1
The construcon meframe for Lightsource bp’s solar farms varies based on the size of the project, construcon workforce and the site-specific characteriscs. During this me standard construcon hours are adhered to and the site is monitored 24 hours a day by security staff. We’re dedicated to following best pracce, making sure our sites are of high quality, and avoiding or migang any potenal adverse impacts. The order in which different stages of construcon happen, and how much they overlap, will vary from site to site, but the construcon of a typical solar farm usually follows this paern: Safety first Creating and maintaining a long term, continuously safe and healthy environment is our top priority. Safety is a mindset and attitude we adopt and apply to everything we do. We ensure all safety measures are taken to protect our employees, customers and business partners. We are committed to safe delivery of our business to the communities and partners we work with and are continuously creating sustainable solutions that are safe by design. We adhere to the criteria set out by the International Organization for Standardization, or ISO, to make sure we’re working to the highest possible standards. Working with local businesses The majority of work that takes place on our solar farms is performed by our trusted EPC partners, all of whom have to go through our stringent onboarding process. These specialist solar construction companies often choose to subcontract out the less specialised, non-solar- specific aspects of building a solar farm to local contractors. This includes civil works, fencing, security and landscaping. CONSTRUCTION – WHAT TO EXPECT 20200420_PLN_UK_D3 PANEL ASSEMBLY The panels are fied to the frames, which are laid out in evenly spaced rows. ELECTRICAL COMPONENT FOUNDATION PREPARATION AND INSTALLATION Foundaons are prepared for the electrical components (inverters, transformers, substaon). Pre-fabricated components are then installed, others are built on site. SECURITY INSTALLATION Fencing is installed around the solar farm, alongside CCTV cameras which are posioned to monitor the fence line and solar farm interior. HIGH VOLTAGE WORKS Highly trained electrical engineers undertake the high voltage work needed for the solar farm to produce electricity. COMMISSIONING The solar farm undergoes final tesng and is connected to the grid. CONSTRUCTION DECOMMISSIONING & CIVIL WORKS Once the site is successfully commissioned, all construcon equipment is removed and any necessary restoraon works to the site and the road system are completed. LANDSCAPING (ACCORDING TO PLANTING SEASON) Depending on whether or not the season is appropriate for planng, the site and boundaries will be seeded and planted as per the bespoke planng plan. If the site is completed outside of ideal planng seasons, the planng will take place at the next opportunity. SITE PREPARATION & GROUNDWORKS Before construcon starts, the Lightsource bp Project Manager oversees the preparaon and groundworks to get the site ready. FRAMING INSTALLATION The frames for the solar panels are pile driven into the ground to ensure minimal ground disturbance. CABLING & TRENCHING Trenches for the cables are dug, and the electrical wires are safely protected and buried underground.

CONSTRUCTION – WHAT TO EXPECT - Amazon S3

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

The construction timeframe for Lightsource bp’s solar farms varies based on the size of the project, construction workforce and the site-specific characteristics. During this time standard construction hours are adhered to and the site is monitored 24 hours a day by security staff. We’re dedicated to following best practice, making sure our sites are of high quality, and avoiding or mitigating any potential adverse impacts.

The order in which different stages of construction happen, and how much they overlap, will vary from site to site, but the construction of a typical solar farm usually follows this pattern:

Safety first

Creating and maintaining a long term, continuously safe and healthy environment is our top priority. Safety is a mindset and attitude we adopt and apply to everything we do. We ensure all safety measures are taken to protect our employees, customers and business partners. We are committed to safe delivery of our business to the communities and partners we work with and are continuously creating sustainable solutions that are safe by design. We adhere to the criteria set out by the International Organization for Standardization, or ISO, to make sure we’re working to the highest possible standards.

Working with local businesses

The majority of work that takes place on our solar farms is performed by our trusted EPC partners, all of whom have to go through our stringent onboarding process. These specialist solar construction companies often choose to subcontract out the less specialised, non-solar-specific aspects of building a solar farm to local contractors. This includes civil works, fencing, security and landscaping.

C O N S T R U C T I O N – W H A T T O E X P E C T

2 0 2 0 0 4 2 0 _ P L N _ U K _ D 3

PA N E L A S S E M B LY

The panels are fitted to the frames, which are laid out in evenly spaced rows.

E L E C T R I C A L C O M P O N E N T F O U N D AT I O N P R E PA R AT I O N A N D I N S TA L L AT I O N

Foundations are prepared for the electrical components (inverters, transformers, substation). Pre-fabricated components are then installed, others are built on site.

S E C U R I T Y I N S TA L L AT I O N

Fencing is installed around the solar farm, alongside CCTV cameras which are positioned to monitor the fence line and solar farm interior.

H I G H V O LTA G E W O R K S

Highly trained electrical engineers undertake the high voltage work needed for the solar farm to produce electricity.

C O M M I S S I O N I N G

The solar farm undergoes final testing and is connected to the grid.

C O N S T R U C T I O N D E C O M M I S S I O N I N G & C I V I L W O R K S

Once the site is successfully commissioned, all construction equipment is removed and any necessary restoration works to the site and the road system are completed.

L A N D S C A P I N G ( A C C O R D I N G T O P L A N T I N G S E A S O N )

Depending on whether or not the season is appropriate for planting, the site and boundaries will be seeded and planted as per the bespoke planting plan. If the site is completed outside of ideal planting seasons, the planting will take place at the next opportunity.

S I T E P R E PA R AT I O N & G R O U N D W O R K S

Before construction starts, the Lightsource bp Project Manager oversees the preparation and groundworks to get the site ready.

F R A M I N G I N S TA L L AT I O N

The frames for the solar panels are pile driven into the ground to ensure minimal ground disturbance.

C A B L I N G & T R E N C H I N G

Trenches for the cables are dug, and the electrical wires are safely protected and buried underground.