CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH OF SEPTEMBER, 2018

CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · -13th floor slab deshuttering & cleaning work.-12th floor block work.-10th floor electrical wall conduting work.-9th floor

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · -13th floor slab deshuttering & cleaning work.-12th floor block work.-10th floor electrical wall conduting work.-9th floor

CONSTRUCTION UPDATE OF OUR

PROJECTS FOR THE MONTH OF SEPTEMBER,

2018

Page 2: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · -13th floor slab deshuttering & cleaning work.-12th floor block work.-10th floor electrical wall conduting work.-9th floor

Keshav Nagar, Pune

Page 3: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · -13th floor slab deshuttering & cleaning work.-12th floor block work.-10th floor electrical wall conduting work.-9th floor

Construction Update – September ‘18

‘A’ BUILDING :

- 3rd slab RCC is completed.

- Excavation & backfilling work completed.

- Plinth completed.

‘B’ BUILDING :

- Terrace floor pargola casting work.

- 13th floor slab deshuttering & cleaning work.

- 12th floor block work.

- 10th floor electrical wall conduting work.

- 9th floor toilet base coat work.

- 7th floor beam bottom & jam finishing work.

- 11th floor terrace external plaster work.

- 11th floor dry balcony plumbing work.

- Sales area paving block & curb stone fixing work.

Page 4: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · -13th floor slab deshuttering & cleaning work.-12th floor block work.-10th floor electrical wall conduting work.-9th floor

‘A’ Building

‘B’ Building

Page 5: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · -13th floor slab deshuttering & cleaning work.-12th floor block work.-10th floor electrical wall conduting work.-9th floor

Keshav Nagar, Pune

Page 6: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · -13th floor slab deshuttering & cleaning work.-12th floor block work.-10th floor electrical wall conduting work.-9th floor

Construction Update – September ‘18

‘A’ BUILDING :

- 1st slab RCC work completed - 100%

- 2nd slab RCC work in progress - 55% has been completed.

- All work of the sample flat has been completed.

- Entrance pathway and flower bed work has been completed.

Page 7: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · -13th floor slab deshuttering & cleaning work.-12th floor block work.-10th floor electrical wall conduting work.-9th floor
Page 8: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · -13th floor slab deshuttering & cleaning work.-12th floor block work.-10th floor electrical wall conduting work.-9th floor

Sus, Pune

Page 9: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · -13th floor slab deshuttering & cleaning work.-12th floor block work.-10th floor electrical wall conduting work.-9th floor

Construction Update – September ‘18

RCC - all work is completed.

Brick work - west side compound wall brick work is in progress.

Gypsum work - all work is completed.

Repairing work is in progress at 11th floor.

Waterproofing work – all work is completed.

Parking toilet waterproofing work is in progress.

Electrical work - wall piping and board fixing is completed up to 14th floor.

Wiring work is completed up to 14th floor.

Total 164 flats wiring is completed.

Duct to meter room piping & wiring work is completed.

Switch plate fixing work is completed up to 6th floor.Progress at 7th floor.

Tile work - All work completed.

Repairing work is in progress at 10th floor.

Plaster work -All internal & External plaster is completed.

Repairing work is in progress at parking & lobby area.

Page 10: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · -13th floor slab deshuttering & cleaning work.-12th floor block work.-10th floor electrical wall conduting work.-9th floor

Construction Update – September ‘18

West side Compound wall plaster is in progress.

ABC building landscape area compound wall plaster is in progress.

_Plumbing - all flat internal plumbing work is completed.

all down take line work is completed.

Terrace luping work is in progress.

Drainage line chamber work is in progress.

_Wooden door work -1st to 10th floor All work is completed.

Repairing & polish work is in progress.

Main Wooden door fixing is in progress at 12th & 13th floor.

Toilet & dry balcony wooden door fixing is completed up to 12th floor.

Bedroom door fixing is completed up to 12th floor.

Progress at 13th floor..

Fabrication work - all attached terrace, dry balcony railing fixing is completed.

Lobby area and parking railing fixing is completed.

Page 11: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · -13th floor slab deshuttering & cleaning work.-12th floor block work.-10th floor electrical wall conduting work.-9th floor

Construction Update – September ‘18

Staircase railing fixing is completed.

Sliding door work - All work is completed.

Repairing work is in progress.

Fire work - internal fire fighting work is completed.

External fire work is completed.

Fire pump installation (mechanical) work is completed.

Stilt floor parking fire work is completed.

Progress at upper parking floor.

Solar system - down take line work is completed.

Solar tank fixing work is in progress at terrace.

Paint work - internal flat sanding work (1st coat putty) is completed up to 14th floor.

2nd coat putty work is in progress at 8th floor.

Primer work is completed up to 6th floor.

1st coat paint work is in progress at 4th & 5th floor.

Lobby ceiling 1st & 2nd coat putty work completed up to 14th floor.

Page 12: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · -13th floor slab deshuttering & cleaning work.-12th floor block work.-10th floor electrical wall conduting work.-9th floor

Construction Update – September ‘18

Lobby area wall primer work is completed up to 14th floor.

1st coat paint work is in progress.

Dry balcony primer work is completed.

Dry balcony ceiling 1st coat paint is in progress.

Fire staircase 2coat putty & 1st coat paint work is completed.

Regular staircase 1st & 2nd coat putty work is completed up to 14th floor.

1st coat paint work is in progress.

All duct primer work is completed.

1st coat paint work is in progress.

North, south, east & west side external primer work is completed.

1st coat paint work is completed.

Attached terrace external wall 1st coat paint work is completed.

Stilt floor parking primer work is completed.

STP - All civil work is completed.

Page 13: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · -13th floor slab deshuttering & cleaning work.-12th floor block work.-10th floor electrical wall conduting work.-9th floor

Construction Update – September ‘18

Stp Pump installation(mechanical) work is in progress.

Lift work - 2no passenger lift work is completed.

Service lift work is in progress.

Landscape area - compound wall brick work & plaster work is completed.

Landscape area soling & pcc (civil) work is completed.

In & out ramp soling murum filling work is completed.

Stilt parking floor trimix concrete work planning is on tomorrow.

Page 14: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · -13th floor slab deshuttering & cleaning work.-12th floor block work.-10th floor electrical wall conduting work.-9th floor
Page 15: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · -13th floor slab deshuttering & cleaning work.-12th floor block work.-10th floor electrical wall conduting work.-9th floor

THANK YOU!