    MINNESOTA DEPARTMENT OF TRANSPORTATION

    Construction Quality Plan

    TemplateDesign-Build Program

    The contents of this document provide the minimum level of quality expected from the design-build

    contractor. Each contractor shall update and modify this manual for each project. The contractor shall

    update any standards, procedures, and processes within this template to reflect the most recent

    standards and provisions outlined in Book 1, Book 2, and Book 3 of the RFP.

  • 7/21/2019 Construction sample Quality Plan

    2/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 2 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    Table of Contents

    CQP 100: Construction Quality Plan Overview .............................................................. 6

    CQP 200: Pre-Activity Meetings ................................................................................... 10

    CQP 201: Field Design Change ................................................................................... 11

    CQP 202: Critical Activity Points .................................................................................. 14

    CQP 204: Testing Procedures & Forms ....................................................................... 20

    CQP 301: Clearing and Grubbing ................................................................................ 22

    CQP 302: Grading and Base ........................................................................................ 23CQP 303: Test Rolling .................................................................................................. 25

    CQP 304: Grade Control ............................................................................................... 27

    CQP 305: Embankment ............................................................................................... 30

    CQP 306: Excavation .................................................................................................... 31

    CQP 307: Temporary Erosion and Sediment Control................................................... 33

    CQP 308: Landscaping ................................................................................................ 35

    CQP 309: Pile Driving ................................................................................................... 37

    CQP 310: Portland Cement Concrete Batch Plant ....................................................... 39

    CQP 311: Ready Mix Concrete Mix Design .................................................................. 43

    CQP 312: Paving Concrete Mix Design ........................................................................ 45

    CQP 313: Structural Concrete Pre-Placement .............................................................. 48

    CQP 314: Structural Concrete Placement ..................................................................... 50

    CQP 315: Sidewalk and Curb Paving........................................................................... 52

    CQP 316: Concrete Paving .......................................................................................... 54

    CQP 317: Concrete Curing .......................................................................................... 56

    CQP 318: Bituminous Plant .......................................................................................... 58

    CQP 319: Bituminous Job Mix Design ......................................................................... 60

    CQP 320: Bituminous Paving ....................................................................................... 62

    CQP 321: Third Party Utility Installation ....................................................................... 65

    CQP 322: Bridge Removal ........................................................................................... 67

    CQP 323: Pre- and Post-Vibration Building ................................................................... 68

  • 7/21/2019 Construction sample Quality Plan

    3/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 3 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 324: Vibration Monitoring ...................................................................................... 70

    CQP 325: Electrical ...................................................................................................... 72

    CQP 328: Inspection of Delivered Project Material ....................................................... 74

    CQP 329: Storm Sewer and Culvert Installation ........................................................... 76

    CQP 330: Building Demolition ....................................................................................... 78

    CQP 332: Edge Drain Inspection .................................................................................. 79

    CQP 334: Fence Installation ........................................................................................ 81

    CQP 335: Steel Fabrication Non-Conformances .......................................................... 83

  • 7/21/2019 Construction sample Quality Plan

    4/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 4 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    LIST OF FORMS

    Number Title DateCQP200FA Pre-Activity Meeting (Example)

    CQP200FB Pre-Activity Meeting Minutes (Example)

    CQP201FA Field Design Change

    CQP201FB Field Design Change Log

    CQP202F Critical Activity Point Release Form

    CQP204FA MnDOT Certification Log

    CQP204FB Equipment List

    CQP403F Weekly Grading/Base/Paving Report

    CQP406F Monthly Grading and Base Report

    CQP407F Test Roll Report

    CQP408F Excavation and EmbankmentObservations

    CQP409F Pile Summary Report

    CQP410F Test Pile Report

    CQP411F Spread Footing Report

    CQP412F Concrete Mix Design Log

    CQP413F Request for Concrete Mix Design Approval

    CQP416F Grading Control Tolerance Report

    CQP417F Concrete Placement Inspection

  • 7/21/2019 Construction sample Quality Plan

    5/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 5 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP418F Sidewalk and Curb Paving

    CQP422F Bituminous Paving Observation

    CQP424F Concrete Paving

    CQP425FWeekly Storm Sewer and CulvertQuantities

    CQP428F Materials Certification Report

    CQP428F 1stTime Inspection Report

    CQP429F Daily Field Report

    CQP433F Batch Plant Observations

    CQP437F Low Slump Concrete

    CQP438F Pre-Paving Checklist

    CQP440F Fencing Observation

    CQP443F Bituminous Control Strip

  • 7/21/2019 Construction sample Quality Plan

    6/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 6 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 100: Construction Quality Plan OverviewRev , Date

    PURPOSE

    To provide a plan that outlines the construction quality checks to be performed duringthe Project. This plan defines the roles and responsibilities of MnDOT and theContractor with respect to construction quality.

    All construction activities associated with this Project will be completed under thisquality program. Only controlled products will be delivered to MnDOT. Elements will bebuilt with skilled craftsmen following approved drawings using proper materials andequipment. Inspections and tests will be performed as outlined in this Plan to documentthe construction is proper and meets Project requirements. Periodically, the process

    will be refined based on worker-identified quality problems, test data, inspection results,audits, and MnDOT's satisfaction with the Project.

    SCOPE

    This plan applies to all Work performed on the Project.

    RELATED DOCUMENTS

    Contract Documents

    Special Provisions

    Materials Control Schedule

    RESPONSIBILITIES

    The Contractor is responsible for performing the work in accordance with all aspects ofthe Contract. At a minimum, the Contractor shall perform testing and inspection inaccordance with this Construction Quality Plan.

    None of the Contractors quality staff havethe ability to deviate from Projectrequirements or to interpret Project specifications. Their role is solely to ensure thefinished Work meets the requirements of the Contract. Quality staff has the authority tostop any and all Work that does not meet the Contract requirements.

    FIELD PLAN SHEETS

    The CQM is responsible for ensuring the contractors quality staff performing requiredobservations, checks and documentation of plan sheets that are being used in the fieldfor construction. When new RFC plans are released, the Contractors quality staff willreview the plan sets with the foreman to make sure that the most up-to-date plan setsare being used.

  • 7/21/2019 Construction sample Quality Plan

    7/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 7 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    SUBCONTRACTORS AND SUPPLIERSContractor Quality Management Plans for each major subcontractor and supplier will beincluded in the Project files as an extension of this CQMP. The DQAM or CQM willreview the QMPs for implementation on the project work.

    Contractor Management, subcontractors and supplier contracts will describe work orproducts needed and the schedule required. The documents will contain the qualityrequirements needed by the work or products.

    The responsibility for inspection and testing of off-site materials shall follow allapplicable Mn/DOT specifications associated with that item. Subcontractors andsuppliers will designate representatives to interface with the QM and Mn/DOT. Qualityrecords will be provided to the QM for all work and products to demonstrateconformance to Project requirements.

    The subcontractors and suppliers will make provision for the QM and/or CAPM andMn/DOT personnel to observe, sample, inspect, or test work and product at any point intheir processes. The DQAM or CQM will conduct periodic audits of selected suppliersto verify initial and continued implementation of the QMP.

    PRODUCTS AND MATERIALS

    Quality tests and inspections will be performed during the production of the materials,as materials arrive on the Project Site, and as they are incorporated into theconstruction. Tests and inspections will be performed by a combination of contractor

    staff, testers and inspectors, and subcontractor and supplier quality personnel.

    Suppliers will perform tests on materials as they are produced. Prior to the materialarriving on the Project Site, testing information will be forwarded to the CQMdemonstrating the material meets requirements. The CQM will also audit selectedsuppliers to assure they are following a quality management system and to review theProject requirements with the supplier. The suppliers quality management system willbe reviewed, along with test records from previous production and reporting of qualitydata during production will be established.

    Products and materials are identified from receipt and storage through installation.

    Where appropriate, a unique number will be assigned and a tag attached. Wheretraceability is required, the location of the product or material will be recorded.

    Handling

    Products and materials are handled on site in accordance with supplier'srecommendations, MnDOT's specific requirements, and good construction practice.

  • 7/21/2019 Construction sample Quality Plan

    8/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 8 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    When materials arrive at the Project Site, receiving personnel will document receipt ofthe material in accordance with the appropriate procedure. Quality Control will checkmaterial for conformance to Project requirements. Any damage or deficiency will benoted. The materials will be used or stored as appropriate for the material.

    Some materials, such as concrete, will require physical tests as received and will besampled to determine their conformance. The Work will be conducted following theproper test procedure and documented on the proper form according to thisConstruction Quality Plan.

    Packing slips, mill certificates, or other documents from the supplier showingconformance to requirements will be reviewed by QC and QA personnel and retained byQA. Three-ring binders will be used to compile certificates and will include an updatedlog of accepted shipments.

    Storage

    Products or materials not immediately used will be stored. Material for indoor storage isplaced in bins, shelving, racks, or pallets and positioned in neat and orderly condition forease of retrieval. Material stored outdoors is placed on adequate dunnage andprotected as required by the supplier.

    Protection

    Some products and materials will require special measures to protect them from

    degradation. The supplier's requirements will be followed in providing the properenvironment for the products and materials. The Project Manager will be responsiblefor providing proper conditions.

    QUALITY TESTING AND INSPECTION

    During construction, various elements will be checked and compared to therequirements set forth in the RFP, MnDOT Standard Specifications for Construction(See Book 3), Special Provisions, and MnDOT Materials Control Schedule (Volume III).These checks will be performed following the appropriate procedure and documentedon the proper form. Testing will be preformed to the Project minimums stated in the

    Materials Control Schedule. Additional tests will be performed as needed. Estimatedannual quantities of materials will be used to determine the approximate number of testsand inspections needed annually.

    All documentation shall reference an Activity ID in the Contractors Schedule.

  • 7/21/2019 Construction sample Quality Plan

    9/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 9 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    Any inspection performed by MnDOT does not relieve the Contractor of its qualitymanagement responsibilities.

    CONTROL OF MONITORING AND MEASURING DEVICES

    Monitoring and measuring equipment used on the Project will be appropriate for thework being performed, in working order, and calibrated periodically. When not in use,the devices will be protected from damage and stored in accordance withmanufacturers as well as Owners requirements. Records of the calibration will bemaintained.

    LaboratoriesAny type of test that requires additional testing to assure that materials are meeting theContract requirements will be tested on different equipment by different personnel.

    Independent Assurance Sampling and Testing (IAST)The quality teams will have all testers perform the required IAST tests. These tests willbe done on an annual basis for any quality personnel that have performed a materialtest for the Project in that year. The CQM will keep records verifying completion of therequired IAST tests.

    QUALITY RECORDS

    Test forms, inspection forms, and material receipt forms will be provided to MnDOTthrough document control. Data from these tests will be manually entered into the

    Project's electronic document management system. MnDOTs TRACS will be used forthe material testing database and Daily Field Reports. Reports from TRACS will beused to assure that testing rates for the materials installed are sufficient.

    Reports for the material certification of the Project will be produced from TRACS whenpossible and will be supplemented with the Word and Excel certification forms whenneeded.

    QUALITY AUDITS

    Quality audits will be conducted in accordance with the Quality Management Plan. The

    CQM is responsible for any clarifications or corrective actions that may be needed asrequired by the audit findings.

    NON-CONFORMING WORK / STOP WORKNon-conforming work and stop work orders will be performed in accordance with theQuality Management Plan.

  • 7/21/2019 Construction sample Quality Plan

    10/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 10 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 200: Pre-Activity MeetingsRev , Date

    PURPOSE

    To establish required Construction Quality procedures and reporting requirements forpre-activity meetings for each activity preformed on the project.

    SCOPE

    Pre-activity meetings are held prior to beginning construction work on new types of orlarge segments of work to be preformed on the project. For example, pre-activitymeetings may be held prior to demolition activities or prior to installation of a complexitem or component such as a bridge.

    The Design-Builder is also strongly encouraged to conduct a pre-activity meeting priorto commencing Design activities on the project to ensure all parties have a clearunderstanding of the goals, objectives, quality procedures and intended outcomes oftheir portion of the project.

    RESPONSIBILITIES

    The Project Manager is responsible for ensuring that a pre-activity meeting is held priorto starting construction on any major construction component or new activity. He is alsoresponsible for complete implementation of this procedure.

    PROCEDURE

    1. Prior to work, the Project Manager, or a Superintendent that the PM designates,and will seek feedback from their staff and the Department and will draft anagenda and will invite QA staff, construction staff and the Department to a pre-activity meeting prior to construction. This person will chair the meeting.Chairman will send around sign-in sheet.

    2. After the meeting, the chairman of the meeting will draft pre-activity meetingminutes. The meeting chairman will deliver the minutes to Document Controland provide a distribution list for the minutes to Document Control.

    3. Document Control will distribute the minutes and file them in the DCS. DCS will

    produce a log of all Pre-activity meetings held on the project.

    FIGURES AND FORMS

    CQP200FA: Pre-Activity Meeting (Example)CQP200FB: Pre-Activity Meeting Minutes (Example)

  • 7/21/2019 Construction sample Quality Plan

    11/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 11 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 201: Field Design ChangeRev , Date

    PURPOSE

    To establish the scope, responsibilities, procedures, and forms affecting anddocumenting changes proposed by the Contractor to address situations discoveredafter the design package has been Released for Construction.

    SCOPE

    Design changes initiated by the Contractor to documents Released for Construction arecompleted under a Field Design Change (FDC). Examples of Contractor-initiatedsituations that require modifications to the original RFC documents include:unanticipated site conditions, alternative construction method/material proposals fromthe Contractor, among many others.

    RESPONSIBILITIES

    The Contractor generates Field Design Change requests. FDCs should be filteredthrough the Construction Manager(or his designee), and forwarded to DocumentControl for distribution to the Designer.

    The Post-Design Manageris responsible for responding to all FDC requests. ThePost-Design Managerwill facilitate the review of all FDCs according to the

    requirements of the QMP.

    The Construction Manageris responsible for controlling the construction activitiesonce the FDC has been documented to avoid further work activities that may requireremoval or rework as a result of the FDC disposition. The Construction Manager willkeep the Project Manager, the Post-Design Manager, and the Department apprisedof the impacts to ongoing construction operations as a result of the anticipated designchange.

    The Construction Quality Managerwill be responsible for notifying field qualitypersonnel in charge of assessing the work for conformance with the Quality Plan of theupcoming changes to the RFC documents. Field quality personnel will monitor the work

    elements impacted by the FDC, and report on observed activities, which may becontrary to the intended modifications.

    MnDOTs Project Manager or Construction Managerwill sign each FDC prior toRelease for Construction. MnDOT reserves the right to take ten (10) days of reviewtime for each FDC.

  • 7/21/2019 Construction sample Quality Plan

    12/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 12 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    PROCEDURE

    The procedures outlined below are to be used to process all Field Design Changes.

    Revisions may require modifications to the RFC plans and/or specifications, and can beclassified according to the following:

    Level 1Request for Existing Conditions Adjustments (Considered Minor inscope). These revisions are adjustments to match project elements with conditionsencountered in the field. They are limited to minor dimensional and layout adjustmentsto released design documents, and do not impact future construction and installation.

    Level 2Request for Adjustments to Match As-Constructed Details (ConsideredMinor in scope, but require review for major implications). These accommodatespecific details of work elements already constructed by the Contractor. They are

    limited to dimensional and layout adjustments to design documents released forconstruction, and do not impact future construction and installation.

    Level 3Request for Revision to Design Documents Released for Construction(Considered Major in scope). These are revisions to RFC documents that involvedesign changes that do not deviate from project requirements, but are considered to bemajor in scope. Examples include revisions to major dimensions and layout, materialschanges, or design revisions to accommodate adjustments to the work. Revisions ofthis nature may impact several disciplines, and will undergo a review process prior to re-release.

    Level 4Request for Deviation from Project Requirements (Considered major in

    scope). These are revisions to RFC documents that involve changes that deviate fromContract requirements. The proposed revisions should involve an isolated part of theproject, and should be fully justified by the Contractor prior to MnDOT consideration.Revisions of this nature may impact several disciplines, and will undergo a reviewprocess prior to re-release.

    Specific procedures follow:

    1. FDCs are initiated by the Construction Manager (or his designee). The first point ofcontact for the initiator is Document Control, who will identify and reserve the nextnumber in the FDC log.

    2. Document Control will issue an FDC Notice providing the base information of therevisions requested. The FDC will be transmitted to the Design Manager or thePost-Design Manager (or his designee) for action.

    3. The scope of the FDC will be thoroughly analyzed by the Design Manager or thePost-Design Manager to confirm the circumstances described in the FDC Notice.

  • 7/21/2019 Construction sample Quality Plan

    13/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 13 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    The Design Manager or the Post-Design Manager will enlist additional informationfrom field personnel as necessary to clearly define the scope and detail of therevisions required, as well as to identify the schedule for FDC resolution.

    4. If plan revisions are necessary, all design changes to plans, specifications,calculations, and reports will be sealed by a Minnesota licensed Engineer. Alldesign work will conform to the QC checking procedures governing design asidentified in other sections of the QMP.

    5. Plan and specification revisions classified as Major (includes Level 3 and 4 revisionsand occasionally Level 2 revisions) will be subject to a design review and approvalprocess similar to that for the original design. The Design Manager or thePost-Design Manager will classify FDC requests as minor or major, and willdetermine the scope of plan review necessary.

    6. The FDC form will be completed by the Design Manager or the Post-DesignManager or his designee. This summary form will identify the reason for the change,the revisions made, the specifications and plan sheets modified.

    7. The completed FDC form and any plan revisions will be returned to DocumentControl for duplication and documentation, and will be forwarded to the ConstructionManager accompanied by a Re-Release of Drawing transmittal.

    DISPOSITION

    1. All check prints and design calculations are stored in Document Control after the

    plans have been approved by the Design Manager or the Post-Design Manager.

    FIGURES AND FORMS

    CQP201FAField Design ChangeCQP201FBField Design Change Log

  • 7/21/2019 Construction sample Quality Plan

    14/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 14 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 202: Critical Activity PointsRev , Date

    Critical Activity Points will be established in order to ensure that the proper inspectionand testing has been performed prior to starting, or before proceeding to the nextactivity or next stage of that particular construction activity. Critical Activity Points willbe signed off by the foreman in charge of the operation (or his superior), the Critical

    Activity Point Manager, and MnDOT. If MnDOT feels that there is an issue that needsto be resolved, the CQM may be called if needed.

    Critical Activity Points will also occur when any material is used for the first time on theProject. The CQM or CAPM will collect material certifications and any otherdocumentation for the material, and QC staff will perform the required tests per the

    Materials Control Schedule. All documentation, including certifications of the materialwill be forwarded to the Critical Activity Point Manager for sign-off, prior to the materialbeing incorporated into the Project.

    The QM, CAPM and CQM shall stop work if the Contractor does not adhere to a CriticalActivity Point.

    RELATED DOCUMENTS

    The following documents are referenced in this Quality Procedure:

    MnDOT Standard Specifications for Construction

    Contract Documents

    Schedule of Materials Control Construction Quality Inspection and Testing Plan (Vol. II)

    RESPONSIBILITIES

    The Critical Activity Point Manager (CAPM) is responsible for ensuring that theproper inspection and testing has been performed at a defined Critical Activity Point,collecting inspection and testing forms, and verifying that the inspection and test datameets Contract requirements. The CAPM will sign off on the Critical Activity Point oncethis information is in place. The CAPM shall have the following MnDOT TechnicalCertifications when reviewing CAPs in the following operations:

    Structural Concrete, Bridges and WallsBridge Construction

    Bituminous Control StripBituminous Street

    All other operations with CAPs Grading and Base, Level 2

  • 7/21/2019 Construction sample Quality Plan

    15/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 15 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    The foreman or superintendent in charge of the construction activity will ensure that thework is being built to the Contract requirements and will sign the proper testing orinspection forms when the tests/inspections are completed and provide passing data.

    The CQMis responsible for ensuring MnDOT certified inspectors/technicians performrequired observations, checks, and documentation of the work as required.

    The Critical Activity Points will be held at the following operations:

    Excavation and Embankment

    Test Rolling: The foreman, CAPM and MnDOT will oversee test rollingperformed. The Contractor shall not proceed with placement of Select Granular

    Borrow, aggregate base, or any other material on top of the subgrade or gradinglevel that requires test rolling until form CQP-407F, Test Roll Reporthas beencompleted by the CAPM and signed-off by MnDOT and the QC Inspector.

    Subgrade Excavation: Prior to backfilling any subgrade excavation, thecontractor shall complete Form CQP408F Excavationand Embankment Reportfor sign-off by the QC Inspector.

    Grading Construction: Prior to placing any aggregate base in any given area, theCAPM shall certify that the Contractor has performed all testing and materialscertification on all underlying materials. The CAPM shall provide complete

    testing records, material certification reports, and complete Form CQP444F forsign-off.

    Aggregate Base: After the placement of aggregate base, prior to paving, the testson the aggregate base, The CAPM shall certify that the Contractor hasperformed all testing and materials certification on the aggregate base materials.The QC Inspector shall complete Form CQP438F, Pre-Paving Checklist.

    Drainage and Utilities

    Delivery of Pipe and Drainage Structures: After delivery of a load of pipe and

    prior to the installation of the pipe and drainage structures, the CAPM shallprovide certification records from the producer. No materials will be installed untilcertification records have been provided. The CAPM shall retain a copy of thecertifications. The CAPM will fill out the applicable sections of form CQP428FMaterials Certification Report..

  • 7/21/2019 Construction sample Quality Plan

    16/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 16 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    Structural Concrete, Bridges and Walls

    Foundation and Footing Excavation: Prior to backfilling any pipe, drainage orutility excavation, the QC Inspector shall complete Form CQP408F Excavationand Embankment Report.

    Following the Setting of Structural Concrete Forms Prior to Casting Concrete:Form CQP417, ConcretePlacement Inspection willbe completed prior to theplacement of concrete. If the structural concrete is for a spread footing, FormCQP411F Foundations - Spread Footing Report will be completed prior to anyplacement of concrete.

    Retaining Wall Reinforcement: Prior to placing structural concrete, the CAPM

    shall provide certification records from the producer. No structural concrete shallbe placed until certification records have been provided. The CAPM shall retaina copy of the certifications. The CAPM will fill out the applicable sections of formCQP428F Materials Certification Report.

    Pile Driving: Forms CQP409F and CQP410F, Pile Summary Report and TestPile Report will be completed and reviewed prior to the placement of concretefor the footing.

    Superstructure Reinforcement Placement: After placement of the superstructurereinforcement and prior to the placement of structural deck concrete, the

    following two critical activity points will occur:

    o a dry run with the screeds will be done and Form CQP417F, ConcretePlacement Inspection will be completed prior to the placement ofconcrete.

    o The CAPM shall provide documentation that form elevations and rebarcover depths have been checked by the QC Inspector.

    o Prior to placing structural concrete, the CAPM shall provide certificationrecords from the producer. No structural concrete shall be placed untilcertification records have been provided. The CAPM shall retain a copyof the certifications. The CAPM will fill out the applicable sections of form

    CQP428F Materials Certification Report.

    Low Slump Overlay: After the structural deck surface preparation and prior to lowslump deck placement, a dry run with the screeds will be done and FormCQP437, Low Slump Concrete will be completed prior to the placement ofconcrete.

    Pavements

  • 7/21/2019 Construction sample Quality Plan

    17/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 17 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    Concrete Pavement: Prior to concrete paving, the CAPM shall provide materialcertification for reinforcement and dowel bars. The QC Inspector shall confirmthat the reinforcement required over culverts is ready for concrete placement and

    joint layouts are correct. Prior to placement of concrete paving, Section I of FormCQP424F, Concrete Paving will be filled completedby the QC Inspector.Sections II, III, IV and V will be filled out during and after the paving operationsare done.

    Bituminous Control Strip: After conducting a bituminous test strip for ordinarycompaction and prior to using the established rolling pattern for ordinarycompaction, Form CQP443F, Bituminous Control Strip Hold Point For OrdinaryCompaction will be completed prior to continuation of the established rollingpattern.

    Removals

    Buildings and Bridges: Prior to demolition of any building or bridge, the Design-Builders Environmental Compliance Manager and MnDOTs EnvironmentalCompliance Manager shall provide written authorization to proceed withdemolition. This review should include a review of the RFC plans for the removalWork along with any reports, field testing and/or supplemental data to ensure allenvironmental permits and regulations are being properly followed andaddressed.

    Environmental

    Pre-Construction Environmental Reviews: Before any construction occurs otherthan to install BMPs and environmental controls, the Design-BuildersEnvironmental Compliance Manager shall verify and provide a writtencertification that all BMPs and environmental controls are installed according tothe RFC Design and RFP requirements. This is especially important before anyclearing and grubbing or tree removal operations commence.

    Traffic

    Traffic Switches: Before any traffic switches occur, including both temporary andpermanent switches, the Design-Builders Traffic Engineer shall provide writtencertification that all traffic control devices and controls as noted in the Releasedfor Construction designs are properly installed and that no further devices orcontrols are necessary.

  • 7/21/2019 Construction sample Quality Plan

    18/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 18 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    Striping Layout: Before any temporary or permanent striping activities areconducted, the Design-Builders Traffic Engineer shall provide written certificationthat the striping is properly depicted in the field layout and conditions areacceptable to continue.

    Signal System Activation: Before any newly installed temporary or permanentsignal system is activated, the Design-Builders Traffic Engineer shall provide awritten certification that the signal systems are properly installed as depicted inthe Released for Construction design plans. This activity may be replaced by aSignal System Activation plan that is reviewed and accepted by the Departmentprior to activation.

    Miscellaneous

    Miscellaneous Products: Each time a material listed in Section I through XI in theMaterial Control Schedule is used for the first time on the project, the CQM shallensure that the material meets the requirements of the Materials ControlSchedule, Special Provisions and Standard Specifications. The Contractor shallnot install these items until CQM ensures that the product meets the above listedrequirements. After the product is accepted for installation, the Contractor mayinstall the product and subsequent testing and sampling will occur in accordancewith the Materials Control Schedule.

    PROCEDURE

    1. At a defined Critical Activity Point, the CAPM will review the Construction QualityInspection and Testing Plan to the testing and/or inspection procedures anddocumentation that is required for that Critical Activity Point.

    2. The CAPM will ensure that the required tests and/or inspections have beenperformed and provide passing data, according to the Project requirements.

    3. The CAPM will collect the required documentation (inspection and/or testingforms) and ensure that the required signatures have been made on the forms.

    4. Once it has been determined that the work meets the Project requirements, the

    proper inspection and testing has been performed, the required documentationhas been completed and signed by the QC Inspector in charge of the activity, theCAPM will complete form CQP-444 for sign-off by MnDOT.

    5. Once the CAPM and MnDOT and has signed off at the Critical Activity Point,work may proceed to the next activity.

  • 7/21/2019 Construction sample Quality Plan

    19/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 19 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    6. The CAPM will provide a copy of each Critical Activity Point sign-off to MnDOTsdocument control and enter the information into MnDOTs TRACS system.

    7. The CAPM shall document each Critical Activity Point acceptance on form CQP-429F Daily Field Report.

    FIGURES AND FORMSCQP444F: Critical Activity Point Release FormCQP429F: Daily Field Report

  • 7/21/2019 Construction sample Quality Plan

    20/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 20 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 204: Testing Procedures & FormsRev , Date

    PURPOSE

    To document the contractor test procedures according to the Materials ControlSchedule.

    RELATED DOCUMENTS

    The following documents are referenced in this Quality Procedure:

    Mn/DOT Standard Specifications for Construction (2005)

    Materials Control Schedule (MCS)

    MnDOT Laboratory Manual

    MnDOT Grading and Base Manual

    MnDOT Bituminous Manual

    MnDOT Concrete Manual

    RESPONSIBILITIES

    The Construction Quality Manager (CQM)is responsible ensuring properly trainedand certified technicians perform quality control testing in accordance with the MCS,test results are documented on the appropriate form in accordance with the MCS, andtest results are properly stored in Document Control and uploaded into the TRACS

    system.

    PROCEDURE1. Prior to work, a pre-activity meeting will be initiated to ensure that the contractor

    staff has the appropriate testing forms and certifications to perform the testing.The CQM shall develop and maintain form CQP-204F (MnDOT Certification Log)for all quality employees performing testing on the project. The pre-activitymeeting will also discuss the processes and procedures for storing theinformation in document control and providing the information to Mn/DOT inTRACS.

    2. Prior to testing materials for the first time, the QM or CQM shall verify that allcontractor test equipment is properly calibrated. The CQM shall collect andretain calibration records on Form CQP 204FB and place in document control.

    3. The CQM shall issue a Stop Work order if testing is being performed withoutproper certification.

  • 7/21/2019 Construction sample Quality Plan

    21/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 21 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    FIGURES AND FORMSCQP204FA: MnDOT Certification LogCQ204FB: Equipment List

    {Contractor to provide a list of forms to be used (as required by the MCS plus additionalquality control / quality assurance forms desired by the contractor) and include a copy ofeach form in the Construction Quality Plan}

  • 7/21/2019 Construction sample Quality Plan

    22/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 22 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 301: Clearing and GrubbingRev , Date

    PURPOSE:

    To establish required Construction Quality procedures for inspection and reportingrequirements for clearing and grubbing operations performed on the project.

    SCOPE

    Clearing and grubbing applies to the removal and disposal of vegetation that is notdesignated for preservation.

    RELATED DOCUMENTS:

    The following documents are referenced in this quality procedure: MnDOT Standard Specifications for Construction

    Contract Documents

    Released for Construction Plans

    RESPONSIBILITIES:

    The CQMis responsible for verifying that the erosion control devices are in place as perthe contract documents and environmental permits.

    MnDOT will provide construction testing and inspection.

    PROCEDURE:

    1. Prior to work, a pre-activity meeting will be initiated to ensure that clearing andgrubbing will be performed in accordance with MnDOT Specification 2101, Book2 Section 10, and the Released for Construction documents.

    2. Prior to work, the CQM will verify all erosion control devices are in place perNPDES, SWPPP, and the approved erosion control plans and specifications.

    3. The Contractor will adhere to the Tree Preservation Plan.

    DRAWING, FIGURES AND FORMS:CQP-429F: Daily Field Report

  • 7/21/2019 Construction sample Quality Plan

    23/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 23 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 302: Grading and BaseRev , Date

    PURPOSE

    To establish required Construction Quality procedures and reporting requirements, andprovide a methodology for inspection of adequate grading and base operationsperformed on the project.

    SCOPE

    This work shall include: select granular and modified select granular, aggregate baseand shouldering, subsurface drain tile.

    RELATED DOCUMENTSThe following documents are referenced in this Quality Procedure:

    MnDOT Standard Specifications for Construction

    Contract Documents

    Special Provisions {Contractor to insert special provisions that apply}

    Schedule of Materials Control

    Released for Construction Plans

    RESPONSIBILITIES

    The CQM is responsible for ensuring MnDOT certified testers perform required testing

    and documentation of grading and base operations to include aggregate base,aggregate shouldering, bedding for sanitary and storm sewers, manholes, catch basins,culverts, subsurface drains, and rip rap.

    The CQMis responsible for ensuring that the Contractor adherers to all Critical ActivityPoints related to Excavation and Embankment items.

    MnDOT will provide inspection, acceptance testing of the materials installed, and sign-off on Critical Activity Points.

    PROCEDURE1. Prior to work, a pre-activity meeting will be initiated to ensure that grading and

    base construction will be performed in accordance with MnDOT Specifications,the Materials Control Schedule, the RFC documents, and contract provisions.

    2. Prior to bringing grading and base materials onto the Project, the CQM shallprovide test results and certifications that all materials to be installed meet theproduction testing requirements of the Materials Control Schedule. The CQMshall enter this information into TRACS and provide a hard copy to MnDOT.

  • 7/21/2019 Construction sample Quality Plan

    24/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 24 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    3. The CQM shall provide contractor test results and certification that all materialsinstalled meet the placement requirements of the Schedule of Materials Control.The CQM shall enter this information into TRACS and provide a hard copy toMnDOT. MnDOT may elect not to perform any agency acceptance testing priorto receiving this information.

    4. The CQM shall coordinate Critical Activity Point sign-offs.

    5. The CQM shall verify that the materials are installed at the proper grades(tolerance). See CQP 304 Grade Control.

    6. The CQM shall complete the Daily Field Report (CQP-429F) and enter thisinformation into MnDOT TRACS system. The daily report shall include quantitiesplaced with supporting documentation/calculations.

    7. The CQM shall complete the Weekly Grading/Base/Paving Report (Form CQP-

    403F) and provide this information to MnDOT via document control and enter thisinto TRACS.

    8. The CQM shall complete and submit the Monthly Grading and Base Report(Form CQP-406F) to MnDOT.

    FIGURES AND FORMSCQP-403F: Weekly Grading/Base/Paving ReportCQP-406F: Monthly Grading and Base ReportCQP-429F: Daily Field Report

  • 7/21/2019 Construction sample Quality Plan

    25/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 25 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 303: Test RollingRev , Date

    PURPOSETo establish the required Construction Quality procedures for the testing, inspection,documentation, and reporting on Test Rolling.

    SCOPETest Rolling is a means to assess the bearing measure of a roadbed. Test Rolling willbe performed only where specifically required by the Contract.

    RELATED DOCUMENTS

    The following documents are referenced in this Quality Procedure: MnDOT Standard Specifications for Construction

    Contract Documents

    RESPONSIBILITIESThe CQM is responsible for ensuring that the Contractor adheres to the Critical ActivityPoint related to Test Rolling and Excavation and Embankment items.

    PROCEDURE

    1. Prior to test rolling, a pre-activity meeting shall be held to discuss theContractors test rolling procedures, review the plans, and discuss

    testing/inspection responsibilities.

    2. The CQM (or CAPM) shall verify that the test roller meets MnDOT specification2111. The CQM (or CAPM) shall document this on form CQP-407F Test RollReport.

    3. Prior to test rolling, the Contractor will protect culverts and structures fromdamage by the test roller or request an exception where protection is notfeasible.

    4. Test rolling will be performed in accordance with the following table:

    Case Test Rolling Location Number ofpasses per

    strip

    Allowableyielding or

    rutting

    {to be filled in by QM} {to be filled in by QM} {to be filled inby QM}

    {to be filled in byQM}

  • 7/21/2019 Construction sample Quality Plan

    26/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 26 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    {to be filled in by QM} {to be filled inby QM}

    {to be filled in byQM}

    {to be filled in by QM} {to be filled inby QM}

    {to be filled in byQM}

    {to be filled in by QM} {to be filled in by QM} {to be filled inby QM}

    {to be filled in byQM}

    {to be filled in by QM} {to be filled in by QM} {to be filled inby QM}

    {to be filled in byQM}

    5. The foreman, CQM (or CAPM) and MnDOT will oversee testing rollingperformed.

    6. If test rolling passes, the foreman, CQM (or CAPM) and MnDOT will sign-off onthe Test Rolling Critical Activity Point.

    7. If test rolling does not pass, the CQM (or CAPM) and MnDOT will document thelocation of the failure on form CQP-407F. The Contractor shall develop and takecorrective actions. The foreman, CQM (or CAPM) and MnDOT will overseeretesting until test rolling passes and the Testing Rolling Critical Activity Point hasbeen signed-off. Corrective action and result will be noted on form CQP-407F.

    8. The CQM (or CAPM) shall complete the Daily Field Report (CQP-429F) and

    enter this information into MnDOTs TRACS system.

    FIGURES AND FORMSCQP-407F: Test Roll ReportCQP-429F: Daily Field Report

  • 7/21/2019 Construction sample Quality Plan

    27/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 27 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 304: Grade ControlRev , Date

    PURPOSETo establish required Construction Quality procedures for inspection, testing, andreporting requirements regarding roadway elevations using standard methods andGPS-guided machines.

    SCOPEThis procedure will be used to determine depth of subcut excavations, tolerance the topof sand grading grade, and delineate the limits of muck excavation.

    RELATED DOCUMENTSThe following documents are referenced in this Quality Procedure:

    MnDOT Standard Specifications for Construction

    Contract Documents

    Special Provisions {Contractor shall insert special provisions that apply}

    RESPONSIBILITIES

    The CQM is responsible for ensuring that grade control is performed in accordance withthe following procedures and project requirements. The CQMis responsible forensuring that the Contractor adheres to all Critical Activity Points related to Excavation

    and Embankment items.

    MnDOT will sign-off on Critical Activity Points, and verify that the Contractor hasprovided sufficient grade control through verification inspections.

    PROCEDURE

    Subcut Excavation1. {Contractor shall enter means and methods to perform subgrade excavation (e.g.

    Machine control and procedures for set-up and calibration}

    2. {Contractor shall methods to have the CQM check tolerance. For example,provide Blue top elevations will be placed by Design-Builder surveyors fromProject Survey Controls every 700 in tangent sections and 500 in vertical andhorizontal curve locations. Exceptions will be under bridges or in other areaswhere GPS does not have coverage. In these areas blue tops will be placedevery 100.}

    3. {Contractor shall provide methods that will allow MnDOT to check tolerance (e.g.provide blue tops, provide rovers with data}

  • 7/21/2019 Construction sample Quality Plan

    28/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 28 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    4. {Contractor state the allowable tolerances per Specification}

    5. When the subcut excavation is complete, the CAPM shall verify with the foremanthat the excavation has been performed in accordance with the Released forConstruction Plans and Specification 2112. The CAPM shall document thegrade control check on Form CQP416F.

    6. The CAPM shall provide MnDOT Form CQP416F and inform MnDOT that thegrade is ready for a Critical Activity Point inspection. MnDOT will performverification inspection on the grade control. If acceptable, the foreman, MnDOTand CAPM will sign-off on the Critical Activity Point.

    7. If the tolerance is not acceptable, the CAPM will document the unacceptablelocations on form CAP-416F. The Contractor shall take corrective action until theCritical Activity Point is signed-off by MnDOT, the foreman and CAPM.

    Material Installation1. Backfill material will only be installed after the Subgrade Excavation Critical

    Activity Point is signed-off by MnDOT and the CQM (or CAPM) has provideddocumentation that production test results of the material have met the minimumrequirements of the Materials Control Schedule.

    Grading Grade1. {Contractor shall enter means and methods to perform subgrade excavation (e.g.

    Machine control and procedures for set-up and calibration, tolerance}

    2. {Contractor shall enter methods to to check tolerance (e.g. Select Granualr willbe installed to the required elvations and checked by utilizing GPS every 100with random offsets from Centerline).

    3. {Contractor shall provide methods that will allow MnDOT to check tolerance (e.g.provide blue tops, provide rovers with data}

    4. {Contractor state the allowable tolerances per Specification}

    5. When the grade is ready for tolerance, the CAPM shall verify with the foremanthat the excavation has been performed in accordance with the Released forConstruction Plans and Specification 2112. The CAPM shall document thegrade control check on Form CQP416F.

  • 7/21/2019 Construction sample Quality Plan

    29/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 29 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    6. The CAPM shall provide MnDOT Form CQP416F and inform MnDOT that thegrade is ready for a Critical Activity Point inspection. MnDOT will performverification inspection on the grade control. If acceptable, the foreman, MnDOTand CAPM will sign-off on the Critical Activity Point.

    7. If the tolerance is not acceptable, the CAPM will document the unacceptablelocations on form CQP-416F. The Contractor shall take corrective action untilthe Critical Activity Point is signed-off by MnDOT, the foreman and CAPM.

    8. The CQM shall complete the Daily Field Report (CQP-429F) and enter thisinformation into MnDOT TRACS system.

    FIGURES AND FORMSCQP-416F: Grade Control Tolerance ReportCQP-429F: Daily Field ReportCQP-403F: Weekly Grading-Base-Paving ReportCQP-406F: Monthly Grading and Base Report

  • 7/21/2019 Construction sample Quality Plan

    30/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 30 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 305: EmbankmentRev , Date

    PURPOSETo establish the required Construction Quality procedures for testing, inspection,documentation, and reporting embankment fill placement.

    SCOPEEmbankment applies to all new embankment material placed.

    RELATED DOCUMENTSThe following documents are referenced in this quality procedure:

    MnDOT Standard Specifications for Construction

    Contract Documents Special Provisions {Contractor to insert special provisions that apply}

    Schedule of Materials Control

    RESPONSIBILITIESThe CQM is responsible for ensuring MnDOT certified testers perform the requiredtesting, and ensuring that the Contractor adheres to all Critical Activity Points related toEmbankment items.

    MnDOT will perform acceptance testing, sign-off on critical activity points, and provideinspection.

    PROCEDURE1. Prior to work, the Contractors Environmental Compliance Manager will verify all

    erosion control devices are in place per the approved erosion control plans andspecifications.

    2. Embankment observations shall follow the requirements of CQP302-1 (Gradingand Base).

    3. The QC Inspector shall complete form CQP-408F. The CPAM or CQM shallaudit this process periodically.

    4. The CQM shall complete the Daily Field Report (CQP-429F) and enter thisinformation into MnDOT TRACS system.

    DRAWING, FIGURES AND FORMS:

    CQP-408F: Excavation and Embankment ObservationsCQP-429F: Daily Field Report

  • 7/21/2019 Construction sample Quality Plan

    31/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 31 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 306: Excavation

    PURPOSE:

    To establish the required Construction Quality procedures for testing, inspection,documentation, and reporting of excavation operations.

    RELATED DOCUMENTS:The following documents are referenced in this quality procedure:

    MnDOT Standard Specifications for Construction

    Contract Documents

    Schedule of Materials Control

    Special Provisions {Contractor to insert list of special provisions that apply}

    RESPONSIBILITIES:

    The CQMis responsible for ensuring MnDOT certified testers perform the requiredtesting, and documentation of embankment fill operations.

    The CQMis responsible for ensuring that the Contractor adheres to all Critical ActivityPoints related to Excavation Items.

    MnDOT will perform acceptance testing, sign-off on critical activity points, and provideinspection.

    PROCEDURE:

    1. Prior to work, the Contractors Environmental Compliance Manager will verify allerosion control devices are in place per the approved erosion control plans andspecifications.

    2. Excavation activities will be performed in accordance with the ContractDocuments.

    3. The CQM will coordinate with the Contractors Geotechnical Engineer to identifyundercut requirements based on exposed conditions of questionable subcutareas. The Geotechnical Engineer and/or CQM shall process a Field DesignChange through the Construction Manager in accordance with CQP201 FieldDesign Change if necessary.

    4. Upon completion of clearing and grubbing, the Contractors CQMwill inspect thesubgrade for suitability.

  • 7/21/2019 Construction sample Quality Plan

    32/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 32 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    5. The QC Inspector shall complete form CQP-408F. The CPAM or CQM shallaudit this process periodically.

    6. The CQM shall complete the Daily Field Report (CQP-429F) and enter thisinformation into the MnDOT TRACS system.

    7. The CQM shall verify that the Critical Activity Points for backfilling excavationsare met prior to proceeding with any backfill operations.

    Muck Excavation1. {contractor shall establish procedures for how to check muck limits (e.g. A Cat

    385 backhoe will be fitted with GPS grade control to establish muck excavationlimits and data will be retrieved showing the actual depth and width the machinereached. The muck excavation limits will be detailed within the data recorder andcompared to the cross sections for correct depth and width of the excavation.}

    2. {contractor to provide methods that will allow MnDOT to check tolerance}

    3. After completion of muck excavation in wet ponds, Piezocone tests will beutilized to determine the mechanical properties of the soil in order to judge thesuitability of the excavation activities.

    FIGURES AND FORMS:

    CQP-408F: Excavation and Embankment ReportCQP-429F: Daily Field Report

  • 7/21/2019 Construction sample Quality Plan

    33/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 33 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 307: Temporary Erosion and Sediment ControlRev , Date

    PURPOSETo establish required Construction Quality procedures for observation and thedocumentation of erosion and sediment control.

    SCOPEErosion and sediment control is the prevention of soil erosion and sedimentation duringconstruction operations. This work includes implementing horizontal slope grading,construction phasing, and other construction practices to minimize erosion as well asfurnishing and installing sediment control devices.

    RELATED DOCUMENTSThe following documents are referenced in this Quality Procedure:

    MnDOT Standard Specifications for Construction

    XXXX Special Provisions

    Environmental Management Plan

    RESPONSIBILITIES

    The CQMis responsible for ensuring that the Contractor adheres to the Critical ActivityPoints related to Environmental and Miscellaneous items.

    The Environmental Compliance Manager (ECM) is responsible for performing checks ofthe required observations and documentation of erosion and sediment control.

    MnDOT will perform inspections of temporary erosion control and sediment items withthe Contractors ECM.

    PROCEDURE1. Prior to work, a pre-activity meeting will be initiated to ensure that temporary

    erosion control and sediment control will be installed according to the MnDOTStandards Specifications, permits, the Materials Control Schedule, the RFCdocuments, and contract provisions. The pre-activity must include MnDOTs

    Environmental Compliance Manager.

    2. The CQM shall verify that the Miscellaneous Products Critical Activity Point hasbeen performed prior to installation of any product.

    3. The CQM shall provide test results and certifications that all materials installedmeet the requirements of the Schedule of Materials Control. The CQM shallenter this information into TRACS and provide a hard copy to MnDOT.

  • 7/21/2019 Construction sample Quality Plan

    34/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 34 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    4. The contractor shall construct, maintain, and remove temporary erosion controlmeasures as required by the RFC documents, contract documents, permits, oras ordered by MnDOT.

    5. The CQM shall ensure the contractor conducts inspections and maintains a logas per the NPDES permit.

    6. The Contractor shall invite MnDOTs Environmental Compliance Manager to allinspections.

    7. {Contractor shall identify special permitting or environmental issues that need tobe addressed}

    8. The Contractors environmental staff are responsible for preventing or minimizingthe potential for erosion after temporary erosion control measures have beeninstalled.

    9. The contractor shall use {to be filled in by the Contractor}to preserve and protectvegetation according to the Vegetation Preservation Plan.

    FIGURES AND FORMSNPDES inspection forms and logs

  • 7/21/2019 Construction sample Quality Plan

    35/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 35 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 308: LandscapingRev , Date

    PURPOSETo establish required Construction Quality procedures for observation, testing anddocumentation of landscaping operations.

    SCOPEThis work shall include mulch placement, turf establishment, and plant installation,including, tilling, liming, fertilizing, seeding, and sodding.

    RELATED DOCUMENTSThe following documents are referenced in this Quality Procedure:

    MnDOT Standard Specifications for Construction Contract Documents

    Special Provisions {Contractor shall insert list of special provisions that apply}

    Schedule of Materials Control

    Released for Construction Drawings

    RESPONSIBILITIES

    The CQM is responsible for ensuring MnDOT certified testers perform the requiredtesting and the Contractor adheres to the Critical Activity Points.

    MnDOT will sign-off on Critical Activity Points and inspect landscaping installation.

    PROCEDURE1. Prior to work, a pre-activity meeting will be initiated to ensure that landscaping

    items will be installed according to the MnDOT Standards Specifications, permits,the Materials Control Schedule, the RFC documents, and contract provisions.The pre-activity must include MnDOTs Environmental Compliance Manager.

    2. The CQM shall verify that the Miscellaneous Products Critical Activity Point hasbeen performed prior to installation of any product. For products that requireVisual Inspection, MnDOT and the CQM shall review these products and develop

    procedures and process for evaluating procedures for acceptance.

    3. The CQM shall provide test results and certifications that all materials installedmeet the placement requirements of the Schedule of Materials Control. TheCQM shall enter this information into TRACS and provide a hard copy toMnDOT.

  • 7/21/2019 Construction sample Quality Plan

    36/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 36 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    4. Seeding and Fertilizer quantities will be reported by the contractor and a copy ofthe quantity report will be submitted to the CQM each time crews are mobilized tothe project. The CQM will verify the accuracy of each report and provide theinformation to MnDOT and enter the data into TRACS.

    FIGURES AND FORMS

    CQP-429F: Daily Field Report

  • 7/21/2019 Construction sample Quality Plan

    37/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 37 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 309: Pile DrivingRev , Date

    PURPOSETo establish the required Construction Quality procedures for observation, inspection,testing and reporting for installation of steel piles.

    SCOPESteel piles will be used to support heavily loaded structures for the project includingbridge piers and abutments.

    RELATED DOCUMENTS

    The following documents are referenced in this Quality Procedure:

    MnDOT Standard Specifications for Construction

    Schedule of Materials Control

    Contract Documents

    Special Provisions {Contractor shall insert list of special provisions}

    Released for Construction Plans

    RESPONSIBILITIES

    The CQMis responsible for ensuring MnDOT certified inspectors perform requiredobservations, testing, and documentation of pile driving activities. The Quality

    Assurance inspector will be onsite during all pile driving activities.

    MnDOT will provide oversight inspection and verification.

    PROCEDURE

    1. Prior to work, a pre-activity meeting will be initiated to ensure that piling will beinstalled according to the MnDOT Standards Specifications, permits, theMaterials Control Schedule, the RFC documents, and contract provisions.

    2. In accordance with Specification 2452, the CQM shall verify and submit the MillTest Reports and Mill Shipping Papers to MnDOT prior to installation of pile.

    3. The CQM shall provide a MnDOT certified bridge inspector to inspect theinstallation of the each Test Pile and provide documentation of the test pileresults on form CQP-410F. The CQM shall coordinate the results of the test pileto the Contractors Lead Design Engineer Structures.

  • 7/21/2019 Construction sample Quality Plan

    38/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 38 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    4. The CQM shall provide a MnDOT certified bridge inspector to inspect anddocument the installation of each non-test pile on form CQP-409F.

    5. The CQM shall immediately report all deviations to the RFC plans to the QM forresolution.

    FIGURES AND FORMSCQP-409F: Pile Summary ReportCQP-410F: Test Pile ReportCQP-429F: Daily Field Report

  • 7/21/2019 Construction sample Quality Plan

    39/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 39 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 310: Portland Cement Concrete Batch PlantRev , Date

    PURPOSETo establish the required Construction Quality procedures for testing, inspection, andreporting for Portland Cement ConcreteBatch Plant Inspections.

    SCOPEConstruction quality personnel will perform observations of the batch plants.

    RELATED DOCUMENTS

    The following documents are referenced in this Quality Procedure: Special Provisions {Contractor to insert list of Special Provisions}

    Contract Documents

    Schedule of Materials Control

    MnDOT Standard Specifications for Construction

    RESPONSIBILITIES

    The CQMis responsible for maintaining test records and documents provided by thecontractor.

    The certified supplieris responsible for providing MnDOT certified Concrete Plant Iand Concrete Plant II technicians, and providing documentation to the CQM asrequired. The supplier is responsible for obtaining and maintaining their certified plantstatus.

    PROCEDURE

    Ready Mix Plant1. Quality Control testing will be the responsibility of the Plant Quality Supervisor

    who will record all information regarding the project in a Quality Logbook. Thelogbook will be maintained in accordance with MnDOT 2461 and provide thefollowing information:

    a. Yards produced daily is recordedb. The appropriate concrete mix is utilizedc. Certified Materials are usedd. Daily moisture and gradation reports are completede. MnDOT Form TP 24143-03(2000) is completed and submitted

  • 7/21/2019 Construction sample Quality Plan

    40/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 40 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    f. Control Charts will be completed in a manner approved by theEngineer and will contain the following information:

    I. Test data from moisture content of aggregatesII. Gradation Testing

    The producer/contractor will test the materials in accordance with the Schedule ofMaterials Control and will forward records to the CQM weekly who will forward them toMnDOT.

    The following procedure is to be followed when sampling for the minus #200 test:

    a. The samples will be taken from the belt using the MnDOT flat-nosed sampling scoop.

    b. The samples will be taken side by side off the belt.c. The samples are then placed directly in the pan for testing.

    Paving

    The CQM or his representative will verify the following:

    a. Producer has MnDOT approved mix designs designated for thisproject. Aggregate quality source testing has been performed byMnDOT. The CQM will keep a record of mix designs used on theproject on form CQP- 412F.

    b. Plant has calibrated and correlated the testing equipment inaccordance with prescribed MnDOT testing procedures as listed in theMnDOT Concrete Manual.

    c. Coarse and fine aggregate gradations have been completed properly.

    d. Producer quality personnel have MnDOT Concrete Plant I and Plant IIcertifications.

    e. Producer Concrete Level II supervisor is on site at all times or has acellular phone in their possession and able to be at the plant in areasonable amount of time.

    f. Control Charts will be completed in a manner approved by the MnDOTand will contain the following information:

  • 7/21/2019 Construction sample Quality Plan

    41/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 41 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    I. Test data from moisture content of aggregates, total water inmix, W/C ratio, admixture dosage, and flexural strength aresummarized; gradation and air content are summarized andplotted on control charts.

    II. The control charts contain: date, time, lot and sublot, andapplicable specifications.

    III. The charts are a readable size and are displayed on thetesting facility wall.

    IV. Batch weight adjustments are noted on the control chartsunder a remarks column.

    g. Contractors aggregate sources are verified and preliminary tests aredone well in advance of project date.

    h. Mix designs are submitted and approved.

    i. A concrete Paving Contact Report (FORM2164) is completed.

    j. Scales and water meter are calibrated.

    k. Verify cementitious materials and admixtures are approved andsampled

    l. Batch trucks are checked and appropriate items are reviewed on Form433F.

    m. Stockpiling and loading of delivered aggregate are monitored andrecorded on Form 433F.

    n. Aggregate hopper and scales are reviewed and recorded on Form433F.

    o. Cementitious hopper and scales are checked and recorded on Form433F.

    p. Moisture tests are performed per the schedule of tests and recordedon the proper form.

    q. Gradation tests are performed per the schedule of tests and recordedon the proper form.

    r. Quality tests are obtained.

  • 7/21/2019 Construction sample Quality Plan

    42/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 42 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    s. Daily diary including necessary information and recorded on Form433F.

    CQM or his representative will audit that the contractor has documented inspectionswith a Batch Plant Observation Form (CQP-433F). This form includes inspection ofplant certification, technicians, certificate of compliance, supervisor logbook, materials,and general operations.

    The producer/contractor will test the materials in accordance with Schedule of MaterialsControl \nd will forward records to the CQM weekly who will forward them to MnDOT.

    MnDOT testing of materials will be in accordance with Schedule of Materials Controland will forward records to the CQM weekly.

    FIGURES AND FORMS

    CQP-412F: Concrete Mix Design LogCQP-433F: Batch Plant ObservationCQP-222F: Paving Aggregate WorksheetMnDOT Form TP 24143-03(2000)

  • 7/21/2019 Construction sample Quality Plan

    43/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 43 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 311: Ready Mix Concrete Mix DesignRev , Date

    PURPOSETo establish required Construction Quality procedures for preparing Portland CementConcrete (PCC) mix designs.

    SCOPEPortland Cement Concrete (PCC) is defined as precast or cast-in-place Portlandcement concrete placed as structural concrete, slope protection, sidewalks, gutters, flatwork, approach slabs, driveways, median barriers, fences, and ditch linings. Theconcrete mix design for pavement slabs is addressed in the Portland Cement Paving-Mix Designs.

    RELATED DOCUMENTSThe following documents are referenced in this Quality Procedure:

    MnDOT Standard Specifications for Construction

    Special Provisions {Contractor to insert list of Special Provisions}

    Contract Documents

    Materials Control Schedule

    RESPONSIBILITIESThe CQMis responsible for assuring theAgencysProject Manager that only approved

    concrete mixes are used on the project. The CQM will retain on file all approved mixdesign submittals.

    PROCEDURE1. If allowed by the RFP, the Contractor has three options available pertaining to

    concrete job mix proportions:a. The Contractor may request concrete mix designs and concrete mix

    design adjustments from the MnDOT Concrete Engineering Unit. Themix designs are considered trial mixes.

    b. The Contractor may revise the concrete mix designs requested from

    MnDOT following mix design procedures stated in {insert SpecialProvision} of the Design-Build Modifications to the MnDOT SpecialProvisions, as required for the type of concrete used.

    c. For all other cases, the Contractor shall produce concrete mix designsfollowing mix design procedures stated in {insert Special Provision}of

  • 7/21/2019 Construction sample Quality Plan

    44/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 44 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    the Design-Build Modifications to the MnDOT Special Provisions, asrequired for the type of concrete used.

    I. A mix that meets MnDOT specifications for the project: this mixdesign can be sent to a MnDOT project representative who willforward the design to the Concrete Office for verification.

    II. A pre-approved mix: this is a mix design that has previously beenused on state projects; advise MnDOT of that project number orreference.

    III. A non-standard mix design: this is a mix design that does not meetthe MnDOT mix design requirements but can be proven to meet theprojects required compressive/flexural strength, air content, etc.through a trial mix.

    IV. A mix containing High Range Water Reducer (HRWR): this is astructural concrete mix (CQP-311) that has specific requirementsset forth in {insert Special Provision

    V. The CQM will ensurethat the concrete mix has been designed tomeet the MnDOT Specification 2461 and {insert Special Provision,and has been submitted to MnDOT on the appropriate form forreview. If it is a Contractor-design mix, it must meet the specificrequirements of {insert Special Provision.

    2. The CQM will ensurethat the MnDOT mix and strength requirements based onmaximum aggregate size in the mix, and the calculated water-cement ratio aremet. The CQM will ensurethat the aggregate testing has been performed inaccordance with MnDOT standards.

    3. The CQM will ensurethat the materials used (ie. cement, pozzolan, water, andadmixtures) are from MnDOT verified sources.

    FIGURES AND FORMS

    CQP-412F: Concrete Mix Design LogCQP-413F: Request for Concrete Mix Design Approval

  • 7/21/2019 Construction sample Quality Plan

    45/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 45 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 312: Paving Concrete Mix DesignRev , Date

    PURPOSE

    To establish the required Construction Quality procedures for preparing PortlandCement Concrete PavingMix Designs.

    SCOPE

    Portland Cement Concrete (PCC) paving is defined as high performance concrete asspecified in MnDOT 2301 and modified by Special Provision {insert Special Provision ifapplicable}.

    All Contractor mix designs shall be submitted to the MnDOT Concrete Engineering Unit

    for review and preliminary Approval prior to concrete placement on the Project. MnDOTfinal approval of the Contractors mix designs shall be based on satisfactory fieldplacement.

    The Contractor is required to contact the MnDOT Concrete Engineering Unit a minimumof 2 days prior to any mixing so that a MnDOT representative can observe the process.This same 2-day notification is required prior to any physical testing on hardenedconcrete samples. Additionally, any hardened concrete test specimens must beretained for a minimum of 90 days and be made available for MnDOT.

    RELATED DOCUMENTSThe following documents are referenced in this Quality Procedure:

    MnDOT Standard Specifications for Construction

    Special Provisions {Contractor to insert list of special provisions that apply}

    Contract Documents

    Materials Control Schedule

    RESPONSIBILITIESThe CQMis responsible for assuring theAgencysProject Manager that only approvedconcrete mixes are used on the project. The CQM will retain on file all approved mixdesign submittals.

    PROCEDURE1. If allowed by the RFP, the Contractor has three options available pertaining to concrete

    job mix proportions:

    A. The Contractor may request concrete mix designs and concrete mixdesign adjustments from the MnDOT Concrete Engineering Unit. Themix designs are considered trial mixes.

  • 7/21/2019 Construction sample Quality Plan

    46/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 46 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    B. The Contractor may revise the concrete mix designs requested fromMnDOT following mix design procedures stated in {insert special

    provision}of the Design-Build Modifications to the MnDOT SpecialProvisions, as required for the type of concrete used.

    C. For all other cases, the Contractor shall produce concrete mix designsfollowing mix design procedures stated in {insert special provision}ofthe Design-Build Modifications to the MnDOT Special Provisions, asrequired for the type of concrete used.

    2. The Contractor shall contact MnDOT or designated representative to coordinatepreliminary sampling of aggregate for concrete paving as soon as coarse andfine aggregate are available for testing. MnDOT will sample and test theaggregate to verify specific gravity and absorption data and perform other testsas determined by MnDOT. If Class B or C aggregate is used, the Contractorsaggregate testing shall be in conformance with Special Provisions {insert specialprovision}.

    3. A minimum of 21 days prior to the commencement of paving operations, theContractor shall submit to MnDOT for review and approval. The concretepavement placement may commence 15 days after preliminary approval of theContractor's concrete pavement mix design and job mix formula (JMF) byMnDOT (final Approval is based on satisfactory placement in the Project).

    4. Structural Concrete Pavement mix designs shall be submitted in accordance with

    MnDOT Specification 2461 and Special Provision {insert special provision}

    5. High Early mixes shall contain a minimum cement content of 600 lbs per cubicyard, and a minimum flexural strength of 500 psi or a minimum compressivestrength of 3000 psi within 48 hours.

    6. The concrete gradation shall meet the requirements for well graded aggregate inaccordance with Special Provision {insert special provision}.

    7. The coarse aggregate is subject to the disincentive set forth in Special Provision{insert special provision}.

    8. The water/cementitious ratio shall conform to the requirements of Table WC-1 ofSpecial Provisions {insert special provision}

    9. The air content for all paving grade concrete shall be 7.0 percent plus or minus1.5 percent {insert special provision}

  • 7/21/2019 Construction sample Quality Plan

    47/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 47 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    10. An approved Type A water reducing concrete admixture may be used at thediscretion of the Contractor. The use of any admixtures other than air entrainingagents and Type A water reducers require the Approval of MnDOT.

    11. The materials used (ie. cement, pozzolan, water, and admixtures) are fromMnDOT certified/verified sources.

    12.The Contractors quality testing shall be in accordance with Special Provisions{insert special provision}.

    13. The Contractor will seal the joints with Preformed Elastomeric Compression JointSeals meeting the requirements of MnDOT Specification 3721.

    FIGURES AND FORMSCQP-412F: Concrete Mix Design LogCQP-413F: Request for Concrete Mix Design Approval

  • 7/21/2019 Construction sample Quality Plan

    48/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 48 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 313: Structural Concrete Pre-PlacementRev , Date

    PURPOSETo establish required Construction Quality procedures for, inspecting, documenting andreporting for Concrete Pre-placement observations.

    SCOPEThis procedure covers concrete pre-placement observations for Portland cementconcrete placed per approved plans and the project documents.

    RELATED DOCUMENTSThe following documents are referenced in this Quality Procedure:

    MnDOT Standard Specifications for Construction Contract Documents

    Special Provisions {Contractor to insert list of applicable special provisions}

    MnDOT Concrete Manual

    Schedule of Materials Control

    RESPONSIBILITIESThe CQMis responsible for ensuring the MnDOT certified testers perform requiredtesting.

    The CQMis responsible for ensuring that the Contractor adheres to all Critical Activity

    Points such as Structural Concrete, Bridges and Walls.

    MnDOT will provide inspection of reinforcement.

    PROCEDURE1. The Contractor shall install all items necessary for concrete pre-placement (eg.

    forms, rebar).

    2. The CQM shall provide MnDOT with copies of all material certifications andtesting results prior to placing concrete.

    3. The QC Inspector shall fill out form CQP-417F. The CQM or CAPM shallperform periodic audits this process.

    4. For spread footings, the QC Inspector shall fill out form CQP-411F. The CQM orCAPM shall perform periodic audits of this process.

  • 7/21/2019 Construction sample Quality Plan

    49/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 49 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    5. The CQM shall verify that the appropriate Critical Activity Points have beenperformed prior to placing concrete.

    6. The CQM shall complete the Daily Field Report (CQP-429F) and enter thisinformation into the TRACS system.

    7. MnDOT will verify that the items have been installed in accordance with theContract requirements prior to placing concrete.

    FIGURES AND FORMSCQP-411F: Spread Footing ReportCQP-417F: Concrete Placement InspectionCQP-428F: 1stTime Inspection ReportCQP-429F: Daily Field Report

  • 7/21/2019 Construction sample Quality Plan

    50/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 50 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 314: Structural Concrete PlacementRev , Date

    PURPOSE

    To establish required Construction Quality procedures for testing, inspecting,documenting and reporting Structural Concrete Placement.

    SCOPE

    This procedure covers structural concrete placement or cast-in-place Portland cementconcrete placed in structures per approved plans and the project documents.

    RELATED DOCUMENTS

    The following documents are referenced in this Quality Procedure:

    MnDOT Standard Specifications for Construction

    Contract Documents

    Special Provisions {contractor to insert list of applicable special provisions}

    MnDOT Concrete Manual

    Schedule of Materials Control

    RESPONSIBILITIES

    The Contractor is responsible for ensuring the Concrete Producer supplies certifiedReady-Mix concrete in accordance with the MnDOT Standard Specifications forConstruction.

    The CQMis responsible for ensuring MnDOT certified inspectors perform requiredtesting of structural concrete placement.

    The CQMis responsible for ensuring that the Contractor adheres to all Critical ActivityPoints.

    MnDOT will perform acceptance testing and inspection as listed below.

    PROCEDURE1. Structural concrete placement operations shall be performed in conformance of

    MnDOT Standard Specifications for Construction.

    2. The QC Inspector shall fill out form CQP-417F. The CQM or CAPM shallperform periodic audits this process.

  • 7/21/2019 Construction sample Quality Plan

    51/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 51 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    3. Prior to any placement of structural concrete, the CQM shall verify that all CriticalActivity Points have been signed-off.

    4. Test rates for concrete placement will be performed according to the Schedule ofMaterials Control.

    FIGURES AND FORMSCQP-417F: Concrete Placement InspectionCQP-429F: Daily Field Report

  • 7/21/2019 Construction sample Quality Plan

    52/85

    {CONTRACTOR}XXXX Design-Build ProjectS.P. XXXXCONSTRUCTION QUALITY PLAN

    District X Rev {date} 52 of 85

    MnDOT Design-Build Quality Template (June, 2011)

    CQP 315: Sidewalk and Curb PavingRev , Date

    PURPOSETo establish required Construction Quality procedures for testing, inspection, andreporting of Portland Cement Concrete (PCC) sidewalks and curb and gutter.

    SCOPEThis procedure includes procedures regarding the preparation for placing, jointconstruction of concrete curbing and walks and concrete finishing and curingoperations.

    RELATED DOCUMENTSThe following documents are referenced in this Quality Procedure:

    Special Provisions {contractor to insert list of applicable special provisions}

    MnDOT Standard Specifications for Construction

    Schedule of Materials Control.

    RES