana had been undertaken by PRDC. Even though this process
had been completed, all the data sought as per stipulated formats for modelling in PMS has
been pending from certain stations. In view of the time-bound nature of the PMS project,
monthly review Meetings are being planned regarding submission of pending PMS data to
PRDC.
Automated Fault Analysis System (AFAS) envisaged under PMS project was successfully
implemented for 400/ 230 – 110 kV Palavadi SS (Pilot Station), and was put under service with
effect from 18th April, 2018.
In this regard, the issues which have potential to delay the project like partial or late
submission of required data for building Protection Database by various Utilities, furnishing
details of the models employed for Governor, AVR & PSS by Generating Utilities, and
furnishing all required information for updating 132/ 110/ 66 kV power network of SR-grid
had been high-lighted.
With respect to updating 132/ 110/ 66 kV Network of SR-grid, considering the time-bound
nature of the project, and the criticality of the issue, it was agreed that SRPC Secretariat would
take steps to resolve it on priority basis by involving all stakeholders by seeking nominations of
suitable Nodal Officers from SRLDC and SLDC & STU of all states, who have thorough
knowledge of their respective 132/ 110/ 66 kV network. It was also decided that that these
members would participate in the Network Reconciliation Meetings that would be held state-
wise at SRPC Secretariat, Bengaluru, and would take lead in updating/ correcting connectivity
of each grid-connected substation at 132/ 110/ 66 kV level in their states.
All SR-Constituents (Genco’s/ Transco’s/ LDC’s/ ISGS Utilities/ ISTS Utilities/ IPP’s/
other Generators/ etc.) were requested to kindly extend full-fledged cooperation in terms
of furnishing required information/ data for setting up & maintaining protection
database, and ensure that PMS project is made operational by the targeted time-line of
9th
February, 2019.
SRPC noted the same.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 87
30 COMPLIANCE STATUS OF NEW PROTECTION AUDIT RECOMMENDATIONS
As part of GSC (Task-II) under Package-A, protection audit check of 15 stations was carried
out by M/s Tractebel Engineering (TE) in Southern Region during the period, December, 2015
– July, 2016, wherein certain recommendations were also given for each of these stations for
compliance.
Subsequently, protection audit of various stations in SR had also been regularly conducted by
SRPC teams in line with CERC Order dated 27.04.2015 in respect of APTRANSCO Petition
No.95/MP/2015 and CERC Order dated 14.05.2015 in respect of TSTRANSCO‟s Petition
NO:83/MP/2015. So far, protection audit of 11 stations was carried out during the period
December, 2016 – July, 2018, wherein certain recommendations were also given for each of
these stations for compliance.
The list of Stations audited & compliance % of the recommendations given is given below for
kind reference:
Sl. No. Name of the Station Period of Protection Audit Compliance %
APTRANSCO 51.31
1 400/ 220 kV Narnoor SS 16–18 February, 2016
64.52
2 400/ 220 kV Uravakonda SS 5-6 April, 2018 38.10
TSGENCO (Thermal) 62.41
1 (i) 220 kV KTPS (O&M) 14-16 March, 2016 52.78
1 (ii) 220 kV KTPS (Stage-V) 14-16 March, 2016 40.91
1 (iii) 220 kV KTPS (Stage-VI) 14-16 March, 2016 93.55
TSTRANSCO 81.82
1 400/ 220 kV Shankarapally SS 20-21 March, 2017 81.82
KPCL 48.31
1 400 kV & 220 kV Raichur TPS 8-10 June, 2016 46.34
2 220 kV Nagjheri PH 14-16 July, 2016 54.84
3 220kV Sharavathy GS 30-31 October, 2017 43.75
KPTCL 65.25
1 400/ 220 kV Guttur SS 4-6 May, 2016 79.07
2 400/ 220 kV Nelamangala SS 8–10 February, 2016
51.43
KSEBL 34.88
1 220 kV Edamon SS 18-20 January, 2016 34.88
TANTRANSCO 38.73
1 400/ 230 kV Alamathy SS 4-6 January, 2016 51.61
2 230 kV Alundur SS 17 December, 2016 31.25
3 400/ 230 – 110 kV Palavadi SS 14-15 May, 2018 33.33
Puducherry ED 08.79
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 88
1 230/ 110 kV Villianur SS 10 July, 2017 9.68
2 230/ 110 kV Bahour SS 11 July, 2017 7.89
PGCIL (SR-I) 48.57
1 400 kV & HVDC Gazuwaka SS 28-30 December, 2015
50.00
2 400/ 220 kV Gooty SS 12th,13
th and 15
th February,
2016 50.00
3 765/ 400 kV Nellore PS 19-20 June, 2017 80.00
4 765/ 400 kV Maheshwaram SS 8-9 February, 2018 14.29
PGCIL (SR-II) 63.75
1 400 kVHosur SS of PGCIL (SR-II) 9-11 December, 2015 25.00
2 400 kV Tirunelveli SS 8th,
,9th and 11
th January, 2016
50.00
3 400 kV Alundur SS 16 December, 2016 100.00
4 400/ 220 kV Kozhikode SS 21-22 December, 2017 80.00
NTPC 85.00
1 400 kV Ramagundam STPS 18-20 February, 2016 85.00
NPCIL 33.33
1 220 kV Kaiga GS 4-6 April, 2016 33.33
NLCIL 56.25
1 400 kV NLC TPS-II Station 8–10 February, 2016
56.25
Details of the stations audited during the period March, 2018 - June, 2018 are given below for
kind reference:
Remarks given by the audit teams for the above stations are enclosed at Annexure - LIX for
kind reference.
APTRANSCO, TSGENCO, TSTRANSCO, KPCL, KPTCL, KSEBL, TANTRANSCO,
Puducherry ED,NTPC (RSTPS), NPCIL (KGS), NLCIL, PGCIL (SR-I) & PGCIL (SR-II)
were requested to kindly take suitable action to comply with their respective pending
remarks.
SRPC noted the same.
31 AUTO-RECLOSURE IMPLEMENTATION ON ALL 220 KV & ABOVE
TRANSMISSION LINES OF SOUTHERN REGION
It is common knowledge that majority of the faults that occur on transmission lines are of
transient nature; hence provision of Auto-Reclosure certainly helps not only in preventing
Sl. No. Name of the Station
Audited
Period of Protection
Audit
Composition of Audit
Team
1 400/ 220 kV Uravakonda SS
of APTRANSCO
5-6 April, 2018 SRPC, SRLDC &
PGCIL (SRTS-I)
2 400/ 230 – 110 kV Palavadi
SS of TANTRANSCO
14-15 May, 2018 SRPC, SRLDC &
PGCIL (SRTS-II)
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 89
forced outage of the subject transmission line, but also in averting cascade trippings, in some
cases, of adjacent transmission lines due to consequent over-loading.
Further, provision for Auto-Reclosure is also mandated by Regulation 43 (4) (c) of CEA
Technical Standards for Construction of Electrical Plants and Electric Lines, 2010, which has
force of law. Therefore, it is in the interest of grid security that all Constituents implement
auto-reclosure feature on all 220 kV & above transmission lines in their respective control
areas. Any exceptions in this regard need to be properly justified.
In this connection, logics for implementing A/R have been clarified in various PCSC Meetings,
and their implementation status is being monitored periodically. From the details furnished by
various Constituents, it is noted that the main issues in implementing A/R are the adopted
conservative protection philosophies, lack of proper PLCC communication, and breakers‟
suitability/ supportability. Hence, it is intimated that if there are no issues w.r.t. carrier
communication and breakers‟ supportability, concerned Constituents shall make efforts to
implement A/R immediately in their respective networks. Where communication & breaker
related issues stand in the way of implementing A/R, concerned Constituents shall take steps to
address them appropriately on priority basis, and implement A/R in their respective networks
in a phased manner at the earliest.
Status of implementation of A/R by SR-Constituents on their 220 kV & above transmission
lines in SR-grid and the action plan proposed for implementing A/R where it is presently not in
service was reviewed in the 76th
Meeting of PCSC held on 26.07.2018. The details are
enclosed at Annexure – LX for kind reference.
All concerned Constituents [APGENCO (Hydro), APGENCO (Thermal), APTRANSCO,
TSGENCO (Thermal), TSGENCO (Hydro), TSTRANSCO, KPCL, KPTCL, KSEBL,
TANGEDCO, TANTRANSCO, NPCIL (KKNPP), NPCIL (MAPS), NLCIL, UPCL &
JSWEL] were requested to take action accordingly to implement A/R on their lines.
SRPC noted the same.
32 COMPLIANCE STATUS OF PCSC RECOMMENDATIONS
All trippings involving 220 kV & above system on account of mal-operation/ non-operation
of protection systems in place are regularly discussed in the monthly held meetings of
Protection Coordination Sub-Committee (PCSC) meetings of SRPC with a view to identify
their root cause and scrutinize correctness of operation of protection systems put in place by
the concerned Constituents. In the process, appropriate measures required to be taken for
system improvement are being suggested/ recommended for compliance by concerned
Constituents. These recommendations, communicated vide Minutes of the PCSC meetings,
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 90
are also being monitored in these meetings for compliance by concerned Constituents.
In this regard, the latest status of implementation of PCSC recommendations pertaining to
various SR-Constituents for necessary compliance is enclosed at Annexure – LXI.
33 COMMERCIAL COMMITTEE ISSUES
33.1 Following issues were brought to the kind attention of TCC/ SRPC:
Transmission Charges pertaining to Kudgi STPS
Chairperson, SRPC vide letter dated 22.03.2018 (Annexure-LXII) had taken up the
issue of changing the LTA quantum from 2392.49 MW to 2262 MW with CMD, PGCIL.
Vide letter dated 28.06.2018 (Annexure-LXIII) COO, (CTU-Plg), had requested NTPC
to furnish the following details;
a) How the LTA quantum of 2392.49 MW has been arrived at when LTA was
sought against the installed capacity of 2400 MW and
b) Computation of revised LTA
NTPC vide mail dated 03.07.2018 had informed that the information sought had already
been communicated vide mail dated 24.04.2018 and it was again forwarded.
CTU vide letter dated 25.07.2018 (Annexure-LXIV) had stated that NTPC is required
to relinquish the LTA quantum of 130.49 MW as per CERC Connectivity Regulations,
2009.
TCC deliberations
PCKL had stated that installed capacity minus the normative auxiliary consumption
is the power which would be injected into the grid. Financial implication due to
LTA higher than this value would have to be taken care by NTPC only. Whether
beneficiary approval was taken for LTA quantum also needs to be ascertained?
TSTRANSCO had sought clarification that whether similar approach was adopted
by NTPC in other regions. Also, under „Change in Law‟, whether CTU could
consider it favorably. ?
NTPC had stated that LTA application had been made on behalf of beneficiaries
and quantum (overload of 105% and max DC of 101%) was arrived as per the
prevailing Regulations. Liability to pay transmission charges is solely with
beneficiaries. Application was made with certain conditions that payment of
transmission charges would be with beneficiaries. In other regions also similar
approach had been adopted by NTPC and the beneficiaries are directly taking up
with CTU for relinquishment/surrender. LTA had been signed by beneficiaries with
CTU only and NTPC was not a party to it. Beneficiaries were informed at each
step.
CTU had informed that legal opinion in this regard had been taken. Hon‟ble CERC
had come out with Order that even for change in auxiliary consumption it has to be
associated with relinquishment. Secondly on whether overload capacity can be
considered in approved injection, it may be noted that change in Sharing
Regulations is effective from March 2012, while this LTA was granted in October
2011. Relinquishment can be done prospectively and not retrospectively.
KSEBL had stated that they were in agreement with PCKL and the error was made
by NTPC which needs to be amended by NTPC only.
TANGEDCO had also stated that the issue has arisen because of erroneous
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 91
application furnished by NTPC. The quantum physically available should be billed
to beneficiaries. Beneficiaries should not be burdened with relinquishment charges.
CTU and NTPC should settle the issue bilaterally.
It was noted that PoC charges are not a function of LTA but LTA has a direct
bearing on Reliability and HVDC charges. Kudgi was the first CG Station in SR
which had come through LTA route. MoP allocation is for 2,400 MW.
All beneficiaries concluded that the additional quantum needs to be relinquished
immediately to avoid future liabilities.
All beneficiaries stated that NTPC should apply for relinquishment. The sharing of
the relinquishment charges could be sorted out based on 92/MP/2015 order.
NTPC had stated that they would apply relinquishment on behalf of the
beneficiaries, however charges, if any, would need to be borne by the beneficiaries.
SRPC deliberations
PCKL stated that they had gone through the detailed procedure notified by
CERC regarding Connectivity Regulations. There is a provision under general in
para 30.2 as reproduced below:
30.2. Any amendment/modification to an existing application, except for reasons
specifically mentioned in the procedure, shall be treated as a fresh
application.
30.3. All costs/expenses/charges associated with the application, including bank
draft, bank guarantee etc. shall be borne by the applicant.
……………..
30.7. All complaints regarding unfair practices, delays, discrimination, lack of
information, supply of wrong information or any other matter related to
Long-term access in ISTS shall be directed to CERC for redressal.
PCKL stated that as can be seen from the above the question of relinquishment
does not arise. Further, CERC could be approached under provision para 30.7
since there was some error in the LTA quantum.
NTPC informed that they had applied for grant of LTA on behalf of the
beneficiaries after obtaining consent from them. LTA was applied on similar
lines for all the projects by NTPC as per the extant provisions of the Regulations
during that time. There had been no error on part of NTPC on the LTA quantum
applied. These LTA agreements have been signed by the beneficiaries directly
with CTU and NTPC is not a party in the Agreement. Beneficiaries were well
aware of the LTA quantum at the time of signing of the Agreement. Since
surrender has been caused by changes in the provisions of CERC Regulations,
the beneficiaries are needed to relinquish the LTA. Benefits of revision would be
for the beneficiaries and NTPC does not have any role / interest. In case of
BRBCL, Railways had given undertaking to bear the relinquishment charges to
CTU and on that basis; CTU has accepted the relinquishment application. NTPC
is only a facilitator for ensuring a combined application to CTU. It would be
better in case SRPC approaches Hon‟ble CERC in this regard.
It was noted that states had also not committed any error in this regard. NTPC on
behalf of the beneficiaries could approach Hon‟ble CERC through Petition to
have clarity on the issue. The plea should be for error and not for relinquishment.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 92
Chairperson, SRPC noted that Hon‟ble CERC generally does not provide
clarifications but they entertain Petitions only. Under provisions of 30.7 of the
Procedure, NTPC could approach Hon‟ble CERC through a petition.
Regional ED, NTPC stated that NTPC could seek clarification from Hon‟ble
CERC, however they would not go through petition. NTPC will not apply for
relinquishment also. This is not the lone case and there were similar issues in
case of Railways, etc and this would affect the stand on those cases also.
CTU clarified that till the quantum is relinquished or some Order is received
from CERC, full LTA quantum would be continued to be billed.
SRPC noted that NTPC would approach Hon‟ble CERC for clarification on the
matter.
URS Accounting
It was noted that the 5th
Amendment had been notified on 12th
April 2017 (wef
01.05.2017) which had clear provisions on power sold beneficiary-wise to market.
This information was not being communicated to SRPC which was leading to
erroneous URS computations. This had commercial implication on fixed charge
reapportionment, approved injection in RTA, fixed charge apportionment in RRAS,
computation of incentive charges, compensation calculation etc. The issue had been
discussed in the Special Meeting held on 29.01.2018.
NTPC/NLC were to furnish consent quantum details beneficiary wise, cleared
quantum details beneficiary wise in PX for the period from 01.05.2017 to
10.12.2017.
Change in URS allocation procedure during ramp violation
Whenever a state has surrendered power (URS) and the same is taken by some other
state, and when that power is returned and in cases of the ramp violations, the
violation quantum was being booked to the URS surrendering beneficiary. It has
been noted that the causer (whichever beneficiary avails the URS) the ramp violation
need to be booked to the causer. Therefore the ramp violation quantum will be
booked to the causer.
It was agreed to implement the same in SR.
PPA wise DC to be furnished by the IPPs
SRPC had observed that in line with CERC Order dated 31.08.2017 in Petition No
28/MP/2016 PPA wise DC has to be furnished by all ISGS. SRLDC vide letter dated
28.05.2018 (Annexure-LXV) had requested all the IPPs in SR to furnish the PPA
wise DC (as per the format attached with the letter).
Pending payments between WR& SR Constituents as on 16.03.2018 are as follows:
State Receivable from Payable to
Entity Rs Entity Rs
Andhra Pradesh
/ Telangana
MPPMCL 1,21,76,270 MPPMCL Nil
Karnataka MPPMCL 13,27,208 GUVNL Nil
Kerala MPPMCL 1,21,47,260
CSPDCL 7,05,279
Tamil Nadu MPPMCL 1,17,17,268 CSPDCL 92,77,878
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 93
The matter was further discussed in the CCM (77th
) of WRPC held on 20.4.2018. As
decided in the CCM, one to one Meeting with MPPMCL and SR constituents (Andhra
Pradesh, Karnataka and Tamil Nadu) was held on 9.5.2018 at Jabalpur, to reconcile the
figures.
The status update after 38 CCM is as under:
Karnataka: Karnataka had claimed an amount of Rs. 13,27,208/- towards power
purchase. MPPMCL had claimed Rs.26,38,440/- which was said to be paid by
Karnataka to PTC.
PCKL had informed that the matter was again taken up with MPPMCL on 27.6.2018
and the reply was awaited
Tamil Nadu: Tamil Nadu claimed an amount of Rs. 1,17,17,268/- towards power
purchase. MPPMCL claimed Rs.32,93,935/- which was said to be paid by Tamil Nadu
to PTC. MP had agreed to verify the same within 15 days.
Andhra Pradesh: AP has claimed an amount of Rs. 1,21,76,270/- towards power
purchase for the period 03/97 to 12/2002, out of which, figures related to 2002 &
wheeling charges are reconciled. It was informed by MPPMCL that Andhra Pradesh
Power Co., vide letter no.387 dated 20.08.2010,had claimed net amount payable by MP
after adjustment of wheeling charges as Rs.66.32 Lakhs. MPPMCL had requested
APPCC to verify their claim.
MPPMCL has also submitted details of claims of Rs.5.62 crores as receivable from Andhra
Pradesh for verification of its payments to Chhattisgarh. AP has agreed to provide the same
within 15 days.
Kerala: KSEBL had informed that they would take up the matter for an early meeting
with GRIDCO
Payable amount to PGCIL (WRTS) by SR Constituents (as discussed in 38th
CCM)
Pending payments of NTECL
In the 38th
CCM (29.06.2018), NTECL had expressed concern on pending
payments by beneficiaries and dues were as follows:
Sl. No. Beneficiary
Outstanding dues for
more than 60 days as
on 25.06.2018
1 APPCC Rs. 73.01 Cr.
2 TSPCC Rs.93.43 Cr.
Constituent Amount to be
refunded (Rs.)
Status
AP & TSTRANSCO 17,34,898
Karnataka DISCOM's 18,36,027 Paid
KSEB l0, 17,023 Paid
TNEB 17,40,999
PED 3, 40,692 Paid
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 94
3 GESCOM Rs. 17.60 Cr.
4 HESCOM Rs. 69.71Cr.
5 CESCORP Rs. 7.38 Cr.
TANTRANCO vide letter dated 28.12.2017 had requested PCKL to clear the dues of Rs.
26,49,88,513/- as per the decision taken in 123rd
SREB Meeting. In the 36th
CCM held
on 24.11.2017, KPTCL/PCKL had informed that needful would be done at the earliest.
In the 33rd
SRPC meeting, MD, PCKL had assured that the payment issues with
TANTRANSCO would be resolved before the next SRPC Meeting.
In the 38th
CCM (29.06.2018), PCKL informed that the payment was likely to be
processed in first week of July 2018.
In the TCC Meeting, it was noted that PCKL vide letter dated 31.07.2018 had
cleared the dues of Rs 16,14,28,857 to TNEB towards the monetary compensation
of energy transactions for the period from December 1998 to March 2001 after
deducting wheeling charges receivable by KPTCL from TANTRANSCO.
(TANTRANSCO letter dated 16.08.2018 in this regard is enclosed at Annexure-
LXVI. This gesture of PCKL in settling long pending issue was appreciated.
SRPC deliberations
Director (O), TANTRANSCO thanked PCKL / KPTCL and this forum for the
clearing the payments which were due since long.
Default in payment of outstanding dues by SR beneficiaries
PGCIL vide letter dated 26.07.2018 (refer Annexure-XXIX) had furnished the details of
outstanding dues for more than 60 days as on 06.07.2018 in respect of SR beneficiaries
of POWERGRID are as under:
(Rs in Crores)
Name of the DIC 60-90 days >90 days
Telangana 94.57 ---
AP (AP TRANSCO) 32.12 ---
KSK Mahanadi (AP) 17.88 59.98
Meenakshi Energy Pvt Ltd 9.73 36.01
NTPC Kudgi 28.37 221.45
Simhapuri Energy Ltd 14.55 74.68
Kerala (KSEB) 1.57 ---
Karnataka (HESCOM) 18.72 ---
KSK Mahanadi (TNEB) 7.96 7.35
Coastal Energen (MTOA) 1.11 22.41
PGCIL had requested the concerned utilities to liquidate the outstanding dues on priority
and update the status.
Wheeling Charges from 1.7.2011 onwards
As also noted in the 38th
Meeting of Commercial Sub-Committee held on 29th
June
2018, the transmission charges for natural inter-state lines would be covered under
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 95
PoC mechanism from 1.7.2011. Most of the states had filed tariff petitions with
Hon‟ble Commission in respect of natural inter-state lines.
Wheeling charge computations in REA (as per erstwhile SREB decision) comprised
of wheeling charge for usage of natural inter-state lines, wheeling charges for lines
emanating from MAPS (completely embedded in STU) and wheeling charge for
Sirsi- Guttur portion of 400 KV Kaiga-Guttur line. Thus, the wheeling charges
reflected in the monthly REA were discontinued and constituents advised to reconcile
and settle the amounts.
Further, in the 3rd
Amendment to Sharing regulations 2015, it has been stated
“(vii) In case an ISGS is connected only to STU network and the shares of the
beneficiaries of the said station are being delivered through the STU network, such a
line of the STU network shall be considered as an ISTS for the purpose of these
regulations.”
Thus, MAPS evacuation lines are to be considered as ISTS and to be treated
accordingly.
Further, in respect of Sirsi-Guttur line, the procedure approved in the 31st SRPC
Meeting is being adopted.
KSEBL letter dated 03.08.2018 on the above issue is enclosed at Annexure-LXVII.
KPTCL and TNEB had been requested to refund the charges.
Accounting of Drawal of power during complete outage of station including one or
more unit under RSD
The matter had been discussed in the 38th
Meeting of Commercial Sub-Committee held on
29th
June 2018. After discussions, the Sub-Committee had recommended the following
procedure to be implemented.
In case of complete outage of a station (ISGS whose tariff is decided by CERC) then the
exchange of power with ISTS would be accounted in the REA and beneficiaries would
settle it under DSM with the Regional Pool.
Methodology:
Whenever ON BAR DC of the station is zero,
Schedule for the blocks = actual drawal
DC for the blocks = DC OFF BAR+ actual drawal.
Deviation computed for these blocks will be shared by Beneficiaries.
NTPC letter dated 24th
July 2018 is attached as Annexure-LXVIII.
TCC deliberations
NTPC had stated that the deviations in such cases are to be settled under DSM as being
followed in all the other regions. In Petition 42/2005 in case of Talcher, Hon‟ble CERC
had observed that such drawal has to be treated under DSM.
It was noted that in Petition 42/2005, NTPC‟s plea was different. Further no direction
had been passed by the Commission. Hon‟ble Commission had noted that different
Regions are following different methodology and no specific methodology was
advised. SR is following CEA‟s suggested method which NTPC was supporting all
these years.
4th
Amendment of DSM was proposed and NTPC may consider changing its stand
again.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 96
NTPC had stated that a principled approach should be followed. Something different is
being followed in SR and thus uniformity was being sought with the practice in other
regions.
TSTRANSCO had noted that NTPC was silent since 2005, and now since they are
impacted commercially, they were seeking review.
It was agreed to continue with the existing practice as agreed in 38th
CCM, However
this procedure would be reviewed in next CCM.
SRPC noted the above.
Compensation revision
NTECL vide mail dated 10.05.2018 had requested for revision of compensation amount
due to revision in landed price and GCV (changes in ECR) of fuel for 2017-18.
TCC deliberations
It was noted that para 5(ii) of the Compensation Procedure approved by Hon‟ble
Commission vide order dated 05.05.2017 states „Generating station shall submit the
requisite data along with compensation calculation to RPC secretariat as prescribed in
Annexure-I to Appendix II for a month by 15th
day of the following month. The data to
be submitted is for the month and reconciled up to the month‟.
TCC noted that variable cost furnished by ISG stations by 15th
April of each year (for
the previous year) would be considered for compensation. Any implication due to
change in ECR (landed price, GCV etc) subsequently would be required to be borne by
the generator / beneficiaries as applicable.
SRPC noted the above.
34 IEGC RELATED ISSUES REQUIRING ATTENTION/ACTION
34.1 Automatic Demand Management Schemes
34.1.1 In line with clause 5.4.2 (d) of IEGC, Automatic Demand Management Scheme was to
have been provided by all constituents. Revised logic at 49.85 Hz, Min DSM violation
for 15 minutes had been implemented by all the States/UT.
34.1.2 Number of incidents satisfying the existing logic is given below:
Month
Present settings as per IEGC
Frequency < 49.85 Hz for 15 Min. and OD = Min DSM limit
No of
instances
Meeting the
freq. limit
No of
instances
applicable to
states
No of instances applicable to states
AP Kar Ker TN TS
Feb-18 1 0 0 0 0 0 0
Mar-18 19 3 1 0 0 1 0
Apr-18 22 2 2 0 0 0 0
May-18 107 23 13 0 0 9 1
June-18 34 20 7 0 0 11 2
July-18 28 9 4 1 0 2 1
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 97
SRPC noted the above and suggested that ADMS with proper logic should in place at all
times.
34.2 UFR and df/dt reliefs
34.2.1. Details of recommended, implemented, SCADA monitorable and actual relief being
realized are shown in the Table below:
State AP TS KAR KER TN PUD SR
Recommended MW A 2782 2965 3539 1173 4176 103 14738
Implemented MW B 2782 2978 3575 1427 4399 109 15270
% B/A 100 100 101 122 105 106 104
SCADA monitorable MW C 1650 2318 3575 1399 3790 100 12832
% C/B 59 78 100 98 86 92 84
Average Visible
Relief in Feb 2018 MW D 1592 1750 3232 1255 2779 77 10685
Wrt monitorable % D/C 96 75 90 90 73 77 83
Average Visible
Relief in Mar 2018 MW E 1633 2238 3205 1350 3416 79 11921
Wrt monitorable % E/C 99 97 90 96 90 79 93
Average Visible
Relief in Apr 2018 MW F 1436 1526 3001 1369 3463 86 10881
Wrt monitorable % F/C 87 66 84 98 91 86 85
Average Visible
Relief in May 2018 MW G 1564 1075 2173 1276 3030 91 9209
Wrt monitorable % G/C 95 46 61 91 80 91 72
Average Visible
Relief in June 2018 MW H 1431 1156 1988 1120 2853 79 8626
Wrt monitorable % H/C 87 50 56 80 65 79 64
Average Visible
Relief in July 2018 MW I 1334 1651 2135 1087 2847 83 9136
Wrt monitorable % I/C 81 71 60 78 65 83 68
34.2.2 In earlier Meetings, the following had been noted:
SCADA mapping was to be improved for AP, TS and TN.
Visible relief to be improved for Karnataka and Telangana.
In the special meeting held on 09.07.2018 in respect of pending issues of Karnataka,
it was noted that on account of RE injection which was substantial, the direction of
power flow on some of the identified features had reversed and also in some feeders,
the net flow has been reduced considerably. SRPC vide letter dated 09.07.2018
(Annexure-LXIX) had requested all the states to review the identified feeders for
UFR and if required, to have more number of radial feeders at lower voltage levels.
TCC deliberations
Mapping in AP & TS has to be improved.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 98
TCC had noted the above and requested all the concerned entities to improve the
relief, improve the mapping and look into RE issues leading to reverse/net low
flows.
SRLDC in coordination with states are jointly validating the reverse/ low net flow
(because of RE) and all the states were requested to kindly coordinate and take
corrective action as and when the issues are identified.
SRPC noted the above.
34.2.3 NPC had sought views of members on the review of quantum of load shedding and
stages of frequency.Therefore, RPCs were to deliberate on additional slabs of frequency
as well as raising the set frequency for UFR operation. These views of RPCs would be
put up in next meeting of NPC. In the 32nd
TCC meeting the following had been noted:
All constituents had expressed concern on paucity of additional radial feeders without
overlap and also since islanding loads could not be identified for any of the relief
schemes. Being a large integrated grid, chances of fall of frequency were less and
system should be provided space for self-healing before df/dt or UFR sets in.
TCC had endorsed these decisions of OCC that there was no need presently for
additional slabs of frequency as well as raising the said frequency for UFR operation.
SRPC noted the same.
34.2.4 Review of UFR quantum and set points
NPC Secretariat vide letter dated 30.05.2018 (Annexure-LXX) had furnished UFR
quantum to be adopted by SR in the current Grid Environment, which was to be ratified
by NPC. Further NPC secretariat had sought comments on retaining the same set points
(49.2 Hz, 49.0 Hz, 48.8 Hz & 48.6 Hz) or enhancing the set points by 0.2 Hz (49.4 Hz,
49.2 Hz, 49.0 Hz & 48.8 Hz).
KSEBL vide letter dated 20.06.2018 had stated that the existing set points can be
retained. TSTRANSCO vide letter dated 20.06.2018 had suggested that the revision of
set frequencies could be deliberated in the TCC meeting for arriving at consensus on the
issues. APTRANSCO vide letter dated 05.07.2018 had stated that they were agreeable
for increase in settings of 0.2 Hz. In the special meeting held on 09.07.2018, KPTCL
had confirmed that they were agreeable for the increase in setting of 0.2 Hz.
TCC deliberations
TSTRANSCO had stated that existing settings may be retained.
TCC had concluded that existing settings may be retained and the same may be
recommended to NPC.
SRPC noted the above.
34.3 Restricted Governor Mode of Operation (RGMO)/FGMO of Generating Units
34.3.1 RGMO response is being analyzed in the Meetings of OCC. SLDCs were also to
analyze RGMO instances posted by SRLDC for the generators in their control area and
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 99
initiate suitable action as per Order in respect of 84/MP/2015. Inadequate Response
was to be taken up with SERC (Petition No.302/MP/2013).
34.3.2 Performance of RGMO is being analyzed in the OCC forum. Summary for Southern
Region (state-wise details are given in Annexure-LXXI) is given in the Table below:
Hydro Thermal TOTAL
Possible
(MW)
Actual
(MW) %
Possible
(MW)
Actual
(MW) %
Possible
(MW)
Actual
(MW) %
30.01.2018 (1250 MW loss at Koderma)
41 53 130% 669 159 24% 710 211 30%
23.04.2018 (3090 MW generation loss due to multiple trippings at Kotra (PG)
81 109 135% 1282 380 30% 1363 489 36%
34.3.3 As per 5th
Amendment to IEGC, gas stations above 50 MW Installed Capacity were also
to come under RGMO/FGMO Operation w.e.f. 1st October 2017. SLDCs (AP & TN
and NTPC (Kayamkulam) had been requested to take necessary action to comply with
this Amendment.
34.3.4 All generators should keep a Margin for RGMO response while declaring DC in all
level ie at full load/partial load operation.
34.3.5 FRC computations were also to be undertaken by the SLDCs in line with approved
methodology of CERC.
34.3.6 In the OCCM, it was pointed out that necessary checks / interlocks needed to be in
place so as to ensure that RGMO margin is available in all the generators under SRLDC
control area. Regulation 5.2(h) of IEGC states, „…………….For the purpose of ensuring
primary response, RLDCs/SLDCs shall not schedule the generating station or unit (s)
thereof beyond ex bus generation corresponding to 100 % of the Installed capacity of
the generating station or unit (s) thereof.‟
34.3.7 SRLDC vide letter dated 07.02.2018 (Annexure-LXXII) had taken up the issue with
IPPs/MPPs.
34.3.8 SRLDC vide letter dated 29.05.2018 (Annexure-LXXIII) had requested all the SLDCs
to furnish the list of all hydro stations and gas stations which are covered under
FGMO/RGMO response along with the status clearly mentioning the CERC Order in
case exemption/extension is received from Commission may be furnished.
SRPC noted the above and suggested the Generators and SRLDC/SLDCs to initiate
necessary action to ensure compliance of IEGC provision.
34.4 Demand Estimation for Operational Purpose (Clause 5.3 of IEGC)
Load Forecasting tool meeting the regulatory requirement was yet to be developed by all
utilities. The forecast was required for RRAS and Renewable Framework also.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 100
States had been requested to break the state load into sub components like district
wise/substation wise while carrying out the forecasting incorporating weather conditions
etc.
SRPC suggested the states to comply with IEGC provisions.
34.5 Sudden Change in Demand/Frequency Excursion (Clause 5.2 (j) of the IEGC)
Necessary action is sought in respect of demand and generation management as well as
power purchases, so that clause 5.2 (j) of IEGC Regulations is not violated.
SRPC suggested the states/generators to comply with IEGC provisions.
34.6 Arranging of interruptible loads in four groups
As per IEGC, to maintain the frequency within stipulated band and also to ensure
network security, interruptible loads are to be arranged in four groups of loads. This was
for the purpose of scheduled power cuts/load shedding, loads for unscheduled load
shedding, loads to be shed through UF relays, df/dt relays and loads to be shed under any
SPS Scheme. These loads are to be grouped in such a manner that there was no
overlapping between different groups of loads.
Existing schemes were not meeting Regulatory requirement fully and further action was
required in this regard. Constituents had been requested to ensure necessary compliance.
SRPC suggested the states to comply with IEGC provisions.
34.7 PSS Tuning
5th
Meeting of PSS tuning was conducted on 26th
July 2017 and MoM is available at
SRPC website. PSS Study group had analyzed the Step Response Test Reports for the
generators which had furnished the reports and recommendations had been finalized. It
had been kindly requested that necessary action may be taken as finalized in the PSS
Meetings. SRT of following units had been analyzed in the PSS Meetings and necessary
action had to be taken as per Recommendations:
Entity Generating Stations/Units
APGENCO Rayalaseema TPS U1 to U5; VTPS U1 to U4 & U7; SDSPP U1&
U2 (Reports to be analyzed); Srisailam RB HEP U1 to U7; Lower
Sileru HEP U1
AP IPP HNPCL U1 & U2
TSGENCO Nagarjunasagar HEP U1 to U8; Srisailam LB HEP U1 to U6;
Kakatiya TPS U1 & U2; Kothagudem TPS U 7 & 8 (Report to be
analyzed) U10 & U11; Singareni Collieries U1 & U2 (Reports to
be analyzed)
KPCL Raichur TPS U1,2,3,5,6,7& 8; BTPS U1 to U3; Varahi UGPH
HEP U1 to U4; Nagjheri HEP U1 to U6 (U6 report to be
analyzed); Sharavathy HEP U1,2,3,4,5,6,7,9, 10 & 8 (Report to be
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 101
analyzed), Raichur TPS U4 (Report to be analyzed)
KAR IPPs UPCL U1 & U2; JSWEL U1 to U3
KSEBL
TANGEDCO MTPS-I U1 to U4 (U1 Report to be analyzed); NCTPS St-I U1 to
U3; Tuticorin TPS U1 (Report to be analyzed) U2 to U5; NCTPS
St-II U1; Kadamparai HEP U1 & U2, Mettur-II (Report to be
analyzed).
TN IPPs
CGS NTPC- Ramagundam U7 & U4 (Report to be analyzed); NTPC-
Simhadri U1 to U4; NTPC-Talcher STPS St-II U3 to U6; NTECL-
Vallur TPS U1 to U3; NLC-Neyveli TPS II U4 to U7; NLC-
Neyveli TPS II U1 to U3; KGS U2 (Report to be analyzed);
NPCIL-KKNPP U1 & U2 (Report to be analyzed); NLC-Neyveli
TPS II Exp. U1 & U2; (NLC & TN JV) NTPL U1; NTPC-Kudgi
U1 & 2 (Report to be analyzed).
ISTS connected IPPs TPCIL U1 & U2 (U2 Report to be analyzed); Coastal Energen U1;
((Report submitted, to be analyzed), Coastal Energen U1; ((Report
to be analyzed), Coastal Energen U2; IL & FS U1 & U2
For the following Units, PSS is to be tuned and SRT to be carried out / information not
available.
Entity Generating Stations/Units
APGENCO VTPS U5 & U6; Lower Sileru HEP U2 to U4
AP IPPs
TSGENCO
KPCL Yeramarus TPP
KAR IPPs JSWEL U4
KSEBL Idukki HEP U1 to U6
TANGEDCO NCTPS St-II U2; Kadamparai HEP U3 & U4
TN IPPs STCMS
CGS NTPC-Ramagundam U1, U2, U3, U5 to U6; NLC-Neyveli TPS I
Exp. U1 & U2 (SRT reports not submitted); NPCIL- KGS U1, U3
& U4 ( Full Report not submitted for U4); NPCIL-MAPS U1 &
U2;
ISTS connected IPPs Lanco Stage II & III; SGPL-Nellore; SEL U1 to U4; MEL U1 &
U4
SRPC suggested generators to kindly initiate necessary action on the recommendations
finalized in the PSS Meetings.
34.8 Relocation of SPS schemes
A comprehensive report on the SPSs to be shifted to Raichur and SPSs being retained at
Kolar would be furnished by SR-I and SR-II to all the states/UT, SRPC and SRLDC.
States would also communicate the corresponding load to the mapped to the respective
SPSs. The location of new DTPCs would also be coordinated in the exercise.
SRPC noted the above.
34.9 Other Issues requiring kind attention of TCC / SRPC
Following issues which are being followed up in the Meetings of Sub-Committees of
SRPC also merit kind attention:
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 102
SR-II had requested shutdown of IL&FS-Nagipatnam D/C lines for LILO of Neyveli-
Bahoor at Karaikal. IL&FS had suggested alternative method like hot line which
would not require any generation outage at IL&FS. SRPC had requested SR-II to
consider hot line crossing as it would ensure generation continuity at IL&FS and also
ensure Karaikal regional drawal of Puducherry is accounted in the monthly REA and
other commercial account as planned.
On 13.02.2018 and 14.02.2018, there were sudden variations in the DC by Simhadri.
In the 141st OCC meeting, it was noted that sudden intra-day DC variations would be
stopped by ISGS during coal deficit condition. Further, it was noted that clause 6.4.16
of IEGC could be followed in letter and spirit, „……….During fuel shortage
condition, in case of thermal stations, they may specify minimum MW, maximum MW,
MWh capability and declaration of fuel shortage.‟ OCC had noted that even during
supercritical coal stock, fuel shortage was not being declared by some of ISGS
stations. OCC suggested that less than 3 days coal stock need to be declared as fuel
shortage. ISGS need to ensure that in case average DC is less than Ex-bus
(normative) over a day, then DC would need to be maximized during 06:00 to 09:00
hours and also during 18:00 to 21:30 hours, while appropriately reducing DC during
other hours.
CEA vide letter dated 16.02.2018 had informed that a Special Task Force had been
constituted under IGEF Sub-Group-1 for enhancing the flexible operation of existing
coal-fired power plants. The committee has recommended the implementation of
measures for 50 %, 40 % and 25 % minimum load in thermal power stations. The
measures for 50 % minimum load operation requires no investment or minimal
investment (Report is available on CEA website under TRM division). Subsequently,
a meeting was held under the Chairmanship of Member (Thermal) on 08.02.2018. In
this regard and it was decided that 55 % minimum load operation would be
implemented nationwide in first phase. Further, six units, including two units of
NTPC and one unit each from DVC, GSECL, APGENCO, MSPGCL, would be taken
up for 55 % minimum load operation in line with the CERC notification dated
06.04.2016 and 05.05.2017 (IEGC) (4th
amendments). Accordingly SRPC vide letter
dated 23.02.2018 had requested APGENCO to communicate the unit where the 55 %
minimum load operation would be implemented to CE, TRPM Division, CEA, New
Delhi with a copy to SRPC, Bengaluru. In the 144th
OCCM, APTRANSCO informed
that APGENCO had agreed for any of the Rayalaseema unit for flexibility (CEA
letter 16.02.2018). APGENCO would be informing it to CEA.
CEA vide letter dated 10.04.2018 had sought the following data for the study (as
decided in the 3rd
meeting of the Committee)
Historic generation data of renewables (RES) on hourly basis and, if possible, at
15 minutes interval for a period of one year.
Location of installed capacity of all current renewable energy sources and
location of anticipated RES installations by 2022.
The generation data of renewables as received from SRLDC had already been
submitted to CEA. All the states had been requested to kindly furnish location of
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 103
installed capacity of all current renewable energy sources and location of anticipated
RES installations by 2022.
CEA vide letter dated 13.04.2018 (Annexure-LXXIV) had informed regarding
registration of all existing and upcoming electricity generating units of the country of
capacity 0.5 MW and above under National Level Data Registry System
The issue of Kudgi DC being more than LGB target was taken up by Chairperson,
SRPC with Chairperson, CERC vide letter dated 28.02.2018 (Annexure-LXXV).
KKNPP had closed both the 400 / 230 kV ICTs from 09.03.2018.
In the OCC Meeting, it was agreed that availability certification of natural inter-state
lines and RPC certified intra-state lines would be carried out by SRPC. The procedure
for submitting the details had been circulated by SRLDC. All the states were to
furnish the element wise outage data with availability computations duly vetted by
SLDC to SRLDC by second of every month as per procedure. The same has to be
verified by SRLDC and furnish to SRPC Secretariat to issue the availability
certificate.
SPS on 400 kV Nellore-NPS line was agreed and implemented on 08.04.2018.
TSTRANSCO vide letter dated 28.02.2018 (Annexure-LXXVI) addressed to
Hon‟ble CERC had taken up the issues of, revision of schedule of inter-state short
term transaction (presently 2 clear days), advance intimation by ISGS units revival
and reduction in processing time for contingency transaction in Energy Exchanges.
Ministry of Power vide Order dated 17.03.2017 had allocated 540 MW of power from
Ratnagiri Gas and Power Private Limited (RGPPL) to Indian Railways. 35 MW MoP
allocations to Railways (Karnataka) from RGPPL was operational from 25.10.2017.
50 MW & 100 MW to TSTRANSCO & TANTRANSCO was to be made
operational.
Request of SEIL for enhancement of net exportable quantum from 1240 MW to 1254
MW was recommended by the group and noted in the 144th
OCC meeting.
In the OCC meeting, it was reaffirmed (as noted in the 125th
OCC) that for shutdown
of 400 kV bays (for 765 kV bays, NLDC approval was required) code would be
exchanged with SRLDC, though it was not be covered under OCC approval.
KPTCL had been requested to study the high loading of UPCL – Kemar lines and
take up reconfiguration if required.
33rd
TCC: KPTCL informed that after commissioning of 400/220 kV
Arasapadavu S/s, the over loading of 220 kV UPCL-Kemar line would get
relieved.
The issue of frequent tripping of Konaje – Manjeswaram on overload and the set
points was to be settled mutually between KSEBL and KPTCL.
33rd
TCC: KPTCL informed that action has been initiated to change the
relay setting of 110 kV Konaje –Manjeshwar line. Now there are no
trippings.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 104
CEA vide letter dated 04.05.2018 had sought data required for development
Geospatial Energy Map of India which is a part of initiative of Government of India,
Niti Aayog. Data may kindly be arranged to be furnished.
NIWE vide letter dated 09.05.208 had communicated that NIWE is in process of
carrying out Geo-Tagging/Online registry of wind turbines for maintaining a
centralized system of data base. SRPC was requested to revert back with
suggestions/clarifications, if any. SRPC vide letter dated 18.05.2018 had replied to
NIWE in this regard.
It was agreed in the OCC that OCC approval for taking A/R in non-auto mode would
not be taken, however, code would be exchanged (instead of messages) with SRLDC
/ NLDC.
In the OCC meeting, SRLDC had informed that the following practices may be
adopted/continued in real time grid operation for keeping transmission lines in open
condition on account of over voltage with immediate effect:
a. Hand tripping of lines on account of O/V: The existing practice of issuing
real time code from Control Room for hand tripping a line due to over voltage
will be continued during hand tripping.
b. Lines tripping on O/V Protection: Real time code may be issued from Control
Room to continue to keep the line in open condition on account of over voltage
continues to persist in the system. As and when the system voltage becomes
conductive, real time code may be issued for taking the line into service.
c. Lines already tripped due to fault excluding over voltage protection: After
attending the fault, when SLDC/POWERGRID/Other ISTS Licensee is
conveying its readiness, real time code may be issued to take the line into
service without delay. In case due to system constraint or over voltage persisting
in the system, Real time code may be issued from Control Room to continue to
keep the line in open condition on account of over voltage condition. The
remarks column of the respective line in the outage portal may be suitably
modified.
On the observation of NTPC Simhadri, a study on Simhadri-Kalpakka-Gazuwaka
power corridor was carried out by SRPC/SRLDC and discussed with NTPC
Simhadri. It was noted that the system was N-1 compliant. During the outage of one
of the lines of Simhadri-Kalpakka, other two lines loading was expected to go up in
the range of 600 - 650 MW which was well within the thermal loading limits.
Vemagiri (PG)-Nunna (Vijayawada) SPS was disabled as recommended by SRLDC
and approved by OCC.
Mock tests to check the healthiness of KKNPP & Talcher-Kolar SPSs were carried
out on 21.05.2018 and for Raichur -Sholapur SPS on 22.05.2018. Identified issues
were being addressed.
SRLDC had furnished the summary of MVAR testing and the pending observations
were to be closed by the respective entities and it is being reviewed in the OCC.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 105
NLDC letter dated 15.06.2018 (Annexure-LXXVII) had furnished the status report
and expressed concern on multiple tower collapses.
TSSLDC vide letter dated 09.05.2018 (Annexure-LXXVIII) had requested to clarify
whether state utilities and distribution utilities can be addressed to include suitable
clause in the connectivity conditions, that models figuring in the RLMM list are
added to the Grid. SRPC vide letter dated 28.05.2018 (Annexure-LXXIX) had
informed that in the Guidelines issued by MNRE for development of Onshore Wind
Power Projects it had been mandated that no wind turbine model shall be allowed for
installation in the country until it has obtained type and quality certification. MNRE
has stipulated verification of complete certificates of the models etc which needs to
be carried out by the concerned procurement agency.
It was agreed that URS availing on D-1 day will be processed at 2000 hrs after the PX
transactions are cleared.
Power Number for SR states for the year 2018-19 (based on the actual consumption
and Maximum Demand figures during the year 2017-18) are AP: 301, TS: 328, KAR:
355, KER: 129, TN:524, Pudu:13. (Total SR: 1650)
In the 7th
NPC Meeting held on 8th
September 2017, NPC had emphasized the need
for having an accurate All India power system data base for carrying out accurate
power system studies for operational and planning horizons. POSOCO was to prepare
requires formats and circulate to all RPCs and in turn RPCs may obtain data from
their constituents. It was noted that NLDC had furnished the formats to NPC.
Further to the follow up by SRLDC and TSSLDC on DG set requirement to start
auxiliaries at Jurala for black start and reply dated 30.11.2017 of TSGENCO,
TSTRANSCO vide letter dated 17.03.2018 (Annexure-LXXX) had advised
TSGENCO to take up the work in compliance of CEA Regulations.
SRPC vide letter dated 28.06.2018 (Annexure-LXXXI) had enclosed CEA letters
dated 26.06.2018, 20.06.2018 and 01.06.2018 informing about that newly developed
National Power Portal (NPP) which has replaced earlier established Information
Management System (IMS) in CEA. All entities have been requested to enter their
relevant data in NPP (npp.gov.in)
In Petition No. 58/TT/2017 on tariff determination for transmission elements in SR ,
Hon‟ble CERC in its Order dated 05.07.2018 had noted „The Commission during the
hearing of Petition No. 38/TT/2017 filed by the petitioner for approval of
transmission tariff from COD to 31.3.2019 for Assets (10 nos.) of ERSS IX Project in
Eastern Region on 18.1.2018 directed as under:-
“2. Since the petitioner has not submitted proper reply regarding requirement of
regional spares vis a vis their current availability, the Commission directed to
submit a proper reply. The Commission further directed to set up a Committee
consisting of representatives from PGCIL, NLDC and CEA under the Chairmanship
of the Chief(Engineering) of the Commission to assess the requirement of regional
spares including bus reactors, line reactors, ICTs, etc., present availability and
other related issues and submit a comprehensive report on the requirement of spare
bus reactors, line reactors, ICTs and related equipment in different regions of the
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 106
country to the Commission by 9.3.2018. The Commission also observed that final
tariff in the matter would be allowed only after consideration of the Report to be
submitted by the Chief (Engineering) of the Commission…….
we direct the Committee to finalize the report and submit the same to the
Commission within two months of this order.”
Based on the tariff orders issued by the SERCs/JERCs for FY 2017-18, the APPC at
the National level has been determined as Rs. 3.53/kWh by CERC in Petition No
4/SM/2018 vide Order dated 21.06.2018.
In Petition No. 198/TT/2017 in the matter of „Determination of transmission tariff
for Asset-I: ±800 kV 3000 MW HVDC Pole-III and LILO of Bishwanath Chariali -
Agra HVDC line for parallel operation of the HVDC station at Alipurduar, Asset-II:
±800 kV 3000 MW HVDC Pole-IV along with Earth electrode station and Earth
Electrode line at Alipurduar and Agra end….‟, Hon‟ble CERC in its Order dated
13.06.2018 had stated, „The AFC allowed in this order shall be applicable from the
date of commercial operation of the transmission system and the billing, collection
and disbursement of the transmission charges shall be governed by the provisions of
CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010,
as amended from time to time. Further, the transmission charges allowed in this
order shall be subject to adjustment as per Regulation 7(7) of the 2014 Tariff
Regulations.‟
In Petition No. 245/TT/2017 in the matter of „Approval of transmission tariff from
COD i.e. 1.12.2015 to 31.3.2019 for Gooty-Madhugiri 400 kV D/C line and 2x500
MVA transformers along with downstream bays at Madhugiri Sub-station upon
bifurcation of capital cost and hence transmission tariff as per directive of the
Commission vide order dated 18.7.2017 in Petition 54/RP/2016….‟, Hon‟ble CERC
in its Order dated 24.05.2018 had stated, „In response, the petitioner submitted that
KPTCL shall bear the tariff for the Gooty-Madhugiri 400 kV D/C transmission line
(Asset-I) from 1.12.2015 to 24.8.2016 and for 2 x 500 MVA transformers at
Madhugiri Sub-station along-with bays for downstream system (Assets-II, III, IV and
V) from the COD to the commissioning of the downstream assets in terms of order
dated 18.7.2017 in Petition 54/RP/2016. The transmission charges of Asset-I shall
be included in the PoC computation from 25.8.2016 i.e. from the date of
commissioning of 400 kV D/C Madhugiri-Bidadi Transmission Line (TBCB) and for
Assets II, III, IV and V from the date of commissioning of downstream assets.
Accordingly, transmission charges for assets II to V have been withdrawn from PoC
Pool and are being borne by KPTCL till commissioning of downstream assets.‟
In Petition No. 3/TT/2018 in the matter of „Approval of transmission tariff from
COD to 31.3.2019 for “Bunching of Tirunelveli – Edamon section of the Tirunelveli
–Muvathapuza (Cochin) 400 kV quad D/C line initially (and temporarily) at 220 kV
with existing Tirunelveli – Edamon 400 kV twin D/C line (400 kV line charged at
220 kV) under Transmission System associated with Kudankulam Atomic Power
Project”….‟, Hon‟ble CERC in its Order dated 24.05.2018 had stated, „The
Commission directed the staff to request CEA to clarify whether bunching of the
Bunching of Tirunelveli-Edamon section of the Tirunelveli-Muvathapuza (Cochin)
400 kV quad D/C line initially (and temporarily) at 220 kV with existing Tirunelveli-
Edamon 400 kV twin D/C line (400 kV line charged at 220 kV) under Transmission
System associated with Kudankulam Atomic Power Project enhances power flow
between buses and POSCO to validate the reason for increase in 167 MW flow as
claimed by the petitioner within a month..‟
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 107
In Review Petition No. 44/RP/2017 in Petition No. 103/MP/2017 along with I.A.
No. 74/2017, Hon‟ble CERC in its Order dated 21.05.2018 had stated, „The Review
Petitioner had raised similar issue in Petition No. 229/RC/2015. The Commission in
its order dated 8.3.2018 in Petition No.229/RC/2015 has dealt with the issue as
under:
“52. CTU has expressed apprehension that if LTA is operationalized in the absence
of LC, the Petitioner would not be able to recover the transmission charges in the
event of default by the DICs. In our view, though there is provision in the BCD
Procedure for opening of LC one month prior to the effective date, LC is not a
condition precedent for operationalization of LTA. If LTA is not operationalized
pending opening of LCs, this will give perverse incentives to the DICs not to open
the LCs to avoid paying the transmission charges. There is therefore a need for
prescribing certain deterrent measures against the defaulting DICs. In our view, a
DIC who has been granted LTA but does not intend to open the LCs, he shall be
debarred from applying for medium term open access and short term open access.
As a result, the DIC in order to avail the medium term and short term open access
will be forced to make payment of LTA charges. Accordingly, we direct that if the
DIC fails to make payment of the transmission charges or open letter of credit at the
end of the month after operationalization of LTA, it shall be denied medium term
open access and short term open access till it makes payment of transmission
charges and open letter of credit.”
Therefore, non-payment of transmission charges and non-opening of LC under the
LTA shall result in the denial of MTOA or STOA.
8. The Commission in the impugned order has decided that opening of LC is not a
condition precedent for operationalization of LTA which has also been reiterated in the
order dated 8.3.2018 in Petition No. 229/RC/2015. The Commission, in the said order
has held also that if a DIC who has been granted LTA but does not intend to open the
LCs, then he shall be debarred from applying for MTOA and STOA. Accordingly, there
is no error apparent in the impugned order...‟
SRPC noted the above and suggested the concerned entities to close the pending issues.
35 COMPLIANCE OF ORDER OF HON’BLE CERC IN PETITION NO. 420/MP/2014 –
IN RESPECT OF LVRT AND OTHER PROVISIONS OF CEA/CERC
REGULATIONS
35.1 Four Meetings had been conducted so far in compliance of Order of Hon‟ble CERC
(Petition No.420/MP/2014) in respect of LVRT and other provisions of CEA/CERC
Regulations. Hon‟ble Commission had specified time lines for a number of actionable
points for various entities.
35.2 Quarterly reports of the SR constituents jointly validated by SRLDC/SRPC Secretariat were
being communicated to Hon‟ble CERC with regard to monitoring of the installation and
performance of LVRT installed on existing WTGs as per the directives of Hon‟ble CERC.
35.3 CEA had issued draft second amendment in CEA (Technical Standards for connectivity to
the Grid) Regulations. The final notification is awaited.
35.4 The following had been noted in earlier Meetings:
New wind and solar units need to comply with LVRT/HVRT provisions and
STU/SLDC was to ensure necessary compliance. Required mechanism needs to be in
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 108
place for this purpose. SLDCs were requested to approve connectivity to new
generators only on confirmation of availability of LVRT feature and other CEA/CERC
requirements.
Identification of optimal location for installing PMUs for LVRT analysis purposes.
Conducting capacity building workshop regarding forecasting and scheduling of RE.
35.5 MNRE had brought out OM dated 01.03.2018 (Annexure-LXXXII) on compliance of
WTG models to applicable CEA Technical standards for Connectivity to the Grid (as
amended from time to time) as stipulated in the MNRE Guidelines/procedure for Revised
List of Models and Manufacturers (RLMM). MS, SRPC vide letter dated 19.04.2018
(Annexure-LXXXIII) addressed to CEA had sought certain clarification wrt MNRE OM
dated 01.03.2018. Further, it was requested that the second amendment to Connectivity
Regulations may please be arranged to be notified at an early date.
35.6 A Meeting to discuss the OM was held at NIWE, Chennai on 23.04.2018 and the minutes
are available at SRPC website. The following was noted:
Status of LVRT testing facility
NIWE had informed that they were in the process of equipping themselves to test all
the provisions of CEA Regulations.
NIWE had informed that at present 21 models from 9 OEMs are having valid
Statement of Compliance (SoC)/Conformity Statement (CS) and figure in the
RLMM list. They are complying with the provisions of CEA Regulations.
A Comprehensive Indian Wind Turbine Certification Scheme was being prepared
and it would cover :
Type Certification
Wind Farm Project Certification
Life Assessment of Wind Turbine – Failure Analysis, Safety Assessment,
Residual Life Assessment, Life Extension & Decommissioning Procedure.
35.7 The forum had strongly felt that there was a need for enabling agency similar to NIWE to
ensure compliance of CEA Regulations for Solar generators since solar targets were
significant and the addition was rapid pace. Based on the recommendations, Chairperson,
SRPC vide letter dated 09.05.2018 (Annexure-LXXXIV) had taken up the issue of
effective implementation of provisions of CEA Regulations (including LVRT / HVRT)
and other security features to agencies like NISE (on similar lines of NIWE).
SRPC noted the above.
36 GRID OPERATION
36.1 Salient Achievements
Overarching Agreement was successfully implemented on 28.02.2018 between Kerala
and Karnataka.
Kudgi Unit-I was taken under RSD on 28.02.2018. This was for the first time that any
ISGS unit was taken under RSD. This would pave way for further RE integration.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 109
KGS-1 is operating continuously since 13.05.2016 (770 days as on 22.06.2018). It has
surpassed the earlier record (among NPCIL stations) for longest continuous run of 765
days set by RAPS-5. With this achievement, KGS-1 now stands second in the world
among Pressurized Heavy Water Reactors (PHWR) and fourth among all nuclear
power reactors in terms of continuous operation.
Kaiga GS PLF > 97.77% for the year 2017-18.
NTPC Ramagundam received the Golden Peacock Award on Energy Efficiency
Management in 20th
World Congress on Environment Management and Climate
Change at New Delhi on 06.07.2018.
NTPC officials visited Kothagaudem new station of TSGENCO to gain experience on
best utility practices as the unit was brought up in a compressed time schedule.
SEIL received the Golden Peacock Award for Environment Management for the year
2018 in 20th
World Congress on Environment Management and Climate Change at
New Delhi on 06.07.2018. Renewable energy arm Sembcorp Green Infra has also won
Greentech Gold Award.
Kolar HVDC Station completed two years of „Zero Tripping‟ & „Zero Forced Outage‟
as on 23.06.2106.As per CIGRE Reports, it is a World/Global Record.
Sembcorp (SEIL & SGPL thermal GS in SR) was biggest FDI in India with Installed
capacity of 4000 MW.
Ramagundam stage-I & II, Ramagundam stage-III, Neyveli stage-II and Neyveli TS-I
Expn. had achieved PAFs of > 90% during the year 2017-18.
Ramagundam stage-III and Talcher-II had achieved PLFs of > 85% during the year
2017-18.
On initiative of SRPC secretariat, SR got additional ramp of 262 MW/block from ISG
Stations.
36.2 Grid Highlights during February 2018
SR demand touched all time maximum of 45325 MW.
MVAR testing of SEIL and SGPL completed on 02nd
& 03rd
March 2018.
Revised ADMS settings were adopted by Kerala and Telangana also.
220/132 kV Gachibowli SS in Rangareddy district of existing 2 x 160 + 2 x 100 MVA
was commissioned on 19.02.2018 with augmented capacity of 3 x 160 + 1 x 100
MVA by TSTRANSCO.
220/132 kV Minpur SS in Medak district of existing 2 x 160 + 1 x 100 MVA was
commissioned on 21.02.2018 with augmented capacity of 3 x 160 MVA by
TSTRANSCO.
125 MVAR reactor at 400 kV Mamidipally SS was commissioned on 23.02.2018 by
TSTRANSCO.
4.6 MW of wind (private), 0.004 MW of Solar (state), 0.002 MW of Solar (private)
and 1.3 MW of biomass was commissioned in AP. 36 MW of Solar (private) and 11
MW of other RE was commissioned in TS. 14 MW of Solar (private) and 6 MW of
mini hydro was commissioned in Kerala. 29.4 MW of Wind (private) and 500.875
MW Solar (private) were commissioned in Karnataka.
36.3 Grid Highlights during March 2018
SR Demand touched all time maximum demand of 47210 MW
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 110
SR Consumption touched 1080 MUs.
LILO of 220 kV ADR Palem – Bobbli D/C line from loc. No.43 to proposed 400 kV
SS to Garividi in Vizianagaram district of 2 Ckm was commissioned on 15.03.2018
by APTRANSCO.
220 kV D/C line from 400 kV SS Gani to 220 kV SS Somayajulapalli in Kurnool
district of 34.6 Ckm was commissioned on 31.03.2018 by APTRANSCO.
220 kV SS Gundala in Krishna Dist of Existing 3 x 50 MVA was commissioned on
25.03.2018 by APTRANSCO with augmented capacity of 1 x 80 + 2 x 50 MVA.
220 kV D/C line with Moose conductor from 220/132 kV Narketpally SS to Udaya
Samudram 220/11 kV SS in Nalgonda dist of 18.18 Ckm was commissioned on
31.03.2018 by TSTRANSCO.
220 kV Chandrayagutta in Rangareddy Dist of existing 2 x 160 + 2 x 100 MVA was
commissioned on 20.03.2018 by TSTRANSCO with augmented capacity of 3 x 160 +
1 x 100 MVA.
Nelamangala-Yelahanka (39.006 Km) OPGW Fibre communication link of Central
Sector was put into service for commercial operation w.e.f 28.03.2018 by SR-II,
PGCIL.
Hoody-Yelahanka LILO point of Nelamangala – Hoody, Hoody-HSR (KPTCL),
Peenya-NRS-Hebbal (KPTCL), Hoody-HAL (KPTCL), LILO of Pondy –
Sriperumbadur to SV Chatram (TANTRANSCO), LILO of Neyveli TS-II – Neyveli
TS-I to NNTPS, Salem(PG) – Salem (TNEB) and Sriperumbadur (PG) to
Sriperumbadur (TNEB) OPGW Fibre links (98.484 Km) were put under commercial
operation w.e.f 28.03.2018 by SR-II, PGCIL.
1x 125 MVAR, 400 kV Bus Reactor along with its associated bays and equipments at
Tumkur (Pavagada) pooling station were put under commercial operation w.e.f 00:00
hrs of 31st March 2018 by SR-II, PGCIL.
1 x 500 MVA 400/230 kV ICT along with associated bays and equipment at
Tirunelveli 400/230 kV substation were put under Commercial Operation w.e.f 00:00
hrs of 31st
March 2018 by SR-II, PGCIL.
LILO of 400 kV D/C Bellary-Tumkur (Vasantnarsapur) (Quad Moose) TL at Tumkur
(Pavagada) pooling station along with associated bays and equipments were put under
Commercial Operation w.e.f 00:00 hrs of 31st March 2018 by SR-II, PGCIL.
1 x 500 MVA 400/230 kV ICT along with associated bays and equipment at
Karaikudi 400/230 kV substation were put under Commercial Operation w.e.f 00:00
hrs of 2nd
April 2018 by SR-II, PGCIL.
1 x 500 MVA 400/230 kV ICT along with associated bays and equipment at Arasur
400/230 kV substation were put under Commercial Operation w.e.f 00:00 hrs of 31st
March 2018 by SR-II, PGCIL.
136.4 MW of wind (private) and 3 MW of Solar (private) was commissioned in AP.
27.5 MW of Solar (private) was commissioned in TS. 190.175 MW of Wind
(private) was commissioned in TN. 203.5 MW of Wind (private) and 909.3 MW
Solar (private) were commissioned in Karnataka.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 111
36.4 Grid Highlights during April 2018
220 kV SS Parchur in Prakasam district of existing 3 x 100 MVA was commissioned
on 22.04.2018 by APTRANSCO with augmented capacity of 2 x 100 + 1 x 160
MVA.
220 kV D/C line from 400 kV Asupaka SS to 220 kV Aswaraopet SS in Khammam
dist of 40.282 Ckm was commissioned on 28.04.2018 by TSTRANSCO.
220/132 kV SS Aswaraopet (Upgradation of existing 132/33kV SS Aswaraopet) in
Khammam district with 100 MVA capacity was commissioned on 28.04.2018 by
TSTRANSCO.
220 kV Mandamari SS in Mancherial Dist of existing 2 x 100 MVA was
commissioned on 06.04.2018 by TSTRANSCO with augmented capacity of 3 x 100
MVA.
220 kV Chandrayanagutta SS in Rangareddy Dist of existing 3 x 160 + 1 x 100 MVA
was commissioned on 09.04.2018 by TSTRANSCO with augmented capacity of 4 x
160 MVA.
1 x 500 MVA, 400/220 kV ICT along with bays and equipment at Kozhikode
400/220 kV Substation were put under commercial operation w.e.f 00:00 hrs of 3rd
April 2018 by SR-II, PGCIL.
1 x 500 MVA transformer at 400/220 kV Narendra substation (replacement of
existing 2nd
1 x 315 MVA 400/220 kV transformer) was put under commercial
operation w.e.f 00:00 hrs of 16th
April 2018 by SR-II, PGCIL. It was informed that
the replaced 1 x 315 MVA transformer shall be utilized as a regional spare.
18 MW of wind (private) and 61.896 MW of Solar (private) was commissioned in
AP. 2.5 MW of Solar (private) was commissioned in TS. 22.5 MW of Wind (private)
was commissioned in TN. 4.5 MW of wind (private) and 58 MW of Solar (private),
was commissioned in Karnataka.
36.5 Grid Highlights during May 2018
187 MU of Wind generation recorded on 10.06.2018 in SR.
220 kV S/C line from Chakrayapeta to LILO point of 33/220 kV pooling SS in
Animala of 25.662 Ckm was commissioned on 19.05.2018 by APTRANSCO.
220 kV D/C line from Chakrayapeta to Talamanchipatnam in Kadapa dist of 174.396
Ckm was commissioned on 19.05.2018 by APTRANSCO.
220 kV D/C line for making LILO of existing one circuit of 220 kV Vemagiri to
Undiline at proposed 220/132/33 kV SS Duvva in West Godavari district of 0.64 Ckm
was commissioned on 27.05.2018 by APTRANSCO.
220/132/33 kV SS Duvva in West Godavari district with 116 MVA capacity was
commissioned on 27.05.2018 by APTRANSCO.
220/132/33 kV SS at Chakrayapeta in Kadapa district with 100 MVA capacity was
commissioned on 19.05.2018 by APTRANSCO.
220 kV SS Tekkali in Srikakulam district of existing 2x100 MVA was commissioned
on 16.05.2018 by APTRANSCO with augmented capacity of 3x100MVA.
400 kV Gajwel to Ramadugu I 129.529 Ckm was commissioned on 06.05.2018 by
TSTRANSCO.
400 kV Ramadugu to STPP I 67.909 Ckm was commissioned on 06.05.2018 by
TSTRANSCO.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 112
400 kV KTS – VII to Julurupadu I 39.08 Ckm was commissioned on 19.05.2018 by
TSTRANSCO.
400 kV KTS – VII to Julurupadu II 39.08 Ckm was commissioned on 19.05.2018 by
TSTRANSCO
400/220 kV Gajwel SS in Siddipet district of existing 3 x 315 MVA was
commissioned on 03.05.2018 by TSTRANSCO with augmented capacity of 3 x 315 +
1 x 500 MVA.
220/132 kV SS Gunrock in Hyderabad District of existing 2 x 160 MVA was
commissioned on 24.05.2018 by TSTRANSCO with augmented capacity of 3 x 160
MVA.
220/132 kV LI SS Huzurabad in Karimnagar Dist of PTR I 100 MVA capacity was
commissioned on 14.05.2018 by TSTRANSCO.
LILO of 400 kV S/C Nelamangala – Hoody Transmission Line, 2 x 500 MVA,
400/230 kV ICTs at new 400/220kV GIS Substation at Yelahanka with 1 x 63 MVAR
420 kV Bus Reactor, along with associated bays & equipments were put on COD
w.e.f 00:00 hrs of 1st April 2018 by SR-II.
2 x 400 kV D/C (Quad) Tirunelveli (Tuticorin II) PS - Tuticorin PS, 2 x 500 MVA,
400/230 kV transformers, 2 x 125 MVAR 400kV Bus Reactors along with associated
bays & equipment were put under Commercial Operation w.e.f 00:00 hrs of 10th
June
2018 by SR II.
12 MW of wind(private) and 4.004 MW of Solar (private) was commissioned in AP.
06 MW of solar (private) was commissioned in TS. 1.25 MW of solar (private) was
commissioned in Kerala. 50 MW of Solar (private) was commissioned in Karnataka.
36.6 Grid Highlights during June 2018
17 MW of wind (private) & 251 MW of Solar (private) was commissioned in Andhra
Pradesh, 27 MW of wind (private) was commissioned in Telangana, 90 MW of solar
(private) was commissioned in Karnataka, 8.849 MW of solar (private) was
commissioned in Kerala and 37.375 MW of wind (private) was commissioned in
Tamil Nadu.
Highest ever Wind generation of 223 MU recorded on 27.06.2018 in SR.
220 kV D/C line for making LILO of existing 220kV Nellore – Ongole line at
proposed 220/132 kV SS Racharlapadu in Nellore district of 16 Ckm was
commissioned on 07.06.2018 by APTRANSCO.
220 kV D/C line for making LILO of 132 kV Podili-Nellore to proposed 220/132 kV
SS Kandukur in Prakassam district of 107.4 Ckm was commissioned on 30.06.2018 by
APTRANSCO.
220/132/33 kV SS Racharlapadu I in Nellore district with 100 MVA capacity was
commissioned on 06.06.2018 by APTRANSCO.
220/132/33 kV SS Kandukur I in Prakasam district with 100 MVA capacity was
commissioned on 30.06.2018 by APTRANSCO.
400/220 kV SS Kalikiri II in Chittoor district with 315 MVA capacity was
commissioned on 18.06.2018 by APTRANSCO
220 kV SS Brandix (Idle charge) in Visag district of Existing 2 x 100 MVA was
commissioned on 28.06.2018 by APTRANSCO with augmented capacity of 3 x 100
MVA.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 113
400 kV Ghani II SS in Kurnool district of was commissioned on 28.06.2018 by
APTRANSCO with capacity of 125 MVAR.
220 kV Twin Moose DC/SC line from 400 kV Budidampadu SS (PGCIL) 500 MVA
PTR bay to 220 kV Budidampadu SS I 0.5 Ckm was commissioned on 14.06.2018 by
TSTRANSCO.
400 kV Gajwel to Narsapur II 48.6 Ckm was commissioned on 12.06.2018 by
TSTRANSCO
1 x 500 MVA, 400/230 kV ICTs along with associated bays and equipments at
400/230 kV Pondicherry Substation were put under Commercial Operation w.e.f 00:00
hrs of 22nd
June 2018 by SR-II.
1 no. 400/220 kV 500 MVA ICT III along with associated bays and equipment at
Khammam S/s & 1 no. 400/220 kV 500 MVA ICT III along with associated bays and
equipment at Warangal S/s were put under Commercial Operation w.e.f 00:00 hrs of
28th
June 2018 by SR-I.
1 no. 400/220 kV 500 MVA ICT III along with associated bays and equipment at
Gooty S/s was put under Commercial Operation w.e.f 00:00 hrs of 1st July 2018 by
SR-I.
36.7 Demand Variation (Peak Vs Off-peak)
Issue regarding large variation between minimum and maximum demands has been
under the consideration of TCC/SRPC. Issue is also being discussed in the monthly
Meetings of OCC. Following was observed with regard to the period from February
2018 to July 2018:
Description
Minimum to Maximum Demand Variation %
Andhra
Pradesh Telangana Karnataka Kerala
Tamil
Nadu Pudu
Southern
Region
February 2018
Highest 41.59 36.27 27.02 38.89 34.82 41.18 27.24
Date (Day) 02.02.2018
(Friday)
08.02.2018
(Thursday)
09.02.2018
(Friday)
05.02.2018
(Monday)
05.02.2018
(Monday)
05.02.2018
(Monday)
05.02.2018
(Monday)
Lowest 31.30 20.09 13.28 29.59 15.52 21.14 12.48
Date (Day) 10.02.2018
(Saturday)
25.02.2018
(Sunday)
25.02.2018
(Sunday)
24.02.2018
(Saturday)
25.02.2018
(Sunday)
11.02.2018
(Sunday)
25.02.2018
(Sunday)
Average 34.69 29.57 18.99 33.19 27.51 33.74 20.53
March 2018
Highest 35.05 45.69 29.40 37.66 30.14 42.13 23.39
Date (Day) 03.03.2018
(Saturday)
17.03.2018
(Saturday)
16.03.2018
(Friday)
31.03.2018
(Saturday)
19.03.2018
(Monday)
17.03.2018
(Saturday)
17.03.2018
(Saturday)
Lowest 22.24 11.38 11.48 25.04 9.27 19.41 9.17
Date (Day) 18.03.2018
(Sunday)
31.03.2018
(Saturday)
29.03.2018
(Thursday)
13.03.2018
(Tuesday)
25.03.2018
(Sunday)
28.03.2018
(Wednesday)
25.03.2018
(Sunday)
Average 28.40 19.99 17.27 30.56 21.29 29.40 15.14
April 2018
Highest 35.41 52.13 29.42 36.20 22.43 44.67 19.61
Date (Day) 24.04.2018
(Tuesday)
06.04.2018
(Friday)
22.04.2018
(Sunday)
04.04.2018
(Wednesday)
30.04.2018
(Monday)
25.04.2018
(Wednesday)
02.04.2018
(Monday)
Lowest 17.49 9.37 10.83 25.04 8.66 18.42 7.09
Date (Day) 29.04.2018
(Sunday)
15.04.2018
(Sunday)
14.04.2018
(Saturday)
13.04.2018
(Friday)
14.04.2018
(Saturday)
14.04.2018
(Saturday)
29.04.2018
(Sunday)
Average 25.19 21.22 17.99 30.32 14.52 27.55 13.67
May 2018
Highest 34.96 58.06 42.93 43.97 26.41 35.73 28.58
Date (Day) 01.05.2018
(Tuesday)
03.05.2018
(Thursday)
03.05.2018
(Thursday)
04.05.2018
(Friday)
29.05.2018
(Tuesday)
27.05.2018
(Sunday)
04.05.2018
(Friday)
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 114
Lowest 18.91 15.48 12.24 17.07 8.12 14.63 7.68
Date (Day) 05.05.2018
(Saturday)
24.05.2018
(Thursday)
01.05.2018
(Tuesday)
13.05.2018
(Sunday)
13.05.2018
(Sunday)
30.05.2018
(Wednesday)
06.05.2018
(Sunday)
Average 26.82 22.84 25.11 31.64 17.82 25.64 15.85
June 2018
Highest 29.13 31.43 37.00 48.05 26.35 44.26 25.62
Date (Day) 21.06.2018
(Thursday)
23.06.2018
(Saturday)
04.06.2018
(Monday)
12.06.2018
(Tuesday)
11.06.2018
(Monday)
15.06.2018
(Friday)
04.06.2018
(Monday)
Lowest 15.29 15.10 17.91 27.86 9.21 14.53 9.01
Date (Day) 12.06.2018
(Tuesday)
10.06.2018
(Sunday)
16.06.2018
(Saturday)
02.06.2018
(Saturday)
03.06.2018
(Sunday)
24.06.2018
(Sunday)
03.06.2018
(Sunday)
Average 21.92 23.02 25.68 36.23 17.65 24.43 16.48
July 2018
Highest 29.52 31.68 34.17 50.72 29.59 57.85 24.64
Date (Day) 29.07.2018
(Sunday)
18.07.2018
(Wednesday)
13.07.2018
(Friday)
17.07.2018
(Tuesday)
03.07.2018
(Tuesday)
16.07.2018
(Monday)
13.07.2018
(Friday)
Lowest 15.04 16.86 20.74 30.56 9.66 15.26 10.74
Date (Day) 11.07.2018
(Wednesday)
29.07.2018
(Sunday)
07.07.2018
(Saturday)
08.07.2018
(Sunday)
22.07.2018
(Sunday)
21.07.2018
(Saturday)
29.07.2018
(Sunday)
Average 20.74 24.78 26.58 37.93 19.18 25.29 18.10
Note: Highest & lowest figures for the month have been computed based on the daily
values.
36.8 Frequency of Operation of Southern Grid
Frequency of operation of the Southern Grid for the period under review is furnished
below please:
Month
Percentage of time when frequency (Hz) was Month
Avg.
freq.
Less
than
49.5
49.
5
to
49.
49.7
to
49.9
49.9
to
50.0
50.0
to
50.05
50.05
to
50.20
More
than
50.20
Within
IEGC
range
49.9 to
50.05
February 2018 0.00 0.00 9.68 53.15 27.00 10.17 0.00 80.15 49.98
March 2018 0.00 0.00 12.99 55.23 23.95 7.82 0.01 79.18 49.97
April 2018 0.00 0.02 12.74 53.66 25.72 7.86 0.00 79.37 49.97
May 2018 0.00 0.22 22.29 48.41 21.44 7.64 0.00 69.85 49.95
June 2018 0.00 0.13 11.71 46.60 30.07 11.46 0.03 76.66 49.98
July 2018 0.00 0.09 10.33 49.16 29.12 11.30 0.00 78.28 49.98
During the period under review, caution / violation messages (Annexure-LXXXV)
were issued to the constituents by SRLDC. Matter regarding overdrawal at low
frequency by some of the constituents is being regularly deliberated in the OCC
forum. Utilities were requested to kindly adhere to the Regulations in this regard.
In the OCC meetings, SRPC & SRLDC had pointed out that sustained violation of
reversal of sign was to be avoided for compliance of IEGC /DSM Regulations.
Regulation 6.4.6 of IEGC states „…………… Every regional entity shall ensure
reversal of sign of deviation from schedule at least once after every twelve time
blocks.‟ Regulation 7(10) of DSM Regulations states, „In the event of sustained
deviation from schedule in one direction (positive or negative) by any regional entity,
such regional entity (buyer or seller) shall have to make sign of their deviation from
schedule changed, at least once, after every 12 time blocks.‟
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 115
37 CERTIFICATION OF NON-ISTS LINE CARRYING INTER-STATE POWER FOR
THE YEAR 2018-19
As per provisions of CERC Regulations and as per the methodology approved in the 31st
Meeting of SRPC, SRPC Secretariat vide letter dated 20th
March 2018 (Annexure-LXXXVI)
has certified the non-ISTS lines carrying inter-state power for the year 2018-19. The studies
were done in close consultation with SRLDC.
TCC noted the above.
APTRANSCO vide letter dated 31.07.2018 (Annexure-LXXXVII) had stated that non-ISTS
lines carrying inter-state power of more than 50% of total power transmitted as per load flow
studies are only certified by SRPC for including in POC pool for recovery of YTC of the
lines. As per CERC (Sharing of Inter-state Transmission Charges and Losses) (3rd
amendment) Regulations, 2015, the cutoff 50 % has been removed. Hence, it was requested
to remove the cutoff percentage for certification for certifying of non-ISTS lines carrying
ISTS power.
TCC deliberations
APTRANSCO had stated that this would affect all the states and AP was affected
severely due to it being the entry point into SR due to geographical position. For any
new connection to ISTS, POC charges for AP increases. For the ISTS power of other
states, APTRANSCO should get to recover the associated charges through POC
mechanism. Many a times CTU is stating interconnectivity to STU for system
strengthening but the same is impacting the POC charges subsequently.
PCKL had pointed out that the landing points of 765 kV line in Karnataka also
contribute significantly towards POC charges for Karnataka.
TANGEDCO had endorsed the views of APTRANSCO and stated that the state network
is being utilized by the RE generators. The cutoff needs to be reduced from 50%.
It was noted that STU lines get constructed for evacuation of state power. When these
lines are connected to ISTS, there would be incidental flows as per laws of physics. One
way to view the matter would be to consider whether the other states would be able to
receive their power through ISTS lines if the state lines are taken out from studies.
Considering these issues it makes sense to put some threshold (say 50%) to recover the
YTC of intra-state lines through POC. If a state over designs its system, then the other
DICs may be burdened, in case no threshold is considered.
TSTRANSCO had observed that 50 % was fixed as per the recommendations of the CC
Meeting and approval of the TCC/SRPC. Most likely 50% was being considered in
other regions as cutoff and the same should continue in SR.
It was agreed that this issue would be discussed further in a separate Meeting.
SRPC noted the above and suggested that the issue could be further deliberated in a
separate meeting.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 116
38 EFFECT ON POC CHARGES ON ACCOUNT OF SCHEDULING WIND AND
SOLAR STATIONS BY RLDC
APTRANSCO vide letter dated 30.07.2018 (Annexure-LXXXVIII) had requested
deliberation on the effect on POC charges for any state in case RLDC does the scheduling of
RE power as per IEGC.
TCC deliberations
It was noted that there would be no effect on PoC charges in case the scheduling is taken
over by RLDC for RE generators.
SRPC noted the above.
39 MEMBERSHIP OF TRADER IN SRPC FOR THE YEAR 2018-19
CEA, New Delhi vide letter dated 9th
April 2018 (Annexure-LXXXIX) had communicated
that M/s. Mittal Processors Pvt. Ltd. would be the Member (Trader) in SRPC for the year
2018-19.
SRPC noted the above
40 REIMBURSEMENT OF SRPC EXPENDITURE
Statement showing net amount payable by Member Utilities of SRPC for the year 2018 -19,
after adjustment of surplus/deficit for the previous period is furnished in Annexure-XC.
Members were kindly requested to ensure payment, wherever due.
41 OPERATION OF HYDRO POWER PROJECTS IN PEAKING MODE
A special meeting was held at SLDC, KSEBL, Kalamassery on 13.04.2018 (MOM enclosed
at Annexure-XCI). In the 143rd
OCC meeting, the forum had concluded that the performance
of hydro stations cannot be assessed by means of any standard formats. In view of this, OCC
had unanimously agreed to drop the matter regarding monthly performance from the OCC
agenda since this issue had already been deliberated at length in various forums also.
SRPC noted the above.
42 RSD & TECHNICAL MINIMUM
42.1 KSEBL and TSTRANSCO had raised certain issues in respect of scheduling during RSD of
one of the units at Kudgi and these issues were discussed in detail in the OCC and CC
meetings. NLDC vide letter dated 06.04.2018 (Annexure-XCII) had proposed discussion on
RSD procedure in each of the RPC as noted in the approved RSD procedure. In the OCC
meeting, it was noted that NLDC had confirmed that the procedure being followed was in
line with the Regulations / Procedure. However, the concern of the states (TS/Kerala) would
be communicated to Hon‟ble CERC as they have sought comments on the TM / RSD
procedure and Compensation Mechanism. The states had also been requested to furnish their
views to NLDC on TM / RSD Procedure. SRPC vide letter dated 16.04.2018 (Annexure-
XCIII) had furnished its comments to Hon‟ble CERC. Subsequently, SRPC vide letter dated
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 117
05.07.2018 (Annexure-XCIV) had taken up the concern of SR states on RSD procedure
with Director (MO), POSOCO.
42.2 In the OCCM, NTPC, Kudgi had informed that the requirement of 35 hours to bring back the
Kudgi super critical unit from cold start under RSD would be taken up through NTPC
Corporate with NLDC / CERC.
42.3 The following was noted in the TCC Meeting:
TSTRANSCO had pointed out RSD decision is taken based on surrender but share
allocation on the requisitions and recall provision of 8 hours (8 hours of continuous
schedule) is not being factored in present methodology. The Procedure implementation
needs to be reviewed. This is a Procedure prepared by NLDC in consultation with
constituents and approved by CERC. The Commission could be apprised of the issue by
NLDC and the decision would be complied.
It was noted during periods when Karnataka is not requiring power they are scheduled
power as per the Onbar DC.
KSEBL had stated that RSD of Kudgi is getting reflected as a forced surrender by
Kerala. Karnataka when putting machines in RSD should be permitted only the share
available with the running unit after allocating the full share requested by other
constituents. Scheduling by cherry picking by availing the entire share when units are
put in RSD by one constituent should not be permitted.
TSTRANSCO and KSEBL had stated that NLDC needs to appropriately consider their
inputs in the feedback to Hon'ble CERC.
NLDC had stated that they would consider the remarks of TS and KSEBL. However it
requested TS and KESBL to kindly take up the issue independently also.
NLDC had once again clarified that the same procedure which is existing is being
followed in all the regions and is line with the procedure / regulations.
SRPC noted the above.
43 FREQUENT REVISION OF OUAGE PLAN BY ISG STATIONS
NTPC/NTECL had revised the annual outage plan for the FY 2018-19 in the month of April
2018 from the plan originally submitted. SRPC vide letter dated 16.04.2018 (Annexure-
XCV) had expressed concern that frequent changes in the annual outage plan have been well
deliberated in the earlier OCC /TCC meetings. Based on the outage plan furnished by the
generators and the MoP target, LGBR and the outage plan are prepared. These inputs are also
utilized by the states for their regulatory compliance, purchase planning etc. The need for
adhering to the outage plan was also highlighted.
SRPC noted the above.
44 COMPLIANCE OF CEA REGULATIONS FOR GRID CONNECTIVITY OF
RENEWABLE ENERGY SOURCES
44.1 CEA vide letter dated 12.04.2017 and 08.05.2017 (enclosing MoP letter dated 06.04.2017)
and in Special Meetings held on 28.06.2017 and 11.09.2017 had observed that it was
obligatory for all grid connected renewable generators to provide necessary facilities for data
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 118
communication and data storage and other parameters as may be stipulated. It had been
decided by CEA that respective states would submit weekly reports of data communication
status to CEA as well as to respective RPC / RLDC and NLDC. The issue had been further
discussed in the 4th
Meeting of LVRT / RE issues held on 25th
October 2017 at SRPC,
Bengaluru. (Minutes available on SRPC website). The following is updated status with
regard to availability of RE SCADA:
State SCADA availability as on
31.07.2018 Mapped I/C
Remarks
AP Wind: 3908/4009 MW (97%)
Solar: 2033/2518 MW (81%)
Total: 5941/6527MW (91%)
Pending SCADA availability was for
RE connected distribution level and
for which action had been taken for
compliance.
TS Wind: 121.8/121.8 MW (100%)
Solar: 3075/3319 MW (93%)
Total: 3203/3448 MW (93%)
Action for balance SCADA
availability at 33 kV and below was
being followed up and notices had
been issued.
KA Wind: 4751/4795 MW (99%)
Solar: 4602/5093 MW (90%)
Total: 9353/9888 MW (94.59%)
KE Wind: 16/59.3 MW (27%)
Solar: 93/111 MW (83%)
Total: 109/170.3 MW (64%)
TN Wind: 8090/8255 MW (98%)
Solar: 648/2278 MW (28%)
Total: 8738/10533 MW (89%)
Notices had been issued for SS under
10(1) for SCADA availability. 100%
SCADA availability of wind was
likely to be ensured by December
2017. TANTRANSCO
(Communication) and TANGEDCO
(Metering) had jointly initiated action
for Solar SCADA availability and was
targeted to be completed by July 2018.
44.2 A Meeting regarding “Furnishing Real Time/Daily Renewable Energy Generation Data”
was held at Jaipur, Rajasthan on 04.05.2018 under the Chairmanship of Member
(Planning), CEA (MOM is available at Annexure-XCVI). In the meeting, it was decided
that the status of the pooling stations having data communication would be ascertained and
the percentage of availability of communication link/system should be monitored and
reported on a weekly basis. States had agreed to follow the same.
SRPC noted the above. States were requested to furnish the information in a time bound
manner.
44.3 In respect of REMC project (SRLDC, AP, Karnataka & TN) it had been noted that
sanction of GoI had been received during September 2017 and implementation schedule
was of 14 months. The effective date of contract is 29.01.2018 (Awarded to M/s
Chemtrols/OSI (JV), date of Award is 29.09.2017) with completion schedule of 14 months
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 119
(29.03.2019). The following is the updated status (as on 05.07.2018):
a) Site survey of Control Centres is completed and the Control Centre buildings of
KPTCL & APTRANSCO are expected to be ready by October 18.
b) Database & display building is expected to be completed by August 18 for the
stations envisaged under the project (TN-140, AP-48, KAR-78 & SRLDC-5)
c) ICCP testing successfully completed with SCADA systems of RLDC & SLDCs for
the integration of RE stations reporting to existing SCADA systems.
d) Vendor is finalized for forecasting & scheduling services.
e) Engineering activities are in progress and expected to be completed by August 18.
f) Supplies (SCADA hardware & Software and Video projection displays) are expected
to resume from end October 18 and total commissioning is expected by Jan 19.
g) Training programs on RE introduction, System administration, system software &
Historian & Application software are completed and course on RE forecasting &
scheduling is proposed in August 18.
SRPC noted the above.
45 SCHEDULING OF ANANTHAPURAMU ULTRA MEGA SOLAR PARK /
RAMAGUNDAM SOLAR PROJECT
45.1 In the Meeting held on 15.06.2018, it was agreed that the complete share of 10 MW of
Ramagundam Solar Power project would be availed by Telangana (including 6 MW
presently allocated to AP) along-with 10 MW from unallocated power of coal based NTPC
stations of SR (MoM available on SRPC website). The same was implemented from
01.07.2018 after the concurrence from CEA.
45.2 In the special meetings held on 02.05.2018 and 08.05.2018, it was agreed that scheduling of
Ananthapuramu Ultra Mega Solar Park (1500 MW) would be carried out by SRLDC.
SRPC vide letter dated 10.05.2018 (Annexure-XCVII) had communicated the activities of
the SPDs and SPPD.
45.3 Further, to have clarity on issues, SRPC vide letter dated 25.05.2018 (Annexure-XCVIII)
had communicated the feedback on Procedure for implementation of the Framework on
forecasting, scheduling and in balance handling for Renewable Energy (RE) generating
stations including power parks based on wind and solar at inter-state level with CERC.
45.4 NTPC vide letter dated 09.07.2018 (Annexure-XCIX) had raised certain issues on metering
and scheduling of Ananthapuramu Ultra Mega Solar Park. SRPC Secretariat vide letter
dated 30.07.2018 (Annexure-C) had replied to the queries raised by NTPC.
45.5 The following had been noted in the TCC Meeting:
It was agreed that SPDs would complete all the requirements as communicated by
SRLDC.
APSPCL had informed that Meters are to be replaced with compatible Meters by the
SPDs. SPDs till now are not aware of the deviation charges/financial implications and
some trial period may be required.
It was noted that similar RE framework was already implemented in AP. APTRANSCO
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 120
informed that from 01.07.2018 accounts will be issued within one week.
Mock exercise would be taken up from 1st September to 10
th September 2018.
From 11th
September 2018, scheduling would be carried out by SRLDC. Entire
compliance would be ensured by SPDs.
NTPC committed for the mock exercise and also scheduling by SRLDC as per the above
time schedule.
45.6 The following was noted in the SRPC meeting:
MD, APSPCL informed that on 23.08.2018, a meeting with Developers was planned at
Bengaluru and issues would be resolved. He assured that the time lines finalized in this
Meeting would be adhered.
SRPC noted that the scheduling of Ananthapuramu Ultra Mega Solar Park by SRLDC
would be undertaken with commercial settlement and as per RE procedure from
11.09.2018.
46 KARAIKAL DRAWAL
Karaikal would be drawing power through LILO of Neyveli-Bahour which is a PGCIL ISTS
line. SR-II had been kindly requested to update on the readiness along with the proposal ( hot
line crossing) for LILO works, especially in view of the fact that line crossing of generation
evacuation line (ILFS) is involved.
SR-II confirmed that the crossing would be taken using hot line crossing techniques.
47 GRID STUDY COMMITTEE (GSC) MEETINGS ON PACKAGE-A & PACKAGE-B
MoP (GoI) has constituted a "Task force on Power System Analysis under Contingencies" in
December 2012 as a follow up of the recommendations of Enquiry Committee under
Chairperson, CEA on Grid Disturbances of 2012 in Indian Grid.
The Task Force broadly made recommendations regarding analysis of the network behaviour
under normal as well as contingency scenarios, review of the philosophy of operation of
protection relays, review of islanding schemes and technological options to improve the
performance of the grid. To ensure secure and reliable operation of the National Grid and also
for optimizing the transfer of power through the Inter-regional lines/corridors, it was also
found necessary to review the criteria related to Transfer Capability of these lines/corridors
through a consultant.
With the above objectives, MOP directed POWERGRID to appoint Consultants to conduct the
study/ analysis to ensure secure and reliable operation of the National Grid. MOP also directed
that a Grid Study Committee comprising of members from CEA, CTU, STUs, POSOCO & other
members as required, would be constituted to facilitate the consultant‟s study/analysis.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 121
Accordingly, the Terms of Reference (TOR) were prepared by POWERGRID in consultation
with CEA and POSOCO. The works were undertaken in two separate packages:
Package-A: To review the status of implementation of recommendation of Enquiry Committee
on Grid Disturbance and Protection Audit: Awarded to M/s Tractebel Engineering, Romania.
The consultancy assignment for Package A comprised two Tasks as follows:
Task - I: To study and review the status of implementation of recommendations of the
Enquiry Committee.
Task - II: To conduct on site Protection audit check of the works already carried out, for
10% (76 nos.) of 762 Substations across the country after grid failure of July 2012.
Package-B: To review transmission system transfer capability and review of operational and
long term planning: Awarded to M/s Powertech Lab Inc. (PLI), Canada. The consultancy
assignment for Package-B comprised six Tasks as follows:
Task-I: Examination and Recommendation of Methodology for Optimum Calculation of
Transfer Capability (TIC/ATC/TRM) in the Planning and the Operational Horizons.
Task -II: Calculation of Transfer Capability (TIC/ ATC/TRM) for entire country.
Task-III: Guidelines for developing and implementing System Protection Scheme (SPS)
and Islanding schemes and review existing schemes.
Task-IV: Operational Planning and Long-term planning for secure and efficient operation
of the grid.
Task-V: Suitable suggestions in the Regulatory framework to ensure Secure and efficient
grid operation.
Task-VI: To review the tuning of all Power Electronic Devices (including FACTS and
HVDC) and suggest retuning of setting of these devices, as per report of Task Force.
The Grid Study Committee (GSC), which was constituted to facilitate the consultant's study/
analysis, had so far held five meetings (GSC-1 on 22.05.2015; GSC-2 on 16.07.2015; GSC-3 on
18.11.2015).
GSC in the 4th
Meeting held on 16.01.2018 (its minutes issued vide NPC letter dated 01.03.2018
were circulated to SR-Constituents along with the minutes of PCSC-72 meeting issued vide
SRPC letter dated 13.04.2018), accepted the following reports:
Reports of the Consultant M/s Tractebel Engineering on Task I & II under Package A.
Reports of the Consultant M/s Powertech Labs Inc. on Task I, II & III under Package B.
GSC in the 5th Meeting held on 18.06.2018 (minutes issued vide NPC letter dated 26.06.2018
were circulated to SR-Constituents along with the minutes of PCSC-75 meeting issued vide
SRPC letter dated 17.07.2018), accepted the following reports:
Reports of the Consultant M/s Powertech Labs Inc. on Task IV, V & VI under Package
B.
As decided in the GSC-5 meeting, an action plan for implementation of various
recommendations for all Tasks under Package-A & Package-B is under finalization by CEA
in consultation with CTU & POSOCO. After finalization, the same would be made available
to SR-Constituents for appropriate action, please.
SRPC noted the same.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 122
48 OVR Grading of 400 kV and 765 kV Transmission Lines of Southern Region
In the past one year, a number of new 400 kV and 765 kV transmission lines have been added
to SR-Grid in addition to reconfiguration (including LILO) works of the existing 400 kV and
765 kV transmission lines. In this regard, a comprehensive exercise of OVR grading for
400 kV and 765 kV transmission lines of Southern Region (existing as on March, 2018) has
been carried out, and the new OVR Gradings proposed to be adopted for these lines (along
with study results) had been circulated to all Constituents for modifications/ omissions/
comments. After duly incorporating Constituents' comments, the final OVR gradings to be
adopted for 400 kV and 765 kV lines in the Southern Region had been issued vide SRPC letter
dated 01.05.2018 for implementation with immediate effect. The above OVR gradings have
also been kept in SRPC Website for easy reference.
49 COMPLIANCE OF CERC (COMMUNICATION SYSTEM FOR INTER-STATE
TRANSMISSION OF ELECTRICITY), REGULATIONS 2017
49.1 A Special Meeting was held on 08th
May 2018 at SRPC, Bengaluru (Minutes available on
SRPC website) on compliance of CERC (Communication System for inter-State
Transmission of Electricity) Regulations, 2017 which had come into force w.e.f. 01.07.2017.
There were two activities assigned for RPCs - periodic auditing of communication system
and ensuring cyber security third party audits. Audit procedure (Annexure-CI) had been
finalized in that Meeting and the same is put up for kind approval of the TCC/SRPC. All the
entities had agreed for annual periodicity (FY) for Cyber Security Audit.
49.2 A Sub Group Meeting to finalize the guidelines for Cyber Security Audit was conducted on
13th
June 2018. Further on the request of the constituents, a guiding Code for Cyber Security
audit (Annexure-CII) has been prepared in consultation with the stake holders and circulated
to all the constituents.
49.3 The following had been noted in the TCC Meeting:
TCC had recommended the Audit procedure for implementation.
TCC had recommended for annual periodicity (FY) for Cyber Security Audit and noted
Cyber Security guideline.
49.4 SRPC approved the TCC recommendations.
50 SPECIAL MEETING ON THE TRIPPINGS OF POLES - 1 & 2 AT HVDC
GAJUWAKA SS OF POWERGRID (SRTS-I)
A Special Meeting was held on 02nd
April, 2018 at RHQ POWERGRID (SRTS-I), Hyderabad
to deliberate on all outstanding issues involved in the recent HVDC Gajuwaka Pole trippings -
esp. two categories of trippings that occurred in the past one year - viz., Pole-1 trippings on
A.C. auxiliary supply failure and Pole-2 trippings on ferro-resonance detection. The following
issues were discussed in the meeting:
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 123
Deliberations on HVDC Pole trippings in the past one year
Resolution of Issues w.r.t. Pole-1 Trippings (ALSTOM make)
Resolution of Issues w.r.t. Pole-2 Trippings (ABB make)
Compliance of Protection Audit Recommendations (PAR) pertaining to Gajuwaka (HVDC
& HVAC) Substation
The issue had also been raised in the Operational Feedback (Jan-Mar 2018) by POSOCO. The
minutes of the meeting were circulated vide SRPC letter dated 11.04.2018.
In this regard, the compliance status furnished by PGCIL (SRTS-I) w.r.t. various measures
suggested [copy enclosed at Annexure – CIII] was reviewed in the PCSC-76 meeting held on
26.07.2018. It was noted that necessary action had been taken by PGCIL (SR-I) in attending to
issues relating to (i) Pole-1 trippings on AC auxiliary supply failure, and (ii) Pole-2 trippings
on Ferro-resonance detection [short-term & medium-term]. Similarly, as agreed in the special
meeting, PGCIL (SR-I) was also requested to kindly initiate necessary action, as a long-term
measure for avoiding pole trippings under ferro-resonance conditions, to undertake necessary
refurbishment works of controller protections at Jeypore end for detecting ferro-resonance
locally at FSC location (Jeypore end) and effect automatic by-passing of FSCs by putting
necessary infrastructure in place at Jeypore end.
51 SPECIAL MEETING ON THE PENDING PROTECTION ISSUES OF
PUDUCHERRY SUBSTATIONS
A Special Meeting was held on 20th
July, 2018 at Puducherry ED HQ to deliberate on all
outstanding protection issues involving Puducherry substations. The following issues were
discussed in the meeting:
Root-cause Analysis of the Villianur GD‟s on 30.05.2018, 05.06.2018 & 15.06.2018
Review of status of implementation of Protection Audit Recommendations of Villianur and
Bahour Substations.
Review of compliance status of the recommendations given in the special meeting held
on 3rd
January, 2017 w.r.t. Neyveli Grid Disturbance on 25.11.2016.
The minutes of the meeting were circulated vide SRPC letter dated 30.07.2018. PED was
requested to kindly take appropriate action w.r.t. measures suggested/ recommended and
ensure that protection systems in place at their substations are maintained in healthy
condition.
52 UPCOMING RENEWABLE PROJECTS AND THEIR INTEGRATION WITH
TRANSMISSION NETWORK
52.1 In the earlier Meetings it was noted that RE schemes are getting modified at times while
some are getting dropped also. TCC had suggested that the RE Projects/evacuation schemes
may kindly be reviewed and updated status communicated. It was observed that timely
progress on these schemes needs to be communicated to SRPC Secretariat, being a critical
issue monitored by various bodies.
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 124
52.2 Transmission scheme for Wind Energy Zones (WEZs) in Southern Region
In the 42nd
SCPSPSR, representative of POWERGRID stated that Govt of India has set an
ambitious target for 175GW renewable capacity by 2022, out of which 60 GW is envisaged
to be set up through wind power projects. In view of the wind capacity expansion plan as
well as connectivity applications received in ISTS for wind capacity & SECI bids, it is
expected that wind capacity may cross the milestone of 60 GW in next 3-4 years. SECI has
already bid 6050 MW ISTS connected wind bids (awarded-4050 MW) and planning to bid
10,000 MW in FY18-19. Therefore, there is a requirement of development of ISTS
infrastructure in wind rich pockets. To identify actual developable wind potential by 2022,
several rounds of discussions were held with MNRE & other stakeholders. Further, wind
energy zones along with projected capacity in each WEZ were identified, which may come
up by 2022 in wind resource rich states were prioritized. Accordingly, five WEZs viz.
Koppal (2,500 MW) in Karnataka, Kurnool (3,000 MW) in Andhra Pradesh, Karur (2,500
MW) in Tamil Nadu, Dwarka (2,000 MW) in Gujarat and Osmanabad (2000 MW) in
Maharashtra were identified for which ISTS substation/infrastructure was decided to be
developed/made available.
After deliberations, it was decided that due to large scale integration of renewable
generation in SR, detailed study considering the proposals of renewable rich states of SR
and CTU need to be carried out. The results of the study would be discussed in joint study
meeting.
Joint System Study Meeting of SR was conducted on 10th
& 11th
May 2018 at SRPC,
Bengaluru (refer Annexure-XL)
Comments furnished by TANTRANSCO are enclosed at Annexure-CIV.
SRPC noted the above.
53 PATROLLING / MAINTENANCE OF CRITICAL LINES AND SUBSTATIONS
53.1 Insulator tracking had been observed in Transmission lines and Substations located in the
coastal and polluted areas. SRPC vide letter dated 05th
May 2016 had communicated to the
concerned in this regard. Transmission Lines and Substations in the most vulnerable
terrain, coastal and polluted areas were to be categorized for monitoring to ensure that
Patrolling and Maintenance is being carried out as per Patrolling guidelines.
53.2 Concerned entities need to kindly initiate/continue necessary steps to ensure that Patrolling
and Maintenance is carried out regularly as per the Patrolling Guidelines.
53.3 SRPC noted the above
54 ROSTER FOR HOSTING THE SRPC MEETINGS
As per the roster the SRPC meetings are to be hosted in the following sequence:
Minutes of the 34th Meeting of SRPC held on 11.08.2018 Page 125
(1) UPCL (2) JSWEL (3) NPCIL (4) SGPL
UPCL agreed to host the next SRPC Meeting.
55 CONLCUSION
Chairperson, SRPC thanked all the participants for lively deliberations. On a number of
issues consensus had been arrived while on some other issues, further action like having
special meeting or further deliberations may be required. It shows that SR is a vibrant
region in power sector. Wherever support from MoP, CERC, CEA, Railways and Coal
companies is required the issues are being flagged to them. He opined that Railway Board,
MCL, SCCL and other coal companies need to kindly understand the issues being faced at
the generating end. In addition, the wind and solar power was becoming a reality over a
period of time and thus APSPCL had been requested to be part of the meeting to be
appraised of the grid requirements. IWPAI had also requested to participate in the Meeting
as a special invitee and they are present here. The entire sector from thermal, hydel, RE and
transmission had been discussed and the forum had tried to resolve the issues. He thanked
all for their active participation and support in strengthening the SRPC. He once again
thanked PGCIL for making excellent arrangements.
56 DATE & VENUE OF THE NEXT MEETING OF SRPC
The date and venue would be finalized in consultation with Chairperson, SRPC.
**********************