Construction Update_29th September

Embed Size (px)

Citation preview

  • 8/3/2019 Construction Update_29th September

    1/20

    We havemoved in.Soon it could beyour turn

  • 8/3/2019 Construction Update_29th September

    2/20

    As our first milestone of beginning thedelivery schedule on 11.11.11 beckons

    we move steadily ahead

    Promises being kept.

    Your support, ourefforts @ work

  • 8/3/2019 Construction Update_29th September

    3/20

    Dear Friend,

    The momentum has been gathering the rightful pace. From our last update to now the 11.11.11

    dateline has become our clarion call. More than just a delivery milestone it has become a beaconof speed and agility that will convince all Alien residents that intelligent living is now a delivery

    away. We have moved from the exteriors into the interiors. Work is apace and the completion

    within schedule is a winnable challenge. We are there and your support is giving us that extra

    acceleration.

    The 30-floor permission is wrapped up now and we will be soon moving up tot take the Alien

    and intelligent living experience to greater heights! And as we do all of that , our commitment to

    quality remains as solid as the Raft Foundation in your Space Station. The ISO adherence

    program we have undertaken only reiterates our diligence.

    In this Update you will find detailed information and perhaps with clear pointers on your specific

    Station and in some cases the flat too. However, as always, should you want answers to specific

    queries our Care Team is there to help and share with you all the necessary information.

    DearFriendWork is apace

    and the

    completion

    within

    schedule is a

    winnablechallenge.

  • 8/3/2019 Construction Update_29th September

    4/20

  • 8/3/2019 Construction Update_29th September

    5/20

  • 8/3/2019 Construction Update_29th September

    6/20

    Finishing is in progress for 40 flats which comprises of putty, 1st stage electrical clearance,buffing & MEP works

    Mockup Flat has been Completed Up to 60%

    T 81-T 83, B3a-C3a Corridor 18th level has been casted.

    T 79-CoreT 80, i.e A1 - Core wall Corridor is at 16th level.

    And additional Corridor For T 77- T78 is At 10th level

    Over all 10 levels of Station 14, Block 01 has been completed.

    Overall 100 units casting has been completed in Station-14

    Flooring work for 15 Flats have been completed (Excluding Master Bedroom).

    Station 14 continued...

  • 8/3/2019 Construction Update_29th September

    7/20

    Interiors of Station 14

  • 8/3/2019 Construction Update_29th September

    8/20

    Interiors of Station 14

  • 8/3/2019 Construction Update_29th September

    9/20

    Station 06

  • 8/3/2019 Construction Update_29th September

    10/20

    Station 06

    Basement 01 Raft has been completed up to the mark.

    A substantial part of the upper basement was completed, followed by the Ground floorSlab & Transverse Slab which is 100% complete

    Columns Form GR- TRANSVERSE SLAB was done in the month of March'2011

    Internal Core Wall is completed till TRANSVERSE SLAB Level

    Core floor slab is completed till Transverse Slab

    Coming to the Transverse slab, out of the 03, all 03 pours are completed.

    Aluminum shuttering for the Station 06 has arrived at the site and shuttering for 3 units

    i.e. D3 T-37, B2 T-38, C3c T-35 and core wall is in progress. 2 levels of core-wall is completed and 3 rd level will casted at the end of this month.

    1st level of D3 and C3c is completed.

    Beam for the Ramp are Casted at UB level.

    Core floor slab @ B1 and UB Are also casted

    Passenger Hoist has been installed to gain speed in the construction activity.

    Other units reinforcement is done for the 1st level and aluminum shuttering for these

    units are expected to arrive.

  • 8/3/2019 Construction Update_29th September

    11/20

    100% concreting is done for all pours in raft.

    Followed by the Columns reinforcement and ColumnsConcreting is been planned in this month.

    Reinforcement for Retaining wall is completed and 100% ofConcreting is done.

    Substantial part of the lift pit Raft is done.

    Station 02

    Station 01 & Station 02

    Station 01 pour 01 raft is successfully completed.

    Bottom and top Mat for the Main 1600 Raft is done.

    Lift pit raft is done.

    Lift pit side walls have also been casted, followed by pour02 and pour 03 of the Raft have been casted.

    Column above the respective rafts have also beenerected and 80 % have been casted too, the remainingwill be casted by the mid of Oct'11.

    Steel for the Retaining wall is in progress.

    Pedestal for the footing along the retaining wall have been successfully casted. Station 01 main Raft is 100 % completed.

    Station 01

  • 8/3/2019 Construction Update_29th September

    12/20

    Pour 1 Raft is substantially completed i.e. 400 Raft.

    Steel for the retaining wall is completed. Concreting is in progress.

    Lift pit raft is completed.

    Plum Concreting and back filling is completed.

    PCC is almost done and remaining 20% will be completed this month.

    Bottom Matt for the 1600 MM Raft is planned in this month.

    Station 04

    All the pedestals on Pour 1 raft are substantially completed,followed by the columns reinforcement and concreting.

    Reinforcement for Retaining wall is completed and 100% ofConcreting is done.

    Bottom Mat for the Main 1600 Raft is done.

    Substantial part of the lift pit Raft housekeeping will bedone.

    Concreting for the lift pit will be planned in the 2nd week ofOct11.

    Remaining 10% of PCC for the raft is in progress.

    Station 03

    Station 03 & Station 04

  • 8/3/2019 Construction Update_29th September

    13/20

    100% of B1-UB Columns have been casted.

    Pour 4 Columns steel is completed followed by concreting andshuttering for the above final pour of UB Level which is in progress andexpected to be casted in the month of Oct11

    Core wall from B1-UB is Completed

    Core wall (UB-GF) is in progress and is planned to be casted this month

    100 % of the Retaining wall is completed (B1-UB) along block 02

    Columns for pour 01 ground floor have been casted and shuttering forthe Pour 01 is in progress

    Columns for pour 02 ground floor have been casted

    Station 07

    Station 05 & Station 07

    Station 05 Lift Pit for pour 1 Raft at B1 Level concreting is planned

    for this month.

    100% of Reinforcement for the pour 01 raft has been

    completed and the concreting is planned in this month. Reinforcement for the pour 02 raft is in progress.

  • 8/3/2019 Construction Update_29th September

    14/20

    Lift Pit Raft is Done

    100% of Reinforcement for the pour 01 raft is done and theconcreting is done

    100 % of reinforcement for the complete station is laid.Concreting is planned for this month

    Station 08

    Concreting for the pour 02 raft is being completed.

    Retaining wall is in progress. Reinforcement for Lift Pit Raft is completed.

    Substantial part of concreting is done.

    Station 09

    Station 08, 09 & Station 10

    100% of Excavation has been completed

    Lift Pit Dewatering is in progress.

    Retaining Wall is Completed up to B1 Level.

    Station 10

    S i 11

  • 8/3/2019 Construction Update_29th September

    15/20

    Station 11

  • 8/3/2019 Construction Update_29th September

    16/20

    Basement 02 Raft has been completed

    Basement 01 Slab has been completed

    Columns (B1-UB) are 90% done External Lift core wall has been completed till B1 level

    Shuttering for pour 02, 03 UB Slab is completed. Reinforcement for pour 02,03 UB slab is completed

    Pour 02, 03 UB Slab Concreting is planned in the first week of Oct11

    90 % of the Retaining wall has been completed till UB Level

    Station 11

    St ti 12

  • 8/3/2019 Construction Update_29th September

    17/20

    Station 12

  • 8/3/2019 Construction Update_29th September

    18/20

    Basement 02 raft Is completed up to the Mark

    Columns (B2-B1) are 100% done

    Slab Shuttering @ B1 Level is done with 100 % of Concreting

    Lift core wall is completed till UB level.

    100% of columns from B1-UB are casted.

    Slab concreting @ UB level is completed.

    External core wall from UB-GF is casted

    Ground floor pour1 along station 14 is completed.

    80% of Shuttering & reinforcement for Pour-2 & Pour-3 on Ground floor is

    completed. Ground floor Pour-2 concreting is completed & Pour-3 will be casted in the

    first week of Oct-2011.

    Transverse Slab for for pour1 has been casted and Staging for Pour-2 is inprogress.

    Station 12

    Clubhouse

  • 8/3/2019 Construction Update_29th September

    19/20

    Clubhouse

    For beams in Phase 1 Ramp is completed.

    Concreting for Phase 02 Ramp is done..

    Now block 05 and Block 02 Club house is connected with

    the ramp. 100 % of Retaining wall is done while 75% of raft is

    completed.

    Other 25% is planned in the mid of Oct-2011.

    90% of Sump pit is been completed and water tank is inprogress.

    Clubhouse

    Note:

    Contact No - 9966235235

    Timings 10am 6pm; Monday- Sunday

    Email id - [email protected]

    As per safety guide lines we request you to intimate us in advance before a visit to the site, so that we canmake necessary arrangements at the site to avoid the wait. To help us serve you better please feel free tointimate us in the below mentioned contacts before 2 days of your visit. Hence we can ensure that ourexecutive is available on the site to guide you, resolve queries and give you the updates.

    This program is established for mutual benefit of construction workers, contractors and customers by setting acommon standard for health and safety