Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
August 2013
Consultation Report Doc.No. F-STC-RP-004
Pursuant to Section 37(3)(c) of the Planning Act 2008 Application reference: 5.1
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 © 2013 Forewind Consultation Report Page ii
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 © 2013 Forewind Consultation Report Page iii
Document Title Dogger Bank Creyke Beck
Consultation Report
Forewind Document Reference F-STC-RP-004 Issue 3
Date August 2013
Drafted by Nikki Young
Checked by Melissa Read / Andrew Riley
Date / initials check 19-Jul-2013 MR/AR
Approved by
Date / initials approval
Forewind Approval Mark Thomas
Date / Reference approval 21-Aug-2013 MT
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 © 2013 Forewind Consultation Report Page iv
Title: Dogger Bank Creyke Beck Consultation Report
Contract No. (if applicable) Onshore / Offshore
Document Number: F-STC-RP-004
Issue No: 3
Issue Date: 19-Jul-13
Status: Issued for 1st. Technical Review Issued for 2nd. Technical Review
Issued for PEI3 Issued for Application Submission
Prepared by: (Forewind)
Nikki Young
Checked by: (Forewind) Melissa Read / Andrew Riley
Approved by: Mark Thomas
Signature / Approval meeting
Mark Thomas
Approval Date: 21-Aug-2013
Revision History
Date Issue No. Remarks / Reason for Issue Author Checked Approved
22-Oct-12 1 Issue for 1st.Technical Review NS NS -
4-Apr-13 2 Issued for Approval NY MR/AR MT
19-Jul-13 3 Issued for technical review post PEI3 NY MR/AR MT
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 5 © 2013 Forewind
Contents
1 Executive summary ..................................................................................................... 15
2 Introduction ................................................................................................................. 17
2.1 Policy Context ................................................................................................... 17
2.2 Structure of this consultation report .................................................................. 18
2.3 Forewind ........................................................................................................... 19
2.4 Dogger Bank Zone ............................................................................................ 19
2.5 Project background ........................................................................................... 20
2.6 Overview of the consultation process ............................................................... 20
3 Section 42 consultation process ................................................................................. 25
3.1 Section 42 consultees ....................................................................................... 25
3.2 Identification of the prescribed consultees ........................................................ 25
3.3 Identification of the relevant local authorities .................................................... 26
3.4 Identification of landowners and others with an interest in the land .................. 29
3.5 Two stages of statutory consultation ................................................................. 30
3.6 First stage of statutory consultation .................................................................. 31
3.7 Second stage of statutory consultation ............................................................. 32
4 Section 47 consultation process ................................................................................. 34
4.1 Summary of the SoCC rationale ....................................................................... 34
4.2 Consultation on the content of the draft SoCC .................................................. 35
4.3 Publication of the SoCC .................................................................................... 35
4.4 First stage of statutory community consultation ................................................ 37
4.5 Second stage of statutory community consultation ........................................... 38
4.6 Compliance with the SoCC commitments ......................................................... 39
4.7 Additional community consultation activities undertaken .................................. 41
5 Section 48 publicity ..................................................................................................... 43
5.1 Legislative context ............................................................................................ 43
5.2 Publications and timing ..................................................................................... 43
5.3 Content of the notice ......................................................................................... 44
5.4 Relevant responses to Section 48 publicity ...................................................... 44
6 Non-statutory consultation .......................................................................................... 45
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 6 © 2013 Forewind
6.1 Non-statutory consultees .................................................................................. 45
6.2 Non-statutory consultation process ................................................................... 45
6.3 Fisheries liaison ................................................................................................ 47
7 Consultation under the EIA and Habitats Regulations ................................................ 49
7.1 Introduction ....................................................................................................... 49
7.2 Scoping ............................................................................................................. 49
7.3 Transboundary consultation .............................................................................. 50
7.4 Habitats Regulations Assessment .................................................................... 51
8 Summary of relevant responses ................................................................................. 53
8.1 Introduction ....................................................................................................... 53
8.2 General comments ............................................................................................ 53
8.3 Health and Safety ............................................................................................. 54
8.4 EIA Process (ES Chapter 4) ............................................................................. 55
8.5 Project description (ES Chapter 5) .................................................................... 56
8.6 Site selection and alternatives (ES Chapter 6).................................................. 58
8.7 Consultation (ES Chapter 7) ............................................................................. 60
8.8 Designated sites (ES Chapter 8) ....................................................................... 62
8.9 Marine physical processes (ES Chapter 9) ....................................................... 63
8.10 Marine Water and Sediment Quality (ES Chapter 10) ...................................... 65
8.11 Marine and Coastal Ornithology (ES Chapter 11) ............................................. 65
8.12 Marine and Intertidal Ecology (ES Chapter 12) ................................................. 67
8.13 Fish and shellfish ecology (ES Chapter 13) ...................................................... 69
8.14 Marine Mammals (ES Chapter 14) .................................................................... 70
8.15 Commercial fisheries (ES Chapter 15) .............................................................. 72
8.16 Shipping and Navigation (ES Chapter 16) ........................................................ 74
8.17 Other Marine Users (ES Chapter 17) ................................................................ 75
8.18 Marine and Coastal Archaeology (ES Chapter 18) ........................................... 77
8.19 Military Activities and Civil Aviation (ES Chapter 19) ........................................ 79
8.20 Seascape and Visual Character (ES Chapter 20) ............................................. 80
8.21 Landscape and Visual (ES Chapter 21) ............................................................ 81
8.22 Socio-economics (ES Chapter 22) .................................................................... 82
8.23 Tourism and recreation (ES Chapter 23) .......................................................... 83
8.24 Geology, Water Resources & Land Quality (ES Chapter 24) ............................ 84
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 7 © 2013 Forewind
8.25 Terrestrial Ecology (ES Chapter 25) ................................................................. 85
8.26 Land Use and Agriculture (ES Chapter 26) ....................................................... 86
8.27 Onshore cultural heritage (ES Chapter 27) ....................................................... 87
8.28 Traffic and Access (ES Chapter 28) .................................................................. 88
8.29 Noise and Vibration (ES Chapter 29) ................................................................ 90
8.30 Air Quality (ES Chapter 30)............................................................................... 91
9 Statements of common ground ................................................................................... 92
10 Conclusion .................................................................................................................. 94
Annex 1 – Compliance checklist ........................................................................................ 95
Table of Tables
Table 2.1 Overview of consultation activities .......................................................... 23
Table 3.1 Local authorities identified in accordance with section 43 ....................... 26
Table 4.2 Publications in which Forewind published the SoCC .............................. 36
Table 4.3 Compliance with SoCC commitments ..................................................... 39
Table 4.4 Elected representative engagement activities ......................................... 42
Table 5.1 Section 48 notices – publication details................................................... 43
Table 6.1 Examples of conferences at which Forewind presented ......................... 46
Table 9.1 Statements of common ground currently in progress .............................. 92
Table of Figures
Figure 2.1 Zone development process .................................................................... 21
Figure 2.2 Multi stage project consultation process ................................................ 22
Figure 3.1 Section 43 - Local Authority Map ........................................................... 28
Table of Appendices
Appendix A Stakeholder Engagement Plan
Appendix B Fisheries Liaison Plan
B1 Fisheries Liaison Plan (2011)
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 8 © 2013 Forewind
B2 Fisheries Liaison Plan (2013)
Appendix C Consultees
C1 EIA Regulation 9 list of consultees
C2 List of prescribed consultees (Sections 42(1) (a), (aa) and (b)
C3 Ofgem lists of electricity and gas licence holders
C4 First landowner questionnaire
C5 Second landowner questionnaire
C6 Unregistered land site notices and location map
C7 List of non-statutory consultees
Appendix D Section 42 cover letters (stage 1 consultation)
D1 15.11.2011 S42 and non-stat pre-notice of exhibitions
D2 31.11.2011 S42 and non-stat notice of start of consultation
D3 06.12.2011 S42 and non-stat confirmation that stakeholder can access documents online
D4 15.11.2011 Landowner pre-notice of exhibitions
D5 07.12.2011 Landowner notice of start of consultation
Appendix E Section 42 cover letters (stage 2 consultation)
E1 06.12.2012 Hard copy request letter
E2 14.03.2013 S42 and non-stat advance notice letter
E3 16.04.2013 Cover letter to Planning Inspectorate
E4 16.04.2013 Cover letter to S42 and non-stat
E5 03.04.2013 Pre-notice letter to S42(1)(d)
E6 16.04.2013 Cover letter to S42(1)(d)
E7 Additional S42d consultation cover letter
E8 Landowner factsheet
Appendix F Statement of Community Consultation (SoCC)
F1 SoCC Consultation cover letters
F2 SoCC Consultation Document
F3 Relevant responses to the SoCC Consultation
F4 The published SoCC
F5 Copies of the SoCC newspaper notices
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 9 © 2013 Forewind
F6 List of libraries where the SoCC was made available
F7 12.12.2012 Letter about one DCO application
F8 Letters to consultees regarding final SoCC
Appendix G Section 47 stage 1 consultation materials
G1 14.11.2011 Elected representative invitation
G2 15.11.2011 Community consultee invitation
G3 17.11.2011 Press release about forthcoming exhibitions
G4 Press coverage of public exhibitions
G5 Poster
G6 Library list
G7 Exhibition panels
G8 Community consultation summary leaflet
G9 Questionnaire
G10 Freepost response card
Appendix H Section 47 stage 2 consultation materials
H1 19.04.2013 Elected representative invitation
H2 22.04.2013 Community consultee invitation
H3 Press releases
H4 Press coverage
H5 Poster
H6 Library list
H7 Exhibition panels
H8 Community consultation summary leaflet
H9 Questionnaire
H10 Electric and Magnetic Fields Factsheet
Appendix I Newsletters
I1 Dogger Bank News
I2 Fishing News
Appendix J Converter Station Community Working Group
J1 15.02.2012 ERYC email regarding the SoCC
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 10 © 2013 Forewind
J2 Terms of reference
J3 List of members
J4 Press releases
J5 08.03.2012 Meeting One materials
J6 03.05.2012 Meeting Two materials
J7 25.10.2012 Meeting Three materials
J8 25.04.2013 Meeting Four materials
J9 Agreement to close group
Appendix K Section 48 notices
K1 Section 48 Notice
K2 Copies of the Section 48 newspaper notices
Appendix L EIA Regulation 24 notice
L1 EIA Regulation 24 notice
L2 EIA Regulation 24 letter from the Planning Inspectorate
L3 15.11.2012 Minutes of meeting with the Planning Inspectorate
L4 EEA States‘ responses to Regulation 24 notice
Appendix M Relevant response tables
M1 Responses to consultation on the content of the SoCC
M2 Landowner route alignment requests
M3 Responses relating to health and safety
M4 ES Chapter 4 – EIA process
M5 ES Chapter 5 – project description
M6 ES Chapter 6 – site selection and alternatives
M7 ES Chapter 7 - consultation
M8 ES Chapter 8 – designated sites
M9 ES Chapter 9 – marine physical processes
M10 ES Chapter 10 – marine water and sediment quality
M11 ES Chapter 11 – marine and coastal ornithology
M12 ES Chapter 12 – marine and inter-tidal ecology
M13 ES Chapter 13 – fish and shellfish
M14 ES Chapter 14 – marine mammals
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 11 © 2013 Forewind
M15 ES Chapter 15 – commercial fisheries
M16 ES Chapter 16 – shipping and navigation
M17 ES Chapter 17 – other marine users
M18 ES Chapter 18 – marine and coastal archaeology
M19 ES Chapter 19 – military activities and civil aviation
M20 ES Chapter 20 – seascape visual character
M21 ES Chapter 21 – landscape and visual
M22 ES Chapter 22 – socio-economics
M23 ES Chapter 23 – tourism and recreation
M24 ES Chapter 24 – geology, water resources and land quality
M25 ES Chapter 25 – terrestrial ecology
M26 ES Chapter 26 – land use and agriculture
M27 ES Chapter 27 – terrestrial archaeology
M28 ES Chapter 28 – traffic and access
M29 ES Chapter 29 – noise
M30 ES Chapter 30 - air quality
Appendix N Other communication records
N1 April 2010 ZAP Workshops - facilitator‘s report
N2 List of commercial communications with landowners
N3 18.05.2011 Ornithology meeting
N4 07.09.2011 IPC Meeting regarding need to repeat Scoping
N5 22.09.2011 ERYC approval of community consultation area
N6 26.01.2012 Workshop on selection of converter stations site
N7 14.02.2012 JNCC and Natural England meeting
N8 01.03.2012 JNCC Meeting regarding need to repeat Scoping
N9 April 2012 Offshore EIA Workshop
N10 19.04.2012 Shipping and Navigation Hazard Workshop
N11 August 2012 Parish Council Workshops
N12 Example letter to EEA state on trans boundary effects and HRA
N13 09.09.2012 Archaeology Workshop
N14 11.03.2013 HRA Screening meeting
N15 24.04.2013 Round table meeting with ERYC
N16 June 2013 Offshore EIA Workshop
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 12 © 2013 Forewind
N17 21.08.2013 Point by point response to JNCC and Natural England
N18 21.08.2013 Point by point response to MMO and Cefas
Appendix O Examples of general press coverage
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 13 © 2013 Forewind
Glossary of abbreviations
AEZ Archaeological Exclusion Zones
AIL Abnormal Indivisible Loads
APFP Regulations Infrastructure Planning (Applications: Prescribed Form and Procedures) Regulations 2009
CD Compact Disk
Cefas Centre for Environment, Fisheries & Aquaculture Science
CEMP Construction Environmental Management Plan
CNPMEM Comité National des Pêches Maritimes et des Elevages Marines
DCO Development Consent Order
DECC Department for Energy and Climate Change
DEFRA Department of Environment Food and Rural Affairs
DFA Danish Fisherman‘s Association
DVD Digital Versatile Disk
EEA European Economic Areas
EH English Heritage
EIA Environmental Impact Assessment
EMF Electric and Magnetic Field
EPS European Protected Species
ERYC East Riding of Yorkshire Council
ES Environmental Statement
EU European Union
FLC Fisheries Liaison Co-ordinators
GW Gigawatts
HDD Horizontal Directional Drilling
HETA Humberside Engineering Training Association
HGV Heavy Goods Vehicle
HIA Health Impact Assessment
HRA Habitats Regulation Assessment
HSC Historic Seascape Characterisation
IFAW International Fund for Animal Welfare
IPC Infrastructure Planning Commission
JNCC Joint Nature Conservation Committee
Km Kilometres
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 14 © 2013 Forewind
LWS Local Wildlife Sites
MCA Maritime and Coastguard Agency
MMMP Marine Mammal Mitigation Protocol
MMO Marine Management Organisation
MP Member of Parliament
NEIFCA North Eastern Inshore Fisheries Conservation Authority
NFFO National Federation of Fishermen‘s Organisations
NGET National Grid Electricity Transmission
NIFCA Northumberland Inshore Fisheries and Conservation Authority
NPS National Policy Statements
NSIP Nationally Significant Infrastructure Project
NSRAC North Sea Regional Advisory Council
NTS Non-Technical Summary
PEI Preliminary Environmental Information
Ramsar The Ramsar Convention (1971) The Convention on Wetlands of International Importance
RSPB Royal Society for the Protection of Birds
RWE RWE npower renewables (subsidiary of RWG Innogy)
SoCC Statement of Community Consultation
SPZ Source Protection Zone
SSE SSE plc
SVIA Seascape and Visual Character Impact Assessment
UK United Kingdom
WDCS Whale and Dolphin Conservation Society
WFD Water Framework Directive
WSI Written Scheme of Investigation
ZAP Zone Appraisal and Planning
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 15 © 2013 Forewind
1 Executive summary
1.1.1 This Consultation Report has been submitted to the Planning Inspectorate in
support of the application for a Development Consent Order (DCO) for Dogger
Bank Creyke Beck.
1.1.2 The purpose of this Consultation Report is to fulfil Forewind‘s obligation under
section 37(3)(c) of the Planning Act 2008 as amended (the Planning Act), which
states that an application for a DCO must be accompanied by a consultation report
(as defined in section 37 (7) of the Planning Act).
1.1.3 The Consultation Report demonstrates that Forewind has complied with sections
42, 47, 48 and 49 of the Planning Act, and has had due regard to relevant guidance
published under section 50 of the Planning Act. A compliance statement is included
in Annex 1.
1.1.4 Forewind has gone above and beyond the minimum requirements for pre-
application consultation to ensure that stakeholders are fully informed about Dogger
Bank Creyke Beck and have had several opportunities to provide feedback that
could influence the proposals. Consultation has been carefully co-ordinated to
ensure that stakeholders are kept informed and engaged throughout the pre-
application period, without imposing excessive consultation burdens.
1.1.5 Forewind began engaging with stakeholders at a very early stage, as part of the
Zone Appraisal and Planning process. Once Dogger Bank Creyke Beck had been
identified as the first stage of development of the Dogger Bank Zone, there were
two phases of statutory consultation under sections 42 and 47 of the Planning Act.
The proposed application was publicised once in accordance with section 48, to
coincide with the final stage of consultation carried out in accordance with section
42 and section 47.
1.1.6 In accordance with section 47 of the Planning Act, Forewind consulted the relevant
local authorities and Marine Management Organisation (MMO) on the content of the
Statement of Community Consultation (SoCC).
1.1.7 As the first stage of statutory consultation was carried out before the enactment of
the Localism Act 2011, the SoCC was published in full in a number of local
newspapers, in accordance with the original wording of section 47 of the Planning
Act. Publishing the SoCC in full was above and beyond the current (post Localism
Act 2011) requirements of section 47, which states that the applicant must publish a
notice stating where and when the SoCC can be inspected in full. Therefore,
Forewind considers that it has met the current requirements of section 47 of the
Planning Act in this regard.
1.1.8 Forewind consulted stakeholders outside of the statutory consultation periods as
part of the iterative design process and Environmental Impact Assessment (EIA).
This ―non-statutory‖ consultation has also had a clear influence on the proposals
and, as such, is discussed in this report. Consultation on the EIA included
consultation on the Habitats Regulations Assessment and consultation with trans-
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 16 © 2013 Forewind
boundary stakeholders.
1.1.9 Forewind has compiled an extensive database of stakeholders which includes those
prescribed by the Infrastructure Planning (Applications: Prescribed Forms and
Procedure) Regulations 2009 (the APFP Regulations), local authorities, landowners
and others with an interest in the land, the near shore and offshore fishing industry,
the local onshore community and a number of other organisations with a special or
technical interest in the proposals. Given that there was a wide range of differing
interests and technical knowledge across the stakeholders, the methods of
consultation were carefully considered to ensure that information was accessible
and that stakeholders had several different ways to provide their feedback.
1.1.10 Forewind has consulted the Planning Inspectorate, the MMO and East Riding of
Yorkshire Council (ERYC) on drafts of a number of other application documents,
including the draft DCO.
1.1.11 Forewind has responded to stakeholder feedback in several ways; altering the
design of the proposals (for example reducing the height of the onshore converter
stations), changing the approach to environmental surveys (for example adding an
additional season of fish surveys) and changing the way Forewind consulted (for
example setting up a community working group to consult on the onshore converter
stations).
1.1.12 The key issues raised during consultation, and the account Forewind has taken of
relevant responses, are summarised in Chapter 8 of this report, according to their
relevance to each chapter of the Environmental Statement or other application
document. Tables summarising all relevant responses received during the statutory
consultation periods are included in Appendix M. In accordance with the
Department for Communities and Local Government‘s Guidance on the Pre-
Application Process, (DCLG, 2013), Forewind has not included a full list of all
responses received outside of the statutory consultation periods, however these
records are available on request.
1.1.13 Throughout the pre-application process, Forewind has endeavoured to be
transparent in its stakeholder communications and has sought to achieve
agreement on as many issues as possible before the application is submitted.
Statements of Common Ground have been initiated pre-application and are draft
documents at the application stage which will be updated during the examination
stage, to reflect on-going consultation.
1.1.14 This Consultation Report complies with the Data Protection Act 1998 and is fit for
public consumption in that regard.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 17 © 2013 Forewind
2 Introduction
2.1 Policy Context
2.1.1 This document has been produced to fulfil Forewind Limited‘s (Forewind) obligation
under section 37(3)(c) of the Planning Act 2008 as amended (the Planning Act),
which states that an application for a Development Consent Order (DCO) must be
accompanied by a consultation report (as defined in section 37 (7) of the Planning
Act).
2.1.2 The Consultation Report demonstrates compliance with sections 42, 47, 48 (and
additionally section 49) of the Planning Act in relation to the Dogger Bank Creyke
Beck application, in that Forewind has:
Under section 42, consulted with all those required to be consulted under that
section, namely: the consultees prescribed by Schedule 1 of the Infrastructure
Planning (Applications: Prescribed Forms and Procedure) Regulations 2009
(the APFP Regulations), the Marine Management Organisation (MMO), the
relevant local authorities, and landowners or others with an interest in the land;
Under section 47, consulted the local authority on the content of the Statement
of Community Consultation (SoCC), published a notice in a local newspaper
stating where and when the SoCC can be inspected, made the SoCC available
to the public, and consulted the local community in accordance with the
published SoCC;
Under section 48, publicised the proposed application in the manner prescribed
by Regulation 4 of the APFP Regulations; and
Under section 49, taken account of relevant responses to the consultation and
publicity.
2.1.3 During the pre-application period for Dogger Bank Creyke Beck, there have been
legislative changes that have affected the consultation process, particularly the
enactment of the Localism Act 2011 (the Localism Act) and The Infrastructure
Planning (Prescribed Consultees and Interested Parties etc.) (Amendment)
Regulations 2013. Forewind has taken care to ensure that it has complied with any
changes brought about by this legislation.
2.1.4 In designing the consultation process and preparing this report, Forewind has had
regard to guidance published by the Department for Communities and Local
Government (DCLG), in accordance with section 50 of the Planning Act. Namely:
DCLG (2009) Planning Act 2008 Guidance on pre-application consultation; and
DCLG (2013) Planning Act 2008 Guidance on the pre-application process.
2.1.5 Forewind has also taken into account relevant advice notes, in particular:
The Planning Inspectorate (2012) Advice note three: EIA consultation and
notification;
The Planning Inspectorate (2012) Advice note twelve: Development with
significant transboundary impacts consultation;
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 18 © 2013 Forewind
The Planning Inspectorate (2012) Advice note fourteen: Compiling the
consultation report; and
The Planning Inspectorate (2012) Advice note sixteen: The developer‘s pre-
application consultation, publicity and notification duties.
2.1.6 Forewind has also taken into consideration the National Policy Statements (NPS) –
specifically the Overarching NPS for Energy (EN-1), the NPS for Renewable Energy
Infrastructure (EN-3) and the NPS for Electricity Networks Infrastructure (EN-5).
2.1.7 A brief summary of consultation undertaken in accordance with the Infrastructure
Planning (Environmental Impact Assessment) Regulations 2009 (the EIA
Regulations) is included in this report, but the focus is consultation undertaken in
accordance with sections 42, 47 and 48 of the Planning Act.
2.1.8 A compliance statement setting out how Forewind has complied with the relevant
provisions of the Planning Act, APFP Regulations, EIA Regulations and DCLG
Guidance is included in Annex 1.
2.1.9 This Consultation Report complies with the Data Protection Act 1998 and is fit for
public consumption in that regard.
2.2 Structure of this consultation report
2.2.1 Chapters 3, 4 and 5 of this report set out the statutory consultation processes that
Forewind has followed to meet the requirements of section 42, section 47 and
section 48 of the Planning Act.
2.2.2 Chapter 6 explains the non-statutory consultation process that was followed and
how additional non-statutory consultees were identified and consulted both during
statutory and non-statutory consultation periods. This includes a specific section
on fisheries liaison.
2.2.3 Chapter 7 explains how Forewind has met the consultation requirements of the
EIA Regulations, including consultation with trans-boundary consultees.
2.2.4 Chapter 8 summarises the key issues that were raised during consultation
throughout the pre-application stage, and the regard that Forewind had to these
responses, thus demonstrating compliance with section 49 of the Planning Act.
This Chapter is structured in sections relating to ES topics or other application
documents.
2.2.5 Chapter 9 explains Forewind‘s proactive approach to preparing Statements of
Common Ground.
2.2.6 Additional information and evidence is provided in the appendices which are
referenced throughout the report. Of particular note is Appendix M which contains
tables of all relevant responses received during Scoping and the two stages of
statutory consultation. There is one table per ES topic and within each table,
responses are split into the three stages – Scoping, first stage of statutory
consultation (containing responses received under sections 42 and 47 of the
Planning Act) and second stage of statutory consultation (containing responses
received under sections 42, 47 and 48 of the Planning Act).
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 19 © 2013 Forewind
2.3 Forewind
2.3.1 Forewind is a consortium comprising four leading international energy companies;
RWE npower renewables Limited, SSE Renewables Developments (UK) Limited,
Statoil Wind Limited and Statkraft UK LImited. Together, these companies combine
extensive experience of international offshore project delivery and renewable
energy development, construction, asset management and operations. Through
the combined strength of its owner companies, Forewind has the ability to both
make a significant contribution to the future of wind energy in the UK and
demonstrate commitment to the continuing development of offshore wind.
2.3.2 A summary of each of the Forewind partner companies is provided below:
RWE npower renewables Limited is the UK subsidiary of RWE Innogy. RWE Innogy is one of Europe‘s and the UK‘s leading renewable energy developers and operators. It is committed to developing and operating renewable energy projects to produce sustainable electricity across Europe and pools the expertise of its parent RWE Group.
SSE Renewables Developments (UK) Limited is part of the SSE group. SSE has over 3,000MW of renewables generation in its portfolio making it the largest generator of electricity from renewable sources across the UK and Ireland. Statoil Wind Limited is part of Statoil, an international energy company headquartered in Norway that has operations in 36 countries. Statoil is committed to accommodating the world's energy needs responsibly. In undertaking this challenge Statoil draws upon 40 years of experience from oil and gas production in harsh environments such as the North Sea..
Statkraft UK Limited manages Statkraft‘s interests in the UK. Statkraft is Europe‘s largest generator of renewable energy and is the leading power company in Norway. Statkraft owns, produces and develops hydropower, wind power, gas power and district heating. Statkraft is also a major player in European power trading.
2.4 Dogger Bank Zone
2.4.1 In January 2010, following a competitive tender process, The Crown Estate
awarded Forewind the exclusive development rights for ‗Zone 3, Dogger Bank‘; the
largest of the Round 3 offshore wind farm zones. The Dogger Bank Zone
comprises an area of 8660km2, which is approximately the same size as North
Yorkshire, and is located in the North Sea, between 125km and 290km off the coast
of Yorkshire.
2.4.2 Forewind has a target to achieve consent for 9 gigawatts (GW) of projects in the
Dogger Bank Zone. This capacity will be achieved by a series of individual wind
farm arrays, being developed in phases and Forewind‘s priority is to secure the first
six, each up to 1.2GW, or a total installed capacity of 7.2GW. Dogger Bank Creyke
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 20 © 2013 Forewind
Beck is the first stage of development of the Dogger Bank Zone.
2.5 Project background
2.5.1 In 2010, Forewind identified ―Dogger Bank Project One‖, a single offshore wind farm
array with a maximum installed capacity of 1.4 GW, and associated infrastructure
connecting to the Creyke Beck Substation, near Cottingham in the East Riding of
Yorkshire. This proposal was presented at the earliest stages of non-statutory
consultation and was the subject of a formal Scoping request (Forewind, 2010), to
the then Infrastructure Planning Commission (IPC), now the Planning Inspectorate,
in October 2010.
2.5.2 During 2011, it became clear to Forewind that a second grid connection may
become available at Creyke Beck, facilitating connection of a second wind farm at
this location. This additional grid connection increased the scale of the
development to a maximum installed capacity of 2.8GW (two wind farm arrays,
each up to 1.4GW). The amended proposal was renamed ―Dogger Bank Creyke
Beck‖ and all subsequent consultation was carried out on the basis of this larger
development.
2.5.3 By the second stage of statutory consultation, Forewind had refined its proposals
and identified that the maximum installed capacity per wind farm array in Dogger
Bank Creyke Beck was 1.2GW, rather than 1.4GW. Therefore the maximum
installed capacity for Dogger Bank Creyke Beck was refined to 2.4GW at the
second stage of statutory consultation.
2.5.4 Forewind has prepared an application for a single Development Consent Order
(DCO) for Dogger Bank Creyke Beck, which is supported by a single Environmental
Statement (ES) and Consultation Report. Forewind considers that all consultation
undertaken on Dogger Bank Project One is relevant to Dogger Bank Creyke Beck.
2.6 Overview of the consultation process
2.6.1 This section provides an overview and narrative of the whole pre-application stage.
It includes a quick reference guide summarising all consultation activities in
chronological order, as recommended by Advice Note Fourteen (The Planning
Inspectorate, 2012).
2.6.2 The consultation process for Dogger Bank Creyke Beck is iterative and started with
Forewind informing the stakeholder community of its intention to seek open and
transparent consultation, on the day that it was awarded the development rights for
the Dogger Bank Zone.
2.6.3 In line with The Crown Estate‘s guidance on the Zone Appraisal and Planning (ZAP)
process, Forewind consulted stakeholders about the Dogger Bank Zone, to inform
the identification of the locations of the first projects. The ZAP process is
summarised in Figure 2.1.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 21 © 2013 Forewind
Figure 2.1 Zone development process
2.6.4 This ZAP consultation included three stakeholder workshops, which were held in
April 2010. Over 88 stakeholder organisations attended these workshops, including
statutory bodies, UK and international fishing organisations, environmental non-
governmental organisations and developers of other offshore infrastructure projects.
The workshops were a success in that they ensured that stakeholders were
engaged in the Dogger Bank Development from an extremely early stage, and their
feedback at the event influenced the content of the Zonal Characterisation Report
and Forewind‘s approach to consultation. The facilitator‘s report summarising the
workshops is provided in Appendix N1.
2.6.5 Forewind‘s overall approach to consultation was set out in the Stakeholder
Engagement Plan (Forewind, 2011), which was published on Forewind‘s website
and is provided in Appendix A. This was supported by the Fisheries Liaison Plan
(Forewind, 2011), which set out Forewind‘s approach to consulting fishing industry
stakeholders. This was also published on Forewind‘s website and updated and
republished in 2013. Both versions of the Fisheries Liaison Plan are provided in
Appendix B.
2.6.6 Once the location of the first grid connection (at the Creyke Beck Substation) was
agreed with National Grid, Forewind commenced the project development and
consenting process. Forewind adopted a multi-stage statutory consultation
process, as recommended by DCLG Guidance (DCLG, 2013). This is illustrated in
Figure 2.2. The ZAP process continued in parallel to enable further stages of the
Dogger Bank Zone to be progressed.
Up to 9.6GW capacity achieved by a series of individual wind
farm projects
Non - statutory
consultation
Zone Appraisal and Planning
Fisheries liaison
Transboundary consultation
Non-statutory consultation on site selection, EIA survey and assessment methodologies
Parish Council workshops, community working group meetings
Statutory
consultation
S47 PEI1 Scoping
S42 PEI1
S47 Consultation on content of the
SoCC
S46
Notification
SoCC published
S47 Draft ES
S42 Draft ES
S48 Draft ES
S48 Notices
published
20
10
2
01
1
20
12
20
13
Figure 2.2 Multi-stage consultation process
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 23 © 2013 Forewind
2.6.7 In order to demonstrate Forewind‘s commitment to transparency and a clear
objective of achieving agreement with stakeholders, Forewind decided to progress
Statements of Common Ground before submitting the application for a DCO. This
is detailed further in Chapter 9 of this report.
2.6.8 A summary of consultation activities is outlined in Table 2.1.
Table 2.1 Overview of consultation activities
Date Stage Activity Consultees
Quarter 1 to quarter 2 2010
Non-statutory Consultation as part of the ZAP Process, which included the ZAP workshops.
Fisheries Liaison Co-ordinators appointed and began fisheries engagement.
Statutory authorities
Selected non-prescribed technical consultees (such as RSPB)
Local authorities
International fishing and shipping organisations
Quarter 3 2010
Non-statutory Pre-scoping meetings with selected consultees on Dogger Bank Project One.
As above
13 Oct to 18 Nov 2010
Scoping Scoping for Dogger Bank Project One
Deemed notification under Regulation 6(b) of the EIA Regulations that Forewind will provide an Environmental Statement (ES)
All those prescribed by Regulation 9 of the EIA Regulations (prescribed bodies)
2011 Non-statutory Consultation on emerging project design and assessment
EIA methodologies and baseline surveys agreed with appropriate consultees
The project doubled in size to two wind farms, and was re-named Dogger Bank Creyke Beck
Land agent began contacting landowners and occupiers
Prescribed bodies
Non-statutory consultees
Local authorities
International fishing and shipping organisations,
Near shore fishermen
Offshore and onshore landowners and occupiers
2011 Section 47 – SoCC preparation and publication
Statutory consultation with the Local Authorities and the MMO on the SoCC
Publication of the SoCC
Local authorities
MMO
3 Dec 2011
Section 46 Notification of proposed application
Provided IPC with Preliminary Environmental Information 1 (PEI1)
IPC
5 Dec 2011 to 20 Jan 2012
Sections 42 and 47 – First stage of consultation
PEI1 was published which included the “Approach to the EIA” document - an update to the Scoping Report.
Wrote to all consultees to notify them of the deadline for responses
Public exhibitions
Prescribed bodies
Non-statutory consultees
Local authorities
International fishing and shipping organisations,
Offshore and near shore fishermen and fishing organisations
Offshore and onshore
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 24 © 2013 Forewind
Date Stage Activity Consultees
landowners and occupiers
The local community through public exhibitions
2012 Non-statutory Non-statutory consultation on site selection and EIA
Community Working Group established to discuss micro-siting and layout of the onshore converter stations
Initial consultation on transboundary impacts with Nature Conservation Authorities, Fishing Authorities and other contacts (provided by the Planning Inspectorate) in other European Economic Area (EEA) Member States
Briefings for Members of Parliament (MP) and Councillors
Two editions of Forewind‘s newsletter produced
Prescribed bodies
Non-statutory consultees
Local authorities
International fishing and shipping organisations,
Offshore and near shore fishermen and fishing organisations
Offshore and onshore landowners and occupiers
The local community through the Community Working Group and Parish Council meetings
Elected representatives
Nature Conservation Agencies for other EU Member States
19 April to 11 June 2013
Sections 42, 47 & 48 Publication and second stage of consultation
Draft ES, Draft Non-Technical Summary (NTS) and a variety of other draft application documents published on the Forewind website and sent to consultees
Section 48 notice sent to section 42 consultees and advertised as prescribed by the APFP Regulations
Wrote to section 42 consultees to advise them of the deadline for responses
Public exhibitions
Prescribed bodies
Non-statutory consultees
Local authorities
International fishing and shipping organisations
Offshore and near shore fishermen and fishing organisations
Offshore and onshore landowners and occupiers
The local community and their elected representatives
Nature Conservation Agencies for other EU Member States
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 25 © 2013 Forewind
3 Section 42 consultation process
3.1 Section 42 consultees
3.1.1 Section 42 of the Planning Act specifies who the applicant must consult about the
proposed application. Those relevant to the Dogger Bank Creyke Beck
development are:
Section 42 (1) (a) – such persons as may be prescribed,
Section 42 (1) (aa) - the Marine Management Organisation (MMO),
Section 42 (1) (b) – each local authority that is within section 43, and
Section 42 (1) (d) – each person who is within one or more of the categories set
out in section 44.
3.1.2 A full list of consultees identified in accordance with Section 42 (1) (a), (aa) and (b)
is included in Appendix C2.
3.1.3 All consultees identified in accordance with Section 42(1)(d) are included in the
Book of Reference (Planning Inspectorate document reference number 4.3).
3.1.4 Details of how these consultees were identified are provided below.
3.2 Identification of the prescribed consultees
3.2.1 The section 42(1)(a) prescribed consultees were identified by careful attendance to
Schedule 1 of the Infrastructure Planning (Applications: Prescribed Form and
Procedures) Regulations 2009 (the APFP Regulations).
3.2.2 Forewind incorporated into its list of prescribed consultees, any bodies consulted by
the Infrastructure Planning Commission (IPC) during Scoping. This information was
provided to Forewind in accordance with Regulation 9(1)(b) of the Infrastructure
Planning (Environmental Impact Assessment) Regulation 2009 (the EIA
Regulations). Neither the IPC, nor its successor, the Planning Inspectorate, made
Forewind aware of any persons identified in accordance with Regulation 9(1)(c)1.
The Regulation 9 list is included in Appendix C1.
3.2.3 Over the course of the pre-application stage, the list of prescribed consultees
changed due to updates to legislation, most notably the Localism Act and The
Infrastructure Planning (Prescribed Consultees and Interested Parties etc.)
(Amendment) Regulations 2013, the Government‘s abolishment of various public
bodies, normal changes in Ofgem gas and electricity licenses and refinement of the
geographical location of the project. Forewind made best endeavours to keep the
list of prescribed consultees up to date and has had regard to Advice Note Three
(The Planning Inspectorate, 2012), which provides further advice on the
identification of consultees.
1 Persons whom the Secretary of State considers likely to be affected by, or may have an interest in, a
proposed NSIP and who are unlikely to become aware of the proposed NSIP through the pre- application consultation and publicity process set out in the 2008 Act.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 26 © 2013 Forewind
3.2.4 In line with the Department for Communities and Local Government (DCLG)
Guidance (DCLG, 2013), Forewind requested and received advice from the
Planning Inspectorate on certain bodies which ceased to exist during the pre-
application stages.
3.2.5 The list of prescribed consultees in Appendix C2 explains the reasons for any
variances between Forewind‘s list of Section 42(1)(a) consultees and the list of
prescribed consultees set out in Schedule 1 of the APFP Regulations,
demonstrating where Forewind has not been able to comply with the statutory
requirements (e.g. where a body has been abolished) and where the named body
has changed between the first and second stage of statutory consultation. The lists
of electricity and gas licence holders downloaded from the Office of Gas and
Electricity Markets (Ofgem) website to inform the selection of relevant consultees at
the second stage of statutory consultation, are included in Appendix C3.
3.2.6 The list of prescribed consultees in Appendix C2 highlights any prescribed
consultees also included in the Book of Reference (Planning Inspectorate
document reference number 4.3) at the time of submitting an application for a
DCO. This includes but is not limited to Beverley and North Holderness Internal
Drainage Board, National Grid Electricity Transmission Plc, Network Rail
Infrastructure Ltd, Northern Powergrid Ltd, The Environment Agency and Yorkshire
Water Services Ltd.
3.2.7 Forewind consulted more bodies than those prescribed by the Planning Act. This is
explained further in Chapter 6 of this report.
3.3 Identification of the relevant local authorities
3.3.1 Forewind applied section 43 of the Planning Act as follows:
Table 3.1 Local authorities identified in accordance with section 43
Name of Authority Category2 Description
East Riding of Yorkshire Council (ERYC)
B Unitary council within whose area the land lies
Hull City Council A Unitary council which shares a boundary with ERYC
City of York Council A Unitary authority which shares a boundary with ERYC
North Yorkshire County Council
A Upper-tier county council which shares a boundary with ERYC
North Lincolnshire Council A Unitary authority which shares a boundary with ERYC
Scarborough Borough Council A Lower tier district council which shares a boundary with ERYC
Ryedale District Council A Lower tier district council which shares a boundary with ERYC
Selby District Council A Lower tier district council which shares a boundary with
2 See Chapter 2 Section 43 (2) of The Planning Act 2008 for a description of these categories
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 27 © 2013 Forewind
ERYC
Doncaster Metropolitan Borough Council
A Unitary council which shares a boundary with ERYC
3.3.2 The relevant local authority boundaries are shown in Figure 3.1.
3.3.3 In the Regulation 9 list compiled by the IPC for the purposes of Environmental
Impact Assessment scoping, Hull City Council was classified as a ‗B‘ authority. This
was because, at that time, it was possible that Hull City Council‘s area could have
been directly affected by the proposals. Since then, the proposals have been
refined and none of the infrastructure will be located in Hull City Council‘s area.
Hence it is now classified as an ‗A‘ Authority.
3.3.4 Advice Note Three (The Planning Inspectorate, 2012) recommends that developers
of offshore schemes also consult local authorities that may be visually impacted by
the offshore elements of the proposals, even if they are not captured within the
categories of A, B, C or D local authorities.
3.3.5 The 35km Zone of Visual Influence for the offshore infrastructure of Dogger Bank
Creyke Beck does not cover any other local authorities. The landfall and near shore
works will be temporary and will only be visible from the East Riding of Yorkshire.
Therefore, no additional authorities have been consulted on this basis.
#
&
&
&
&
&
&
&
&
&
&
&
&
&
&
&
&
&
&
North Yorkshire County Council (A)
East Riding of Yorkshire (B)
York City Council (A)
Doncaster Metropolitan Borough Council (A)
North Lincolnshire Council (A)
HullCity
Council (A)
Ryedale DistrictCouncil (A)
Scarborough BoroughCouncil (A)
Selby DistrictCouncil (A)
HARROGATE
RIPON
RICHMOND
Bainbridge
SKIPTON
MALTON
WHITBY
SCARBOROUGH
DRIFFIELD
BRIDLINGTON
HEDON
HORNSEA
BEVERLEY
SCUNTHORPE
DONCASTER
SELBYHyndburn
District
Blackburn with Darwen
District
ManchesterDistrict
TamesideDistrict
GOOLE
Eden District
County Durham
Craven District
East Lindsey District
Hambleton District
Harrogate District
Richmondshire District
West Lindsey District
Northumberland
Cheshire East (B)
South Lakeland District
Bassetlaw Dis trict
Leeds District
Lancaster Distr ict
High Peak District
Ribble Valley District
Carlisle Distric t (B)
Cheshire West and Chester (B)
Kirklees District
Derbyshire Dales District
Sheffield District
Bradford District
Calderdale District
Barnsley District
Wakefield District
Darlington
Wyre Distr ict
RotherhamDistrict
Warrington
Wigan District
Chorley District
Redcar and Clevela nd
Stockton-on-Tees
Pendle District
Halton
Bolton Distr ict
Rochdale District
Oldham District
Hartlepool (B)
Gateshead District (B)
Rossendale District
Stockport District
Burnley District
Bolsover Distr ict
North East Lincolnshire
Preston District
St. Helens District
BuryDistrict
Sunderland District (B)
Trafford District
Salford District
South Ribble District
Mansfield District
Liverpool District
Middles-brough
Lincoln District (B)
Sefton District
Wirral District (B)
North Tyneside Distric t (B)
400000
400000
450000
450000
500000
500000
4000
00
4000
00
4500
00
4500
00
5000
00
5000
00
¯&
&
&
&
&
MIDDLESBROUGHWHITBY
SCARBOROUGH
KINGSTON UPON HULL
GRIMSBY
0 10 20
KilometresThe concepts and information contained in this documentare the copyright of Forewind. Use or copying of thedocument in whole or in part without the written permissionof Forewind constitutes an infringement of copyright. Forewind does not warrant that this document is definitivenor free of error and does not accept liabil ity for any losscaused or arising from reliance upon information provided herein.
DOGGER BANK CREYKE BECK
T-D ES-0 12 0-0 1
Section 43 - Local Authority Map
DRAWING NUMBER:
VER DATE1 17/09/2012
REMARKS CheckedFirst Issue
DRAWING TITLE
PROJECT TITLE
LEGEND (Inset map)
Data Source:Round 3 © TCE, 2010Substations © National Grid, 2011.International boundary © UKDeal,2010.Background bathymetry image derived in part from TCarta data © 2009 Ordnance Survey data © Crown copyright and database right, 2012Contains UKHO Law of the Sea data © Crown copyright and database right.
BNGOSGB36A41:1,000,000 DATUM PROJECTIONSCALE PLOT SIZE
DrawnAJ NS
LEGEND (Main map)
Creyke Beck A
Creyke Beck B
# Creyke Beck, National Grid SubstationCreyke Beck onshore cable corridorLocal authority boundaryDistrict council boundaryDirectly affected authority (B)Neighbouring local authorities (A)
12nm territorial boundaryOther local authorities - not consulted
Tranche boundaryDogger Bank Round 3 ZoneInternational boundary
Lower tier authorities - not consulted
Creyke Beck ACreyke Beck BCreyke Beck offshore cable corridor
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 29 © 2013 Forewind
3.4 Identification of landowners and others with an interest in the land
3.4.1 Section 42(1)(d) of the Planning Act states that the applicant must consult each
person who is within one or more of the categories set out in section 44. This
includes any owner, lessee, tenant or occupier, any person interested in the land or
has power to sell and convey the land and any person entitled to make a relevant
claim.
3.4.2 All persons consulted under section 42(1)(d) are included in the Book of Reference
(Planning Inspectorate document reference number 4.3), and this list is up to
date at the time of submitting the application for a DCO. It is important to note that
the list of section 42(1)(d) consultees is subject to change over time, as a result of
normal changes in land ownership.
3.4.3 Forewind sought to identify the section 42(1)(d) consultees by diligent inquiry before
each stage of statutory section 42 consultation. This is explained further below.
3.4.4 At the very early stages of the project, Forewind‘s land agent, Dalcour Maclaren,
carried out Land Registry Polygon Searches over the area affected by the preferred
cable route corridors (Mappleton to Creyke Beck and Fraisthorpe to Creyke Beck)
and a 4km radius around the converter station study area, to identify individual land
parcels.
3.4.5 Dalcour Maclaren then sent a land questionnaire (Appendix C4) to all the
addresses identified by this polygon search, seeking information about the land. In
addition, contact referencing was also carried out whereby Dalcour Maclaren
carried out site visits to collect and record landowner information through
discussions with local people. All information gathered by these land referencing
techniques was collated and used to populate the consultation database.
3.4.6 Having gathered this information, Dalcour Maclaren then began contacting all
identified landowners within the 1km survey corridor to seek permission for non-
intrusive survey access via formal access licences.
3.4.7 During the process of agreeing access licences, and latterly negotiating Heads of
Terms for private treaty agreements, Dalcour Maclaren helped to keep landowners
up-to-date on Forewind‘s development activities, both directly and via the
landowners‘ agents. In addition, Dalcour Maclaren also gathered information
regarding land interests and relayed landowners‘ feedback to Forewind. This
included opinions on the red line boundary as well as requests and suggestions for
changes. A list of generic landowner communications relating to commercial
discussions is provided in Appendix N2.
3.4.8 The list of section 42(1)(d) consultees changed over the course of the pre-
application period in line with refinements and changes to the proposals, several of
which were as a result of landowner consultation. There were also normal changes
in landownership or land interests which affected the list, such as changes of
ownership and new tenants.
3.4.9 During the first stage of statutory consultation, Forewind consulted all identified
parties within the preferred 1km wide cable corridor from Barmston and Ulrome to
Creyke Beck and the converter stations search area. Forewind consulted all
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 30 © 2013 Forewind
identified parties with an interest in the preferred study area. Following the public
exhibitions, Dalcour Maclaren met landowners and their agents, where appointed,
to seek their opinions regarding narrowing of the 1km corridor.
3.4.10 Ahead of the second stage of statutory section 42 consultation, Forewind checked
and refreshed the information previously gathered by contracting a specialist land
referencing firm to carry out an independent referencing exercise. The referencing
firm sent a further questionnaire (Appendix C5) to all known landowners and
occupiers, requesting further information about land interests (including information
regarding third party interests, utilities and mortgagees).
3.4.11 In addition, site notices were placed on 11 parcels of unregistered land (Appendix
C6). As a result, a number of calls were received but unfortunately they did not lead
to confirmation of ownership or other interest in the specific land parcels, nor did
they lead to identification of anyone falling within section 52(3) of the Planning Act.
3.4.12 In addition to questionnaires and site notices, the referencing firm sought further
information about land parcels through the electoral roll, 192.com and the Royal
Mail website. Any additional landowners or interests identified were then checked
via Land Registry, if registered, and where necessary, title documents were
requested and reviewed. Questionnaires were then issued to any new interests
identified.
3.4.13 It has not been possible for Forewind to seek formal rights from the Planning
Inspectorate to serve Land Interests Notices, under section 52 of the Planning Act,
because enquiries have not identified anyone on whom such notices could, with
authorisation, be served.
3.4.14 Forewind also classified those with an interest in the seabed affected by the
offshore works, such as pipeline operators, as section 42(1)(d) consultees. These
were identified through interrogation of The Crown Estate‘s Marine Resource
System3 and inspection of charts such as those sourced from the Department of
Energy and Climate Change‘s (DECC) Oil and Gas Licensing website4.
3.5 Two stages of statutory consultation
3.5.1 Forewind carried out a two stage statutory consultation under section 42 of the
Planning Act. This approach was taken to ensure that the prescribed consultees
were engaged from an early stage in the development of the project and had
multiple opportunities to comment.
3.5.2 It also ensured that Forewind satisfied the requirement5 to have complied with
section 42 of the Planning Act before applying to the IPC (now Planning
Inspectorate) for rights of entry under section 53 of the Planning Act, allowing
environmental surveys to be undertaken in a timely manner.
3.5.3 Forewind wrote to all section 42 consultees in advance of each stage of statutory
consultation to notify them of a deadline for receipt of consultation responses and
that this deadline was more than 28 days starting from the day after receipt of the
consultation documents.
3 http://www.marsmapping.co.uk/
4 https://www.gov.uk/oil-and-gas-offshore-maps-and-gis-shapefiles
5 This requirement was subsequently repealed by the Localism Act 2011
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 31 © 2013 Forewind
3.5.4 Before, between and after the two stages of statutory consultation, Forewind
continued to consult the section 42 consultees on an ad hoc basis. Forewind
referred to this as ―non-statutory‖ consultation.
3.6 First stage of statutory consultation
3.6.1 The first stage of statutory consultation was intended to introduce Forewind and
Dogger Bank Creyke Beck to stakeholders, as well as to present options for the
landfall location and onshore converter stations sites and to request further
information that might influence the development process.
3.6.2 Consultation documents were available online and in libraries by the 5 December
2011 and the deadline for responses was the 20 January 2012. Therefore, the total
duration of this consultation was at least 46 days, which was more than the
statutory minimum of 28 days, to allow for the Christmas period.
3.6.3 In order to reduce confusion, the deadline for responses was deliberately co-
ordinated to be the same as that of the first stage of section 47 consultation.
3.6.4 In compliance with section 46 of the Planning Act, Forewind provided the IPC with
the section 42 consultation documents on 3 December 2011 (i.e. before they were
sent to the section 42 consultees and before commencing section 42 consultation)
at a meeting at the IPC‘s offices in Bristol.
3.6.5 Consultation documents entitled ―Preliminary Environmental Information 1‖ (PEI1)
were published on Forewind‘s website. PEI1 consisted of:
Preliminary Environmental Information 1 – the overarching consultation
document;
Appendix A - Project Description;
Appendix B – Approach to Environmental Impact Assessment;
Appendix C – Landfall Selection Report;
Appendix D – Onshore Converter Station Selection Report;
Appendix E – Onshore Cable Corridor Selection Report; and
Appendix F – Offshore Cable Corridor Selection Report.
3.6.6 Forewind initially wrote to the section 42 (1)(a), (aa) and (b) consultees (plus
additional non-statutory consultees) on 15 November 2011 (Appendix D1) to
provide advanced notice of the forthcoming consultation and the fact that
consultation documents would be available from 5 December 2011 on Forewind‘s
website. Forewind wrote to these stakeholders again on 31 November 2011
(Appendix D2) to confirm that the consultation documents were already available
online (they were made available early), the deadline for responses and details of
the public exhibitions in the East Riding of Yorkshire, should they wish to attend.
On 6 December 2011, Forewind wrote to these consultees to request that they
confirm they are able to access the documents online, or else to request the
documents in some other format (Appendix D3).
3.6.7 Forewind wrote to all the Section 42 (1)(d) consultees (that had been identified at
that time) on 15 November 2011 (Appendix D4) to provide advanced notice of the
consultation and in particular, the details of public exhibitions that were to be held in
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 32 © 2013 Forewind
accordance with Section 47 of the Planning Act (see Section 4.4). On 7
December, Forewind wrote to all the Section 42 (1)(d) consultees again and
provided a compact disk (CD) copy of the PEI1 documents (Appendix D5).
3.6.8 Following the PEI1 consultation, Forewind reviewed all relevant responses and any
late responses. All responses were recorded and considered in the further
development of the project. Relevant responses are summarised in the tables in
Appendix M.
3.7 Second stage of statutory consultation
3.7.1 The second stage of statutory consultation started on 19 April 2013 and the
deadline for responses was 11 June 2013. Therefore, the total duration of this
consultation period was 54 days, which is longer than the statutory minimum of 28
days, to reflect the volume and detail of consultation materials. In order to reduce
confusion, Forewind deliberately co-ordinated the deadline for responses to the
section 42, section 47 and section 48 consultations.
3.7.2 Forewind provided the Planning Inspectorate with the consultation documents in
advance of the section 42 consultation period, on 16 April 2013 (Appendix E3).
3.7.3 Forewind endeavoured to give stakeholders sufficient notice of the final
consultation. In December 2012, Forewind wrote to the Section 42 (1)(a), (aa) and
(b) prescribed consultees plus additional non-statutory consultees to confirm
whether they would require hard copies of any of the consultation documents, and
to outline the consultation process (Appendix E1). In March 2013, Forewind wrote
to the same consultees to provide an update on the forthcoming consultation and to
explain the reason for a short delay (Appendix E2). On 16 April 2013, Forewind
wrote to all these consultees again to inform them that the consultation documents
were available, to confirm the deadline for responses and to outline the key
elements of the proposals. This letter included a DVD copy of the consultation
documents and hard copies of any document, if previously requested (Appendix
E4).
3.7.4 Forewind wrote to all Section 42(1)(d) consultees that had been identified on 3 April
2013 to provide advance warning of the consultation (Appendix E5), and then on
17 April 2013 to notify them that the consultation period had begun (Appendix E6).
This second letter included a DVD copy of the consultation documents and, for
onshore stakeholders, a factsheet designed to highlight landowner and occupier
specific issues (Appendix E8).
3.7.5 At this stage, the main consultation documents comprised a draft ES and draft Non-
Technical Summary (NTS). The draft ES was informed by both responses to the
first stage of statutory consultation and a significant amount of non-statutory
consultation that was carried out between these statutory periods. The draft ES and
NTS were available to download from the Forewind website.
3.7.6 A number of other draft application documents, including the draft DCO and draft
Works Plans, were sent to both the MMO and ERYC for comment. Forewind held
meetings with both the MMO and ERYC to discuss and take on board their
comments, and to inform the final drafts of the application documents.
3.7.7 Draft application documents were made available to all other statutory consultees
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 33 © 2013 Forewind
on request. Forewind chose not to circulate all these draft documents as a matter
of course, to ensure that the consultation was focussed on the draft ES and to avoid
overwhelming consultees with information. The cover letter sent to each section 42
consultee (and additional non-statutory consultees) explained which additional draft
application documents were available.
3.7.8 Forewind offered meetings to all section 42 consultees during the consultation
period to answer questions and aid understanding of the consultation documents.
Meetings were held with both onshore and offshore consultees. An example of
such a meeting is the round table discussion that was held with various officers at
East Riding of Yorkshire Council on 24 April 2013 (Appendix N15).
3.7.9 During the second stage of statutory section 42 consultation, a number of additional
land interests were identified. Forewind sent all those identified, an amended
section 42 cover letter (Appendix E7) and consultation documents, and extended
the deadline to allow 28 days for those persons to respond. Comments were
received from two of the additional land interests identified.
3.7.10 Following the consultation deadlines, Forewind recorded and considered all
relevant responses in finalising the application. These are summarised in
Appendix M.
3.7.11 More information on how responses were taken into account can be found in
Chapter 8 of this report, and in the relevant chapters of the ES (Planning
Inspectorate document reference number 6).
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 34 © 2013 Forewind
4 Section 47 consultation process
4.1 Summary of the SoCC rationale
4.1.1 Throughout the development process, Forewind consulted the local community on
the two wind farm projects that comprise Dogger Bank Creyke Beck, as one
development. Forewind chose to do this, despite the initial uncertainty about
whether one or two Development Consent Order (DCO) applications would be
submitted, to ensure that it was clear to the local community what the maximum
possible scale of the proposal was.
4.1.2 Forewind published its Statement of Community Consultation (SoCC) in November
2011, at an early stage in the development process (Appendix F4). Consultation
was carried out in accordance with the commitments made within the SoCC and
this included two stages of statutory community consultation on preliminary
environmental information (PEI).
4.1.3 Over the course of the pre-application period, Forewind refined its approach to
community consultation and carried out additional consultation, above and beyond
the commitments made in the SoCC. These additional activities are outlined in
Section 4.7.
4.1.4 The SoCC explained that the project could be the subject of one or more
applications for a DCO. The decision to submit a single DCO application was taken
in 2012 and Dogger Bank News newsletters (Appendix I1) made it clear that a
single application would be submitted. Forewind also wrote to the statutory and
non-statutory consultees to inform them of this decision in December 2012
(Appendix F7) and the Forewind website was updated in January 2013.
4.1.5 In accordance with Regulation 10 of the Infrastructure Planning (Environmental
Impact Assessment) Regulations 2009 (the EIA Regulations), the SoCC set out that
the development is EIA development and how Forewind intended to publicise and
consult on the PEI.
4.1.6 The two stages of community consultation on PEI were carried out in parallel with
the two statutory consultations carried out in accordance with section 42. This was
done to ensure that the published section 42 and section 47 consultation
documents were consistent, and that all of Forewind‘s stakeholders were given an
opportunity to comment on the proposals at least twice before the application was
submitted.
4.1.7 Forewind adopted a tiered approach to community consultation. Those likely to be
most impacted by the scheme (i.e. those with postal address up to 1km from the
converter stations study area and/or 500m either side of the onshore cable route)
were sent a letter inviting them to the public exhibitions and copies of each edition
of the Dogger Bank News newsletter.
4.1.8 Other members of the local community, likely to be less impacted than those
described in paragraph 4.1.7, but nevertheless still interested in the scheme, were
targeted through the general media, posters and word of mouth, such as via the
community organisations that Forewind included in its database of non-statutory
consultees. Forewind also took into account whether the impacts of the scheme on
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 35 © 2013 Forewind
a particular community were temporary or permanent. As a result, focussed
community consultation, particularly via the converter station community working
group, was carried out with the communities in the vicinity of the onshore converter
stations.
4.1.9 A number of free-of-charge channels were available for consultees to access
information and provide comments and feedback on the proposals. These
included:
lodging hard copies of the consultation documents at local libraries during the
consultation periods,
making consultation documents available to download from the Forewind
website,
CDs or DVDs containing the consultation documents were available on request
and at the public exhibitions,
questionnaires available at the public exhibitions,
a Freephone telephone number (available at any time),
Freepost address (available at any time),
e-mail address (available at any time), and
website enquiry form (available at any time).
4.1.10 The public exhibition questionnaires proved to be the main channel for the local
community to provide feedback.
4.2 Consultation on the content of the draft SoCC
4.2.1 East Riding of Yorkshire Council (ERYC) (being the relevant B Authority), Hull City
Council and the Marine Management Organisation (MMO) were consulted on the
content of the draft SoCC. The Infrastructure Planning Commission (now the
Planning Inspectorate) was also asked to comment. These consultees were
consulted a number of times, due to the change in the scale of the scheme, and
therefore change in consultation strategy.
4.2.2 The final statutory consultation on the content of the SoCC was carried out from 3
October 2011 to 1 November 2011, which allowed consultees at least 28 days to
provide comments. The cover letters to each of the consultees and the SoCC
Consultation Document are included in Appendices F1 and F2.
4.2.3 The relevant responses to the SoCC consultation are provided in Appendix F3,
and a table explaining the regard that Forewind had to both these responses, and
non-statutory responses on the content of the SoCC, is included in Appendix M1.
ERYC approved the proposed Community Consultation Area in a meeting on 22
September 2011 (Appendix N5).
4.2.4 Forewind provided ERYC, Hull City Council and the MMO with a final version of the
SoCC and confirmed how it would be published in November 2011 (Appendix F8).
4.3 Publication of the SoCC
4.3.1 Forewind published the SoCC in November 2011, before the Localism Act was
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 36 © 2013 Forewind
enacted, and therefore it was published in full in a number of local newspapers.
Forewind considers that this goes above and beyond the current requirement of
section 47 and therefore that it has satisfied the requirements of this section. Table
4.2 details the newspapers that were used to publicise the SoCC and copies of the
SoCC, as it appeared in each of these publications, are included in Appendix F5.
Table 4.2 Publications in which Forewind published the SoCC
4.3.2 The SoCC was made available for inspection on the Forewind website, in hard copy
at the local libraries listed in Appendix F6, and was referenced in the Kingfisher
Bulletin on 24 November 2011.
4.3.3 Forewind also posted a hard copy of the SoCC to all addresses within the
Consultation Area and posted or emailed a copy of the SoCC to all elected
representatives and community groups on Forewind‘s database, as part of the
invitation to the December 2011 exhibitions (Appendices G1 and G2).
4.3.4 The SoCC Consultation Document, which was originally provided to the local
authorities and MMO during the statutory SoCC consultation period, was updated to
reflect the consultation responses and a query from the MP for Hull North regarding
Publication Date
Published
Distribution Purpose
Advertiser
Series
17
November
2011
Holderness, East Hull, Beverley,
West Hull, West Hull villages
Free weekly newspaper delivered
across the East Riding and Hull
reaching people who do not buy a
newspaper
Bridlington
Free Press
17
November
2011
Bridlington and neighbouring
villages in the Bridlington Bay
and Flamborough Head area,
online
Weekly tabloid newspaper. The
biggest selling newspaper in the
Bridlington area. To capture people in
the landfall area and northern stretch
of the cable route corridor
Fishing
News
18
November
2011
Commercial fishing industry,
online
To capture offshore users notable
those commercial fishing interests that
may use the Dogger Bank Zone
Holderness
Gazette
17
November
2011
Holderness and East Coast from
Hornsea down to Spurn Point,
online
To capture the eastern area of the
East Riding including Holderness and
the East Coast
Hull Daily
17
November
2011
Barton-upon-Humber, Beverley,
Bridlington, Driffield, Filey,
Flamborough, Goole, Hornsea,
Howden, Hull, Market Weighton,
Pocklington, Scarborough,
Withernsea, York, online
To capture the southern extent of the
East Riding of Yorkshire (Holderness)
coast
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 37 © 2013 Forewind
the reference to illiteracy. It was then published on the Forewind website to provide
further information about how the content of the SoCC was determined.
4.4 First stage of statutory community consultation
4.4.1 The purpose of the first stage of statutory consultation was to raise the profile of the
scheme and to gather early feedback from the local community on the broad
proposals, as well as to gather information about the local community to help refine
the consultation process.
4.4.2 Public exhibitions were held in the five locations set out in the SoCC between 5 and
10 December 2011, namely Barmston, Bridlington, Brandesburton, Cottingham and
Beverley.
4.4.3 All addresses in the Community Consultation Area (as defined by the SoCC) were
sent a letter (Appendix G2) approximately two weeks in advance of the events,
inviting them to the exhibitions, along with a hard copy of the SoCC. Elected
representatives such as councillors and MPs were also sent a copy of the SoCC
and invited (Appendix G1) to attend one of four special briefings.
4.4.4 A press release (Appendix G3) was put on the Forewind website and circulated to
local newspapers to publicise the events. Posters (Appendix G5) advertising the
exhibitions were put up in the vicinity of each exhibition venue a few days before the
events.
4.4.5 In addition to the newspapers that Forewind used to publish the SoCC (Table 4.2),
a number of other local newspapers ran a story on the exhibitions which increased
publicity. This included the Scarborough News and Yorkshire Post (Appendix G4).
4.4.6 Over 281 people6 attended these exhibitions, including members of the public, ward
and parish councillors and representatives of various interest groups.
4.4.7 The exhibition consisted of 12 information panels (Appendix G7), with further
detailed information available in hard copies of the PEI1 documents. A non-
technical community consultation summary leaflet (Appendix G8) was handed out
along with CD copies of the PEI1 documents. A number of Forewind staff were on
hand to answer questions and visitors were asked to complete a questionnaire
(Appendix G9) or Freepost response card (Appendix G10) with their comments.
4.4.8 Hard copies of the PEI1 documents were also lodged at a number of local libraries
(Appendix G6) for the duration of the consultation period.
4.4.9 Forewind received 50 completed exhibition questionnaires and six Freepost
response cards before the consultation deadline, which was over 28 days after the
last exhibition date.
4.4.10 Summaries of the relevant responses, including questionnaire responses are
provided in Chapter 8 and Appendix M.
4.4.11 The information and feedback gathered at this stage influenced Forewind‘s
approach to consultation throughout the EIA phase. The early engagement ensured
that the local community had already influenced the proposals presented at the
second stage of statutory consultation.
6 Number of people who signed in at the exhibitions in December 2011
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 38 © 2013 Forewind
4.4.12 Forewind published the first edition of Dogger Bank News (Appendix I1) in Spring
2012. This included a brief summary of the first stage of statutory community
consultation, including the key issues that were raised and how Forewind took them
into account, particularly the establishment of the Community Working Group. The
newsletter was distributed in hard copy to all addressed in the Consultation Area
and to all other stakeholders on Forewind‘s database by email or hard copy as
appropriate.
4.5 Second stage of statutory community consultation
4.5.1 At the second stage of consultation on the draft ES, the refined details of the
proposals were presented. This included the final proposed locations of the
onshore and offshore infrastructure and the results of the EIA and proposed
mitigation.
4.5.2 Two options were presented for the onshore high voltage direct current cable route
through the Woodmansey area. It was not possible to rule out either cable option
before the consultation and therefore Forewind sought stakeholders‘ feedback at
this stage before finalising the selection.
4.5.3 Public exhibitions were held in six locations - Ulrome, Beeford, Bridlington,
Cottingham, Beverley and Hull on successive days from Tuesday 7 May to Sunday
12 May 2013. It was decided to add an extra venue (Hull) at this stage to publicise
the development to the wider community who may be particularly interested in the
socio-economic benefits of the development. The landfall public exhibition venue
was changed from Barmston to Ulrome to reflect the fact that the final landfall
location is closer to Ulrome.
4.5.4 All addresses in the Consultation Area were sent an invitation (Appendix H2) to
public exhibitions with a CD copy of the draft ES, draft NTS and Community
Consultation Summary.
4.5.5 Local fishermen were sent the first edition of Forewind‘s Fishing Newsletter
(Appendix I2), in addition to an invitation to the public exhibitions, with a CD copy
of the draft ES, draft NTS and Community Consultation Summary.
4.5.6 Elected representatives were also sent an invitation (Appendix H1) to the
exhibitions with an additional note inviting them to a special briefing an hour before
the publicised opening time of the first exhibition.
4.5.7 In addition to the Section 48 Notice placed in local and national newspapers (see
Chapter 5), the exhibitions were advertised by press releases (Appendix H3)
published on the Forewind website on 17 April 2013 and 30 April 2013 and picked
up in a number of local newspapers (Appendix H4).
4.5.8 Edition 4 of Dogger Bank News (Appendix I1), was distributed around 11 April
2013 to all addresses in the Consultation Area and Forewind‘s database of
consultees. Posters (Appendix H5) advertising the exhibitions were put up in the
vicinity of each exhibition venue a few days before the events.
4.5.9 The exhibitions consisted of 15 exhibition panels (Appendix H7) summarising the
proposals, with further detail available in hard copy of the draft ES, draft NTS and
large scale maps. A Community Consultation Summary booklet (Appendix H8)
was offered to all visitors, which provided a take-away summary of the proposals
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 39 © 2013 Forewind
and specific consultation questions. CDs containing the draft ES, draft NTS and
Community Consultation Summary were also available to take away.
4.5.10 Forewind staff with a range of expertise (including its Land Agent), were on hand to
answer questions and encourage visitors to complete questionnaires (Appendix
H9) and/or the Freepost response cards.
4.5.11 Hard copies of the consultation documents were also lodged at a number of local
libraries (Appendix H6) for the duration of the consultation period.
4.5.12 Over 2817 people attended the exhibitions and 77 questionnaires were returned.
4.5.13 Summaries of the consultation responses received, including questionnaire
responses, are provided in Chapter 8 and Appendix M.
4.5.14 In line with DCLG Guidance (DCLG, 2013), following the end of the consultation
period, Forewind published an extended edition of Dogger Bank News (Appendix
I1) summarising the key points raised by the local community and how Forewind
took them into account. This was circulated by email or post to all of Forewind‘s
stakeholders.
4.6 Compliance with the SoCC commitments
4.6.1 Table 4.3 sets out how Forewind met the commitments made in the SoCC.
Table 4.3 Compliance with SoCC commitments
7 Number of people who signed in at the exhibitions in May 2013
Category Commitment made in the SoCC Compliance
Phase One –
what will be
consulted on
Forewind will clearly explain the site
selection work done to date… Forewind
will set out why the proposed location
has been selected and what further
refinement is required.
Forewind will ask the local community to
provide any comments or information on
the site selection work…
This information was included in PEI 1 and a
summary was provided in the community
consultation summary leaflet and exhibition
panels.
A questionnaire and postage paid response
cards were provided for any comments. See
Appendix G9.
Phase One
public
exhibitions
Public exhibitions would be held at the
places and times set out in the SoCC
Exhibitions were held at the places and times
set out in the SoCC (Paragraph 4.4.2)
Availability of
Phase One
consultation
documents
Consultation documents will be
available at local libraries and to
download from the Forewind website
from 5 December.
Consultation documents were delivered to
libraries on 4 December 2011 and uploaded
to the website on 28 November 2011
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 40 © 2013 Forewind
Phase Two –
what will be
consulted on
Forewind will ask the local community
for comments on the detailed proposals
for Dogger Bank Creyke Beck.
Forewind will be able to explain the
potential impacts of the development
and any proposed mitigation
measures…
Questionnaires and postage paid response
cards were provided. See Appendix H9
The detailed proposals and mitigation were
set out in the draft ES. A draft NTS was
available as well as a community consultation
summary.
Consent
strategy
decision
The decision about whether to submit a
single DCO application or two separate
applications will be presented to
stakeholders prior to the Phase Two
consultation
Website updated January 2013
Dogger Bank News (Appendix I1)
Section 48 Notice published April 2013
(Appendix K)
Publication
of Phase
Two events
The dates and locations of the Phase
Two consultation events will be
published in the local press and marine
journals and on the Forewind website at
least two weeks beforehand. The
period of the consultation and the
deadline for responses will be publicised
when known.
The dates and locations of the Phase Two
consultation events, plus the deadline for
responses, were publicised in the Section 48
notice in local newspapers and marine
journals from 22 April 2013 (Appendix K),
via press releases on 17 April and 30 April
(Appendix H3) and in Dogger Bank News
Edition 4, published on 11 April (Appendix
I1).
PEI PEI will be available during both stages
of consultation
PEI1 was made available during Phase One.
The draft ES and draft NTS were available
during Phase Two.
Local
Community
Consultees
Forewind will send direct invitations to
the consultation events to the following
people, hereafter referred to as the
―Local Community Consultees‖…
At Phase One, over 1300 invitations were
sent to the Local Community Consultees.
At Phase Two, over 1500 invitations were
sent.
Fisheries
Liaison Plan
Details of the fisheries consultation
process will be published separately in
Forewind‘s Fisheries Liaison Plan.
The Fisheries Liaison Plan was published in
November 2011. It was updated and
republished in April 2013. See Appendix B.
International
consultees
Forewind will work with the Examining
Body and the relevant UK and EU
governments to ensure that appropriate
international stakeholders are consulted.
Forewind consulted international shipping and
fishing companies and relevant departments
of EU and European Economic Area (EEA)
Member States. See Appendix C7.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 41 © 2013 Forewind
4.7 Additional community consultation activities undertaken
4.7.1 Over and above the commitments made in the SoCC, Forewind informed and
consulted the local community by means of the Community Working Group and
elected representative briefings.
Community Working Group
4.7.2 Following the first stage of statutory community consultation, Forewind set up a
community working group to discuss the micro-siting, design and landscaping of the
converter stations.
4.7.3 This was a direct response to a request from members of the local community and,
therefore, was not included in the original SoCC. ERYC confirmed (Appendix J1)
that it was not necessary for Forewind to amend and re-publish the SoCC to include
the community working group. Instead, Forewind committed to issuing a press
release before each meeting of the community working group and publishing
minutes of each meeting on the Forewind website.
Public
exhibitions
Information and printed materials to be
provided. Forewind staff will be at the
exhibitions to answer questions.
Visitors will be asked to submit feedback
and comments via questionnaires.
See Section 4.4 and Section 4.5.
Newsletters
and
Factsheets
Forewind will produce zone level
newsletters and subject-specific
factsheets at key stages of the project to
ensure that the local community is kept
up to date with the development.
Dogger Bank News (Appendix I1) has been
distributed by post or email to all those
registered in Forewind‘s stakeholder
database. A fisheries newsletter will also be
published about three times a year, starting
in Spring 2013. (Appendix I2) A landowner
factsheet was produced to support Phase
Two consultation (Appendix E8)
Lodging of
consultation
documents
in public
All PEI documents, questionnaires,
factsheets and newsletters will be
lodged at libraries, and wherever
possible at East Riding of Yorkshire
Council‘s and Hull City Council‘s
Customer Service Centres, within and
close to the Consultation Area. They will
also be available to download from the
Forewind website.
The list of libraries for stage one is provided
in Appendix G6 and for stage two in
Appendix H6.
ERYC subsequently informed Forewind that
their Customer Service Centres are
paperless and would not accept the
consultation documents.
All documents were available to download
from the Forewind website.
Overlapping
consultations
with other
developers
Where possible, Forewind will avoid
scheduling consultation events that
overlap with other companies‘
consultations.
None of the consultations overlapped.
Forewind actively engaged, in particular, with
National Grid Carbon to avoid overlapping
consultation at the landfall.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 42 © 2013 Forewind
4.7.4 Membership of the community working group included representatives of the Parish
Councils, community and special interest groups directly affected by the converter
stations search area presented in the PEI1 documentation.
4.7.5 The community working group met four times before the application was submitted
and proved to be a very effective way of gaining local community input to the site
selection and design process. The group had a direct influence on the proposals; of
particular note is the fact that one of the group‘s suggested locations for the
converter stations was taken forward as the final site.
4.7.6 A list of the members of the group, the terms of reference, press releases,
presentations and minutes of each meeting are provided in Appendix J.
Elected representative briefings
4.7.7 Forewind endeavoured to keep elected representatives up to date throughout the
development process. Relevant activities, over and above the statutory
consultations are shown in Table 4.4.
Table 4.4 Elected representative engagement activities
Date Consultees Activity
1 Feb 2011 Skidby Parish Council Presentation and questions
12 July 2011,
18 April 2012
Barmston & Fraisthorpe Parish Council Presentation and questions
28 March 2012 ERYC and Hull City Council Councillors Councillor Briefing
11 April 2012 Lissett & Ulrome Parish Council Presentation and questions
7 August 2012 Beeford Parish Council, Brandesburton Parish
Council, North Frodingham Parish Council
Workshop on proposed cable
route and construction access
8 August 2012 Barmston & Fraisthorpe Parish Council, Lissett
& Ulrome Parish Council, Skipsea Parish
Council, East Wolds & Coastal Ward Councillors
Workshop on proposed cable
route and construction access
9 August 2012 Beverley Town Council, Woodmansey Parish
Council, Tickton and Routh Parish Council,
Minster and Woodmansey Ward Councillor
Workshop on proposed cable
route and construction access
21 Nov 2012,
13 June 2013
Graham Stuart MP, Beverley and Holderness
Constituency
Update meetings
2 July 2013 Robert Goodwill MP, Scarborough and Whitby
Constituency
Update meeting
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 43 © 2013 Forewind
5 Section 48 publicity
5.1 Legislative context
5.1.1 Section 48(1) of the Planning Act states that the applicant must publicise the
proposed application in the ―prescribed manner‖, namely in accordance with
Regulation 4(2) of the Infrastructure Planning (Applications: Prescribed Form and
Procedures) Regulations 2009 (the APFP Regulations).
5.1.2 Regulation 11 of The Infrastructure Planning (Environmental Impact Assessment)
Regulations 2009 (the EIA Regulations) states that where the proposed application
is for EIA development, the applicant must send a copy of the Section 48 Notice to
all the prescribed bodies at the same time as publishing the Section 48 Notice.
5.1.3 The proposed Dogger Bank Creyke Beck DCO application was prepared, published
and distributed in accordance with Section 48 of the Planning Act, the APFP
Regulations and the EIA Regulations. Further details are provided in this chapter.
5.1.4 Copies of the notice, as they appeared in the press are provided in Appendix K.
5.2 Publications and timing
5.2.1 DCLG Guidance (DCLG, 2013) notes that this publicity is ―an integral part of the
local community consultation process‖ and advises that,
―where possible, the first of the two required local newspaper advertisements
should coincide approximately with the beginning of the consultation with
communities‖.
5.2.2 Forewind chose to publicise (in accordance with section 48) the Dogger Bank
Creyke Beck application once, to coincide with the final stage of statutory Section
42 and Section 47 consultation. This reflected Forewind‘s stakeholder engagement
strategy to prioritise consultation with those most affected by the proposals.
5.2.3 The notices appeared in the press at the start of the Section 42 and Section 47
consultation period, two weeks before the start of public exhibitions, and so acted
as both publicity about the intended application as well as publicity about the
imminent public exhibitions and opportunity for the local community, and wider
general public to have their say on the proposals. Table 5.1 details the publications,
dates and distribution area of the section 48 notices against the requirement of
Regulation 4 of the APFP Regulations.
Table 5.1 Section 48 notices – publication details
APFP
Reference
Publication First
publication
Second
publication
Distribution
4(2)(a) Advertiser
Series
Wednesday
24 April 2013
Wednesday
01 May 2013
Holderness, East Hull, Beverley, West
Hull, West Hull villages
4(2)(a) Bridlington
Free Press
Thursday 25
April 2013
Thursday 02
May 2013
Bridlington and neighbouring villages in
the Bridlington Bay and Flamborough
Head area
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 44 © 2013 Forewind
5.2.4 In accordance with Regulation 11 of the EIA Regulations, a hard copy of the
Section 48 Notice was sent to all the prescribed consultees listed in Appendix C2
on 17 April 2013, along with the Section 42 consultation materials and cover letter
(Appendix E4).
5.2.5 The Section 48 Notice was also made available on the Forewind website from 11
April 2013.
5.3 Content of the notice
5.3.1 The Section 48 Notice was prepared with reference to Regulation 4(3) of the APFP
Regulations and included all matters prescribed by it. The Compliance Checklist in
Annex 1 details where the prescribed matters can be found in the Section 48
notice.
5.3.2 A deadline was set for receipt of responses to the publicity. In the spirit of IPC
Guidance Note 1 on Pre-Application Stages, Forewind co-ordinated the final stage
of consultation so that the response deadline for the Section 48 Publicity was the
same date as for the Section 42 and Section 47 Consultation. The deadline was
Tuesday 11 June, which was 40 days after the date that the Section 48 Notice was
last published.
5.4 Relevant responses to Section 48 publicity
5.4.1 None of the responses received before the deadline explicitly referenced the
Section 48 Notice.
4(2)(a) Holderness
Gazette
Thursday 25
April 2013
Thursday 02
May 2013
Holderness and East Coast from Hornsea
down to Spurn Point
4(2)(a)
Hull Daily
Monday 22
April 2013
Monday 29
April 2013
Barton-upon-Humber, Beverley,
Bridlington, Driffield, Filey, Flamborough,
Goole, Hornsea, Howden, Hull, Market
Weighton, Pocklington, Scarborough,
Withernsea, York
4(2)(b) The
Independent
Monday 22
April 2013
N/A UK national
4(2)(c) London
Gazette
Monday 22
April 2013
N/A Official newspaper of record for the UK
4(2)(d)(i) Lloyd‘s List Monday 22
April 2013
N/A Leading maritime industry newspaper
4(2)(d)(ii) Fishing
News
Friday 26
April 2013
N/A Commercial fishing industry in UK and
Ireland
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 45 © 2013 Forewind
6 Non-statutory consultation
6.1 Non-statutory consultees
6.1.1 DCLG Guidance (DCLG, 2013) encourages applicants to consult widely on project
proposals. Forewind has an extensive list of consultees that goes beyond those
prescribed by section 42 and those captured as part of the community consultation
process under section 47.
6.1.2 Forewind has consulted these groups according to their level of interest and
technical expertise. For example, the Royal Society for the Protection of Birds
(RSPB) was treated as a section 42 consultee and invited to meetings alongside
the Joint Nature Conservation Committee (JNCC) and Natural England, whereas
the local onshore archaeology group was invited to join the community working
group. Some non-statutory consultees were just added to Forewind‘s mailing list for
the Dogger Bank News newsletter and other project updates.
6.1.3 In addition to this, all those on Forewind‘s Dogger Bank Creyke Beck consultee
database (prescribed or non-statutory) were notified of the statutory consultation
periods and how to respond, by email wherever possible.
6.1.4 Contact methods (Freephone, Freepost, email and website) were available
throughout the pre-application period.
6.1.5 A full list of the non-statutory consultees is provided in Appendix C7.
6.2 Non-statutory consultation process
6.2.1 Whilst Forewind held two stages of statutory consultation, stakeholders were also
consulted before, between and after these statutory periods. Whilst this
consultation was not strictly carried out under a statutory section 42, 47 or 48
process, Forewind considered any feedback and it has helped to shape the
application. Such responses are classified by Forewind as ‗non-statutory
consultation‘.
6.2.2 This consultation took place by means of one-to-one meetings, workshops on
specific subjects to which several different stakeholders were invited, written
correspondence or telephone conversations. Wherever possible, Forewind
endeavoured to minimise the consultation burden on stakeholders by ensuring that,
where appropriate, multiple topics or Dogger Bank projects were covered in a
session, suitable pre-reading was sent in advance with plenty of notice, accurate
minutes of meetings were produced and an acceptable amount of time was allowed
for post meeting comments to be submitted.
6.2.3 The majority of this consultation concerned elements of the environmental impact
Assessment (EIA) process such as micro-siting, survey and assessment
methodologies and mitigation proposals. Forewind provided the Planning
Inspectorate, Marine Management Organisation (MMO) and East Riding of
Yorkshire Council (ERYC) with draft versions of the Development Consent Order
(DCO) and Consultation Report for comment.
6.2.4 A notable example of such a non-statutory workshop was the offshore EIA
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 46 © 2013 Forewind
workshop held in April 2012 (Appendix N9). This was a two day workshop to
consult statutory consultees on the data collected so far, and impact assessment
methodologies. A number of subjects were covered including physical processes,
ornithology, marine mammals as well as Forewind‘s approach to cumulative impact
assessment and habitats regulations assessment.
6.2.5 Forewind hosted an archaeology workshop in September 2012 (Appendix N13).
English Heritage and the Council for British Archaeology attended along with
representatives of Birmingham University and the Joint Nautical Archaeology Policy
Committee. Forewind presented an update on archaeology survey and
assessment.
6.2.6 In addition, Forewind sought to keep a broad range of stakeholders informed of its
progress through attending and presenting at a number of relevant conferences,
both in the UK and abroad. Examples of these are provided in Table 6.1.
Table 6.1 Examples of conferences at which Forewind presented
6.2.7 Numerous press stories about Dogger Bank Creyke Beck were published in the
Date Conference Location Summary of communication
4 May
2011
North Sea Regional
Advisory Council
(NSRAC)
London Presentation to the Spatial Planning
Working Group on Forewind‘s
development process and engagement
with European fishing community
11 May
2011
IAG Good Practice Hull An overview of the careers opportunities
and skills required in the offshore wind
industry
25 May
2011
Supply Chain Event
organised by
Scarborough Borough
Council
Whitby Supply chain introduction to Round 3
Offshore Wind with focus on Dogger Bank
3 Nov
2011
Preparing Young
People for Careers in
Offshore Wind
Whitby An overview of the careers opportunities
and skills required in the offshore wind
industry
5 Oct
2012
North Sea Days 2012
- Deltares, NIOZ &
WUR Imares
Egmond aan Zee,
Netherlands
Introduction of the Dogger Bank project to
a wide European audience consisting of
scientists and policy makers
30 Nov
2012
Renewable UK Annual
Conference
Glasgow Planning Act 2008 - Stakeholder
engagement and consultation
6 Mar
2013
SNS2013: The Sea of
Opportunity
Norwich Developing the world‘s largest offshore
wind project: Dogger Bank
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 47 © 2013 Forewind
national, industry and regional press, publicising the progress of the development
and the consultation activity. They appeared in both printed and online versions. On
the whole, press coverage was focussed on the opportunity to create jobs and
develop the offshore renewables supply chain both in the Yorkshire region and the
wider UK. A significant amount of local press coverage was generated by the
Champions for Wind careers education programme that Forewind launched in the
East Riding of Yorkshire in partnership with the Humberside Engineering Training
Association (HETA). Some examples of press coverage are included in Appendix
O.
6.3 Fisheries liaison
6.3.1 Forewind made it clear, from the start of the development process, that engaging
with the fishing industry is a fundamental element of its consultation strategy by
inviting representatives of both national and international fishing organisations to the
Zone Appraisal and Planning (ZAP) workshops (Appendix N1).
6.3.2 At this early stage in the development process, Forewind also appointed two
individuals with considerable experience of the fishing industry within the North Sea
to undertake the role of Fisheries Liaison Co-ordinators (FLC). The FLCs are
responsible for engagement and negotiations with key UK national and international
fishing organisations, such as the North Sea Regional Advisory Council (NSRAC),
the National Federation of Fishermen‘s Organisations and the Scottish Fishermen‘s
Federation, and other equivalent bodies in other relevant countries around the North
Sea whose fishing vessels operate or have operated in areas relevant to the
potential development zone. They also provide advice and support to Forewind on
fishing issues, managing any fishing related data and ensuring that Forewind
complies with relevant guidance and legislation.
6.3.3 Given the varying location of fishing activity on the Dogger Bank over the course of
the year, it was recognised that fisheries liaison would have to be on a zonal, near
shore and cable corridor basis, rather than on a project basis. This is in accordance
with section 2.6.128 of the National Policy Statement for Renewable Energy
Infrastructure (EN-3), which states that:
Where a number of offshore wind farms have been proposed within an
identified zone, it may be beneficial to undertake such consultation at a zonal,
rather than a site-specific, level.
6.3.4 In November 2011, Forewind published its Fisheries Liaison Plan. This plan sets
out Forewind‘s objectives and approach to fisheries liaison, and is in line with the
Fisheries Liaison with Offshore Wind and Wet Renewables Group
―Recommendations for Fisheries Liaison - Best Practice guidance for offshore
renewables developers‖ (The Department for Business, Enterprise and Regulatory
Reform, 2008). The Fisheries Liaison Plan was updated and republished in April
2013. Both versions of the Fisheries Liaison Plan are provided in Appendix B.
6.3.5 The Fisheries Liaison Plan was referenced in the Statement of Community
Consultation (Appendix F4) to acknowledge that some near shore fishermen may
wish to engage in the community consultation process as well as, or instead of, the
fisheries liaison process. However, very few fishermen have engaged in the
community consultation process to date, instead choosing to attend the fishing-
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 48 © 2013 Forewind
specific meetings that Forewind held during the statutory consultation periods or
liaising on a one-to-one basis with Forewind‘s FLCs. In addition, Forewind met
several times with the Bridlington and Flamborough Fishermen‘s Society, Hornsea
Fishermen, Withernsea Fishermen and the Holderness Coast Fishing Industry
Group, as well as the principal of Normandale Trawlers Ltd, based in Scarborough.
6.3.6 Forewind consulted the international fishing community by attending and presenting
at several NSRAC meetings and organising one-to-one meetings with relevant
fishing industry bodies. These included national and regional fishermen‘s
representative organisations, as well as individual skippers and fishing vessel
owners from Norway, the Netherlands, Sweden, Denmark, Belgium, France and
Germany. Consultation meetings were also held with national fisheries directorates,
national fisheries departments, data centres and fisheries research institutes.
6.3.7 At the second stage of statutory consultation, Forewind produced the first edition of
a fishing newsletter called Fishing News, which will be distributed approximately
three times a year going forwards. Fishing News is provided in Appendix I2.
6.3.8 Any consultation responses received from offshore fishing stakeholders are
recorded as being relevant to the whole Dogger Bank Zone and, therefore, may
have influenced the development of other stages of the Dogger Bank Zone. Any
consultation responses received from near shore fishermen are considered as
being only relevant to Dogger Bank Creyke Beck.
6.3.9 Many of the survey vessels undertaking work on behalf of Forewind have a
Fisheries Liaison Representative (FLR) on board, who liaises directly with any
fishing vessels encountered during the surveys. Contact details for these FLRs are
published in the Notice to Mariners issued before each survey begins.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 49 © 2013 Forewind
7 Consultation under the EIA and Habitats Regulations
7.1 Introduction
7.1.1 Advice Note Fourteen (The Planning Inspectorate, 2012) states:
“Applicants may wish to draw attention to consultation responses received
under the EIA process, but any reference to this consultation should be kept
separate from the statutory consultation carried out under the Provisions of
the Planning Act 2008.‖
7.1.2 The pre-application publicity and consultation requirements of the Infrastructure
Planning (Environmental Impact Assessment) Regulations 2009 (the EIA
Regulations) are consistent with those of the Planning Act 2008 (the Planning Act).
Consultation on preliminary environmental information (PEI) is an integral part of the
Planning Act consultation process and therefore, in the most part, it is difficult to
separate these two processes and the responses received. Chapters 3, 4 and 5 of
this report explain what, when and how PEI was made available to consultees as
part of the Planning Act process.
7.1.3 Chapter 8 of this report summarises the key issues raised during consultation by
categorising them into chapters of the Environmental Statement (ES). Care has
been taken to ensure that the responses have been suitably categorised and that
points were not missed.
7.1.4 Evidence that Forewind has complied with EIA Regulation 10 (Consultation
statement requirements) is provided in Chapter 4. Evidence that Forewind has
complied with EIA Regulation 11 (Pre-application publicity under section 48) is
provided in Chapter 5.
7.1.5 The sections below summarise the consultation processes that specifically relate to
EIA Regulation 8 (Application for a scoping opinion) and EIA Regulation 24
(Development with significant trans-boundary effects).
7.1.6 A brief summary of the consultation process undertaken in accordance with the
Habitats Regulations is also provided below. A summary of issues raised during
this consultation is provided in Chapter 8.
7.2 Scoping
7.2.1 On the 13 October 2010 Forewind submitted a request to the Infrastructure
Planning Commission (IPC) for a Scoping Opinion on Dogger Bank Project One – a
single offshore wind farm with a 1GW grid connection at the Creyke Beck
Substation. Forewind provided the Dogger Bank Project One Scoping Report to
support this request. The IPC provided its Scoping Opinion on the 18 November
2010 (Planning Inspectorate document reference number 6.4.3).
7.2.2 In submitting the information in the Scoping Report, Forewind was deemed to have
notified the IPC under Regulation 6(1)(b) of the EIA Regulations that it proposed to
provide an ES in respect of the proposed Dogger Bank Project One.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 50 © 2013 Forewind
7.2.3 Following receipt of the Scoping Opinion, Forewind secured additional connection
capacity at the existing National Grid Electricity Transmission (NGET) Creyke Beck
Substation, increasing the total connection capacity to 2GW.
7.2.4 Forewind did not repeat the Scoping process as the location of the infrastructure
and approach to the environmental assessment for Dogger Bank Creyke Beck were
not materially different to that for Dogger Bank Project One. This approach was
discussed with the IPC in a meeting on the 7 September 2011 (Appendix N4),
where the IPC stated that Scoping is not a mandatory requirement under the EIA
Regulations, and that should a scheme change substantially during the EIA
process, it is for the developer to decide whether a new Scoping Opinion is
required. The Joint Nature Conservation Committee (JNCC) supported Forewind‘s
decision to not repeat the Scoping process in a meeting on the 1 March 2012
(Appendix N8).
7.2.5 In December 2011, Forewind carried out the first stage of consultation on PEI in
accordance with sections 42 and 47 of the Planning Act on Dogger Bank Creyke
Beck, a development comprising up to two wind farm arrays, both connecting to the
NGET Creyke Beck Substation. The consultation documents produced at this
stage, PEI1, explained the change in scale of the scheme and included an appendix
entitled ―Approach to the Environmental Impact Assessment‖. This provided an
update on Forewind‘s approach to EIA but was not a formal request for a new
Scoping Opinion.
7.3 Transboundary consultation
7.3.1 In the Dogger Bank Project One Scoping Report, Forewind noted that, due to the
Dogger Bank Zone being located adjacent to the UK‘s international boundary,
consideration would be given to the effects on the environment of other European
Economic Area (EEA) member states, including cumulative impacts with other
projects, in accordance with Regulation 24 of the EIA Regulations and the Espoo
Convention (1991).
7.3.2 The IPC acknowledged this requirement in its Scoping Opinion and stated that
Forewind should consult the consenting bodies in other European Union (EU)
states to assist in identifying any cumulative effects with other developments. No
responses from transboundary consultees were received during the first stage of
statutory consultation.
7.3.3 On the 7 August 2012, the Planning Inspectorate published a notice (Appendix L1)
in the London Gazette (in accordance with Regulation 24 of the EIA Regulations),
stating that the Dogger Bank Creyke Beck development may have significant
effects on the environment in Belgium, Denmark, France, Germany, Netherlands,
Norway and Sweden. It also wrote to these EEA States and set a deadline of the
18 September 2012 by which they should indicate their interest in participating in
the process to examine the application. Forewind was also notified by letter
(Appendix L2).
7.3.4 The description of the Dogger Bank Creyke Beck development given in the
Regulation 24 notice was based on the description of the project given in the
Scoping Report and hence was out of date. This was discussed in a meeting
(Appendix L3) with the Planning Inspectorate on the 15 November 2012, at which
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 51 © 2013 Forewind
the Planning Inspectorate acknowledged that the description of the scheme was
incorrect but considered that it would not make a fundamental difference to whether
any of the EEA Member States would want to participate. Therefore, the Planning
Inspectorate stated that it would not republish the notice.
7.3.5 The Planning Inspectorate has a duty to consult any EEA State that registers a
relevant response to the Regulation 24 notice. To date, Forewind is aware that
Germany and the Netherlands have notified the Planning Inspectorate of their
interest in being consulted on Dogger Bank Creyke Beck (Appendix L4).
7.3.6 Between September and November 2012, Forewind wrote to the consenting bodies
in the seven EEA states in which there is potential for likely significant effects on the
environment (Appendix N12). The contacts used in this consultation were those
provided by the Planning Inspectorate and also wider contact was made with
government ministries with responsibility for nature conservation, where these could
be established. This letter was accompanied by a transboundary screening note
and a Habitats Regulations Assessment pre-screening report for transboundary
consultees on which comment was sought, and a meeting was requested to discuss
these documents in more detail.
7.3.7 Forewind subsequently met with the German Maritime and Hydrographic Agency
and the Dutch Ministry for Infrastructure and Environment (Rijkswaterstaat
Waterdienst). In addition, Forewind consulted various international fishing and
shipping organisations and government departments throughout the development
process, both during statutory consultation periods and on a non-statutory basis.
Full details of Forewind‘s consultation with fishing organisations are provided in
Section 6.3.
7.4 Habitats Regulations Assessment
7.4.1 In accordance with DCLG Guidance (DCLG, 2013), Forewind consulted UK
statutory bodies (Natural England, the JNCC, the MMO, the Centre for
Environment, Fisheries & Aquaculture Science (Cefas)) and non-statutory bodies
(RSPB and the Wildlife Trust) as well as trans-boundary consultees in order to gain
evidence for the Habitats Regulation Assessment (HRA).
7.4.2 In September 2012, Forewind produced a list of all sites protected under the
Habitats Directive, Birds Directive and any Ramsar sites that had the potential to be
affected by Dogger Bank Creyke Beck. This ―HRA Pre-Screening Matrix‖ was sent,
with a request for a meeting (Appendix N12), to contacts provided by the Planning
Inspectorate and relevant additional government ministries with responsibility for
nature conservation.
7.4.3 Forewind discussed the HRA Pre-Screening Matrix with the German Maritime and
Hydrographic Agency and the Dutch Ministry for Infrastructure and Environment
(Rijkswaterstaat Waterdienst) during the meetings detailed above in the
―transboundary consultation‖ section.
7.4.4 Subsequently, in November 2012, Forewind produced a HRA Screening Report
which identified the likely significant effects arising from Dogger Bank Creyke Beck
upon sites designated under the Habitats and Birds Directives. This was circulated
to JNCC, Natural England, the MMO and the RSPB in addition to the Planning
Inspectorate and the Department of Environment Food and Rural Affairs (DEFRA).
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 52 © 2013 Forewind
A meeting was held on the 14 February 2013 (Appendix N7) with JNCC and
Natural England to discuss their views on this report to feed into the draft HRA
Report.
7.4.5 The draft HRA Report was finalised based upon comments from the statutory
nature conservation bodies and this document was available for consultation during
the second stage of statutory consultation. Written comments on this draft HRA
Report were received from JNCC and Natural England (jointly) and the RSPB and
subsequently a two day workshop was held in June 2013, at the end of the statutory
consultation period, during which further comments were made (Appendix N16).
Where appropriate, these have been incorporated into the final version of the HRA
Report which includes information to inform the appropriate assessment (Planning
Inspectorate document reference number 5.2).
7.4.6 A point by point response detailing how Forewind had regard to the points raised by
JNCC together with Natural England at the second stage of statutory consultation is
included in Appendix N17.
7.4.7 The production of Statements of Common Ground has been agreed in principle with
the relevant nature conservation bodies and the production of these documents will
continue to progress during and after the submission of the application for a DCO.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 53 © 2013 Forewind
8 Summary of relevant responses
8.1 Introduction
8.1.1 The following sections of the Consultation Report summarise the key issues that
were raised during consultation and how Forewind took account of relevant
responses. In some instances Forewind was not able to change the proposals in
accordance with consultation feedback. Where this applies, it is clearly explained.
8.1.2 In most cases, consultation was an iterative process taking place over several
months or years. To document all consultation in detail in this report would be
neither practicable nor helpful, so the intention of this chapter is to draw out the key
issues only, with a focus on the statutory consultation periods.
8.1.3 The responses are summarised below by their relevance to the chapters of the
Environmental Statement (ES) or other application document. No comments were
received that specifically related to Chapter 1 Introduction, Chapter 2 Project Need,
Chapter 3 Legislation and Policy and Chapter 34 Conclusion of the ES. To avoid
un-necessary repetition, any comments relating to Chapter 31 Inter-relationships,
Chapter 32 Transboundary Effects, Chapter 33 Cumulative Impact Assessment and
Chapter 35 Summary of Monitoring and Mitigation are captured within the relevant
subject sections.
8.1.4 Care has been taken to ensure that the responses are categorised into subjects
appropriately. Where a response referred to multiple ES subjects or application
documents, that response is referenced in each subject table that it refers to.
8.1.5 References are made to the ES (Planning Inspectorate document reference
number 6).
8.1.6 Tables of all relevant responses to the statutory consultation periods, categorised
by ES subject or other application document, are provided in Appendix M.
8.2 General comments
8.2.1 The public exhibition questionnaires made available at both stages of statutory
community consultation included some generic questions, as well as specific
focussed questions relating to what Forewind was consulting on at that stage.
8.2.2 281 visitors signed in at the public exhibitions in December 2011, and of those, 56
people returned questionnaires. Of the 45 people who answered question seven:
―What are your impressions of the project?‖, 73% responded ―positive‖, ―18%
responded ―neutral‖ and 9% responded ―negative‖.
8.2.3 281 visitors also signed in at the public exhibitions in May 2013, and of those, 77
people returned questionnaires. Of the 62 people who responded to question three
―Do you support the concept of the Dogger Bank Creyke Beck‖, 76% said ―yes‖,
15% said ―no‖ and 10% said ―unsure‖. This demonstrates a slight increase in
support for the project over the course of the pre-application stage.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 54 © 2013 Forewind
8.3 Health and Safety
Main stakeholders and methods of consultation
8.3.1 Health and safety is considered within various human topic areas within the ES and
hence the relevant stakeholders for those topics have been consulted. These
include stakeholders involved in military activities, civil aviation, commercial fishing
and shipping.
8.3.2 The Health and Safety Executive, the Health Protection Agency and Public Health
England have an overarching responsibility to ensure that human health and health
and safety is taken into account throughout the project phases; these stakeholders
have also been included in formal consultation throughout pre-application.
8.3.3 For full details of consultation responses please see Appendix M3.
Key Issues raised
8.3.4 Only Health and Safety issues which have not been covered in topic specific
chapters are discussed here and include the following areas:
That pipeline operators should be consulted to ensure that activities associated
with the construction and operation of Dogger Bank Creyke Beck will not pose a
health and safety risk;
That a Health Impact Assessment (HIA) should be prepared;
That electric and magnetic fields (EMFs) associated with the operation of the
onshore high voltage cabling be provided and assessed against the
International Commission on Non-Ionizing Radiation Protection (ICNIRP)
guidelines; and
The importance of electrical safety and chemicals.
Stakeholder feedback and Forewind response
8.3.5 NHS Hull raised the potential health impact associated with the electric and
magnetic fields around substations and the connecting cables or lines as a concern.
The Health Protection Agency made recommendations on limiting public exposure
to EMFs and supports the view that precautionary measures should address solely
the possible association with childhood leukaemia, as opposed to other more
speculative health effects. These issues were considered within a Health Impact
Assessment (HIA) prepared by Forewind that is included as Appendix 5C to
Chapter 5 Project Description of the ES.
8.3.6 Public Health England expects that the operating voltages and worst case field
levels are clearly defined within a HIA. These were presented in the Health Impact
Assessment prepared by Forewind. Any EMFs produced by the onshore Dogger
Bank Creyke Beck assets are well below the accepted threshold levels, and reduce
to background levels within a few metres. No human health impacts have been
identified attributable to EMFs. Forewind also produced an EMF factsheet in
response to the concerns at stage two of the consultation process (Appendix H10).
8.3.7 In relation to electrical safety and chemicals, Forewind has developed a Health and
Safety Statement (Planning Inspectorate document reference number 8.4),
which details the response Forewind has had to these issues.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 55 © 2013 Forewind
8.4 EIA Process (ES Chapter 4)
Main stakeholders and methods of consultation
8.4.1 Comments received through the scoping process during 2010 were used to inform
the selection of survey methodologies for the Environmental Impact Assessment
(EIA). At the first stage of statutory consultation in December 2011, a consultation
document called ―Approach to the EIA‖ was provided to stakeholders as part of
Preliminary Environmental Information 1. This gave an update on the approach to
the EIA and took into account any changes following receipt of the scoping opinion.
8.4.1 During 2012, a series of non-statutory consultation workshops and meetings were
held, at which Forewind presented EIA methodologies to key stakeholders. These
culminated in a two day offshore workshop in April 2012 (Appendix N9) which was
attended by the Centre for Environment, Fisheries and Aquaculture Science
(Cefas), the Joint Nature Conservation Committee (JNCC), the Marine
Management Organisation (MMO), Natural England, the Royal Society for the
Protection of Birds (RSPB), and the Wildlife Trusts. This meeting was used as a
forum to present the finalised survey methodologies and to discuss the next steps in
taking data through the EIA process. Several survey methodologies (for example
on fish ecology and marine physical processes) were signed off at this meeting as
the information presented enabled the stakeholders to agree that the methodologies
were sound. In addition, comments and feedback from this non-statutory
consultation was used to further progress the EIA methodologies for some topics
such as marine and coastal ornithology.
8.4.2 For summaries of all relevant responses please see Appendix M4.
Key issues raised
8.4.3 In addition to comments on the overarching EIA methodology which apply
throughout the Dogger Bank Creyke Beck ES, various comments have been
received relating to specific elements of the methodology applied for specific
receptors. As these are receptor specific, these comments have been considered
in the individual topic chapters and further information on these responses can be
found below, in the relevant sections of Chapter 8 of this consultation report.
8.4.4 Comments relating to the EIA process for the offshore environment included:
The scale of the proposals and how this would be accounted for in the EIA
methodology;
Transboundary impacts and how this might influence the methodology adopted;
Cumulative impacts with other developments in the area;
Adequate consideration should be given to certain ecological impacts such as
marine and coastal ornithology;
8.4.5 For the onshore environment, it was noted that appropriate attention should be paid
to the following topics:
Coastal erosion at the landfall, given the dynamic nature of landform changes in
the area;
Flooding, as the land tends to be low-lying and prone to flooding;
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 56 © 2013 Forewind
Ecological impacts – loss of and disturbance to habitats, with consequent
impacts on protected species;
Landscape impacts – from the construction of the proposed converter stations;
Noise impacts – from construction, including traffic; and
Archaeology – disturbance to known and unknown archaeological sites.
Stakeholder feedback and Forewind response
8.4.6 The Planning Inspectorate has produced an advice note on the use of the Rochdale
Envelope. This outlines the level of detail required and degree of flexibility in the
design as well as the need for inter-relationships to be assessed, so that the
impacts of the proposal as a whole are addressed.
8.4.7 Consultation with transboundary and UK shipping and navigation stakeholders
identified a desire for a report identifying and considering the cumulative effects of
the Dogger Bank, Hornsea and East Anglia Offshore Wind Farm Zones. As a
result, Forewind, alongside SmartWind and East Anglia Offshore Wind
commissioned a study under the Southern North Sea Offshore Wind Forum to
analyse the cumulative impacts of the development plans of the three zones. This
study considers the transboundary shipping routes passing through the Southern
North Sea and has been used in the assessment presented in ES Chapter 16,
Shipping and Navigation.
8.4.8 Forewind developed a cumulative impact assessment strategy (ES Appendix 4A
Forewind CIA Strategy – Offshore).
8.4.9 Forewind has given careful consideration to all potential impacts that may result
from Dogger Bank Creyke Beck, for each parameter, and ensured that the
assessment made for each potential impact is reflective of the realistic worst case
scenario for the specific parameter under investigation. In relation to determining
the ‗worst case scenario‘ Forewind has ensured that only realistic development
scenarios are considered.
8.4.10 The EIA process has been developed to provide an assessment of the impacts of
the development on sensitive receptors. This systematic and auditable approach is
encompassed by Forewind‘s EIA framework which is based on the Source-
Pathway-Receptor model. Appropriate mitigation measures will be proposed in
conjunction with the Regulatory Authorities and relevant stakeholders.
8.5 Project description (ES Chapter 5)
Main stakeholders and methods of consultation
8.5.1 A number of stakeholders commented on elements of the project description as part
of their feedback on receptor specific assessments presented in the preliminary
environmental information. Key issues that were raised and that have impacted the
project description are highlighted in this section and may also be referred to in the
receptor specific sections below.
8.5.2 Stakeholders that commented on the project description included:
JNCC, Natural England and RSPB (ornithology);
The Maritime and Coastguard Agency (MCA), Trinity House Lighthouse
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 57 © 2013 Forewind
Services (THLS), the Chamber of Shipping and various vessel operators
(navigational safety);
A Grimsby based fishing vessel owner (seine fishing);
The Environment Agency (impact of culverts on water flow); and
The local community (onshore converter station site design).
8.5.3 For summaries of all relevant responses please see Appendix M5.
8.5.4 Additional feedback was received relating to site selection, which is covered in
Section 8.4 and Appendix M6.
Key Issues raised
The ornithology collision risk associated with the number of turbines and the
lower blade tip height;
The navigational safety risks associated with vessels transiting through the
zone;
The impact of curved layouts on navigational safety;
Turbine spacing and the impact on seine net fishing;
The impact of introducing new culverts on the flow of water; and
Preference for a shorter converter station building height and larger footprint
rather than a taller building with a smaller footprint.
Stakeholder feedback and Forewind response
8.5.5 Preliminary assessment work suggested potentially significant impacts on
ornithology. In order to mitigate the impact associated with collision risk, the design
envelope was refined to include:
A maximum number of 200 turbines per project (i.e. reduced by 33% from 300);
and
An associated increase in the minimum lower blade tip height (from 22m to
26m) above highest astronomical tide.
8.5.6 Early consultation with a wide range of navigation stakeholders indicated that, due
to the very small deviation distances required to bypass the Zone, and potential
navigation safety concerns associated with vessels passing between Dogger Bank
projects, it was seen as undesirable for transiting vessels to pass through the Zone.
8.5.7 The Zone design was therefore progressed without including corridors for the
navigation of transiting vessels, and project boundaries were not developed to
enable easy access for transiting vessels to pass through the zone.
8.5.8 In response to consultation with the MCA and THLS, Forewind introduced site
layout rules that restrict the potential turbine array patterns employed, in an effort to
provide clarity on what would and would not be considered during the detailed
project design phase. In response to comments on the site layout rules at the
second stage of statutory consultation, the rules were modified to state that only
straight rows would be permitted for Dogger Bank Creyke Beck (although retaining
the option for curved perimeters). The final site layout rules will be subject to
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 58 © 2013 Forewind
approval by the MMO.
8.5.9 The commercial fisheries assessment acknowledged that the seine fishery could
not necessarily continue within the project boundaries should the minimum turbine
spacing be taken forward, but that it could continue between Dogger Bank Creyke
Beck A, Dogger Bank Creyke Beck B and Dogger Bank Teesside B (see Section
8.4).
8.5.10 The necessity for using temporary or permanent culverts for access across ditches
was queried by the Environment Agency. The Environment Agency highlighted that
their own culverting policy is for the removal of culverts and that a justification will be
required wherever culverts are requested. Given the number of ditch crossings and
the potential for sensitive species, such as water voles, the use of culverts
(temporary and permanent) was removed from the project description and the DCO.
A temporary vehicle bridge solution will be used to cross ditches.
8.5.11 Questionnaire responses, provided at the public exhibitions in December 2011,
identified a preference for lower converter station buildings with a larger footprint,
with the converter roof height to be kept in line with existing woodland. Forewind
has observed these preferences in the final proposals and has included a
landscaping strategy in the proposals as mitigation.
8.6 Site selection and alternatives (ES Chapter 6)
Main stakeholders and methods of consultation
8.6.1 Site selection and the consideration of alternatives are relevant to all technical
topics assessed within the ES and hence the relevant stakeholders for those topics
have been consulted. Onshore, the Parish Councils, landowners and members of
the local community played a significant role in selection of the final onshore cable
route and converter stations sites.
8.6.2 At the first stage of statutory consultation in December 2011 to January 2012, all
stakeholders were asked to provide feedback on the proposed location of the
development, within a study area that had been significantly narrowed down since
Scoping. A reasonably broad area was identified offshore (namely Tranche A of the
Dogger Bank Zone) within which the wind farm infrastructure itself would be sited,
and a 2km wide offshore cable corridor was proposed. There were two options for
the landfall location, a 1km wide onshore cable corridor and an onshore converter
station ―study area‖.
8.6.3 A workshop was held with officers from East Riding of Yorkshire Council (ERYC)
and the Environment Agency on 26 January 2012 (Appendix N6) to consider the
preferred sector (within the wider study area proposed during the first stage of
statutory consultation) for locating the converter stations site.
8.6.4 The local community was consulted both through public exhibitions and a converter
station community working group (Appendix J), established by Forewind following
a request raised during the first stage of statutory consultation. This group was
closely involved in the site selection and micro-siting of the converter stations as
well as the siting of the onshore high voltage alternating current (HVAC) cable route
and construction access.
8.6.5 At the second stage of statutory consultation, the location of the proposals both
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 59 © 2013 Forewind
onshore and offshore had been refined. All stakeholders were, however, asked to
comment on two alternative options for the onshore cable route through
Woodmansey.
8.6.6 For summaries of all relevant responses please see Appendix M6.
Key Issues raised
8.6.7 Offshore, the key issues raised were:
The location of the sandeel fishery on the western margins of the Dogger Bank
Zone;
The location of the seine fishing areas within the Dogger Bank Zone;
Pipelines and cables running through, or close to the Dogger Bank Zone;
The need for a buffer to aggregate application area 466/1; and
Known wrecks at the point at which the export cable exits Dogger Bank Creyke
Beck A.
8.6.8 Onshore, the key issues raised were:
Minimising cumulative impacts at the landfall by avoiding the location selected
for the National Grid Carbon Pipeline landfall;
Minimising impacts of the cable route on land use;
At Woodmansey, a preference for the northern cable route option through
Figham Common rather than the southern cable route through private land
A preference to co-locate converter stations;
Preference for a converter stations site that could be accessed from the A1079
rather than Park Lane, that avoided areas of flood risk and that offered greater
potential for landscape screening;
A preference for the Eastern option for the HVAC cable route.
Stakeholder feedback and Forewind response
8.6.9 The IPC (now the Planning Inspectorate) and the JNCC recommended in their
Scoping Opinions that the ES must outline the main alternatives and provide an
indication of the main reason for the applicant‘s choice, taking account of the
environmental effects. The reasons for the preferred choice should be made clear
and the comparative environmental effects identified. Forewind has presented this
in ES Chapter 6 - Site Selection and Assessment of Alternatives and in the
Planning and Design Statement (Planning Inspectorate document reference
number 8.1).
Offshore
8.6.10 Offshore project boundaries were selected to avoid the high density sandeel areas
towards the western boundary of the Dogger Bank Zone. Specifically, the Dogger
Bank Creyke Beck B project boundary was moved to the east of the Shearwater
Elgin Area Line (SEAL) pipeline. This measure will benefit commercial fisheries
targeting sandeel, as well as fish and bird species for which the sandeel forms a
major part of the diet and plays an important part of the North Sea ecosystem.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 60 © 2013 Forewind
8.6.11 The project boundaries of the first four projects (Dogger Bank Creyke Beck and
Dogger Bank Teesside) left the seine net area between Creyke Beck A, Creyke
Beck B and Teesside B open for this fishery.
8.6.12 The design of the Dogger Bank Creyke Beck B boundary also took into account the
request for a 2km buffer between the project boundary and the aggregate
application area 466/1.
8.6.13 The location of the export cable corridor was selected in order to avoid the locations
of known wrecks at the point at which it exits Dogger Bank Creyke Beck A.
Onshore
8.6.14 Two options for a possible cable landfall location were presented at the first stage of
statutory consultation. Whilst not many responses were received on this point,
feedback generally indicated that the preferred cable route should be the shorter of
the two options. Therefore, the landfall located to the north of Ulrome and south of
Barmston, was taken forward as the preferred option.
8.6.15 Forewind had regular update calls with National Grid regarding the location of their
pipeline landfall with the aim of minimising cumulative impacts caused by landfall
works. At the point of writing (August 2013), National Grid and Forewind have
selected different landfall locations for their respective projects.
8.6.16 During the site selection process, Forewind regularly met with individual landowners
to discuss the micro-siting of the onshore cable route across their land.
Approximately 35 requests for minor alignment adjustments were received from
landowners during this process to reduce land wastage and minimise disruption to
the existing land uses. Examples of cable route realignment requests are provided
in Appendix M2. Approximately 30 of these requests resulted in the suggested
adjustment being adopted within the preferred alignment. The remaining proposed
changes were identified as resulting in an unacceptable engineering or
environmental concern and were not taken forward.
8.6.17 At the second stage of statutory consultation, several landowners and members of
the local community objected to the southern option for the cable route through
Woodmansey. Therefore, the northern option, through Figham Common was
selected as the final proposed route.
8.6.18 The converter station sites were co-located as per stakeholder feedback. The
preferred sector of the study area (Sector A) was agreed with ERYC and the
Environment Agency at the workshop in January 2012. The proposed converter
stations site itself was originally identified by members of the Community Working
Group during the first meeting in March 2012 (Appendix J5).
8.6.19 The final design of the converter stations site will be decided post consent and will
be subject to approval by ERYC.
8.6.20 In line with community feedback (Appendices J6 and J7), the Eastern option for
the HVAC cable route was taken forward.
8.7 Consultation (ES Chapter 7)
Main stakeholders and methods of consultation
8.7.1 Forewind sought feedback on its approach to consultation in the public exhibition
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 61 © 2013 Forewind
questionnaires at both stages of statutory consultation. In addition, Forewind
received relevant responses from a number of consultees including ERYC, RSPB,
MMO, JNCC and the Environment Agency that referenced Forewind‘s approach to
consultation.
8.7.2 For summaries of all relevant responses please see Appendix M7.
8.7.3 Relevant responses to the consultation on the content of the Statement of
Community Consultation, is detailed in Chapter 4 and Appendix M1 of this report
and, as such, is not repeated here.
Key Issues raised
8.7.4 In summary, the key issues relating to Forewind‘s approach to consultation were:
Length of the consultation period and requests to extend response deadlines;
Support for Forewind‘s approach to consultation;
Invitations to the public exhibitions were the most successful method of
publicising the events to local community consultees;
The majority of those who returned a questionnaire considered that the public
exhibitions provided enough information;
Need to continue consulting local communities through the construction phase;
and
Concerns about the adequacy of consultation on the alternative cable route in
the Woodmansey area.
Stakeholder feedback and Forewind response
8.7.5 Forewind received requests to extend the deadline for responses at the first stage
of consultation from the JNCC and Natural England, and at the second stage of
consultation from the MMO and the North Eastern Inshore Fisheries and
Conservation Authority. The deadline for responses at both stages of consultation
was longer than the statutory minimum of 28 days and therefore Forewind was not
able to officially extend the deadlines any further without unacceptable delay to the
development programme. Forewind was, however, able to take into account all late
responses received.
8.7.6 General comments of support for Forewind‘s approach to consultation were
received from ERYC, the Environment Agency, RSPB and Yorkshire Water
Services.
8.7.7 At the both stages of statutory consultation, the public exhibition questionnaire
asked consultees how they heard about the exhibitions, whether they thought the
exhibitions provided enough information, and how Forewind could improve its
communications with the local community.
8.7.8 At both stages, the most popular answer to the question about how the consultee
heard about the exhibitions was ―Forewind invitation‖ (38% and 37% respectively),
followed by ―newspaper advert‖ (16% and 24% respectively). This demonstrated
that direct distribution of invitations was the most effective way of reaching the local
community, and that other methods, including posters, radio and the Forewind
website were less effective. At the second stage of consultation, Forewind put up
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 62 © 2013 Forewind
more posters and as a result, this became the third most common answer to the
question (15%).
8.7.9 At the second stage of consultation, 90% of people who responded to question 16
―Could we improve our communication with you?‖, said ―no‖, indicating that the
contact methods used were, on the whole, appropriate for this community.
8.7.10 The majority of questionnaires indicated that the exhibitions provided visitors with
enough information (98% and 89% respectively).
8.7.11 Suggestions about how to improve communications after both stages of
consultation included keeping the Parish Councils up to date, newsletters and more
coverage in local newspapers and on the radio. Following the stage one
consultation, Forewind continued to respond to Parish Council requests for a
Forewind representative to attend meetings, and invited all directly affected Parish
Councils to attend the cable route workshops in August 2012. Forewind began
publishing the Dogger Bank News newsletter in Spring 2012, and this will continue
to be distributed to all stakeholders directly by post or email. In addition, Forewind
continues to make regular press releases which are picked up by local newspapers
and radio.
8.7.12 A very specific request to improve local community involvement in the converter
station site selection and design was received from Cottingham Parish Council at
the first stage of statutory consultation. This led to the establishment of the
Converter Station Community Working Group (Appendix J). At the final meeting,
the Chair of the group stated that she felt that Forewind‘s approach in this regard
was ―refreshing and an example for other organisations to follow”.
8.7.13 Forewind has taken note of the request to continue to keep the local community,
and specifically the Parish Councils, informed and this is reflected in the Outline
Code of Construction Practice which has been submitted with the application for a
DCO (Planning Inspectorate document reference number 8.2).
8.7.14 At the second stage of consultation, Forewind received a number of letters from
three landowners and two occupiers of properties in the Woodmansey area stating
that they were dissatisfied with Forewind‘s consultation process. The MP for
Beverley and Holderness also contacted Forewind in relation to their concerns,
which particularly related to the alternative cable route as it affected land in which
they had an interest. They felt that they had not been adequately consulted on this
alternative route and that, despite attending the public exhibitions, had not had their
questions answered.
8.7.15 Forewind responded in writing to each of the letters and offered meetings to discuss
the proposals in more detail, however only the MP agreed to meet. Following the
consultation period, Forewind removed the alternative route from the proposals and
wrote to all affected persons to explain the decision. No further correspondence on
this matter was received from these consultees.
8.8 Designated sites (ES Chapter 8)
Main stakeholders and methods of consultation
8.8.1 Comments relating to designated sites were received from JNCC, Natural England,
English Heritage and the Yorkshire Wildlife Trust. Other stakeholders made
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 63 © 2013 Forewind
comments on designated sites in relation to specific topics of assessment and these
are considered in the relevant sections.
8.8.2 For summaries of all relevant responses please see Appendix M8.
Key issues raised
8.8.3 Very few comments were made specifically in relation to designated sites as this
chapter is intended to be a summary of other assessments, but key items included:
How assessments have been made and how species of conservation interest
have been considered; and
The approach to the consideration of future designations.
Stakeholder feedback and Forewind response
8.8.4 Forewind agreed with the comments received from the JNCC and Natural England
on this chapter at the second stage of statutory consultation, and appropriate
amendments were made as a result.
8.8.5 In relation to how assessments have been made, Forewind explained that this
chapter is a signposting chapter and presents the conclusions from a number of
other chapters within the ES.
8.8.6 Regarding the consideration of future designations such as Marine Conservation
Zones (MCZ), Forewind chose to screen in the Holderness Offshore and
Holderness Onshore recommended MCZs but not the Swallow Sands
recommended MCZ. This is justified in Chapter 12 Marine and Intertidal Ecology
of the ES, where the assessment of impacts on these MCZs is presented.
8.9 Marine physical processes (ES Chapter 9)
Main stakeholders and methods of consultation
8.9.1 Stakeholders consulted on marine physical processes include Cefas, ERYC, JNCC,
Natural England, the MMO, the Environment Agency (EA), Wildlife Trusts (WT) and
the local community.
8.9.2 For summaries of all relevant responses please see Appendix M9.
Key Issues raised
8.9.3 The key issues that were raised during consultation were:
Coastal erosion, particularly at the landfall location;
Effects on sediment transport of seabed cable protection and other construction
near-shore;
Hydrodynamic and sedimentary processes, particularly the possibility of
increased suspended sediment concentrations and deposition on the seabed
due to construction and operational activities; and
Scour and scour protection, including direct loss of habitat through side casting
and scour protection itself and the timescales over which scour will affect
processes.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 64 © 2013 Forewind
Stakeholder feedback and Forewind response
8.9.4 Potential impacts of the landfall works on coastal erosion, such as increasing the
already fast rate of natural erosion, and future exposure of buried landfall cables
were raised by several members of the local community and the coastal Parish
Councils, particularly Barmston & Fraisthorpe, and Lissett & Ulrome.
8.9.5 In the Dogger Bank Project One Scoping Opinion, ERYC advised Forewind to
consider the emerging Shoreline Management Plan 2 and this was later supported
by the Environment Agency. This plan states that a policy of ‗No Active
Intervention‘ is in place in the location of the landfall, in other words nature will be
allowed to take its course. Forewind was therefore obliged to demonstrate that the
landfall works would have a negligible effect, neither reducing nor increasing the
natural rate of coastal erosion.
8.9.6 Various members of the local coastal community, in particular Lissett & Ulrome
Parish Council, suggested that Forewind should install coastal defences as part of
the Dogger Bank Creyke Beck works. As this would be a clear contravention of the
No Active Intervention policy, it was not possible to incorporate this feedback into
the proposals. Forewind explained this to the Parish Council and contacted ERYC
to make them aware of the local community‘s concerns about coastal erosion.
8.9.7 Forewind agreed a method statement with the JNCC and the MMO which set out
how marine physical processes (including coastal erosion, sedimentary processes,
hydrodynamic processes and cumulative impacts) would be assessed. For the
landfall, a conceptual model was developed which, combined with expert
geomorphological assessment, was used to assess the effects of the landfall works,
scour protection or rock armouring on the existing processes and future evolution of
the shore (including the long shore sediment transport system).
8.9.8 For the marine areas, the conceptual understanding of marine physical processes
was supported by numerical modelling of waves, tidal currents and sediment plume
dispersion. A similar approach was adopted for assessing the physical and
sedimentary process effects in the project areas and associated export cable
corridor, including increase in suspended sediment concentration and deposition on
the seabed. Direct loss of habitat was addressed using plan area estimates of
scour and side cast materials.
8.9.9 Coastal erosion rates advised by ERYC were used to calculate a ‗worst case‘ for
the distance cliffs might erode over the lifetime of Dogger Bank Creyke Beck. This
then informed the decision about where to site the horizontal directional drilling
compounds to ensure that the landfall cables would remain buried for the lifetime of
the project.
8.9.10 The results of these assessments are presented in Chapter 9 Marine Physical
Processes of the ES.
8.9.11 Following discussion on the comments received from the MMO and JNCC and
Natural England on the draft ES at the second stage of statutory consultation, only
minor amendments were made to Chapter 9. On discussion with the stakeholders,
it became apparent that most comments required clarification of the existing
approach rather than additional work. This additional clarification is provided within
Chapter 9.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 65 © 2013 Forewind
8.10 Marine Water and Sediment Quality (ES Chapter 10)
Main stakeholders and methods of consultation
8.10.1 Statutory consultees included the MMO, the Environment Agency, the Health
Protection Agency and the JNCC.
8.10.2 For summaries of all relevant responses please see Appendix M10.
Key issues raised
8.10.3 Stakeholder consultation highlighted concerns regarding the impact on water quality
especially in relation to bathing water due to the following:
Potential spillage;
Leaks; and
Re-suspension or transport of contaminants.
Forewind response
8.10.4 Forewind modelled sediment plumes for the worst case scenario conditions and
concluded that deterioration of water quality due to re-suspension of sediments
and/or contaminants would be minimal during all stages of development. The
modelling results show that any suspended sediments would be quickly dispersed
after activities cease.
8.10.5 Bathing water areas are found within 1km of the landfall works, however any
material excavated as part of this development would be stored on a barge for
replacement after the works are completed and would not have an effect on the
quality of bathing water.
8.10.6 In addition to ensuring that all working practices and vessels adhere to the
requirements of the MARPOL (Prevention of Pollution from Ships) Convention
Regulations, control measures will be included in a Project Environmental
Management and Monitoring Plan (EMMP) in order to minimise the risk of a spill as
far as possible. This is a commitment of the deemed Marine Licence which forms
part of the Development Consent Order (Planning Inspectorate document
reference number 3.1). For further details see Chapter 10 Marine Water and
Sediment Quality of the ES.
8.10.7 The designated bathing waters within the water bodies which are protected under
the ‗protected areas‘ element of the Water Framework Directive (WFD) are located
several kilometres from the export cable corridor and both passed the more
stringent Bathing Waters Directive guideline standards in 2011. In its comments on
the draft ES at the second stage of statutory consultation, the Environment Agency
requested that Forewind undertook a WFD assessment. This has been completed
and is incorporated in the ES (ES Appendix 10A Water Framework Directive
Compliance Assessment).
8.11 Marine and Coastal Ornithology (ES Chapter 11)
Main stakeholders and methods of consultation
8.11.1 Ornithology is a key topic of interest for all offshore wind farm developments and
this has been reflected in the extensive consultation carried out for Dogger Bank
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 66 © 2013 Forewind
Creyke Beck at statutory and non-statutory levels, with national and international
stakeholders. Chapter 11 Marine and Coastal Ornithology of the ES (and
associated appendices) presents a detailed and comprehensive assessment of the
impacts of Dogger Bank Creyke Beck on birds and clearly demonstrates how
stakeholder concerns and recommendations have been central to the development
and execution of the EIA.
8.11.2 In the UK, the main statutory consultees on this topic included the JNCC, Natural
England, the IPC (now the Planning Inspectorate) and ERYC. Non-statutory
consultees included the RSPB, North Yorkshire Moors National Park, North
Yorkshire County Council, the Bridlington and District Civic Society, the Wildfowl
and Wetlands Trust (WWT), Wildlife Trusts and members of the local community.
Consultation at a transboundary level was undertaken with the Danish Ministry of
the Environment, Dutch Ministry for Infrastructure and Environment (Rijkswaterstaat
Waterdienst), the Royal Belgian Institute of Natural Sciences, German Federal
Maritime and Hydrographic Agency (Bundesamt fuer Seeschifffahrt und
Hydrographie) and the Norwegian Coastal Administration and Ministry of the
Environment.
8.11.3 For summaries of all relevant responses please see Appendix M11.
Key issues raised
8.11.4 The key concerns and summary of the comments received throughout the
consultation are:
Collisions of birds with rotating blades;
Direct habitat loss;
Disturbance from construction activities such as the movement of
construction/decommissioning vessels and piling;
Displacement during the operational phase, resulting in loss of foraging/roosting
areas and potential resultant mortality; and
Impacts on bird flight lines (i.e. barrier effect) and associated increased energy
use by birds for commuting flights between roosting and foraging areas and on
migration.
Stakeholder feedback and Forewind response
8.11.5 A meeting to discuss the combined boat and aerial survey methodology was held
between Forewind, the surveyors (Gardline Ltd and Hi-Def Surveying Ltd) and the
JNCC in April 2010. As a result of this, a review of the methodology was instigated,
led by the British Trust for Ornithology (BTO) (Forewind‘s specialist ornithological
consultant).
8.11.6 A follow-up meeting was held in November 2010 with representatives from JNCC
and the RSPB to report initial results from this, covering:
A review of survey data collection protocols;
A review of the survey approach and whether this was sufficient to provide a
robust characterisation of the populations of seabirds present in the Zone and
tranche areas within this;
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 67 © 2013 Forewind
Identification of the key species for assessment and the likely effects for these
species; and
A review of potential methodologies for assessing effects on migratory species.
8.11.7 More detailed discussion of the assessment methodology was initiated in a meeting
held on 18 May 2011(Appendix N3) in London between representatives of
Forewind, BTO, RSPB and JNCC. The purpose of this meeting was to discuss and
review the outcome of the survey trial and the proposed approach for future
surveys, and to discuss the approach for the EIA and HRA. Details of how these
initial meetings fed into the development of the EIA for ornithology can be found in
Appendix 3 of Appendix 11A of the ES.
8.11.8 Building on this, a workshop was held on 11 April 2012 (Appendix N9) in
Peterborough, to discuss the approach to the EIA and HRA in greater detail.
Representatives from JNCC, Natural England, RSPB and the Wildlife Trusts
attended. As a result of this workshop, two documents were produced for
stakeholder review:
A document detailing assumptions and methodology regarding the geographical
scope of the assessment; and
A document providing details of the ecological assumptions used in the
assessment methodology. Stakeholder comments on these documents and
details of how these comments have been addressed are outlined in Appendix
3 of Appendix 11A of the ES.
8.11.9 A further meeting was held on 11 March 2013 (Appendix N14), with
representatives from the JNCC, Natural England and RSPB, to discuss the HRA
screening report for Dogger Bank Creyke Beck and the related assumptions in the
ornithological technical report methodology. Discussions, related to advice notes
produced by Natural England/JNCC (2012, 2013a, 2013b) happened prior to the
meeting. Subsequent comments from Natural England were also taken into
account in producing the final EIA and consequently the HRA (e.g. the use of a 2km
buffer for displacement of all species, except divers).
8.11.10 A final workshop was held in June 2013, following the second statutory
consultation period on the draft ES. This was attended by the JNCC, Natural
England, the RSPB and the MMO and provided an opportunity for further comment
on the assessment prior to its finalisation. Forewind‘s responses to the issues
raised by JNCC and Natural England in the consultation on the draft ES are
included in the point by point response (Appendix N15). The response explains
where Forewind has amended the ES to take account of stakeholder comments,
and also highlights those areas where Forewind does not agree with the comments
raised.
8.12 Marine and Intertidal Ecology (ES Chapter 12)
Main stakeholders and methods of consultation
8.12.1 The prescribed consultees that responded on this topic included the JNCC, Natural
England and the MMO (together with the Cefas as the MMO‘s science advisor).
The main non-statutory stakeholders included The Wildlife Trusts, in addition to the
relevant transboundary consultees in other European Economic Areas (EEA).
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 68 © 2013 Forewind
8.12.2 Two non-statutory consultation workshops were held in April 2012 and June 2013,
which the JNCC, Natural England, the MMO, Wildlife Trust and Cefas all attended
(see Appendix N9 and N16). The purpose of the April 2012 workshop was to
provide stakeholders with an update on the survey and assessment work conducted
to date and to seek views on the final form of the assessment. The June 2013
workshop followed the statutory consultation period on the draft ES and provided an
opportunity for further comment on the assessment prior to its finalisation.
8.12.3 For summaries of all relevant responses please see Appendix M12.
Key issues raised
8.12.4 Early stage consultation (throughout 2010 and 2011) focussed on the nature of the
survey campaigns (geophysical and benthic sampling) and helped to ensure that an
adequate characterisation of the site was achieved. The conservation status of the
Dogger Bank as a candidate Special Area of Conservation (cSAC) was noted from
an early stage. This influenced the survey design and the type of assessment that
was required.
8.12.5 The focus of later consultation shifted to communication of the preliminary findings
of the survey work and the form of the assessment. A particular issue raised in
consultation on the draft ES was the use of Valued Ecological Receptors (VERs) as
a framework for the impact assessment. This is discussed in further detail below.
Stakeholder feedback and Forewind response
Colonisation of new hard substrates
8.12.6 The MMO noted during the statutory consultation on the draft ES that introduced
substrates are colonised by species not naturally present in surrounding
sedimentary habitats, and that those species persist for decades until after the
habitat returns to its natural state following decommissioning. It queried the
conclusion of a negligible impact presented in the draft ES and suggested that
monitoring should be undertaken throughout the operational stage to ascertain how
the long-term presence of introduced substrate and its colonisers influences the
surrounding sedimentary habitats.
8.12.7 In response to these comments, Forewind added further information to its impact
assessment to link the potential impact with the relevant Marine Life Information
Network factor8. It was noted that the benthic receptors present in the study area
are judged to be either not sensitive to this effect/factor or that there is insufficient
evidence on which to base any sensitivity assessment. Forewind has also included
a commitment to monitoring during operation, and the exact detail of suitable
monitoring programmes will be agreed with stakeholders prior to construction.
Monitoring
8.12.8 The MMO noted that under (deemed) Marine Licences it is possible to conduct
monitoring over the lifetime of the project and advised that monitoring should be
conducted at more infrequent, regular intervals throughout the lifetime of the
development. This was noted in the assessment.
8 MarLIN 2013. Marine Life Information Network. Plymouth: Marine Biological Association of the United
Kingdom. Available from: www.marlin.ac.uk
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 69 © 2013 Forewind
Mytilus reef habitat in the export cable corridor
8.12.9 JNCC and Natural England noted the presence of Mytilus reef habitat in one
nearshore section of the export cable corridor and questioned whether this
constitutes Annex I habitat (EU Directive 92/43/EEC on the Conservation of Natural
Habitats and Wild Flora and Fauna (the ‗Habitats Directive‘).
8.12.10 Although it is not possible to provide further information describing this area at
the present time, Forewind has updated Chapter 12 Marine and Intertidal
Ecology of the ES to make it clear that the pre-construction survey (to be carried
out no more than 12 months prior to the start of offshore construction) will be used
to confirm the nature of the Mytilus based biotope complex (SS.SBR.SMus) that
has been identified and specifically, whether it constitutes Annex I reef habitat.
Use of VERs in the impact assessment
8.12.11 JNCC and Natural England requested clarification as to how the biotopes
identified in the Emu report (ES Appendix 12D) related to those in the Envision
report, (ES Appendix 12G) and the suitability of using VERs as a basis for the
impact assessment.
8.12.12 Forewind made several additions to Chapter 12 of the ES in order to clarify
the habitat classifications that have been used, and how the VERs are applied to
the impact assessment and the Habitats Regulations Assessment. This included
the provision of an entirely new Appendix to Chapter 12 which clearly sets out in
table form, for each impact, the relevant MarLIN factors, the VERs, the
representative biotopes corresponding to each VER and the ecological sensitivity
(as defined by MarLIN) of the most sensitive biotope within the VER to each effect
or factor.
8.12.13 In addition to updating this information in Chapter 12 of the final ES, Forewind
also provided additional information on these amendments. No further comment
has been received on this.
8.13 Fish and shellfish ecology (ES Chapter 13)
Main stakeholders and methods of consultation
8.13.1 Prescribed consultees on this topic included the Bridlington Harbour
Commissioners, JNCC, the MMO and Natural England. Other stakeholders
included the RSPB, the Wildlife Trust, Cefas, Shell fishermen‘s Cooperatives and
fishing industry groups.
8.13.2 A workshop (Appendix N9) was held on 10 April 2012 with Cefas in order to
discuss fish and shellfish ecology, particularly sandeel and spawning herring, as
well as to provide the preliminary results of the sandeel survey. The workshop was
also a platform for the presentation of the current state of knowledge in relation to
former spawning grounds in the Dogger Bank Area and results of preliminary noise
assessments.
8.13.3 For summaries of all relevant responses please see Appendix M13.
Key issues raised
8.13.4 Main issues raised included:
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 70 © 2013 Forewind
The potential impact of the development on sandeel habitat and herring
spawning grounds; and
The impact of underwater noise as a result of construction activities on sensitive
species such as herring was highlighted especially in relation to spawning
behaviour;
The effects of the development on species of conservation importance which
are known to be in the area i.e. European eel and smelt; and
The effects of electric and magnetic fields (EMF) associated with the export
cable on fish, elasmobranchs and shellfish.
Stakeholder feedback and Forewind response
8.13.5 Forewind has responded to concerns about the loss or disturbance to sandeel
habitats through design changes which have excluded the development of the
western edge of Tranche A due to high sandeel density and associated commercial
fishing in this area (see ES Chapter 15 Commercial Fisheries section 8.10.5).
8.13.6 Consultation responses were received on the draft ES from JNCC, Natural England
and MMO with input from their scientific advisors, Cefas. These were somewhat
contradictory in their nature so were discussed at a meeting with all four
stakeholders on 18 June 2012. Many of the queries raised were resolved at the
meeting and a way forward was agreed.
8.13.7 There was agreement in taking forward the MMO/Cefas advice in preference to the
JNCC/NE advice, for example on the adequacy of fish ecology surveys and the
impact on sandeel. The exception to this was MMO/Cefas‘ suggestion to apply a
seasonal restriction for cable installation for spawning herring, which Forewind
considers to be inappropriate given the predicted level of impact and would result in
a significant adverse commercial impact. A point by point response was sent to all
four stakeholders to clearly set out how Forewind has had regard to each point
made in their consultation responses (Appendix N17 and N18).
8.13.8 In addition, one comment was raised by The Wildlife Trust in relation to impacts on
sandeel. Forewind consider no further mitigation is considered to be necessary.
8.13.9 In response to concerns about the effects of EMF, Forewind has introduced
mitigation methods including burying cables where reasonably practicable,
armouring and the potential to bundle the HVDC export cables which considerably
reduces the electromagnetic output. Noise modelling studies undertaken by
Forewind have shown that the effect of noise is unlikely to have either lethal or
behavioural impacts on fish or shellfish (see ES Chapter 13 Fish and Shellfish
Ecology).
8.14 Marine Mammals (ES Chapter 14)
Main stakeholders and method of consultation
8.14.1 Statutory consultees on this topic included the JNCC, Natural England, the MMO
and The Crown Estate. Non-statutory stakeholders included the Whale and Dolphin
Conservation Society (WDCS), International Fund for Animal Welfare (IFAW),
Dutch Ministry of Infrastructure and the Environment, Maritime and Hydrographic
Agency of Germany, and The Wildlife Trust.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 71 © 2013 Forewind
8.14.2 For summaries of all relevant responses please see Appendix M14.
Key Issues raised
8.14.3 The key issues raised included:
The potential effect of construction noise on marine mammals, both at a project
level and cumulatively with other developments. JNCC and Natural England
requested that the ES should set out the approach to the noise assessment
including thresholds, units and presentation of data, as well as the full range of
physical impacts including Temporary Threshold Shift (TTS) and Permanent
Threshold Shift (PTS) (total loss of hearing), and the zone and duration of
marine mammal avoidance/displacement; and
The effect of electro-magnetic field (EMF) effects should be assessed for
pinnipeds and cetaceans.
Stakeholder feedback and Forewind response
8.14.4 Following receipt of the consultation response from JNCC and Natural England on
the draft ES, a number of amendments and clarifications were added to the marine
mammal assessment. Forewind agreed with the comments made where it was
possible to accommodate these (i.e. where data was available and a response
possible). In addition to comments from the statutory consultees, a number of non-
governmental organisations provided comments relating to the assessment of
impacts on marine mammals.
8.14.5 Consultation on the baseline data used for the assessment of impacts on marine
mammals included consideration of the Joint Cetacean Protocol, which is intended
to provide population estimates for marine mammals. However, in the consultation
responses received from JNCC and Natural England on the draft ES, it was
confirmed that this protocol would not be available in time to feed into the final ES.
JNCC and Natural England also confirmed that they were, therefore, satisfied with
the use of the other sources of population information utilised for the assessment.
This was with the exception of one comment raised by Natural England, requesting
inclusion of further January 2012 harbour seal telemetry data. Following
investigation, Forewind confirmed that this data was not yet available for use and
hence this was not included in the final ES.
8.14.6 Following statutory consultation on the draft ES, a small number of additional
concerns were raised by JNCC and Natural England on the impact assessment.
JNCC requested that further mitigation for permanent impacts in harbour porpoise
caused by noise from pile driving activity should be considered, and disagreed with
the conclusion of no impact on harbour porpoise for the individual assessment of
each project. JNCC also requested further clarification as to the assignment of
sensitivity to different levels of behavioural disturbance in the ES.
8.14.7 Additionally, JNCC noted than a European Protected Species (EPS) licence is likely
to be needed for additional species and not just harbour porpoise, as suggested by
Forewind. They also requested clarification on how Forewind is considering the
application for the EPS licence.
8.14.8 However, following discussion with JNCC on these concerns, it was concluded that
additional clarification within the ES would resolve the issues and that no significant
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 72 © 2013 Forewind
rework would be required. This clarification has been included in the final ES.
8.14.9 The Dutch Ministry of Infrastructure and the Environment requested that the
cumulative effects in Germany and Denmark must also be taken into account,
specifically raising concerns for harbour porpoise. The Maritime and Hydrographic
Agency of Germany is mainly concerned about noise impacts on marine mammals
and how Forewind intends to mitigate this. Forewind has provided as much
information as possible at this stage to help quantify the potential cumulative
impacts, particularly on harbour porpoise. Forewind is not able to commit to further
mitigation, above those measures already outlined in the ES, for impacts on harbour
porpoise at this time.
8.14.10 During consultation on the draft ES, WDCS and IFAW raised a number of
concerns relating to the impacts from underwater noise and potential mitigation
measures that should be applied. While it is recognised that a significant impact
could arise at the cumulative scale, this is not influenced by the construction or
operation of projects within the Dogger Bank Zone. No mitigation that could be
applied within the Dogger Bank Zone would prevent potentially significant impacts
from occurring elsewhere and, as such, no project specific mitigation is proposed.
In addition, details of mitigation which Forewind is committing to, including
embedded soft start (a process to reduce the likelihood of injury to marine mammals
from noise), as well as commitment to an Environmental Management Plan and
Marine Mammal Mitigation Protocol (MMMP) are included in ES Chapter 14 –
Marine Mammals.
8.14.11 Following the second stage of statutory consultation, Forewind has addressed
all of the issues and concerns raised by JNCC and Natural England, through
additions, amendments or clarifications to ES Chapter 14.
8.14.12 Forewind has addressed comments from WDCS and IFAW where possible,
and despite being unable to commit to any unproven noise mitigation measure at
this development site, re-affirmed its commitment to the development of a MMMP in
consultation with appropriate stakeholders.
8.15 Commercial fisheries (ES Chapter 15)
Main stakeholders and methods of consultation
8.15.1 Statutory consultees included the Bridlington Harbour Commissioners, JNCC,
Natural England and Watton Parish Council. Other consultees included
representatives of national and international fisheries bodies such as the National
Federation of Fishermen‘s Organisations (NFFO), North Eastern Inshore Fisheries
Conservation Authority (NEIFCA), North Eastern Inshore Fisheries and the Royal
Norwegian Ministry of the Environment the Norwegian Ministry of Fisheries and
Coastal Affairs, the Northumberland Inshore Fisheries and Conservation Authority
(NIFCA), and the Comité National des Pêches Maritimes et des Elevages Marines
(CNPMEM).
8.15.2 Inshore and offshore independent fishermen were also consulted as part of the
process since commercial fisheries takes place throughout the North Sea and is
undertaken by fleets from several different countries. Consultation with
representatives of the fishing industry from other EEA states including Germany,
The Netherlands, Denmark, France, Sweden, Belgium and Norway were also
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 73 © 2013 Forewind
undertaken as part of Forewinds‘ responsibility to assess transboundary issues.
8.15.3 The main methods of consultation involved meetings with stakeholders as well as
through an initial Forewind stakeholder workshop (Appendix N1) held on 21 April
2010 with representatives of fishing organisations and independent fishermen.
Forewind developed a Fisheries Liaison Plan (Appendix B) which was a specific
approach to consultation with the fishing industry.
8.15.4 For summaries of all relevant responses please see Appendix M15.
Key issues raised
8.15.5 The main issues raised during consultation included:
Loss or restricted access to fishing grounds;
Safety zones and the impact on shipping and fishing vessels;
Displacement of fishing activity and exclusion zones, both at a project level and
cumulatively with other developments;
Potential impact of construction activities on the population of commercially
exploited fish and shellfish;
Objects on the seabed post-construction causing snagging, damage or loss of
gear; and
Increased steaming times.
Stakeholder feedback and Forewind response
8.15.6 One of the main concerns raised during consultation was displacement of fishing
activity, or loss of grounds due to the wind farm development, which could result in
increased competition for grounds outside the site. This is related specifically to
plaice and sandeel fishing areas and fishing activity in the export cable corridor.
8.15.7 In response to the concerns about the sandeel fishery, especially the high density of
fishing for this species on the western boundary of the Dogger Bank Zone,
Forewind made the decision to locate the project boundary in an eastwards
direction. Loss of fishing ground within the export cable corridor will be temporary
and so will not pose a threat to the fishery. Overall, Forewind considers the area of
disturbance to be small in comparison to the area in which commercial fish and
shellfish are caught within the North Sea.
8.15.8 The potential impact on fish and shellfish ecology of commercial importance is
considered in ES Chapter 15 Commercial Fisheries.
8.15.9 Safety zones in relation to shipping and fishing vessels are covered in ES Chapter
16 Shipping and Navigation. During construction, 500m safety zones will be
implemented around installation features and a rolling safety zone will be employed
around the export cable corridor. This could result in a few temporary deviations in
traditional routes. However, Forewind recognises that in the normal course of
fishing, vessels will have to make frequent deviations to steaming routes to avoid
collision with other vessels, infrastructure or due to weather conditions. Therefore
Forewind considers that the development will not have any discernible impact on
steaming times.
8.15.10 Some stakeholders raised the concern that vessels used during construction
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 74 © 2013 Forewind
could interfere with fishing vessels with towed gear, and potentially result in a loss
of static gear. Forewind has indicated in the ES that construction vessels will
comply fully with the International Regulations for Preventing Collisions at Sea
(COLREGs) so fishing vessels will not have to alter course and there will be no risk
to towed fishing gear. Fishing vessels, as a matter of course, do not deploy gear
within known shipping routes. Construction vessels will also adhere to the
COLREGs to avoid conflict with static gear in the vicinity of transit routes.
8.16 Shipping and Navigation (ES Chapter 16)
Main stakeholders and methods of consultation
8.16.1 In addition to the statutory bodies (the Maritime and Coastguard Agency (MCA) and
Trinity House), the Chamber of Shipping, the Royal Yachting Association, the
Cruising Association and the owners and regular operators of commercial vessels
and fishermen have all been consulted on the Dogger Bank Creyke Beck proposals.
8.16.2 Of particular note is the Hazard Workshop (Appendix N10) that was held on 19
April 2012 and attended by a representative of Dutch Fisherman, DFDS Logistics,
CEMEX UK Marine, the Danish Fishermen‘s Association, the Cruising Association,
RWE Dea (UK), the National Federation of Fishermen‘s Organisations (NFFO),
Associated British Ports, the MCA and GDF Suez. The purpose of this workshop
was to identify any navigational hazards associated with the development.
8.16.3 For summaries of all relevant responses please see Appendix M16.
Key issues raised
8.16.4 Through both statutory and non-statutory consultation, a number of issues have
been identified:
Navigation channels/corridors within projects;
Navigational safety;
Search and rescue; and
Standard approach to design across projects relating to curved turbine layouts,
dense perimeters and the accuracy of AIS data.
Stakeholder feedback and Forewind response
8.16.5 Forewind, together with other Round 3 Offshore Wind Zones, Hornsea and East
Anglia, have formed the Southern North Sea Offshore Wind Forum. The Forum has
undertaken work to assess the cumulative impact on shipping and navigation of all
three zones becoming operational, as well as consulting with shipping associations
and government bodies from Belgium, Denmark, Germany, France and The
Netherlands.
8.16.6 On several occasions, the MCA and the Chamber of Shipping stated concerns
about narrow navigation corridors or channels between individual wind farms. The
MCA decided not to include charted channels within each wind farm, only wind
resource gaps. The MCA raised the issues of dense perimeter and curved layouts
in relation to vessels movement and SAR operations. Following other consultation
responses in relation to curved design Forewind has removed curved layouts from
the design and has re-run the collision modelling to take into account dense
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 75 © 2013 Forewind
perimeter layouts and updated results are provided in ES Appendix 16A. Forewind
has used both AIS data and site specific radar surveys have been used to define
the characteristics of shipping in the area.
8.16.7 Trinity House raised the potential navigational safety risk (under keel clearance) of
rock placement as a method of protecting cables. Forewind has however, included
this cable protection method in the proposals as there are areas where cable burial
will not be possible. The Dogger Bank Export Cables will be buried or protected
appropriately along their length. A detailed cable burial and protection risk
assessment will be carried out to identify the most suitable target burial depth and
level of protection in each area. The assessment will include consideration of
operating characteristics, sediment type, and risk of damage to the cable from
mobile sediments or external activities such as fishing or vessel anchors. Any rock
placement will be carried out to industry standards and will, as far as possible, avoid
impacts on navigational safety and allow fishing vessels to continue trawling.
8.16.8 An emergency response study was submitted as part of the consultation on the
draft ES, but following further discussion with the MCA and THLS, it was agreed
that this would be removed for the final submission. This document will be
maintained as a working document to aid future discussions on potential emergency
response capabilities. In addition, the DCO requires an Emergency Response and
Co-operation Plan to be provided before construction commences, in consultation
with the MCA.
8.16.9 Forewind has drawn up layout rules which will be secured through a requirement of
the DCO, and therefore these principles must be applied to the final layout design of
the consented projects.
8.16.10 The responses received from the MCA, THLS, The Chamber of Shipping,
Royal Yachting Association and the Cruising Association on the draft ES all noted
some concerns in relation to curved turbine arrays. As a result, Forewind decided
to remove the option to install curved arrays from the Rochdale Envelope.
8.16.11 In addition, a number of comments were made by MCA and THLS which
Forewind has committed to address as part of the detailed design of the project post
consent. There are a number of comments which Forewind has not been able to
agree with, such as the commitment to have just one marine coordination centre for
all projects on Dogger Bank (not just the project which is the subject of this
application). Forewind has, however, committed to use of a single Emergency
Response centre. Following further discussion with the MCA and THLS it was
agreed that many issues would be resolved during continued discussion over the
final project design, post consent.
8.17 Other Marine Users (ES Chapter 17)
Main stakeholders and methods of consultation
8.17.1 During the statutory consultation period a large number of organisations with
interests in the seabed (Section 42d offshore landowners) were consulted including:
Oil and gas operators, The Parkmead Group and Bridge Energy, Centrica
Energy, Dana Petroleum, Europa Oil and Gas (Resources Limited), GDF Suez,
Premier Oil Ltd, ConocoPhillips, RD(UK) SNS Ltd, and CGG Veritas;
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 76 © 2013 Forewind
Gas pipeline operators; Gassco Ltd, Atlantic Petroleum, Shell UK Ltd;
Telecommunication cable operators: Tata Communications, BT subsea, Cable
and Wireless and Kingston Communications; and
Aggregate industry: CEMEX UK Marine Ltd, British Marine Aggregate
Producers Association (BMAPA).
8.17.2 Others consulted included the MCA, North Yorkshire County Council, the Health
and Safety Executive, Northumberland Yacht Group and Royal Yachting
Association, ABP Humber Estuary Services, E.ON Climates and Renewables UK,
EDF Energy Renewables, Egdon Resources UK Ltd (onshore), Cleveland Potash
(mining), and National Grid (Carbon Capture and Storage).
8.17.3 A Dogger Bank Creyke Beck Project Hazard Workshop was held in London on 19
April 2012. All presentations and a hazard log were sent to all attendees for
comment. A presentation was given by Forewind to the Subsea Cables UK
Renewables Sub Group. Discussions with the Department for Energy and Climate
Change (DECC) have taken place in relation to the guidance on the proposed oil
and gas clause relating to oil and gas activity within consented wind farm areas.
8.17.4 For summaries of all relevant responses please see Appendix M17.
Key issues raised
8.17.5 The main issue raised during consultation related to disruption or damage to
activities or assets of other marine users including;
Renewable energy – pressure on port facilities;
Carbon capture and storage – distances between CO2 pipeline and Dogger
Bank Creyke Beck export cables;
Oil and gas – the effect of noise during construction and seismic survey work for
oil and gas exploration as well as the relationship between licence blocks which
overlap the project and the project itself. Another area for discussion is the
proximity to the development of helicopter access routes to oil rigs;
Aggregates – the effect on dredger routes;
Subsea cables – ability to maintain subsea assets; and
Subsea pipelines (Shell and Gassco).
Stakeholder feedback and Forewind response
8.17.6 An area of concern is the potential for ports to be affected through increased
demand from other renewable energy projects. In response to this Forewind will
select a port on its ability to adequately service the requirements of the project.
8.17.7 National Grid is responsible for the design, construction and operation of the CO2
transport system and the identification of the offshore storage sites for the Yorkshire
and Humber carbon capture, transportation and storage project. The landfall area
for the CO2 pipeline was initially proposed to be in close proximity to the Dogger
Bank Creyke Beck export cable landfall which caused confusion in the local
community and concern about cumulative impacts. Forewind made efforts to
respond to local concerns regarding the confusion over the landfall location for
Dogger Bank Creyke Beck and the CO2 pipeline project by attending and
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 77 © 2013 Forewind
presenting at a Barmston and Fraisthorpe Parish Council meeting with National
Grid, and ensured that consultation periods on these projects did not overlap. The
two projects have now identified separate landfall locations but Forewind is in
discussion with National Grid to resolve any ongoing concerns regarding the
distance between the export cables and the CO2 pipeline.
8.17.8 In relation to oil and gas activities Forewind has engaged with the relevant oil and
gas developers through a comprehensive programme of consultation and will
continue to do so throughout the life of the development where necessary. Meetings
have been held with oil and gas operators to inform and update them of Forewind‘s
plans and any potential interactions between licence blocks and the Dogger Bank
Creyke Beck development. Forewind has met with all operators at least once and
has provided an update every six months (excluding statutory consultation) to all
those with an interest in Forewind‘s developments. Some operators also attended
the Shipping and Navigation Hazard Workshop.
8.17.9 CEMEX UK Ltd (aggregate dredging) noted the close proximity of the turbines and
inter-array cables to a marine dredging licenced area under application and raised
the issue of the potential effect on dredger navigation routes. In relation to this
CEMEX requested a 2km separation distance between application areas and
offshore wind projects. Forewind has responded by taking this distance into
account in its project boundary selection process (although the site is 3km from the
boundary of Dogger Bank at its closest point), and will continue to engage with
CEMEX.
8.17.10 Forewind has consulted all operators with interests in or in proximity to Dogger
Bank Creyke Beck and is currently seeking Statements of Intent (see Chapter 9 of
this report). TATA communications raised concerns about the ability to maintain
cables during the construction and operational phases and requested that Forewind
demonstrated a commitment to Subsea Cables Guidance No 6. In response to this
Forewind has included a minimum proximity buffer between surface infrastructure
and any cable or pipeline and a buffer distance between active telecommunication
cables and inter-array cables in the design of the development.
8.17.11 The Dogger Bank Creyke Beck project boundaries have been designed with
the location of cables and pipelines in mind especially the western boundary of
Creyke Beck B and the northern boundary of Creyke Beck A.
8.18 Marine and Coastal Archaeology (ES Chapter 18)
Main stakeholders and methods of consultation
8.18.1 Stakeholders consulted on Marine and Coastal Archaeology included, Humber
Archaeology Partnership (HAP), English Heritage (EH), Birmingham University and
the Joint Nautical Archaeology Policy Committee.
8.18.2 Of particular note is an archaeology workshop hosted by Forewind in in September
2012 (Appendix N13). English Heritage and the County Archaeologist attended
along with representatives of Birmingham University and the Joint Nautical
Archaeology Policy Committee. Forewind presented an update on archaeology
survey and assessment.
8.18.3 For summaries of all relevant responses please see Appendix M18.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 78 © 2013 Forewind
Key issues raised / Stakeholder feedback
8.18.4 Issues raised throughout the consultation process were as follows:
The IPC (Now Planning Inspectorate) stated that consultation should seek to
agree a programme of investigative works and appropriate mitigation, as
necessary.
EH noted that ―all development or related activities associated with the
construction, operation and decommissioning of the Creyke Beck wind farms
will be prohibited within the boundaries of AEZs (Archaeological Exclusion
Zones)‖ and encouraged Forewind to discuss with themselves and the MMO
how this provision will be included within any DCO (including Deemed Marine
Licence) granted for this proposed project.
EH also raised issues regarding securing mitigation in the DCO, providing
further information on surveys post-consent and further detail and clarification
on some of the worst case parameters.
EH requested the production of an archaeological Written Scheme of
Investigation (WSI), as necessary, to support delivery of this proposed
development and consideration of the extent to which access to palaeo-
environmental evidence will be affected by the development.
EH requested that geophysical survey operations extend further and a full suite
to be utilised across the marine study areas and also noted that ―it is apparent
that only backscatter data rather than sidescan sonar data was available in the
export cable corridor. Since backscatter data is generally of low resolution it is
not conducive to archaeological analysis‖. EH see this is an important detail
and will provide advice that the deemed marine licence and the WSI identifies
these data for acquisition in the corridor route pre construction.
EH requires further information to be supplied to them regarding the on-going
programme of geo-archaeological analysis.
Forewind response
8.18.5 Measures to deal with impacts to all potential sites and appropriate mitigation to
deal with unexpected discoveries, if they should occur, have been set out in the
project WSI, including the implementation of a reporting protocol, namely, Offshore
Renewables Protocol for Archaeological Discoveries and incorporating aspects of
the relevant model clauses for WSI, both developed for The Crown Estate.
8.18.6 It has been explained and accepted by EH that due to restrictions on towing survey
equipment within the nearshore section of the export cable corridor on account of
bad weather and static fishing gear, sidescan sonar and magnetometer data were
collected for the offshore section of the export cable corridor only.
8.18.7 All embedded and additional mitigation and the details of further work agreed
between Forewind and the curator (EH) will be set out in the high level project WSI,
which should be seen as a living document (see ES Appendix 18B). As noted, a
scheme specific WSI will be produced for each Dogger Bank Creyke Beck project
once the design has been finalised and the methodology and framework for
archaeological works has been agreed with English Heritage and the MMO.
8.18.8 Access to palaeo-environmental evidence (including publication) and the ongoing
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 79 © 2013 Forewind
programme of geo-archaeology is set out in the overriding WSI mentioned above.
8.18.9 Following consultation on the draft ES, Forewind will meet with EH to review
responses to the consultation, and to discuss statements of common ground and
the archaeological scope for the Forewind geotechnical campaigns.
8.19 Military Activities and Civil Aviation (ES Chapter 19)
Main stakeholders and methods of consultation
8.19.1 Stakeholders consulted on this topic included the Civil Aviation Authority (CAA), the
National Air Traffic Service (NATS) (including their subsidiary-NATS en route Ltd
(NERL)), the Defence Estates department of the Ministry of Defence (MoD) and the
Maritime and Coastguard Agency (MCA). Consultation has been undertaken in
accordance with both the Wind Energy and Aviation Interests Interim Guidelines
(Department of Trade and Industry (DTI), CAA, MoD and British Wind Energy
Association (BWEA) (now RenewableUK) 2002).
8.19.2 Consultation with the MoD has been undertaken through a standard proforma
(industry standard consultation document) and subsequent direct correspondence
at the CAA and NATS Round 3 developers workshop held at MCA headquarters,
Southampton, on 6 March 2013.
8.19.3 For summaries of all relevant responses please see Appendix M19.
Key issues raised
8.19.4 The key issues that were raised during consultation were:
Potential effects on communications, navigation and surveillance infrastructure;
Aviation lighting;
Turbine colour;
Updated marine charts showing the turbine locations; and
Cable protection.
Stakeholder feedback and Forewind response
8.19.5 Both the CAA and MoD have highlighted the requirements for wind turbines to be lit
to aid visibility in accordance with their individual criteria. The specific lighting
requirements will be the focus of ongoing consultation with appropriate stakeholders
as the design phase progresses.
8.19.6 The CAA highlighted the requirement for wind turbines to be painted white as well
as for the array of turbines to be charted during the wind farm zone development;
both of these requirements will be realised during the wind farm development.
8.19.7 As is required by the CAA, marine charts will be updated and turbine locations will
be marked on appropriate aeronautical charts for Dogger Bank Creyke Beck A and
B. The Defence Geographic Centre will be kept informed of specific project details
including development location, the location, size and height of each wind turbines,
and construction schedules.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 80 © 2013 Forewind
8.20 Seascape and Visual Character (ES Chapter 20)
Main stakeholders and methods of consultation
8.20.1 Stakeholders that were consulted on the seascape and visual character include
Joint Nature Conservation Committee (JNCC), Natural England and English
Heritage. The Planning Inspectorate has also provided comments on this topic
area with respect to potential visual impact of the development on recreational
users. Comments raised by the Civil Aviation Authority (CAA) and Trinity House
included the need to consider navigation and aviation lights as well as the effect of
night time lighting.
8.20.2 For summaries of all relevant responses please see Appendix M20.
Key issues raised
8.20.3 The key issues raised in the consultation were:
The need for the assessment of the visual impact of offshore components on
offshore recreational users (such as sailing boats, ferries etc.), including any
cumulative effects;
The Seascape and Visual Character Impact Assessment (SVIA) should be
expanded to include Historic Seascape Characterisation (HSC) work;
Consideration of whether other project components are visible from the shore,
such as the onshore transition pit;
Effect of any aviation and navigation warning lights at night time; and
Project locations based on viewpoint selection.
Stakeholder feedback and Forewind response
8.20.4 Natural England and JNCC broadly agreed with the proposed approach to the SVIA
and that the assessment should focus on the marine environment, as the
development will not be visible from land.
8.20.5 The SVIA includes a high level assessment of effects on surface historic seascape
character, with reference to the relevant studies as well as the Marine Archaeology
Technical Report (ES Appendix 18A).
8.20.6 Forewind has assessed the temporary effects of the scheme during construction on
seascape and visual receptors.
8.20.7 The need for warning and navigation lights identified by the CAA and Trinity House
has been considered in the assessment and the effects of lighting at night are
discussed in the SVIA. Forewind have considered this point and navigation lights
are likely to be mounted on the corner turbines, will have a nominal range
representing the minimum required visibility, but the upper limit of visibility depends
on a range of factors, and cannot be precisely determined. The approach taken to
assess the effects on land-based and marine-based receptors in relation to the
construction of the landfall and the export cable is provided in ES Chapter 20
Seascape and Visual Character Section 3 methodology. Further to this, policy
documents that are relevant to the assessment have also been considered in the
assessment.
8.20.8 The Planning Inspectorate recognised that although the development may not be
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 81 © 2013 Forewind
seen from the shore it could represent a visual impact to recreational users and the
cumulative impact should be considered. Forewind noted that the setting of the
wind farms will be open sea, with no potential interaction with the coast. Viewpoints
have been selected to represent the potential presence of visual receptors within
the marine environment surrounding the development area. No permanent features
will be visible from land during the operational phase. Viewpoints have, therefore,
not been selected in relation to the landfall and export cable corridor. The nature of
the temporary visual effects at the landfall and in relation to the export cable corridor
during the construction phase, are described in ES Chapter 20. Forewind
considered that the potential cumulative impact will be on commercial vessels
travelling across the North Sea, since no cruising routes which pass within 50km of
Dogger Bank Creyke Beck A or B will pass another wind farm i.e. Hornsea Project
One.
8.20.9 Forewind agreed with most comments made on the draft ES and has made relevant
updates on this basis. However, Forewind disagreed with the comments on the
scope of the cumulative assessment and believe the current assessment is
adequate. In order to support this position, further information has been added to
the chapter to explain the justification for the current methodology. Forewind‘s full
response to the comments received from JNCC and Natural England can be found
in the point by point response (Appendix N17).
8.21 Landscape and Visual (ES Chapter 21)
Main stakeholders and methods of consultation
8.21.1 Stakeholders consulted on landscape and visual impacts include East Riding of
Yorkshire Council (ERYC), the Design Council (including the Commission for
Architecture and the Built Environment - CABE), English Heritage, Natural England,
Parish Councils and members of the local community.
8.21.2 Forewind established the converter station community working group (Appendix J)
in response to feedback during the first statutory consultation, and the group was
closely involved in the site selection and micro-siting of the converter stations site.
Landscape and visual impact was a key consideration at these meetings.
8.21.3 For summaries of all relevant responses please see Appendix M21.
Key issues raised
8.21.4 A number of issues of particular importance have been identified:
The visual impact of the converter stations and the existing substation and its
associated infrastructure on cultural heritage assets such as Beverley Minster,
residential properties, public rights of way and the Wolds Area of High
Landscape Value;
Landscape and visual mitigation and enhancement measures at the converter
stations site; and
Temporary visual impacts of near shore and landfall works.
Stakeholder feedback and Forewind response
8.21.5 The IPC (now the Planning Inspectorate) recommended in its Scoping Opinion that
landscape and visual mitigation and enhancement measures should be considered
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 82 © 2013 Forewind
together with ecological mitigation, and that mitigation should be considered overall
(not just in relation to a single specialist topic). This recommendation is addressed
in the proposed landscaping and mitigation plans for converter station sites (see ES
Chapter 21 Landscape and Visual).
8.21.6 During the converter stations site selection process, consideration was given to
views from the A1079 to Beverley Minster as well as views from local residential
properties and public rights of way. The potential impacts on the Wolds Area of
Landscape Value were also assessed. These are covered in the landscape and
visual impact assessment (LVIA) in Chapter 21 of the ES.
8.21.7 Forewind‘s proposed site takes advantage of existing woodland as screening.
Furthermore, existing wooded areas are to be consolidated and increased to offer
additional screening. Detailed ecological mitigation and restoration measures are
described in Chapter 25 Terrestrial Ecology of the ES.
8.21.8 The final design for the converter stations site, combining the landscape, ecological
and drainage proposals is to be agreed with ERYC post consent and incorporated
into the Construction Method Statement, Ecological Mitigation and Management
Plan and contract documents, as appropriate.
8.21.9 Questionnaire responses provided at the public exhibitions in December 2011
identified a preference for lower converter station buildings with a larger footprint,
with the converter roof height to be kept in line with existing woodland. These
preferences have been observed in the final proposals.
8.21.10 It was also suggested at the converter station working group, that the
converter stations could be buried to reduce their visual impact. However, the flat
landscape of the surrounding area, the increased flood risk of lowering the finished
floor level, the volume of spoil that would be generated and the increase in traffic
movements for spoil removal, mean burying the converter stations is not a viable
option and so this has not been included in the proposals.
8.21.11 On request, Forewind also prepared and presented indicative visualisations of
the view of the converter stations from both Beverley Minster and St Mary‘s Church
to the Converter Station Working Group.
8.21.12 The temporary visual impacts of the coastal works were fully assessed in the
LVIA. Impacts of the converter stations on the settings of important local cultural
heritage assets have been assessed in Chapter 27 Onshore Cultural Heritage in
the ES. No significant adverse impacts were identified.
8.22 Socio-economics (ES Chapter 22)
Main stakeholders and methods of consultation
8.22.1 Stakeholders consulted on socio-economic impacts include East Riding of
Yorkshire Council and Kingston-upon-Hull City Council, Parish Councils and
members of the local community.
8.22.2 For summaries of all relevant responses please see Appendix M22.
Key issues raised
8.22.3 The key issue raised by the stakeholders was the desire for the proposed
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 83 © 2013 Forewind
development to generate jobs for local communities.
Stakeholder feedback and Forewind response
8.22.4 The IPC (now the Planning Inspectorate) recommended in its Scoping Opinion that
Forewind demonstrate the positive and negative impacts of the proposals. The
types and numbers of jobs generated should be considered in the context of the
available workforce in the area. Potential negative impacts on areas such as
tourism and fishing should be identified. The available workforce information is
provided in Chapter 22 Socio-Economics and was taken from the Office of
National Statistics website.
8.22.5 Impacts on fishing are considered within Chapter 15 Commercial Fisheries and
impacts on tourism are considered in Chapter 23 Tourism and Recreation.
8.22.6 Forewind is committed to investing within the Yorkshire and Humber region to
ensure that it is well positioned to tender for the greatest possible share of the work.
Forewind is actively supporting initiatives such as the Champions for Wind careers
education engagement programme. This scheme, in partnership with Humberside
Engineering Training Association (HETA), is designed to raise awareness and
provide inspiration to 13 to 14 year olds of the potential career opportunities in
offshore wind energy, giving students an understanding of the qualifications and
experience required to gain employment in the industry.
8.23 Tourism and recreation (ES Chapter 23)
Main stakeholders and methods of consultation
8.23.1 Stakeholders consulted on tourism and recreation impacts include East Riding of
Yorkshire Council (ERYC), Natural England, Kingston-upon-Hull City Council,
Parish Councils and members of the local community and the converter station
community working group.
8.23.2 For summaries of all relevant responses please see Appendix M23.
Key issues raised
8.23.3 The main issues identified through consultation included:
Minimising disruption to the 17 public rights of way identified along the onshore
footprint; and
Consideration of the recreational uses of the waters off the Holderness coast.
Stakeholder feedback and Forewind response
8.23.4 The IPC (now the Planning Inspectorate) recommended in its Scoping Opinion that
potential impacts on existing public rights of way are considered and consultation
with the public rights of way officers at the local authority is undertaken. Cross-
reference should be made to any visual impacts on public rights of way identified in
the landscape and visual assessment. The offshore areas are also well used and
the IPC recommended that an assessment of impacts during construction,
operation, maintenance and decommissioning be included in the ES.
8.23.5 The impact on recreational yachting and sailing is considered in Chapter 16
Shipping and Navigation of the ES although other offshore recreational activities
such as diving, surfing and angling are not expected to be impacted by the
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 84 © 2013 Forewind
proposals.
8.23.6 Potential impacts of construction on public rights of way and other recreational
access routes have been assessed by Forewind. Mitigation of impacts on public
rights of way is included in Chapter 23 Tourism and Recreation of the ES. In
addition, Forewind is drafting an outline Code of Construction Practice (Planning
Inspectorate document reference number 8.2) which sets out the responsibility
of the lead operator to communicate closures or diversions of any public rights of
way to the local community and this is included in the application documentation.
Temporary closures will be agreed in advance with ERYC‘s Public Rights of Way
Officer.
8.24 Geology, Water Resources & Land Quality (ES Chapter 24)
Main stakeholders and methods of consultation
8.24.1 Stakeholders consulted on geology, water resources and land quality impacts
include East Riding of Yorkshire Council (ERYC), the Environment Agency,
Yorkshire Water Services, Beverley and North Holderness Internal Drainage Board
and the Health Protection Agency.
8.24.2 Of particular note was a meeting held between Forewind, the Environment Agency
and Yorkshire Water Services in June 2013. The purpose of this meeting was to
discuss the draft ES and whether the Environment Agency and / or Yorkshire Water
would like to see any further clarifications to the assessment.
8.24.3 For summaries of all relevant responses please see Appendix M24.
Key issues raised
8.24.4 The key issues that were raised during consultation were:
The importance of the source protection zone 1 (SPZ1) at Cottingham;
Restrictions relating to piling and discharges within the SPZ1 and SPZ2;
The requirement for a Water Framework Directive (WFD) Preliminary
Assessment, design measures to meet WFD requirements and a detailed
assessment of WFD compliance;
Restrictions relating to the use of culverts in watercourses as a crossing method
during the construction;
The requirement for a robust conceptual site model and Preliminary Risk
Assessment to be undertaken in line with Model Procedures for the
Management of Land Contamination: Contaminated Land Report 11 (CLR11);
The requirement for a Flood Risk Assessment; and
The requirement for an outline Construction Environmental Management Plan,
detailing mitigation measures required in respect to the protection of surface
waters and underlying groundwater bodies.
Stakeholder feedback and Forewind response.
8.24.5 A preliminary risk assessment and conceptual site model undertaken in line with
CLR11 is included within Chapter 24 Geology Water resources and Land
Quality of the ES.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 85 © 2013 Forewind
8.24.6 Both the Environment Agency and Yorkshire Water Services are opposed to any
piling within the SPZ1. Forewind agreed that no piling activities would be
undertaken in the SPZ1 for the Dogger Bank Creyke Beck proposals; however
Forewind cannot make any assurance on behalf of National Grid Electricity
Transmission (NGET). Works at Creyke Beck substation will be subject of a
separate application by NGET. The Environment Agency and Yorkshire Water
Services have outlined the requirement for a Construction Environmental
Management Plan (CEMP) (see ES Appendix 24E) detailing mitigation measures
appropriate to all phases of the development. Forewind has agreed to draft an
outline CEMP setting out the potential impacts and mitigation measures which will
be implemented.
8.24.7 The Environment Agency outlined that current policy is that ‗no watercourses should
be culverted unless there is an overriding need to do so‘. In consideration of this
concern, Forewind has decided to remove the option of culverting watercourses to
facilitate haul road crossings during the construction phase, thus removing any
potential impacts that may have been caused. In addition no permanent culverts
will be included within the scheme. Forewind has undertaken a WFD assessment
which considers the potential for impacts to all water bodies and is included within
Chapter 24 of the ES.
8.24.8 The Environment Agency noted that they were pleased to see that sustainable
waste management had been considered in detail at this stage, that modelling work
had been undertaken with respect to flood risk, and that the proposed converter
stations will be located within Flood Zone 1 (an area with the lowest probability of
flooding). A flood risk assessment has been undertaken and is presented in ES
Appendix 24B.
8.25 Terrestrial Ecology (ES Chapter 25)
Main stakeholders and method of consultation
8.25.1 Stakeholders consulted on terrestrial ecology include East Riding of Yorkshire
Council (ERYC), the Joint Nature Conservation Committee (JNCC), Natural
England, the Royal Society for the Protection of Birds (RSPB), Yorkshire Wildlife
Trust, East Yorkshire Bat Group, the Hull Natural Society, Hull Biodiversity
Partnership and the Environment Agency.
8.25.2 For summaries of all relevant responses please see Appendix M25.
Kay issues raised
8.25.3 The key issues that were raised during consultation were:
Impacts on Local Wildlife Sites (LWS);
Impacts on water voles, in particular habitat fragmentation should culverts be
required;
Loss of roosting and feeding habitat for bat species; and
Potential for habitat enhancement.
Stakeholder feedback and Forewind response
8.25.4 The IPC (now the Planning Inspectorate) recommended in its Scoping Opinion that
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 86 © 2013 Forewind
ecological surveys for protected species and the methodologies should be agreed
by the relevant consultees. Also, that the ES should address fully the needs of
protecting and enhancing biodiversity. The Commission recommended that
appropriate cross reference is made to other specialist reports in the ES and that
mitigation and enhancement measures are considered overall and not just in
relation to a single specialist topic.
8.25.5 Ecological surveys and their methodologies were agreed through consultation with
Natural England and subsequent meetings were held to discuss the results of these
surveys. These surveys were then used to inform the ES chapter and reference to
the survey reports included where appropriate.
8.25.6 Impacts on LWS, water voles and bat species have been identified and considered
within Chapter 25 Terrestrial Ecology of the ES. The mitigation measures
recommended for managing impacts to water voles were discussed and approved
in subsequent consultation with Natural England in July 2012. Impacts to water
voles from the use of culverts were avoided due to the removal of these features
from the scope of works of the project.
8.25.7 Habitat enhancement measures have been outlined in Section 7 of Chapter 25 of
the ES.
8.26 Land Use and Agriculture (ES Chapter 26)
Main stakeholders and methods of consultation
8.26.1 The main stakeholders consulted in relation to impacts on land use and agriculture
include East Riding of Yorkshire Council (ERYC), Natural England, landowners and
the local community.
8.26.2 For summaries of all relevant responses please see Appendix M26.
Key issues raised
8.26.3 The key issues raised were as follows:
Impacts on farm businesses and agriculture during construction including the
sterilisation of land;
The impact of the project on Environmental Stewardship Schemes;
Minimising the area of Best and Most Versatile Agricultural Land impacted;
Management of soils during construction;
Reinstatement of land drains; and
Awareness of Defra‘s Code of Practice for Sustainable Use of Soils on
Construction Sites.
Stakeholder feedback and Forewind response
8.26.4 The impact on land use and agriculture was assessed as per the scope agreed with
Natural England and focussed on the key impacts which included those proposed
by consultees. These included soils, Environmental Stewardship Schemes,
agricultural land and farm businesses. As a result Forewind has proposed a range
of standard mitigation measures to limit the impacts on land use and agriculture in
Chapter 26 Land Use and Agriculture of the ES. These measures include:
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 87 © 2013 Forewind
Where possible, reinstating land to its former condition and use;
Adherence to appropriate guidance for handling soils;
Full and continued consultation with landowners, and compensatory measures
where appropriate;
Adherence to appropriate guidance to minimise risk of spreading disease; and
Consultation with landowners on drainage systems and production of method
statements prior to construction in addition to adhering to set of construction
principles.
8.27 Onshore cultural heritage (ES Chapter 27)
Main stakeholders and methods of consultation
8.27.1 Stakeholders consulted on onshore cultural heritage include East Riding of
Yorkshire Council (ERYC), English Heritage, Humber Archaeology Partnership
(HAP), East Riding Archaeological Society, Parish Councils and members of the
local community.
8.27.2 The potential for impacts to the setting of Beverley Minster and the impacts on
terrestrial archaeology were key topics of discussion at the converter station
community working group meetings (see Appendix J).
8.27.3 For summaries of all relevant responses please see Appendix M27.
Key issues raised
8.27.4 A number of issues of particular importance have been identified:
Impacts of the converter stations on the settings of important local cultural
heritage assets such as Beverley Minster; and
The extent of intrusive survey work required to inform the baseline.
8.27.5 During the converter station site selection process, consideration was given to
views from the A1079 to Beverley Minster. These are covered in Chapter 21
Landscape and Visual and Chapter 27 Onshore Cultural Heritage of the ES.
8.27.6 On request, Forewind also prepared and presented indicative visualisations of the
view of the converter stations from both Beverley Minster and St Mary‘s Church to
the converter station working group.
8.27.7 Impacts of the converter stations on the settings of important local cultural heritage
assets have been assessed in Chapter 27 of the ES. No significant adverse
impacts were identified.
Stakeholder feedback and Forewind response
8.27.8 The IPC (now the Planning Inspectorate) recommended in its Scoping Opinion that
the onshore cultural heritage assessment considers effects upon designated and
non-designated assets including buried and built features.
8.27.9 HAP recommended staged works for onshore assessment comprising Desk-Based
Assessment (DBA), geophysical survey, field walking, trial trench evaluation,
excavation, and/or watching brief where appropriate. Additional trial trenching was
requested by HAP to inform the baseline. However, it was agreed with HAP that
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 88 © 2013 Forewind
the trial trenching should target anomalies identified during the geophysical survey.
This was the approach adopted by Forewind.
8.27.10 Each stage has been agreed with HAP, with draft findings provided for
comment throughout. A Written Scheme of Investigation will be developed in
agreement with HAP and English Heritage ahead of construction to ensure that
impacts to buried archaeology are minimised.
8.27.11 During the site selection and the assessment of alternatives process, known
sites of cultural heritage importance were included in the constraint mapping
exercise. Where possible these features have been avoided when identifying the
preferred location of the converter stations site and the preferred alignment of the
cable route.
8.27.12 In regard to impacts to the setting of Beverley Minster, the operational
converter stations will not be visible at ground level from the Minster, but the tops of
the operational converter stations will be visible from the Minster Tower. However,
due to the distances involved, the converter stations will not be a prominent feature
in the landscape and will represent a negligible change to views to the south of the
Minster.
8.28 Traffic and Access (ES Chapter 28)
Main stakeholders and methods of consultation
8.28.1 Stakeholders consulted in relation to traffic and access include East Riding of
Yorkshire Council (ERYC), the Highways Agency, the Health and Safety Executive,
local Parish Councils and the local community.
8.28.2 Forewind has consulted extensively with the relevant highway authorities (ERYC
and the Highways Agency) through a series of meetings and technical
notes/drawings. These notes and meetings have sought to agree an appropriate
access strategy and ensure that all traffic impacts are fully considered and
appropriately mitigated.
8.28.3 A series of three Parish Council workshops were held in August 2012 to discuss the
onshore cable route and construction access routes (see Appendix N11).
8.28.4 For summaries of all relevant responses please see Appendix M28.
Key issues raised
8.28.5 The main issues identified through consultation can be grouped as:
Temporary traffic borne environmental impacts upon local communities during
construction;
Permanent traffic borne environmental impacts upon local communities from
operational access to the converter station and substation;
Impacts of construction activities upon the highway structure;
The impact of transporting Abnormal Indivisible Loads (AIL); and
Impacts of additional vehicle movements on public rights of way.
Stakeholder feedback and Forewind response
8.28.6 Concerns about increases in construction related traffic passing through local
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 89 © 2013 Forewind
communities during cable installation were raised by Cottingham, Tickton and
Routh, Leven and Brandesburton Parish Councils.
8.28.7 Forewind, in consultation with the ERYC, has sought to ensure that the construction
accesses are located directly off ‗A‘ and ‗B‘ roads and remote from local
communities. The construction accesses will then be linked by temporary haul
roads and bailey bridges. This ‗embedded mitigation‘ strategy reduces the need for
construction traffic to pass through local communities and ensures traffic remains
on the most suitable roads.
8.28.8 ERYC expressed concerns regarding access to the converter stations and
construction traffic using Long Lane. Cottingham Parish Council and the converter
station community working group strongly objected to large volumes of construction
traffic passing through Cottingham and along Park Lane.
8.28.9 To reduce the impact of construction traffic upon Long Lane, Forewind has met with
appropriate officers at ERYC to determine suitable operational and construction
access to the converter station sites. Whilst ERYC agreed to a temporary access
off the A1079 during construction, the council ruled it out as an operational access
(except in emergency) at an early stage on safety grounds.
8.28.10 Operational access to the converter station for smaller vehicles (cars and
vans) is proposed to be via Long Lane and the lane to the west of the site. The
surface of the lane will be repaired and improved but not asphalted (in line with the
needs of equestrians) and there will also be localised widening (i.e. passing places).
Furthermore, the construction access from the A1079 will also be retained solely for
Heavy Goods Vehicles (HGV)s to access the converter stations during maintenance
periods as well as for emergency access for the emergency services.
8.28.11 To reduce the impact of construction traffic upon Cottingham, Forewind has
met with appropriate officers at ERYC to develop a mitigation strategy to ensure
that all of the converter stations construction traffic (including that associated with
the high voltage alternating current cable route from the converter stations to
substation) will be routed along and off the A1079, and then down the temporary
haul road, thus avoiding Cottingham and Park Lane. Upon completion of the
construction works this temporary haul route will be removed.
8.28.12 National Grid Electricity Transmission (NGET) expects to route the traffic
associated with the connection and on-going maintenance works through the main
entrance to the existing NGET Creyke Beck Substation (along Park Lane).
8.28.13 ERYC stated a preference for horizontal directional drilling (HDD) at major
road crossings, to minimise disruption to other road users (including public
transport) and Brandesburton Parish Council also expressed concerns regarding
any potential closure of Mill Road/Rotsea Road to install the cables.
8.28.14 Forewind proposes to use HDD to cross a total of 11 roads or tracks, including
four A-roads, two B-roads, three unclassified roads and two private tracks including
Rotsea Road. The use of HDD will also be employed to install cables under the
railway line thereby reducing disruption to rail services, a concern raised by the
Planning Inspectorate.
8.28.15 ERYC requested an assessment of the impact of transporting AILs to the
converter station. To determine the most suitable route for AILs Forewind
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 90 © 2013 Forewind
commissioned ALE (a specialist AIL haulage company) to undertake an AIL routing
study. The study proposed accommodation measures and concluded that the AILs
would route from the A63 and then via A164 and then access directly from the
A1079.
8.28.16 In January 2012, the Health and Safety Executive advised that workplace
transport accidents, safe traffic/pedestrian segregation and safe traffic movement of
vehicles & plant should be considered.
8.28.17 In response to advice from the Health and Safety Executive, Forewind has
conducted a rigorous traffic and access impact assessment as part of Chapter 28
Traffic and Access of the ES.
8.28.18 Potential impacts of construction and operational vehicle movements on public
rights of way and other recreational access routes were raised by several
stakeholders during the first stage of statutory consultation and by the Converter
Station Working Group. Mitigation of impacts on public rights of way is included in
Chapter 23 Tourism and Recreation of the ES.
8.28.19 Following the submission of a scoping note the Highways Agency declined
further engagement due to the limited impact of the of the development on the
Strategic Road Network.
8.29 Noise and Vibration (ES Chapter 29)
Main stakeholders and methods of consultation
8.29.1 Stakeholders consulted on noise and vibration impacts included East Riding of
Yorkshire Council (ERYC), Parish Councils and members of the local community.
8.29.2 For summaries of all relevant responses please see Appendix M29.
Key issues raised
8.29.3 The main issues identified through consultation included:
Potential operational noise impacts associated with the converter stations on
residents of the dwellings close to Creyke Beck and Cottingham; and
Potential noise and vibration impacts to nearby properties, during the
construction of the cable route and converter stations. Of particular concern
was the proximity of the cable route to houses in the Woodmansey area.
Stakeholder feedback and Forewind response
8.29.4 The IPC (now the Planning Inspectorate) recommended in its Scoping Opinion that
noise impacts on people should be specifically addressed including noise
disturbance at night and other unsocial times such as weekends from the
operational converter stations. Construction noise levels off-site along roads and
public rights of way, and vibration caused by abnormal loads and Heavy Goods
Vehicles (HGVs) should also be assessed. The noise and vibration assessment
should also inform the ecological assessment and historic environment topics
where appropriate.
8.29.5 Potential onshore noise and vibration impacts upon ecological receptors are
considered in Chapter 25 Terrestrial Ecology of the ES; and potential noise and
vibration impacts upon the historic environment are considered in Chapter 27
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 91 © 2013 Forewind
Onshore Cultural Heritage of the ES.
8.29.6 Potential construction noise impacts arising from on-site works, within the working
areas of the landfall, cable route and converter stations were assessed, including
the potential for noise and vibration impacts off site from HGVs.
8.29.7 Operational noise, associated with the converter stations is also assessed in
Chapter 29 Noise and Vibration of the ES. Noise predictions were made at the
four closest residential receptors: Model Farm, Poplar Farm, Halfway House and
Wanlass Farm. Measures to reduce the operational noise to 35 decibels at these
properties are proposed within the chapter.
8.30 Air Quality (ES Chapter 30)
Main stakeholders and methods of consultation
8.30.1 Stakeholders consulted on air quality impacts include East Riding of Yorkshire
Council (ERYC), Parish Councils and members of the local community.
8.30.2 For summaries of all relevant responses please see Appendix M30.
Key issues raised
8.30.3 Beyond the scoping opinion very few air quality issues were raised during
consultation. Issues raised included:
Potential nuisance of dust generated during construction to nearby properties;
and
That the operational phase is unlikely to have any noticeable impact upon air
quality receptors.
Stakeholder feedback and Forewind response
8.30.4 The IPC (now the Planning Inspectorate) recommended in its Scoping Opinion that
the potential impacts associated with increased air emissions particularly particulate
matter (PM10) and NO2 should be addressed. The assessment should assess
implications on nearby sites designated for nature conservation. Impacts of dust
should be considered as the area is predominantly rural.
8.30.5 During the site selection and the assessment of alternatives process, the location of
the converter stations, and the alignment of the cable route, were identified to avoid
built up and residential areas as much as possible. This would also serve to
minimise the number of nearby receptors that could potentially experience air
quality impact.
8.30.6 Air quality receptors within 350m of the proposed converter stations site and cable
route were identified and potential air quality impacts associated with increased air
emissions particularly PM10 and NO2 were assessed. Residual impacts were all
identified as negligible. In addition, the potential air quality impacts upon ecological
receptors are also considered in Chapter 30 Air Quality of the ES and also
assessed as negligible. Best practice mitigation measures will be implemented by
the lead operator, including the development of a dust management plan.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 92 © 2013 Forewind
9 Statements of common ground
9.1.1 Where possible, Forewind is endeavouring to agree Statements of Common
Ground with certain consultees to assist the Planning Inspectorate in understanding
which issues have been agreed and which remain unresolved.
9.1.2 Each Statement of Common Ground sets out a record of consultation undertaken to
date with that stakeholder, the key agreements reached and outstanding
unresolved issues.
9.1.3 The Statements of Common Ground are draft documents at the application stage
and so will be updated during the examination stage, to reflect on-going
consultation.
9.1.4 Forewind is in the process of agreeing Statements of Common Ground with the
consultees presented in Table 9.1. Additional Statements of Common Ground with
other consultees will be drafted as the need arises.
Table 9.1 Statements of common ground currently in progress
Consultee ES Subject
Onshore
Beverley and North Holderness Internal Drainage Board Project description (water crossings) Land use and agriculture
East Riding of Yorkshire Council Site selection Traffic and transport Noise Landscape and visual Terrestrial ecology Health impact assessment Development Consent Order Deemed Marine Licence
English Heritage – Yorkshire and Humber Terrestrial archaeology
Environment Agency Flood risk Geology and hydrogeology Project description (water crossings) Traffic and Access Air Quality Tourism and Recreation (PRoW)
Humber Archaeology Partnership Terrestrial archaeology
Natural England Terrestrial ecology Landscape and visual Ornithology Project description (water crossings)
Yorkshire Water Services Geology and hydrogeology
Offshore
Chamber of Shipping Navigation and shipping
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 93 © 2013 Forewind
Consultee ES Subject
English Heritage – Offshore development Marine archaeology
Joint Nature Conservation Committee Benthic ecology Fish ecology Marine mammals Ornithology
MMO and Cefas Fish ecology Benthic ecology Physical processes Development Consent Order Deemed Marine Licence
Maritime and Coastguard Agency (MCA) Navigation and shipping
Natural England Physical Processes Intertidal ecology Ornithology Marine Mammals
Royal Society for the Protection of Birds (RSPB) Ornithology
Trinity House Navigation and shipping
Fisheries
National Federation of Fishermen‘s Organisations (NFFO) Commercial fisheries
Hornsea Coastal Fishing Industry Group (HCFIG) Commercial fisheries
North Eastern Inshore Fisheries & Conservation Authority (NEIFCA) Commercial fisheries
Danish Fishermen‘s Association (DFA) Commercial fisheries
Swedish Fishermen‘s Federation, Sveriges Fiskares Riksfӧrbund (SFF)
Commercial fisheries
Norway - Fishing Vessel Owners Union/ South Norway Trawlers Association (Sør-Norges Trǻlerlag)
Commercial fisheries
France - Comité National des Pêches Maritimes (CRPM Nord) Commercial fisheries
Belgium - Department of Agriculture & Fisheries (Rederscentrale) Commercial fisheries
9.1.5 Statements of Common Ground or letters of intent are also being sought with other
marine users with whom crossing or proximity agreements may be required. These
are likely to include, but are not restricted to:
Cable & Wireless (on behalf of British Telecom for UK-Germany 6 and UK-
Denmark 4)
Tata Telecoms (Tata North Europe Cable)
Gassco (Langeled Pipeline)
Shell UK (Shearwater Elgin Area Line Pipeline)
Cemex (aggregates dredging Area 485)
9.1.6 In addition, Statements of Common Ground or letters of intent are being sought with
onshore utility companies with whom crossing or proximity agreements may be
required.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 94 © 2013 Forewind
10 Conclusion
10.1.1 Forewind has carried out comprehensive pre-application consultation on Dogger
Bank Creyke Beck, with a wide range of stakeholders.
10.1.2 The consultation process has met and exceeded the requirements of the Planning
Act and has taken into account relevant advice and guidance published by the
Planning Inspectorate (formerly the IPC) and UK Government.
10.1.3 Stakeholders have been engaged in the development process from an early stage
and consultation responses have been carefully documented and considered in the
on-going development work. This has resulted in stakeholders having a clear
influence on the proposals.
10.1.4 Where Forewind has not taken forward a recommendation for a major change to
the application, this has been duly explained in the Consultation Report.
10.1.5 Statements of Common Ground have been initiated pre-application to demonstrate
a clear commitment to transparency and developing mutually acceptable solutions
to issues. These are draft documents at the point of application which point to the
need for further consultation as the application progresses through the acceptance
and examination stages of the planning process.
10.1.6 Forewind has generally received positive feedback on its approach to consultation,
from several stakeholders. Notably, the Chair of the community working group
stated in the final meeting that Forewind had adopted an:
“open, honest and inclusive approach […] from an engagement, education
and involvement perspective [and] that Forewind’s approach is refreshing
and an example for other organisations to follow”. (Cllr Ros Jump, 25 April
2013)
10.1.7 In its response to the second stage of statutory consultation, East Riding of
Yorkshire Council (ERYC) said:
“The Council welcomes the approach taken by Forewind on the project and
its engagement with the Council so far. The quality of consultation and
ongoing dialogue with relevant Officers has been consistently high.” (ERYC,
11 June 2013)
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 95 © 2013 Forewind
Annex 1 – Compliance checklist
Ref Requirement Compliance
Planning Act 2008 as amended by the Localism Act 2011
Section
42 (1)
Duty to consult: See Chapter 3
a) Such persons as may be prescribed, The Applicant consulted all persons
prescribed by the Infrastructure Planning
(Applications: Prescribed Forms and
Procedure) Regulations 2009. See
Appendix C2.
aa) The Marine Management
Organisation,
The Applicant consulted the MMO. See
Appendix C2
b) Each local authority that is within
section 43,
The Applicant consulted each local
authority that is within section 43. See
Appendix C2
c) The Greater London Authority if the
land is in Greater London, and
Not applicable
d) Each person who is within one or
more of the categories set out in
section 44
The Applicant consulted each person
who is within one or more of the
categories set out in section 44. See the
Book of Reference (Planning
Inspectorate document reference
number 4.3)
Section
45
Timetable for consultation under section 42 See Chapter 3
1) The applicant must, when consulting a
person under section 42, notify the
person of the deadline for the receipt
by the applicant of the person‘s
response to the consultation
The Applicant notified all those consulted
under section 42 of the deadline in
writing, either by post or email. See
Appendix D and E.
2) A deadline notified under subsection
(1) must not be earlier than the end of
the period of 28 days that begins with
the day after the day on which the
person receives the consultation
documents
The first stage of section 42 consultation
ran from 5 December 2011 to 20 January
2012 – a period of 47 days.
The second stage of section 42
consultation ran from 19 April to 11 June
2013 – a period of 54 days.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 96 © 2013 Forewind
3) In subsection (2) ―the consultation
documents‖ means the documents
supplied to the person by the applicant
for the purpose of consulting the
person
At the first stage of section 42
consultation, the consultation documents
comprised a cover letter including a
website address from where the
preliminary environmental information
could be downloaded. Those consulted
under section 42 (1) d) were also sent a
CD copy of the PEI.
At the second stage of section 42
consultation, the consultation documents
comprised a DVD copy of the draft ES
and NTS (unless that consultee had
specifically requested a hard copy in
which case hard copies were sent in
addition to a DVD).
Section
46
Duty to notify Secretary of State of
proposed application
See Chapter 3
(1) The applicant must supply the
Secretary of State with such
information in relation to the proposed
application as the applicant would
supply to the Secretary of State for the
purpose of complying with section 42 if
the applicant were required by that
section to consult the Secretary of
State about the proposed application.
At both stages of section 42
consultations, the applicant supplied the
IPC or Planning Inspectorate (as
appropriate) with the same information as
other section 42 consultees.
(2) The applicant must comply with
subsection (1) on or before
commencing consultation under
section 42.
At the first stage, the Applicant delivered
the consultation documents to the IPC on
2 December 2011. The consultation
began on 5 December 2011.
At the second stage, the Applicant
delivered the consultation documents to
the Planning Inspectorate on 16 April
2013. The consultation began on 19 April
2013.
Section
47
Duty to consult the local community See Chapter 4
(1) The applicant must prepare a
statement setting out how the
applicant proposes to consult, about
the proposed application, people living
in the vicinity of the land.
The Applicant has prepared a Statement
of Community Consultation. See
Appendix F
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 97 © 2013 Forewind
(2) Before preparing the statement, the
applicant must consult each local
authority that is within section 43(1)
about what is to be in the statement.
Before preparing the statement, the
Applicant consulted each local authority
that is within section 43(1) on the content
of the statement. See Appendix F for
copies of the cover letters.
(3) The deadline for the receipt by the
applicant of a local authority‘s
response to consultation under
subsection (2) is the end of the period
of 28 days that begins with the day
after the day on which the local
authority receives the consultation
documents.
The Applicant allowed the local
authorities within section 43(1) from 3
October 2011 to 1 November 2011 to
respond to the consultation under
subsection (2). This is a period of 30
days.
(4) In subsection (3) ―the consultation
documents‖ means the documents
supplied to the local authority by the
applicant for the purpose of consulting
the local authority under subsection
(2).
The SoCC consultation document is
provided in Appendix F
(5) In preparing the statement, the
applicant must have regard to any
response to consultation under
subsection (2) that is received by the
applicant before the deadline imposed
by subsection (3).
The Applicant considered all relevant
comments received on the draft SoCC.
See Appendix M1 for a table of
responses.
(6) Once the applicant has prepared the
statement, the applicant must—
(za) make the statement available for
inspection by the public in a way that
is reasonably convenient for people
living in the vicinity of the land,
(a) publish in a newspaper circulating
in the vicinity of the land a notice
stating where and when the
statement can be inspected, and
(b) publish the statement in such
manner as may be prescribed.
The Applicant made the statement
available for inspection by the public in a
number of local libraries and sent a hard
copy to all those addresses within the
community consultation area. A notice
detailing where and when the SoCC (in
full) could be inspected was published in
November 2011. See Appendix F for
copies of the published SoCC.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 98 © 2013 Forewind
(7) The applicant must carry out
consultation in accordance with the
proposals set out in the statement.
The Applicant has carried out the
consultation in accordance with the
SoCC. See Table 4.3.
Section
48
Duty to Publicise See Chapter 5
(1) The applicant must publicise the
proposed application in the prescribed
manner
The Applicant prepared and published a
Section 48 Notice in the manner
prescribed by the Infrastructure Planning
(Applications: Prescribed Forms and
Procedure) Regulations 2009. See
Appendix K for copies of the published
notice.
(2) Regulations made for the purposes of
subsection (1) must, in particular,
make provision for publicity under
subsection (1) to include a deadline for
receipt by the applicant of responses
to the publicity.
The Section 48 Notice included a
deadline for receipt by the Applicant of
responses to the publicity.
The deadline was 11 June 2013.
Section
49
Duty to take account of responses to
consultation and publicity
See Chapter 8
(1) Subsection (2) applies where the
applicant—
(a) has complied with sections 42, 47
and 48, and
(b) proposes to go ahead with
making an application for an
order granting development
consent (whether or not in the
same terms as the proposed
application).
(2) The applicant must, when deciding
whether the application that the
applicant is actually to make should be
in the same terms as the proposed
application, have regard to any
relevant responses.
(3) In subsection (2) ‖relevant response‖
means—
(a) a response from a person
The Applicant has had regard to all
relevant responses to consultation in
accordance with section 42, 47 and 48.
See Appendix M for relevant response
tables which details The Applicant‘s
regard to responses.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 99 © 2013 Forewind
consulted under section 42 that is
received by the applicant before
the deadline imposed by section
45 in that person‗s case,
(b) a response to consultation under
section 47(7) that is received by
the applicant before any
applicable deadline imposed in
accordance with the statement
prepared under section 47, or
(c) a response to publicity under
section 48 that is received by the
applicant before the deadline
imposed in accordance with
section 48(2) in relation to that
publicity.
Section
50
Guidance about pre-application procedure See Chapter 2
(1) Guidance may be issued about how to
comply with the requirements of this
Chapter.
The Applicant has had regard to the
Department for Communities and Local
Government (DCLG) Planning Act 2008
Guidance on the pre-application process
(2013). The Applicant also had regard to
previous versions of this guidance issued
by DCLG and the IPC.
(2) Guidance under this section may be
issued by the Commission or the
Secretary of State
(3) The applicant must have regard to any
guidance under this section
The Infrastructure Planning (Application: Prescribed Forms and Procedure) Regulations 2009
Ref Requirement Compliance
Reg 3 The persons prescribed for the purposes of
section 42(a) (duty to consult) are those listed
in column 1 of the table in Schedule 1 to these
Regulations, who must be consulted in the
circumstances specified in relation to each
such person in column 2 of that table.
The Applicant consulted all those persons
prescribed in column 1 of the table in
Schedule 1 who were deemed relevant to
this application by the descriptions set out
in column 2 of that table.
Regard was had to the Infrastructure
Planning (Prescribed Consultees and
Interested Parties etc.) (Amendment)
Regulations 2013, however noting that
under Regulation 7, the amendments do
not apply to the Dogger Bank Creyke
Beck Application, as the Secretary of
State had been notified in accordance
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 100 © 2013 Forewind
with both Section 46 of the Planning Act
2008 and Regulation 6(1)(b) of the EIA
Regulations before 6 April 2013.
A full list is provided in Appendix C2.
Reg 4 Publicising a proposed application See Chapter 5
(2) The applicant must publish a notice,
which must include the matters
prescribed by paragraph (3) of this
regulation, of the proposed
application-
(a) for at least two successive weeks
in one or more local newspapers
circulating in the vicinity in which
the proposed development would
be situated;
(b) once in a national newspaper;
(c) once in the London Gazette and, if
land in Scotland is affected, the
Edinburgh Gazette; and
(d) where the proposed application
relates to offshore development—
(i) once in Lloyd‗s List; and
(ii) once in an appropriate fishing
trade journal.
The Applicant published a notice which
included all the matters set out in
paragraph (3). Copies of the notice are
provided in Appendix K
(a) The notice was published for two
successive weeks in the
Advertiser Series (24 April and 1
May 2013), the Bridlington Free
Press (25 April and 2 May 2013),
the Holderness Gazette (25 April
and 2 May 2013) and the Hull
Daily Mail (22 and 29 April 2013)
(b) The notice was published in The
Independent on 22 April 2013
(c) The notice was published in the
London Gazette on 22 April 2013
(d)(i) The notice was published in the
Lloyds List on 22 April 2013
(d)(ii) The notice was published in the
Fishing News on 26 April 2013
(3) The matters which the notice must
include are:
(a) the name and address of the
applicant;
(b) a statement that the applicant
intends to make an application for
development consent to the
Secretary of State;
(c) a statement as to whether the
application is EIA development;
(d) a summary of the main proposals,
specifying the location or route of
the proposed development;
(e) a statement that the documents,
plans and maps showing the
nature and location of the
(3) The notice included all matters
required by this regulation.
References below refer to the specific
paragraph of the notice where the
information was provided. See
Appendix K for a copy of the notice.
(a) Paragraph 1
(b) Paragraph 1
(c) Paragraph 6
(d) Paragraphs 2, 3 and 4
(e) Paragraphs 7 and 8
(f) Paragraph 7
(g) Paragraph 9
(h) Paragraph 10
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 101 © 2013 Forewind
proposed development are
available for inspection free of
charge at the places (including at
least one address in the vicinity of
the proposed development) and
times set out in the notice;
(f) the latest date on which those
documents, plans and maps will
be available for inspection (being
a date not earlier than the
deadline in subparagraph (i));
(g) whether a charge will be made for
copies of any of the documents,
plans or maps and the amount of
any charge;
(h) details of how to respond to the
publicity; and
(i) a deadline for receipt of those
responses by the applicant, being
not less than 28 days following
the date when the notice is last
published.
(i) Paragraph 10
The Infrastructure Planning (Environmental Impact Assessment) Regulations 2009
Ref Requirement Compliance
Reg 6 Procedure for establishing whether
environmental impact assessment is
required
See Chapter 7
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 102 © 2013 Forewind
(1) A person who proposes to make an
application for an order granting
development consent must, before
carrying out consultation under section
42 (duty to consult) either—
(a) request the Secretary of State to adopt
a screening opinion in respect of the
development to which the application
relates; or
(b) notify the Secretary of State in writing
that the person proposes to provide an
environmental statement in respect of
that development.
The Applicant requested a Scoping
Opinion from the IPC (now Planning
Inspectorate) in October 2010. The IPC
responded in its Scoping Opinion that it
deemed Forewind to have notified the
Commission under Regulation 6(1)(b) of
the EIA Regulations (Planning
Inspectorate document reference
number 6.4.3)
(3) A request or notification under
paragraph (1) must be accompanied
by—
(a) a plan sufficient to identify the land;
(b) a brief description of the nature and
purpose of the development and of its
possible effects on the environment;
(c) such other information or
representations as the person making
the request may wish to provide or
make.
The Applicant supplied the IPC (now
Planning Inspectorate) with the Dogger
Bank Project One Scoping Report which
included all the information required by
sections (a), (b) and (c) of this regulation.
Reg 10 Consultation statement requirements See Chapter 4
The consultation statement prepared under
section 47 (duty to consult local community)
must set out —
(a) whether the development for which the
applicant proposes to make an
application for an order granting
development consent is EIA
development; and
(b) if that development is EIA development,
how the applicant intends to publicise
and consult on the preliminary
environmental information.
The Applicant included the following in
the Statement of Community
Consultation: ―Dogger Bank Creyke Beck
is an ―EIA Development‖ for the purposes
of Schedule 2 to the Infrastructure
Planning (Environmental Impact
Assessment) Regulations 2009 and
―Forewind will compile the Preliminary
Environmental Information (PEI) required
to assess the environmental impacts of
the project. PEI will be available during
both stages of consultation‖. See
Appendix F for a copy of the SoCC.
Reg 11 Pre-application publicity under section 48 See Chapter 5
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 103 © 2013 Forewind
(duty to publicise)
Where the proposed application for an
order granting development consent is an
application for EIA development, the
applicant must, at the same time as
publishing notice of the proposed
application under section 48(1), send a
copy of that notice to the consultation
bodies and to any person notified to the
applicant in accordance with regulation
9(1)(c).
The Applicant sent hard copies of the
section 48 notice (as described in
paragraph (3)) to the consultation bodies
specified in Appendix C2 at the time of
notifying them of the start of section 42
consultation (17 April 2013). The notice
was publicised between 22 April and 2
May 2013.
DCLG (2013) Planning Act 2008 Guidance on the Pre-Application Process
Ref Requirement Compliance
15 …Instead, applicants, who are best placed
to understand the detail of their specific
project, and the relevant local authorities,
who have a unique knowledge of their local
communities, should as far as possible
work together to develop plans for
consultation. The key aim should be to
ensure that the amount of consultation
undertaken, and who is consulted, should
be in proportionate to the size and scale of
project and where its impacts will be felt.
The Applicant and East Riding of
Yorkshire Council (the ―B‖ Authority) have
worked together closely on the approach
to consultation with the local community.
Hull City Council (an ―A‖ authority) has
also provided The Applicant with helpful
input, including statutory consultation in
accordance with Section 47 of the
Planning Act on the content of the
Statement of Community Consultation, as
well as agreement on additional
community consultation such as the
Community Working Group and Parish
Council Workshops. See Chapter 4.
17 Consultation should be thorough, effective
and proportionate. Applicants will have
their own approaches to consultation and
already have a wealth of good practice on
which to draw. For example, larger, more
complex applications will usually need to
go beyond the statutory minimum
timescales laid down in the Planning Act to
provide enough time for consultees to
understand project proposals and
formulate a response. Many proposals will
require detailed technical input, especially
regarding impacts, so sufficient time will
need to be allowed for this. Consultation
should also be sufficiently flexible to
respond to the needs and requirements of
The Applicant consulted thoroughly on
the application by means of a two stage
statutory process, with significant subject
specific, targeted, non-statutory
consultation between these stages. This
iterative process proved to be an effective
way to gather and incorporate
stakeholder feedback throughout the pre-
application stage. Given The Applicant‘s
development of multiple applications in
the Dogger Bank Zone, care was taken to
ensure that statutory consultations on
different Dogger Bank applications did
not overlap, thereby avoiding
overburdening stakeholders. Where
possible, The Applicant consulted
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 104 © 2013 Forewind
consultees, for example where a consultee
has indicated that they would prefer to be
consulted via email only, this should be
accommodated as far as possible.
stakeholders on a non-statutory basis on
a subject affecting all Dogger Bank
applications, thereby endeavouring to
avoid un-necessary repetition.
All statutory consultation periods under
sections 42, 47 and 48 of the Planning
Act allowed the consultees more than the
statutory minimum of 28 days to respond.
In addition, The Applicant made best
endeavours to give advance notice of
statutory consultation periods and provide
advanced sight of PEI where requested.
The Applicant accommodated all
stakeholder requests about
communication methods, sending out
information by post or electronically as
requested. See Chapters 3, 4 and 5.
18 In addition, applicants may also wish to
strengthen their case by seeking the views
of other people who are not statutory
consultees, but who may be significantly
affected by the project
The Applicant consulted a large number
of additional consultees.
See Chapter 6.
19 Applicants are therefore encouraged to
consult widely on project proposals.
20 Applicants should identify any successor
body and consult with them in the same
manner as they would have with the
original body. Where there is no obvious
successor, applicants should seek the
advice of the Inspectorate, who may be
able to identify an appropriate alternative
consultee. Whether or not an alternative is
identified, the consultation report should
briefly note any cases where compliance
with statutory requirements was impossible
and the reasons why.
The Applicant was able to comply with
statutory requirements, however the
particular bodies consulted changed over
the course of the pre-application process
and The Applicant sought and received
advice from the Planning Inspectorate on
this matter. A full list of Section 42(1)a
consultees is provided in Appendix C2.
See section 3.2.
21 Applicants will often need detailed
technical input from expert bodies to assist
with identifying and mitigating the social,
environmental, design and economic
impacts of projects, and other important
matters. Technical expert input will often be
needed in advance of formal compliance
The Applicant carried out significant non-
statutory consultation on the technical
elements of the applications. See
Section 6.2.
The Applicant discussed the consultation
programme with many of the technical
consultees, including East Riding of
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 105 © 2013 Forewind
with the pre-application requirements. Early
engagement with these bodies can help
avoid unnecessary delays and the costs of
having to make changes at later stages of
the process. It is equally important that
statutory consultees respond to request for
technical input in a timely manner.
Applicants are therefore advised to discuss
and agree a timetable with consultees for
the provision of such inputs
Yorkshire Council (with whom a Planning
Performance Agreement was signed),
MMO (formal charging regime for non-
statutory advice), Natural England and
JNCC. In addition, The Applicant made
best endeavours to give advance notice
of statutory consultation periods.
See Sections 3.5 and 3.6.
25 Where an applicant decides to consult
people living in a wider area who could be
affected by the project (e.g. through visual
or environmental impacts, or through
increased traffic flow), that intention should
be reflected in the Statement of Community
Consultation.
The Statement of Community
Consultation was published ahead of the
2013 Guidance but nonetheless stated
―Anyone outside of the Consultation Area
who may be interested in the project is
welcome to take part in the community
consultation process and should refer to
advertisements in the local newspapers,
marine journals and the Forewind website
for details of the consultation events and
deadlines for responses.‖ Refer to
Appendix F
26 …prior to submitting their draft Statement
of Community Consultation applicants may
wish to seek to resolve any disagreements
or clarifications about the public
consultation design. An applicant is
therefore likely to need to engage in
discussions with local authorities over a
longer period than the minimum
requirements set out in the Act.
The Applicant consulted the local
authorities on the content of the
Statement of Community Consultation
over an extensive period, namely
December 2010 to November 2011.
See Section 4.2.
30 Where a local authority raises an issue or
concern on the Statement of Community
Consultation which the applicant feels
unable to address, the applicant is advised
to explain in their consultation report their
course of action to the Secretary of State
when they submit their application.
All Local Authority comments on the
content of the Statement of Community
Consultation were addressed. Refer to
Appendix M1
31 Where a local authority decides that it does
not wish to respond to a consultation
request on the Statement of Community
Consultation, the applicant should make
reasonable efforts to ensure that all
All Local Authorities consulted on the
Statement of Community Consultation
responded.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 106 © 2013 Forewind
affected communities are consulted. If the
applicant is unsure how to proceed, they
are encouraged to seek advice from the
Inspectorate. However, it is for the
applicant to satisfy themselves that their
consultation plan allows for as full public
involvement as is appropriate for their
project and, once satisfied, to proceed with
the consultation. Provided that applicants
can satisfy themselves that they have
made reasonable endeavours to consult
with all those who might have a legitimate
interest or might be affected by a proposed
development, it would be unlikely that their
application would be rejected on grounds
of inadequate public consultation.
32 Local authorities are also themselves
statutory consultees for any proposed
major infrastructure project which is in or
adjacent to their area. Applicants should
engage with them as early as possible to
ensure that the impacts of the development
on the local area are understood and
considered prior to the application being
submitted to the Secretary of State.
The Applicant engaged with the Local
Authorities from an early stage in the
development process. ERYC and Hull
City Council attended the Zone Appraisal
and Planning Workshops in April 2010.
Refer to Appendix N1
33 Local authorities will be able to provide an
informed opinion on a wide number of
matters, including how the project relates
to local development plans. Local
authorities may also make suggestions for
requirements to be included in the draft
Development Consent Order. These may
include the later approval by the local
authority (after the granting of a
Development Consent Order) of detailed
project designs or schemes to mitigate
adverse impacts. It will be important that
any concerns local authorities have on the
practicality of enforcing a proposed
Development Consent Order are raised at
the earliest opportunity.
The Applicant consulted ERYC on the
draft Development Consent Order and
has had due regard to any comments
received. See the Explanatory
Memorandum (Planning Inspectorate
document reference number 3.2).
35 Applicants will also need to identify and
consult people who own, occupy or have
another interest in the land in question, or
The Applicant began the process of
identifying and consulting people who
own, occupy or have another interest in
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 107 © 2013 Forewind
who could be affected by a project in such
a way that they may be able to make a
claim for compensation. This will give such
parties early notice of projects, and an
opportunity to express their views
regarding them.
the land at an early stage.
See Section 3.4.
36 …People should have as much influence
as is realistic and possible over decisions
which shape their lives and communities. It
is therefore critical that they are engaged
with project proposals at an early stage.
Because they live, work and socialise in
the affected area, local people are
particularly well placed to comment on
what the impact of proposals on their local
community might be; or what mitigating
measures might be appropriate; or what
other opportunities might exist for meeting
the project‘s objectives.
The Local Community was consulted
through two stages of statutory
consultation, enabling them to have an
influence on the proposals from an early
stage. Additional non-statutory
community consultation was carried out
in order to maximise the opportunities for
involvement of the local community.
See Chapter 4.
37 …Applicants should use a range of
methods and techniques to ensure that
they access all sections of the community
in question. Local authorities will be able to
provide advice on what works best in terms
of consulting their local communities given
their experience of carrying out
consultations in their area.
The Applicant employed a range of
consultation methods and any hard to
reach groups were identified through
consultation with the Local Authorities.
See Chapter 4.
38 Applicants must set out clearly what is
being consulted on. They must be careful
to make it clear to local communities what
is settled and why, and what remains to be
decided, so that expectations of local
communities are properly managed. A
short document should be prepared by
applicants specifically for local
communities, summarising the project
proposals and outlining the matters on
which the view of the local community is
sought. It should also describe the key
elements of the project, and explain what
the potential benefits and impacts of the
projects might be. The document should be
written in clear, accessible, and non-
technical language. Applicants should be
At each stage of statutory community
consultation, key consultation questions
were set out on the exhibition panels, in
the questionnaires and in the community
consultation summary booklet. This short
booklet was written in non-technical
language and described the key elements
of the project and what the potential
benefits and impacts of the project might
be. The booklet was available in hard
copy, on DVD and to download from the
Forewind website.
See Section 4.4 and Section 4.5.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 108 © 2013 Forewind
ready to make it available in formats
appropriate to the needs of people with
disabilities if requested. There may be
cases where documents may need to be
made bilingually (for example, Welsh, in
applications affecting Wales), but it is not
the policy of the Government to encourage
documents to be translated into non-native,
foreign languages.
39 Applicants are required to set out in their
Statement of Community Consultation how
they propose to consult those living in the
vicinity of the land, but they are
encouraged to consider consulting beyond
this where they think doing so may provide
more information on the impacts of their
proposals (e.g. through visual impacts or
increased traffic flow).
The Applicant advertised each stage of
statutory consultation more widely than
just in the Consultation Area to ensure
that others with an interest in the
proposals could take part. For this
reason, stakeholders from, for example,
Hull, Scarborough and Whitby took part in
the consultation.
40 The Statement of Community Consultation
should act as a framework for the
community consultation generally, stating
where and when events will be taking
place. The Statement of Community
Consultation should be made available
online, at any exhibitions or other events
held by the applicants and should also be
placed at appropriate local deposit points
(e.g. libraries, council offices) and sent to
local community groups as appropriate.
The Statement of Community
Consultation listed the details of the
Stage One consultation events and was
made available on the Forewind website,
at the public exhibitions and at local
libraries. It was sent in hard copy to all
addresses in the Consultation Area.
Refer to Section 4.4.
41 Applicants are required to publicise their
proposed application under section 48 of
the Planning Act. Regulation 4(2) of the
Infrastructure Planning (Applications:
Prescribed Forms & Procedure)
Regulations 2009 sets out the detail of
what this publicity must entail. This
publicity is an integral part of the local
community consultation process. Where
possible, the first of the two required local
newspaper advertisements should coincide
approximately with the beginning of the
consultation with communities. However,
given the detailed information required for
the publicity in secondary legislation,
The Section 48 Notice was published at
the start of the second stage of statutory
consultation. The first notice was
published two weeks before the start of
the stage two public exhibitions, thereby
also serving to provide due notice of the
forthcoming events.
See Chapter 5.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 109 © 2013 Forewind
aligning publicity with consultation may not
always be possible, especially where a
multi-stage consultation is intended.
43 Applicants have a statutory duty to consult any
local authority in whose land a project is sited.
So, where an offshore project also features
land-based development, the applicant should
treat the local authority where the land-based
development is located as the main consultee
for the Statement of Community Consultation.
The applicant is also advised to consider
seeking views on the Statement of Community
Consultation from local authorities whose
communities may be affected by the project,
for example visually or through construction
traffic, even if the project is in fact some
distance from the area in question. In addition,
applicants may find it beneficial to discuss their
Statement of Community Consultation with any
local authorities in the vicinity where there
could be an effect on harbour facilities.
The Applicant treated ERYC (the ―B‖
authority) as the main consultee for the
SoCC. The 35km Zone of Visual
Influence (ZVI) for the offshore
infrastructure of Dogger Bank Creyke
Beck does not cover any other local
authorities. The landfall and near shore
works will be temporary and will only be
visible from the East Riding of Yorkshire.
Therefore, no additional authorities have
been consulted on the SoCC on this
basis. Given its original inclusion in the
Scoping Area, Hull City Council was also
consulted on the SoCC. No other Local
Authorities were consulted as ―port‖
authorities as the port, and therefore
likely concentration of construction
marine traffic, is not yet known.
45 Applicants should ensure they consider all
the potential impacts on communities
which are in the vicinity of the proposed
project. These are unlikely to affect all
communities to the same degree but might
include potential visual, environmental,
economic and social impacts.
The main impact extending more widely
than the Consultation Area is the
potential socio economic impact. The
Applicant engaged with several
constituency MPs and councils outside of
the Consultation Area on this topic and
has also funded an innovative careers
education programme ―Champions for
Wind‖ to increase awareness of the
career opportunities in offshore wind.
This programme is currently active in
schools across the East Riding of
Yorkshire, North Yorkshire and Teesside.
46 Where the location of a proposed offshore
project is such that the impacts on
communities are likely to be very small or
negligible, applicants are still expected to
inform relevant coastal authorities and
communities of the proposed project, and
give them a chance to take part in any
consultation. When deciding who to consult
in these situations, applicants are
encouraged to think laterally, by, for
A number of coastal local authorities
were consulted as a result of Forewind‘s
interpretation of Section 43 of the
Planning Act.
See Section 3.3.
Given the scale of the proposals, there is
the possibility that a large number of
coastal communities could be impacted in
a small or negligible way but The
Applicant felt it would be
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 110 © 2013 Forewind
example, identifying nearby local
authorities with busy harbours, active
fishing or sailing / water-sports
communities or key local environmental
groups.
disproportionately impractical to consult
them all. The Section 48 Notice was
published in the national press in
advance of the second stage of statutory
consultation, giving the wider population
an opportunity to respond to the
consultation.
See Chapter 5.
47 Where there are no obvious impacts on
local communities, applicants should
consult the local communities closest to the
proposed project. It may be that there are
impacts which are not immediately obvious
but which a consultation can identify.
Equally, local communities may have
concerns, for example, about
environmental impacts, and open
engagement with the applicant will allow
them the chance to express their concerns
and to understand how these concerns are
being addressed. The level of interest
shown by local authorities and
communities will dictate the degree and
depth of consultation required. It may be
that for certain offshore projects, the
consultation process with local
communities can be undertaken at a
focused and proportionate way, and
therefore completed within the minimum
statutory timescales required by the
Planning Act.
The Applicant‘s statutory consultation
with local communities was open to all
those with an interest in the proposals.
48 Ultimately, applicants for offshore projects
should take a pragmatic approach,
consulting in proportion to the impacts on
communities and the size of the project,
whilst ensuring that relevant local
communities are kept informed about the
proposals and offered the chance to
participate in shaping them. Applicants
should use this as a guiding principle for
consultation together with the statutory
requirements as set out in the Planning
Act. Provided they do this, and fully explain
their approach in the consultation report
which accompanies their application, the
The Applicant considers that its
consultation process with the local
community has been pragmatic,
proportionate and open to all. This is
reflected in Forewind‘s consultation
objectives, as set out in the Stakeholder
Engagement Plan.
See Appendix A.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 111 © 2013 Forewind
expectation is that their application will not
be rejected on the grounds of insufficient
public consultation.
49 In addition to relevant local authorities and
their communities, prospective applicants
for development consent for certain types
of projects are required to consult and
engage with the Marine Management
Organisation. They will be also be able to
advise on what, and with whom, additional
consultation might be appropriate.
Additional guidance is available from the
Inspectorate on transboundary
consultations.
The Applicant consulted the MMO on the
content of the draft SoCC. Relevant
responses to the SoCC consultation and
the regard The Applicant had to them are
summarised in Appendix M1.
50 To realise the benefits of early consultation
on a project, it must take place at a
sufficiently early stage to allow consultees
a real opportunity to influence the
proposals. But equally, consultees will
need sufficient information on a project to
be able to recognise and understand the
impacts.
The Applicant carried out two stages of
statutory consultation. This allowed
consultees to comment on the initial, fluid
proposals as well as the near final
proposals, prior to the application being
submitted. In between statutory periods,
The Applicant carried out non-statutory
consultation in order to continue
engaging with relevant stakeholders.
The first stage of statutory consultation
was carried out at an early stage in the
development process, when the study
area was narrowed down from the large
Scoping Area, but the proposals were still
reasonably fluid. This allowed consultees
a real opportunity to influence key
decisions about the design (such as the
landfall location) and approach to the
EIA.
See Chapter 8.
51 Applicants will often also require detailed
technical advice from consultees and it is
likely that their input will be of the greatest
value if they are consulted when project
proposals are fluid, followed up by
confirmation of the approach as proposals
become firmer. In principle, therefore,
applicants should undertake initial
consultation as soon as there is sufficient
detail to allow consultees to understand the
nature of the project properly.
52 To manage the tension between consulting
early, but also having project proposals
that are firm enough to enable consultees
to comment, applicants are encouraged to
consider an iterative, phased consultation
consisting of two (or more) stages,
especially for large projects with long
development periods. For example,
applicants might wish to consider
undertaking informal early consultation at a
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 112 © 2013 Forewind
stage where options are still being
considered. This will be helpful in informing
proposals and assisting the applicant in
establishing a preferred option on which to
undertake formal statutory public
consultation.
53 Where an iterative consultation is intended,
it may be advisable for applicants to carry
out the final stage of consultation with
persons who have an interest in the land
once they have worked up their project
proposals in sufficient detail to identify
affected land interests.
Those with an interest in the land were
consulted at both stages of statutory
consultation to ensure that they were
aware of the proposals as early as
possible.
See Section 3.4
54 …The Planning Act provides for a
minimum 28 day period for consultation. It
is expected that this may be sufficient for
projects which are straightforward and
uncontroversial in nature. But many
projects, particularly larger or more
controversial ones, may require longer
consultation periods than this. Applicants
should therefore set consultation deadlines
that are realistic and proportionate to the
proposed project. It is also important that
consultees do not withhold information that
might affect a project, and that they
respond in good time to applicants. Where
responses are not received by the
deadline, the applicant is not obliged to
take those responses into account.
Forewind allowed more than the statutory
28 days for responses to statutory
consultation periods. These are detailed
in Sections 3.6 and 3.7.
55 Applicants are not expected to repeat
consultation rounds set out in their
Statement of Community Consultation
unless the project proposals have changed
very substantially. For example, where
proposals change to such a large degree
that what is being taken forward is
fundamentally different from what was
consulted on, further consultation may well
be needed. This may be necessary if, for
example, new information arises which
renders all previous options unworkable or
invalid for some reason. When considering
the need for additional consultation,
The proposals did not change to such an
extent during the pre-application process
that additional rounds (over and above
the two stages set out in the SoCC) of
community consultation were required.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 113 © 2013 Forewind
applicants should use the degree of
change, the effect on the local community
and the level of public interest as guiding
factors.
57 If the application only changes to a small
degree, or if the change only affects part of
the development, then it is not necessary
for an applicant to undertake a full re-
consultation. Where a proposed application
is amended in light of consultation
responses then, unless those amendments
materially change the application or
materially changes its impacts, the
amendments themselves should not trigger
a need for further consultation. Instead, the
applicant should ensure that all affected
statutory consultees and local communities
are informed of the changes.
The Applicant met with or responded in
writing to several statutory consultees
regarding any changes made to the
proposals following the final stage of
statutory consultation.
58 Consultation should, however, also be fair
and reasonable for applicants as well as
communities. To ensure that consultation is
fair to all parties, applicants should be able
to demonstrate that the consultation
process is proportionate to the impacts of
the project in the area that it affects, takes
account of the anticipated level of local
interest, and takes account of the views of
the relevant local authorities.
The Applicant has carried out a through
pre-application consultation process as
described in the Consultation Report and
believes that this has been proportionate
to the impacts of the project.
61 Therefore, the consultation report should:
(a) provide a general description of the
consultation process undertaken;
(b) set out specifically what the applicant
has done in compliance with the
requirements of the Planning Act,
relevant secondary legislation, this
guidance, and any relevant policies,
guidance or advice published by
Government or the Inspectorate;
(c) set out how the applicant has taken
account of any response to
consultation with local authorities on
what should be in the applicant‘s
statement of community consultation;
The Applicant produced a Consultation
Report which included all matters set out
in paragraph (61). References below
refer to where examples of compliance
may be found in full.
(a) See Section 2.5
(b) See Section 2.1
(c) See Section 4.2
(d) See Appendix M
(e) See Chapter 8 and Appendix M
(f) See Chapter 8 and Appendix M
(g) The Applicant has endeavoured to
follow all advice of the local authority,
DCLG guidance and relevant advice
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 114 © 2013 Forewind
(d) set out a summary of relevant
responses to consultation (but not a
complete list of responses);
(e) provide a description of how the
application was influenced by those
responses, outlining any changes
made as a result and showing how
significant relevant responses will be
addressed;
(f) provide an explanation as to why
responses advising on major changes
to a project were not followed,
including advice from statutory
consultee on impacts;
(g) where the applicant has not followed
the advice of the local authority or not
complied with this guidance or any
relevant advice note published by the
Inspectorate, provide an explanation
for the action taken;
(h) be expressed in terms sufficient to
enable the Secretary of State to fully
understand how the consultation
process has been undertaken and
significant effects addressed. However,
it need not include full technical
explanations of these matters.
notes issued by the Inspectorate.
(h) The Applicant has endeavoured to
produce the Consultation Report in
terms sufficient to allow the Secretary
of State, consultees and the local
community to fully understand the
consultation process.
62 It is important that those who have
contributed to the consultation are informed
of the results of the consultation exercise;
how the information received by applicants
has been used to shape and influence the
project; and how any outstanding issues
will be addressed before an application is
submitted to the Inspectorate.
A summary of feedback received during
the final stage of statutory consultation
and the regard The Applicant has had to
relevant responses was circulated to all
stakeholders in edition 5 of Dogger Bank
News in early August 2013 (See
Appendix I1). This included a reference
to the full Consultation Report which will
be made available if and when the
Planning Inspectorate validates the
application.
In addition The Applicant met with or
responded in writing to many of the
consultees following the final stage of
consultation.
63 As with the consultation itself, it is likely
that different audiences will require
different levels of information. The local
community may be particularly interested in
what the collective view of the community
is and how this has been taken into
account. Consultees with technical
information will require more detailed
information on what impacts and risks have
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 115 © 2013 Forewind
been identified, and how they are proposed
to be mitigated or managed.
64 The consultation report may not be the
most appropriate format in which to
respond to the points raised by various
consultee groups and bodies. Applicants
should therefore consider producing a
summary note in plain English for the local
community setting out headline findings
and how they have been addressed,
together with a link to the full consultation
report for those interested. If helpful, this
could be supplemented by events in the
local area.
65 Response to points raised by consultees
with technical information is likely to need
to focus on the specific impacts for which
the body has expertise. The applicant
should make a judgement as to whether
the consultation report provides sufficient
detail on the relevant impacts, or whether a
targeted response would be more
appropriate. Applicants are also likely to
have identified a number of key additional
bodies for consultation and may need to
continue engagement with these bodies on
an individual basis.
The Applicant continues to engage with a
number of the technical consultees, on
issues raised during the final stage of
consultation. Statements of Common
Ground have been initiated pre-
application.
See Chapter 9.
73 For the pre-application consultation
process, applicants are advised to include
sufficient preliminary environmental
information to enable consultees to
develop an informed view of the project.
The information required will be different
for different types and sizes of projects and
it may differ depending on the audience of
a particular consultation. The preliminary
environmental information is not expected
to replicate or be a draft of the
environmental statement. However, if the
applicant considers this to be appropriate
(and more cost-effective), it can be
presented in this way. The key issue is that
the information presented must provide
clarity to all consultees. Applicants should
A document entitled ―Preliminary
Environmental Information 1‖ was
provided at the first stage of statutory
consultation and the draft ES was
provided at the second stage of statutory
consultation. These documents were
available to all consultees on the
Forewind website, at public exhibitions, in
local libraries and on DVD on request.
See Appendices G and H.
DOGGER BANK CREYKE BECK
F-STC-RP-004 Issue 3 Consultation Report Page 116 © 2013 Forewind
be careful not to assume that non-
specialist consultees would not be
interested in any technical environmental
information. It is therefore advisable to
ensure access to such information is
provided during all consultations.
77 Applicants may find it helpful to undertake
early informal discussion with a range of
parties on the content of the draft Order.
The draft Order, and the deemed marine
licences, have been the subject of
consultation with the Planning
Inspectorate, the Marine Management
Organisation (MMO), the Crown Estate,
Network Rail and East Riding of
Yorkshire Council. A consultation draft
DCO was also made available to all
consultees upon request throughout the
second statutory consultation period.
Where possible or appropriate Forewind
has sought to take on board any
comments in the documents submitted.
See Paragraph 1.8 in the Explanatory
Memorandum (Planning Inspectorate
document reference number 3.2)