Page 1 of 18 Last Updated 4 June 2020 Construction Projects in the Townsville and North West Queensland Region This information has been gathered by Regional Development Australia Townsville and North West Queensland (RDA) based on information sourced from a variety of organisations’ publications including the 2019 Queensland Major Projects Pipeline Report, 2020 Queensland Major Projects Pipeline Report, Construction Skills Queensland Knowledge Centre and Townsville Enterprise: Opportunity Townsville North Queensland – Edition 04 . We note that project information is frequently changing, and the following is only a guide to the civil and commercial construction projects in Burdekin, Charters Towers, Hinchinbrook, Mount Isa and Townsville Local Government Areas. NOTE: This report has been prepared by Regional Development Australia Townsville and North West Queensland (RDA) to promote the pipeline of civil and commercial construction projects in Burdekin, Charters Towers, Hinchinbrook, Mount Isa and Townsville Local Government Areas. RDA accepts no liability or responsibility whatsoever for or in respect of any use of or reliance upon this report. Project name Project Owner/Sponsor Project Value $M LGA Project Stage 19/20 20/21 21/22 22/23 23/24 2019 QMPP 2020 QMPP CSQ TEL TSV Bulletin Jobs needed Comments 70 The Strand Lachlan Bell 3 Townsville Committed 10 Seven-storey apartment block (12 units) and a two-storey food and drink outlet. Commencing Q2 2020. https://www.townsvillebulletin.com.au/business/70-the-strand-development-to-go-ahead-after- townsville-city-council-ceo-gives-approval/news-story/23d1905d1ffcc0dd22b7c04860684541 Abbot Point Coal Terminal O Project Adani 1500 Mackay Whitsundays Planned 714 New standalone port facility to export up to 70 Mtpa of coal from Carmichael Coal Mine in Galilee Basin https://www.adaniaustralia.com/projects-businesses Adani Carmichael Rail Network Adani 350 Townsville Committed 1500 Workforce to be based out of Townsville and Rockhampton. https://www.townsvillebulletin.com.au/news/bmd-awarded-350m-adani-contract/news- story/a40279bc73d8cd6f412b9e0220766c75 https://www.townsvillebulletin.com.au/business/australian-company-awarded-220m-critical-adani-rail- contract/news-story/b0058f2da5c422f7eaa7501fcdb5194b Agripower Amorphous Silica – Fertiliser Processing Plant Agripower Australia Ltd 663 Charters Towers Prospective 490 Agripower expects to produce one million tonnes of fertiliser from the new facility, to be exported to the world – and to do that with a project life of up to 200 years. http://statements.qld.gov.au/Statement/2019/5/23/new-nq-fertiliser-mine-could-have-200year-life Ardmore Phosphate Rock Project Centrex Metals 58 Mount Isa Planned The Ardmore Phosphate Rock Project (“Ardmore”) is located south of Mt Isa in North West Queensland. The project is linked to the Port of Townsville via an existing rail line. http://www.centrexmetals.com.au/ardmore/ Armoured Vehicle Simulation Centre - Lavarack Barracks Department of Defence 40 Townsville Committed 3 storey simulator facility, construction expected to commence September to mid-2022.

Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

Page 1 of 18 Last Updated 4 June 2020

Construction Projects in the Townsville and North West Queensland Region

This information has been gathered by Regional Development Australia Townsville and North West Queensland (RDA) based on information sourced from a variety of organisations’ publications including the 2019 Queensland Major Projects Pipeline

Report, 2020 Queensland Major Projects Pipeline Report, Construction Skills Queensland Knowledge Centre and Townsville Enterprise: Opportunity Townsville North Queensland – Edition 04 . We note that project information is frequently changing,

and the following is only a guide to the civil and commercial construction projects in Burdekin, Charters Towers, Hinchinbrook, Mount Isa and Townsville Local Government Areas.

NOTE: This report has been prepared by Regional Development Australia Townsville and North West Queensland (RDA) to promote the pipeline of civil and commercial construction projects in Burdekin, Charters Towers, Hinchinbrook, Mount Isa and Townsville Local Government Areas. RDA accepts no

liability or responsibility whatsoever for or in respect of any use of or reliance upon this report.

Pro

ject

nam

e

Pro

ject

O

wn

er/S

po

nso

r

Pro

ject

Val

ue

$M

LGA

Pro

ject

Sta

ge

19

/20

20

/21

21

/22

22

/23

23

/24

20

19

QM

PP

20

20

QM

PP

CSQ

TEL

TSV

Bu

lleti

n

Job

s n

eed

ed

Co

mm

ents

70 The Strand Lachlan Bell 3 Townsville Committed ✓ ✓

10

Seven-storey apartment block (12 units) and a two-storey food and drink outlet. Commencing Q2 2020. https://www.townsvillebulletin.com.au/business/70-the-strand-development-to-go-ahead-after-townsville-city-council-ceo-gives-approval/news-story/23d1905d1ffcc0dd22b7c04860684541

Abbot Point Coal Terminal O Project

Adani 1500 Mackay Whitsundays

Planned ✓ ✓ ✓ 714 New standalone port facility to export up to 70 Mtpa of coal from Carmichael Coal Mine in Galilee Basin https://www.adaniaustralia.com/projects-businesses

Adani Carmichael Rail Network

Adani 350 Townsville Committed ✓ 1500

Workforce to be based out of Townsville and Rockhampton. https://www.townsvillebulletin.com.au/news/bmd-awarded-350m-adani-contract/news-story/a40279bc73d8cd6f412b9e0220766c75 https://www.townsvillebulletin.com.au/business/australian-company-awarded-220m-critical-adani-rail-contract/news-story/b0058f2da5c422f7eaa7501fcdb5194b

Agripower Amorphous Silica – Fertiliser Processing Plant

Agripower Australia Ltd

663 Charters Towers

Prospective ✓ ✓ 490

Agripower expects to produce one million tonnes of fertiliser from the new facility, to be exported to the world – and to do that with a project life of up to 200 years. http://statements.qld.gov.au/Statement/2019/5/23/new-nq-fertiliser-mine-could-have-200year-life

Ardmore Phosphate Rock Project

Centrex Metals 58 Mount Isa Planned ✓ ✓ ✓ ✓

The Ardmore Phosphate Rock Project (“Ardmore”) is located south of Mt Isa in North West Queensland. The project is linked to the Port of Townsville via an existing rail line. http://www.centrexmetals.com.au/ardmore/

Armoured Vehicle Simulation Centre - Lavarack Barracks

Department of Defence

40 Townsville Committed ✓ ✓

✓ 3 storey simulator facility, construction expected to commence September to mid-2022.

Page 2: Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

Page 2 of 18 Last Updated 4 June 2020

Pro

ject

nam

e

Pro

ject

O

wn

er/S

po

nso

r

Pro

ject

Val

ue

$M

LGA

Pro

ject

Sta

ge

19

/20

20

/21

21

/22

22

/23

23

/24

20

19

QM

PP

20

20

QM

PP

CSQ

TEL

TSV

Bu

lleti

n

Job

s n

eed

ed

Co

mm

ents

Australia- Singapore Military Training Initiative

Department of Defence

2300 Townsville Committed ✓ ✓ ✓ ✓

✓ ✓ ✓ ✓ ✓

Construction of a Military Training Facility. Commencing Q4 2022 to 2028 The $2.25 billion Australia Singapore Military Training Initiative will see an estimated $36.2 million spent in Townsville every year throughout its life and will involve about 14,000 Singaporean soldiers training for 14 weeks a year for 25 years. Laing O’Rourke was awarded the $800 million managing contract for Shoalwater Bay. https://www.townsvillebulletin.com.au/news/townsville/businesses-urged-to-tender-for-lucrative-defence-deals/news-story/291d1c3c4737176c7441138c072b3498 https://www.townsvillebulletin.com.au/news/defence/nq-businesses-wanted-for-225-billion-defence-deal/news-story/e351290332fe09c34c6409c7f83577a6 https://www.townsvillebulletin.com.au/news/three-major-contractors-shortlisted-for-joint-australiansingapore-military-training-facility/news-story/28f601f14afa99a00389208798bcd2d1

Australian Taxation Office Federal Government

12.5 Townsville Planned ✓ ✓ ✓ ✓

Ayr Showgrounds Burdekin Shire Council

5 Townsville Planned ✓

Upgrade of the Ayr Showgrounds including Covered Grandstand and Amenities Block

Battery Processing Facility Imperium3 Consortium/ Magnis

2000 Townsville Committed ✓ ✓

✓ ✓ ✓

Two Townsville-based firms have joined the project team to build the lithium-ion battery plant proposed for the city. GHD and Douglas Partners are now engaged through the Imperium3 consortium to build the $2 billion battery plant, which would position Townsville as an international and national leader in advanced manufacturing. 18 GWh lithium-ion battery manufacturing plant will be built in Townsville over 3 years, 6 GWh stages with a net present value of $2.55 billion and estimated 21% internal rate of return. https://www.townsvillebulletin.com.au/business/townsville-battery-plant-moving-forward-after-council-meetings/news-story/9ffd828faf48d6d0c20cfef208999bd0 https://www.pv-magazine.com/2019/10/03/australias-townsville-battery-gigafactory-reaches-new-milestone/

Black Rock Cave Glencore 400 Mount Isa Under Construction

Black Rock further develops the existing copper resource at Mount Isa Mines, using sub-level caving to improve the economic viability of extracting ore from the existing ore-body. https://pybar.com.au/pybar-awarded-underground-contract-at-mount-isa-mines-black-rock-cave-project/#:~:text=PYBAR%20awarded%20underground%20contract%20at%20Mount%20Isa%20Mines'%20Black%20Rock%20Cave%20project,-May%202%2C%202018&text=PYBAR%20will%20complete%20underground%20decline,on%20site%20at%20peak%20production.

Blackview Avenue Subdivision

Townsville Earthmoving

2 Townsville Planned ✓ ✓

Bruce Highway – Ingham to Cardwell Range Deviation

Qld Government & Federal Government

460 Townsville Prospective

Page 3: Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

Page 3 of 18 Last Updated 4 June 2020

Pro

ject

nam

e

Pro

ject

Ow

ner

/Sp

on

sor

Pro

ject

Val

ue

$M

LGA

Pro

ject

Sta

ge

19

/20

20

/21

21

/22

22

/23

23

/24

20

19

QM

PP

20

20

QM

PP

CSQ

TEL

TSV

Bu

lleti

n

Job

s n

eed

ed

Co

mm

ents

Bruce Highway – Sarina to Cairns – Haughton River & Pink Lily Lagoon Upgrade

Qld Government & Federal Government

515 Townsville Under Construction

✓ ✓ ✓

✓ ✓ ✓

Bruce Highway - Haughton River and Pink Lily Lagoon Upgrade. Program of safety and flood immunity upgrades on the Bruce Highway at Giru, including wider and higher-level bridges, reconfigured intersections and 13.5km of upgraded highway pavement across the Haughton River Floodplain. https://www.tmr.qld.gov.au/Projects/Name/H/Haughton-River-Floodplain-Upgrade-Project-Bruce-Highway-Horseshoe-Lagoon-Palm-Creek

Bruce Highway – Sarina to Cairns – Saltwater Creek Upgrade

Federal Government

103 Townsville Announced ✓ ✓ ✓

✓ 280

Construct a high-level bridge and approaches on a new alignment at Saltwater Creek crossing and a new bridge and approaches to Deadman’s Gully on a new alignment. Upgrade four existing floodway sections north of Saltwater Creek between Maryborough and Torbanlea to improve flood immunity. https://investment.infrastructure.gov.au/projects/ProjectDetails.aspx?Project_id=091547-16QLD-NP https://www.ccfqld.com/saltwater-creek-upgrade-project/

Bruce Highway – Townsville Northern Access Intersections Upgrade

Qld Government & Federal Government

107 Townsville Announced ✓ ✓ ✓

This project involves the upgrade of 5.2km of the Bruce Highway between the Veales Road intersection to Pope Road intersection. The project is currently in the planning phase that will determine the project's full scope for delivery. https://investment.infrastructure.gov.au/projects/ProjectDetails.aspx?Project_id=061469-15QLD-NP

Bruce Highway (Townsville to Ingham) Hecths Road-Easter Creek

Qld Government

15 Hinchinbrook Committed ✓ ✓

Burdekin Falls – hydro-electric power station (50MW)

Stanwell 200 Burdekin Prospective ✓ ✓

✓ ✓ ✓

206

Construction of a 30 - 50 MW hydro-electric power station to commence Q2 2020 to Q3 2021. Reported to be on hold TSV Bulletin 6 Feb 2020 https://www.townsvillebulletin.com.au/news/opinion/decision-on-hydro-overdue/news-story/f91d704b9f7691913769b86ac786183e

Burdekin Falls Dam – Saddle Dam and Monolith Improvement

Sunwater 330 Burdekin Announced ✓ ✓ ✓

250

A key project in Sunwater’s Dam Improvement Program. It will ensure the long-term viability of the dam by bringing its infrastructure into line with the safety requirements set out in the Water Supply (Safety and Reliability) Act 2008 (Qld). Improvement works include strengthening of the left spillway abutment, installing post-tensioned anchors to the dam’s main spillway and abutments, and installing anchor bars at the downstream end of the spillway. https://www.sunwater.com.au/projects/burdekin-falls-dam-improvement-project/

Burdekin Solar Farm

220 Burdekin Committed ✓

Construction of a 75MW Solar Farm (72 Cell Panels). Start Q1 2020.

Page 4: Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

Page 4 of 18 Last Updated 4 June 2020

Pro

ject

nam

e

Pro

ject

Ow

ner

/Sp

on

sor

Pro

ject

Val

ue

$M

LGA

Pro

ject

Sta

ge

19

/20

20

/21

21

/22

22

/23

23

/24

20

19

QM

PP

20

20

QM

PP

CSQ

TEL

TSV

Bu

lleti

n

Job

s n

eed

ed

Co

mm

ents

Calcium Cattle Holding Facility

Woodstock Pastoral Services

Approved

The project has the capacity to accommodate 20,000 head of cattle. It is expected to directly generate up to 10 full-time jobs on-site once fully operational and will indirectly support many more in the beef farming and related industries. The facility will be developed in four stages between 2020 and 2029, and will consist of sheltered cattle receiving and handling yards, holding pens, a workshop and hardstand area, feed shed, offices and a weighbridge. https://www.townsvillebulletin.com.au/news/approved-live-cattle-holding-yard-to-create-10-jobs/news-story/080d33b27a5e5e69bc85fd70358715d4

Calvary Christian College 1 Townsville Committed ✓

Classroom block for school - alterations and additions.

Cannington Expansion BHP Billiton 400 Mount Isa Credibly Proposed

✓ ✓ ✓

Carlyle Gardens Carlyle Gardens 85 Townsville Under Construction

Expansion of Existing Retirement Village (additional 344 Homes and 66 Units).

Century Mine Project New Century Resources

113 Mount Isa/ Burke

Under Construction

✓ 69

Located at Lawn Hill, 250km north-west of Mount Isa in the Lower Gulf of Carpentaria, the Century mine began open-pit production in 1999. During its 16 years of operation, Century was one of the largest zinc mines in the world, producing and processing an average of 475,00tpa zinc concentrate and 50,000tpa lead concentrates at Lawn Hill. The product was transferred in slurry form via a 304km underground pipeline to Century’s Port facility at Karumba for shipping to smelters in Australia, Europe and Asia. https://www.newcenturyresources.com/century-mine-project/

CH2 Warehouse Mount Louisa

2 Townsville Planned ✓ ✓

Warehouse - Single Storey. Commencing Q2 2020 to Q4 2020. https://app.estimateone.com/s/lanskey-qld/stage/201576

Charters Towers Citigold Corporation

246 Charters Towers

Prospective ✓ ✓ ✓

✓ ✓

Charters Towers Stock Feed Processing Facility

60 Charters Towers

Planned ✓

111 Project to end Q4 2020.

City Land and City Arcade Redevelopment

Townsville City Council

60 Townsville Under Construction

✓ 31

Redevelopment of the shopping centre. Expected completion Q1 2020.

Cloncurry Copper Project (Roseby Copper/Little Eva/Eva)

Altona Resources

320 Cloncurry Possible ✓ ✓

✓ ✓

395 Open Cut Mine - Iron-Oxide Copper Gold

Cloncurry Rail Loading Facility

Grand Central Industries Holdings

31 Cloncurry Planned ✓ ✓

✓ 12

Multi-user loading facility to continue the link between the north west and Townsville. https://www.i-q.net.au/main/construction-nears-for-31m-freight-terminal-project

Clyde Park Project

750 Townsville Possible ✓

Page 5: Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

Page 5 of 18 Last Updated 4 June 2020

Pro

ject

nam

e

Pro

ject

Ow

ner

/Sp

on

sor

Pro

ject

Val

ue

$M

LGA

Pro

ject

Sta

ge

19

/20

20

/21

21

/22

22

/23

23

/24

20

19

QM

PP

20

20

QM

PP

CSQ

TEL

TSV

Bu

lleti

n

Job

s n

eed

ed

Co

mm

ents

CopperString 2.0 Transmission Line

CopperString 1800 Mount Isa Planned ✓ ✓ ✓

✓ ✓

800

The CopperString transmission line will link the North West Minerals Province’s isolated electricity network into the National Electricity Market (NEM) and deliver lower electricity prices for those critical businesses. The closing date for the submission of proposals in response to the RFP is 1 July 2020. CopperString is preparing an environmental-impact statement to submit to the State Government, while expressions of interest in the project’s engineering, procurement and construction close on March 13. http://copperstring2.com.au/ https://www.townsvillebulletin.com.au/news/state-government-injects-148m-into-copperstring-20-to-help-with-preconstruction-works/news-story/968c07a95e2693806e6cde4601243d27 https://www.townsvillebulletin.com.au/business/developers-seek-contractor-for-15b-nq-power-project/news-story/5e3309e3a86e54c4a8ed3f8d80e9c7df https://reneweconomy.com.au/copperstring-could-unlock-wind-and-solar-and-huge-minerals-province-89804/ https://www.statedevelopment.qld.gov.au/coordinator-general/assessments-and-approvals/coordinated-projects/current-projects/copperstring-project.html

Cosgrove master Planned Community

Parkside Developments

250 Mount Louisa Under Construction

✓ ✓ ✓ ✓ ✓

✓ 537

2,100 lot residential development including retail, business and park facilities as well as a school. (TEL Opportunity Townsville North Queensland - Edition 04)

DriveIt NQ DriveIt NQ 18.5 Townsville Under Construction

✓ 50

The DriveIt NQ proposal is seeking a $18.5M commitment toward the establishment of a state-of-the-art driver education and training facility at Calcium near Townsville. The precinct will address a critical need to support driver education and motorsport in Townsville, generating significant economic and community benefits. The proposed upgraded motorsports facility at Charters Towers, together with a new Driver Education and Motorsport Precinct for Townsville, will enhance Townsville’s profile as a motorsport events destination. BMD North Queensland construction manager Michael Peterson met with DriveIt NQ chairman Greg Fitzgerald at the site on 15 May 2020 to sign the $2.6 million contract to build access roads and the skid pan for a driver education program. https://www.townsvillebulletin.com.au/business/driveit-facility-to-inject-14bn-into-townsvilles-economy/news-story/56545c5250bcef2d4bf3bc34901e98c7

Elliot Springs - Masterplan Lendlease 4700 Townsville Under Construction

✓ ✓

✓ ✓ ✓

Masterplan community up to 15,000 residential lots. https://communities.lendlease.com/queensland/elliot-springs/

Page 6: Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

Page 6 of 18 Last Updated 4 June 2020

Pro

ject

nam

e

Pro

ject

Ow

ner

/Sp

on

sor

Pro

ject

Val

ue

$M

LGA

Pro

ject

Sta

ge

19

/20

20

/21

21

/22

22

/23

23

/24

20

19

QM

PP

20

20

QM

PP

CSQ

TEL

TSV

Bu

lleti

n

Job

s n

eed

ed

Co

mm

ents

Eva Copper Project 600 Cloncurry Under Construction

269

Mine - Iron-Oxide Copper Gold, Gold, Lead, Silver and Zinc https://www.i-q.net.au/main/eva-copper-study-due-out-within-weeks https://www.northweststar.com.au/story/6779961/copper-mountain-bullish-about-eva-project/

Export Distribution Centre Proposed ✓

Townsville applied for an Export Distribution Centre grant (valued at $10M) to assist in building the airfreight opportunities available in the region. Harbourside Coldstores has applied for the development of an Export Distribution Centre to be based in Townsville. Currently, products grown in North Queensland are harvested, aggregated and transported out of the region (primarily towards Brisbane) for accumulation and sale into the domestic market or prepared for export. (TEL Opportunity Townsville North Queensland - Edition 04)

Gardens Hills Units - Belgian Gardens

Ash Agaibey 10 Townsville Committed ✓

12

Construction of units (22) and medical centre. Project end date Q4 2020. https://www.townsvillebulletin.com.au/news/townsville/new-belgian-gardens-development-to-inject-10-million-in-townsville-economy/news-story/ec7edc273d18af7285dcc8345233a899

Glencore Office Refurbishment

Glencore 2.5 Mount Isa Committed ✓ ✓

Refurbishment of existing office.

Gorge Weir to Byerwen Coal Project Pipeline project (110km)

QCoal 240 Townsville Under Construction

✓ ✓

Sourcing and delivery of water for the project from a pipeline system that connects the project to the Burdekin water supply scheme at Gorge Weir and which traverses the western side of the project area. http://eisdocs.dsdip.qld.gov.au/Byerwen%20Coal/EIS/EIS%2026May13/05-project-location.pdf

Great Barrier Reef House Reef House Investment Group

30 Townsville Proposed

Needs the commitment from the leading marine science agencies, the waterfront project would proceed, possibly in 2020. https://www.townsvillebulletin.com.au/news/townsville-developer-reveals-plans-for-30m-reef-offices-project/news-story/908bf66c99a6a531409feaf0ba1e9da

Greater Ascot Residential Development

Parkside Developments

210 Townsville Under Construction

✓ ✓ ✓ ✓ ✓

✓ 451

2,000 lot residential development in northern suburbs of Townsville, with a town centre and school. (TEL Opportunity Townsville North Queensland - Edition 04)

Guthalungra Aquaculture Facility

Pacific Reef Fisheries

100 Mackay Whitsundays

Committed ✓ ✓

Construction of a new 259 ha aquaculture facility http://pacificreef.com.au/guthalungra/ http://www.statedevelopment.qld.gov.au/coordinator-general/assessments-and-approvals/coordinated-projects/completed-projects/guthalungra-aquaculture.html

Haughton Channel Capacity Upgrade

QLD Government

90 Townsville Prospective ✓ ✓

Page 7: Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

Page 7 of 18 Last Updated 4 June 2020

Pro

ject

nam

e

Pro

ject

Ow

ner

/Sp

on

sor

Pro

ject

Val

ue

$M

LGA

Pro

ject

Sta

ge

19

/20

20

/21

21

/22

22

/23

23

/24

20

19

QM

PP

20

20

QM

PP

CSQ

TEL

TSV

Bu

lleti

n

Job

s n

eed

ed

Co

mm

ents

Haughton Pipeline Duplication – Stage 2

QLD Government

250 Townsville Announced ✓ ✓

76

The Haughton Pipeline Duplication Project (HPDP) involves the duplication of a fully functioning and sustainable 36.5km pipeline from the Haughton Pump Station to the Ross River Dam. A backup to the Ross River Dam, the HPDP will provide a bulk raw water supply link to the Burdekin Haughton Water Supply Scheme. The pipeline is capable of pumping raw water into the Ross River Dam to augment or “top up” water levels during periods of very low rainfall. https://www.townsville.qld.gov.au/building-planning-and-projects/council-projects/haughton-pipeline-duplication-project https://www.townsvillebulletin.com.au/news/townsville-city-council-calls-for-tenders-for-next-section-of-pipeline/news-story/5d4880b15f610bbab0393ae48e22711f

Hells Gate Dam 5400 Charters Towers

Possible ✓ ✓ ✓ 12647

Construction of a new 2110 GL dam. THE Hells Gates Dam could generate more than 12,000 jobs in its construction phase and contribute millions of dollars to the local economy, according to analysis of the multibillion-dollar project. A summary of the Hells Gates Irrigation Scheme feasibility study states project would generate about $1.2 billion in household income and create 12,647 full-time equivalent jobs during construction. https://www.hellsgatesproject.com.au/ https://www.townsvilleenterprise.com.au/key-projects/hells-gate-dam-project/ https://www.townsvillebulletin.com.au/business/12000-job-hopes-in-hells-gates-irrigation-scheme/news-story/d1f99b9d295b608d33cc74833a04ecf9

Herveys Range Development Road

Townsville City Council/Qld Gov

8.9 Townsville Committed 14 https://www.townsvillebulletin.com.au/news/state-government-to-fund-widening-of-townsville-region-road/news-story/27b33e8a867369e2aa8493261c56467d

Hinchinbrook Shire Council DFRA Program

Hinchinbrook Shire Council

2 Hinchinbrook Committed ✓ ✓

https://www.hinchinbrook.qld.gov.au/our-council/procurement-and-tenders/current-procurement-and-tender-opportunities/

Hughenden Showgrounds and Aquatic Centre Masterplan

Flinders Shire Council

2 Flinders Possible ✓

Construction of Aquatic Centre, Showgrounds and Racecourse http://www.flinders.qld.gov.au/documents/44837427/44964502/Hughenden%20Showgrounds%20-%20Mater%20Plan%20-%20November%202013.pdf http://www.flinders.qld.gov.au/documents/44837427/44964502/Hughenden%20Memorial%20Aquatic%20Centre%20%28Swimming%20Pool%29%20-%20Master%20Plan%20-%20November%202013.pdf

Page 8: Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

Page 8 of 18 Last Updated 4 June 2020

Pro

ject

nam

e

Pro

ject

Ow

ner

/Sp

on

sor

Pro

ject

Val

ue

$M

LGA

Pro

ject

Sta

ge

19

/20

20

/21

21

/22

22

/23

23

/24

20

19

QM

PP

20

20

QM

PP

CSQ

TEL

TSV

Bu

lleti

n

Job

s n

eed

ed

Co

mm

ents

Illich Park Detention Basin Townsville City Council

6 Townsville Under Construction

Construction of a flood mitigating 65 litre detention basin https://www.townsvillebulletin.com.au/news/townsville/6m-illich-park-upgrade-to-fend-off-floodwaters-and-become-playing-ground-for-residents/news-story/91bdf32ffc3c676fffe0defbf9cac5c1

Ingham Bio-energy Project (110MW)

NQ Bio-Energy Corp

640 Townsville Credibly proposed

Irrigated Agricultural Development Project

Flinders Shire Council

47 Flinders Possible ✓

77

Construction of Logistics Facility, Irrigation Networks and Power Supply Infrastructure https://www.northweststar.com.au/story/6290517/state-approves-hughenden-15-mile-irrigated-agricultural-development/ https://www.statedevelopment.qld.gov.au/coordinator-general/assessments-and-approvals/coordinated-projects/completed-projects/15-mile-irrigated-agricultural-development-project.html

James Cook University Townsville - Masterplan

James Cook University

1000 Townsville Under Construction

✓ ✓ ✓ ✓ ✓

Alterations & Additions to the University Campus. Commenced Q1 2019, anticipated End Q1 2035. https://www.jcu.edu.au/estate-directorate/campus-planning/townsville-campus-master-plan

James Cook University Townsville - ongoing campus renewal

James Cook University

73 Townsville Planned

✓ 348

Adjacent to Technology Innovation Complex, planned to be ready for Semester 1 2022. https://www.jcu.edu.au/estate-directorate/campus-planning/townsville-campus-master-plan https://www.townsvillebulletin.com.au/news/wave-of-development-in-townsville-is-set-to-create-1500-jobs/news-story/cecaeca07c3e474c715c53870081fc7e

James Cook University Townsville - Student Accommodation

James Cook University

53 Townsville Planned ✓ ✓

✓ 348

Adjacent to Technology Innovation Complex, planned to be ready for Semester 1 2022. https://www.jcu.edu.au/estate-directorate/campus-planning/townsville-campus-master-plan https://www.townsvillebulletin.com.au/news/james-cook-university-secures-46-million-naif-loan-to-build-7storey-student-housing-complex/news-story/8fa81a3c44ba2f0134a8d76c026905e0

James Cook University Townsville - Technology Innovation Complex

James Cook University

98 Townsville Under Construction

✓ ✓ ✓

✓ ✓ 270

JCU has announced the development of a state-of-the-art Technology Innovation Complex. This facility would boost enrolment in Science, Technology, Engineering, Arts and Mathematics (STEAM) higher education training for the next generation of employees and entrepreneurs. Creating 270 jobs during construction and operation, this development is part of the larger STEAM program promoting and educating the community through industry engagement, science and art activity development and school programs. (TEL Opportunity Townsville North Queensland - Edition 04) https://www.townsvillebulletin.com.au/business/jcu-seeks-contractor-for-landmark-technology-centre/news-story/6bf627f29223ac7d8808c1e9f8c2e869 https://www.townsvillebulletin.com.au/news/townsville/early-work-will-start-on-270-job-generating-project-next-year/news-story/090ffd30fd9b67d37a10748532e35504

Page 9: Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

Page 9 of 18 Last Updated 4 June 2020

Pro

ject

nam

e

Pro

ject

Ow

ner

/Sp

on

sor

Pro

ject

Val

ue

$M

LGA

Pro

ject

Sta

ge

19

/20

20

/21

21

/22

22

/23

23

/24

20

19

QM

PP

20

20

QM

PP

CSQ

TEL

TSV

Bu

lleti

n

Job

s n

eed

ed

Co

mm

ents

John Flynn Place Museum and Art Gallery

15 Cloncurry Planned ✓

The redevelopment would deliver interactive displays, a new cafe and would address compliance concerns. https://www.i-q.net.au/mount-isa/redevelopment-plans-for-john-flynn-place

Joint Health Command Centre

Department of Defence

11 Townsville Under Construction

✓ ✓

✓ 100

Medical facilities expected completion Q4 2020. https://www.townsvillebulletin.com.au/news/wave-of-development-in-townsville-is-set-to-create-1500-jobs/news-story/cecaeca07c3e474c715c53870081fc7e

Kidston Pumped Storage Hydro Project 250MW

Genex Power 700 Etheridge Committed ✓ ✓ ✓

✓ 500

Bulletin 31/03/20: finalised an energy supply agreement with EnergyAustralia Fed Govt’s Northern Australia Infrastructure Facility offering a concessional loan of up to $610M, Qld Gov committed $132M towards cost of transmission line needed for the project. 270km north of Townsville EOI for subcontractors and suppliers now available on website (01/04/2020) https://www.genexpower.com.au/250mw-kidston-pumped-storage-hydro-project.html https://www.mcconnelldowell.com/about-us/procurement https://www.townsvillebulletin.com.au/business/genex-finalises-power-supply-deal-for-700m-kidston-hydro-project/news-story/f3dab7f6cf5f477b1bbc43522d0a4945+AM51

Kidston Solar Project – Stage 2 (270 MW)

Genex Power 400 Etheridge Prospective ✓ ✓

Kidston Stage 3 Wind Project 150MW

Genex 250 Etheridge Prospective ✓ ✓ ✓

Kidston Transmission Project

Genex/Powerlink

200 Etheridge Prospective ✓

Land 4502 Additional Chinook Facilities

Federal Government

50 Townsville Under Construction

✓ ✓

✓ 400

New facilities for the 5th Aviation Regiment’s CH-47 Chinook helicopters are under construction and include new aircraft shelters, a support resource, working accommodation and tarmac parking for three of the army choppers. The project is expected to be complete this year with around 400 workers directly participating in the construction of the new facilities. https://www.i-q.net.au/construction/lions-share-stays-local-as-raaf-base-job-progresses

Little Street Units - Belgian Gardens

Cable Property Developments

24 Townsville Committed ✓ ✓

✓ 53

Construction of 30 Units across 3 Buildings. Project end date Q4 2020. https://www.townsvillebulletin.com.au/business/developers-return-to-townsville-market-with-24m-unit-project/news-story/532758d404b7382d0edd8ce53abafe5b

Page 10: Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

Page 10 of 18 Last Updated 4 June 2020

Pro

ject

nam

e

Pro

ject

Ow

ner

/Sp

on

sor

Pro

ject

Val

ue

$M

LGA

Pro

ject

Sta

ge

19

/20

20

/21

21

/22

22

/23

23

/24

20

19

QM

PP

20

20

QM

PP

CSQ

TEL

TSV

Bu

lleti

n

Job

s n

eed

ed

Co

mm

ents

Mackay Entertainment and Convention Centre

Mackay Regional Council

1.2 Mackay Under Construction

✓ ✓ https://www.mackay.qld.gov.au/business/suppliers/tenders_and_purchasing

Majors Creek Solar Project 400MW

Edify Energy 500 Townsville Planned ✓

✓ 400

Construction of a Solar Farm (200 MW). Commencing Q3 2020 to Q3 2021. https://www.townsvillebulletin.com.au/news/wave-of-development-in-townsville-is-set-to-create-1500-jobs/news-story/cecaeca07c3e474c715c53870081fc7e

Marina Residences Maidment Group

50 Townsville Planned ✓

74

Construction of Apartments (16) and Townhouses (11). Commencing Q2 2020 to Q1 2021. Colliers International Townsville agent Neville Smith helped negotiate the sale of the land https://www.townsvillebulletin.com.au/business/developers-say-marina-residences-will-be-best-townsville-has-seen/news-story/859b7e26a932ef64cb2f4b8f29591c69

Mount Isa Electrical Works for Government Sites

0.9 Mount Isa Under Construction

✓ ✓ ✓ ✓ ✓

✓ Maintenance Services for Government Sites

Mount Isa Family Fun Park Upgrade

Mount Isa City Council

51 Mount Isa Committed ✓

The Mount Isa Family Fun Park and surrounds will be significantly upgraded in a $5.1 million project jointly funded by the Queensland Government's Building our Regions program and Council. Stage 2 Redevelopment project of the Family Fun Precinct - which comprises the Family Fun Park, Mount Isa Skate Park and Splashez Aquatic Centre - will improve its usability, functionality and appeal. https://www.northweststar.com.au/story/6770772/51m-upgrade-for-mount-isa-family-fun-park/

Mount Isa to Rockhampton Corridor Upgrade (incl. Yeppoon Road Duplication)

Qld Government & Fed Government

318 Mount Isa Announced ✓ ✓

Mount Isa to Townsville Rail Upgrade

Queensland Rail 380 Mount Isa Credibly Proposed

✓ ✓ ✓ ✓

https://www.townsvillebulletin.com.au/news/upgrade-to-crucial-nq-rail-line-is-reaping-dividends-for-regional-towns/news-story/71eb387c0300fdd40b45de923d3da9a0

Mt Elliot - Swan Project Chinova 1800 Mount Isa Possible ✓

✓ ✓

Open Pit & Underground Mine - Copper/Gold

Mt Louisa Walking Track Townsville City Council

1 Townsville Committed ✓

Part of the Townsville 2020 Masterplan. 1.8km track from end of Bayswater Rd up towards summit of Mt Louisa. It will have 2 viewing platforms. https://www.townsvillebulletin.com.au/news/townsville/worldclass-mount-louisa-walking-trail-to-open-in-july-townsville-city-council/news-story/18eb9f07f1e0317fc6a650efe211e44e

Mt Low Masterplan 450 Townsville Planned ✓

870 Master planned Community.

Page 11: Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

Page 11 of 18 Last Updated 4 June 2020

Pro

ject

nam

e

Pro

ject

Ow

ner

/Sp

on

sor

Pro

ject

Val

ue

$M

LGA

Pro

ject

Sta

ge

19

/20

20

/21

21

/22

22

/23

23

/24

20

19

QM

PP

20

20

QM

PP

CSQ

TEL

TSV

Bu

lleti

n

Job

s n

eed

ed

Co

mm

ents

North Queensland Bio Energy – Ethanol Plant

North Queensland Bio Energy

640 Townsville Under Construction

✓ ✓ ✓

✓ ✓

North Queensland Country Club Resort and Equestrian Centre

Landmark Projects

1000 Townsville Planned ✓ ✓

300

The 440-hectare North Queensland Country Club Resort, to be set in 1000 hectares of private land at Toolakea, will feature 2800 rooms, a country club and an Olympic-standard equestrian centre. It hopes to create 300 direct construction jobs over 25 years and directly employ 3750 people and give the local tourism economy an annual $360 million boost. https://www.townsvillebulletin.com.au/news/townsville/regional/north-queensland-country-club-resort-proposal-near-townsville-moving-forward/news-story/79b68a06dbb75e41fa9c2351c967540a

North Queensland Cowboys Centre of Excellence

North Queensland Toyota Cowboys

50 Townsville Planned ✓ ✓

213

NAIF - Multi-sport training spaces, sports medical and allied health service and community spaces. Commencing Q2 2020. https://naif.gov.au/case-studies/cowboys-community-training-and-high-performance-centre/ https://www.townsvillebulletin.com.au/news/cowboys-40m-high-performance-centre-is-set-for-early-2021-completion/news-story/1edb05c369d144a10eb8a58c75ce09a7 https://www.cowboys.com.au/news/2019/11/12/naif-funding-for-cowboys-community-centre-meets-milestone/

North Rail Yards (Townsville Technology Precinct)

Townsville City Council

50 Townsville Planned ✓

Community Precinct. Expected completion Q4 2020. The North Rail Yards, at the western end of Flinders St, will be turned into the Townsville Technology Precinct, focused on the “emerging software development industry”. https://www.townsville.qld.gov.au/about-council/news-and-publications/media-releases/2019/january/north-rail-yards-redevelopment-on-the-right-track https://www.townsvillebulletin.com.au/news/townsville/north-rail-yards-to-become-townsville-technology-precinct/news-story/e948d8a9858527d0b02756b373841939

Oasis Hub Department of Defence

11.1 Townsville Under Construction

✓ ✓

✓ 450

The Oasis Townsville will provide a one-stop shop for veterans and their families to access assistance from government, health services, ex-service organisations (ESOs) and community groups. It will significantly expand and enhance the existing range of services it already offers. The major building works for the project include a partial demolition of the existing building, refurbishment of the remaining half of the building, construction of an indoor/outdoor café, five smaller buildings and other external works. http://statements.qld.gov.au/Statement/2020/5/14/new-facility-for-the-oasis-townsville-one-step-closer-to-completion https://www.townsvillebulletin.com.au/news/defence/tender-packages-to-be-released-this-week-for-construction-of-the-oasis-townsville/news-story/2f5c145e3095c8059aaa9bb13ecfb8ff https://www.townsvillebulletin.com.au/news/defence/hundreds-of-local-jobs-up-for-grabs-to-build-oasis/news-story/5f46726ef425709c89809d29cc001287

Page 12: Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

Page 12 of 18 Last Updated 4 June 2020

Pro

ject

nam

e

Pro

ject

Ow

ner

/Sp

on

sor

Pro

ject

Val

ue

$M

LGA

Pro

ject

Sta

ge

19

/20

20

/21

21

/22

22

/23

23

/24

20

19

QM

PP

20

20

QM

PP

CSQ

TEL

TSV

Bu

lleti

n

Job

s n

eed

ed

Co

mm

ents

Paluma to Wallaman Falls Trail

Townsville City Council

6 Townsville Planned ✓

Biking Trail.

Pentland Bioenergy Renewable Developments Australia

564 Charters Towers

Committed ✓ ✓ ✓ ✓

500

The Pentland Bio Energy project involves the construction of a purpose-built, fully integrated, energy self-sufficient bio-ethanol production facility on 66,152 hectares of land at Pentland (50 km south-west of Charters Towers). https://www.thechronicle.com.au/news/biofuel-project-to-bring-jobs-boom-to-north-queens/3333838/

Pinnacles Satellite City Development - Masterplan

EJ Cooper & Son 2000 Townsville Possible ✓

9910

Master planned Community including Lavarack Barracks, 5,100 dwellings, town centre and industrial precinct. To commence Q1 2020. https://www.celestino.net.au/pinnacles/residential

Port Carpentaria Railway Carpentaria Rail 1500 Mount Isa/ Cloncurry

Planned ✓

The Port Carpentaria Railway is a $1.5B project aimed at increasing export productivity and lowering export costs from the North West minerals province in an increasingly competitive global market. Carpentaria Rail is an alliance between the local aboriginal native title owners and MIEPCO Pty Ltd. As part of the project the company will undertake an extensive ongoing indigenous training and employment program. MIEPCO is undertaking design and feasibility evaluation works to get the project “shovel ready” prior to seeking major project investment. http://www.carpentariarail.com/

Proserpine Entertainment Centre

Whitsunday Regional Council

10 Whitsundays committed ✓ ✓

https://www.whitsunday.qld.gov.au/683/Proserpine-Entertainment-Centre

RAAF Health Care Facility Department of Defence

11 Townsville Committed ✓ ✓

The facility will include primary care including mental health and rehabilitation, inpatient unit, pharmacy, physiotherapy, dental, general support, external works, airfield response and deployable health accommodation for No. 1 Expeditionary Health Squadron. https://www.defenceconnect.com.au/key-enablers/5312-st-hillier-s-property-secures-contract-for-construction-of-townsville-adf-health-centre

Ravenswood Extension Project

Resolute Mining 200 Charters Towers

Possible ✓ ✓

The Ravenswood Expansion Project is expected to extend the life of gold mining in the region by 10-15 years as well as employ up to 350 people, with 99 per cent of the workforce to be hired locally. The company currently held 1600km of exploration tenements in and around the Ravenswood area which had a “very high gold endowment”. They would also be creating a new tailings facility capable of holding more than 100 million tones of tailings, and the processing plant is expected to go from five million tonnes annually to more than seven million tonnes. https://www.townsvillebulletin.com.au/news/townsville/regional/charters-towers/ravenswood-mine-expansion-will-see-more-jobs-for-locals/news-story/ddf154fb9aeb3e2b8066b1597bccc804

Page 13: Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

Page 13 of 18 Last Updated 4 June 2020

Pro

ject

nam

e

Pro

ject

Ow

ner

/Sp

on

sor

Pro

ject

Val

ue

$M

LGA

Pro

ject

Sta

ge

19

/20

20

/21

21

/22

22

/23

23

/24

20

19

QM

PP

20

20

QM

PP

CSQ

TEL

TSV

Bu

lleti

n

Job

s n

eed

ed

Co

mm

ents

Reef HQ Aquarium Federal Government

26.9 Townsville Planned ✓ ✓ ✓ ✓ ✓

✓ ✓

Upgrade of the coral reef exhibit and turtle hospital. The world’s largest living coral reef aquarium, is due to undergo a four-year Federal Government-funded $26.9 million upgrade from mid-2020. https://www.townsvillebulletin.com.au/news/queensland/reef-hq-in-a-critical-state-of-disrepair-will-shut-for-12-months-for-269-million-upgrade/news-story/c4a7900ded258803e48d4b63831cacd5

Riversleigh Fossil Centre Revitalisation

Mount Isa City Council

1.4 Mount Isa Under Construction

Riversleigh Fossil Centre at Outback at Isa is one step closer to revitalisation as planning ramps up and works begin. The $1.44 million project, 75 per cent of which is funded by the Department of Innovation, Tourism Industry Development and the Commonwealth Games as part of the “Outback Tourism Infrastructure Fund” will be a boost to tourism in Mount Isa. https://www.mountisa.qld.gov.au/news/article/6/riversleigh-fossil-centre-revitalisation-project-update

Riverway Plaza Geon Property 33 Townsville Under Construction

✓ ✓

Shopping centre redevelopment. https://geonproperty.com.au/project/riverway-plaza/

Rollingstone Solar Farm ESCO Pacific 210 Townsville Planned ✓ ✓ ✓

✓ ✓ Construction of a 110MW Solar Farm (400,000 Panels). Project to end Q1 2021.

Roseby Project Universal Resources

164 Cloncurry Planned ✓

282

The project is located in north-west Queensland approximately 65 kilometres (km) north-west of Cloncurry and 90 km north-east of Mount Isa wholly within the Cloncurry Shire. https://www.qld.gov.au/environment/pollution/management/eis-process/projects/completed/roseby-copper-project

Royal Flying Doctor Service funding not secured

2 Townsville Possible ✓

100

Aeromedical Facility - Expansion Applying for BBRF for funding- waiting for outcomes https://www.flyingdoctor.org.au/news/flying-doctor-reveals-townsville-expansion-plans/ https://www.townsvillebulletin.com.au/news/townsville/rfds-ready-to-expand-after-reaching-capacity/news-story/3476fd2efb3305d82c6226c89466605f

Saint Elmo Vanadium Project

Multicom Resources

30 Mount Isa Planned ✓

Open-cut vanadium pentoxide mine. Estimated production of 10,000 tpa with a mine life of 30 years. https://www.mcres.com.au/saint-elmo-project https://www.northweststar.com.au/story/6539191/st-elmo-vanadium-gets-major-project-status/

Page 14: Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

Page 14 of 18 Last Updated 4 June 2020

Pro

ject

nam

e

Pro

ject

Ow

ner

/Sp

on

sor

Pro

ject

Val

ue

$M

LGA

Pro

ject

Sta

ge

19

/20

20

/21

21

/22

22

/23

23

/24

20

19

QM

PP

20

20

QM

PP

CSQ

TEL

TSV

Bu

lleti

n

Job

s n

eed

ed

Co

mm

ents

Salvation Army: Townsville Recovery Services Centre

Salvation Army 1 Townsville Committed ✓

Assessment Centre For Rehabilitation Facility - Single Storey. Q1 2020 to Q2 2020.

Sanctum Residential Development

Maidment Development Group

200 Townsville Under Construction

✓ ✓ ✓ ✓ ✓

✓ 430

Master planned estate with associated community infrastructure. Totalling 1,300 lots, with 700 completed. (TEL Opportunity Townsville North Queensland - Edition 04) https://www.maidment.com.au/sanctum/

Sarina State High School Performing Arts & Sports Centre

Mackay Regional Council

11 Mackay Committed ✓ ✓

http://statements.qld.gov.au/Statement/2019/6/19/budget-delivers-more-than-40-million-for-schools-in-mackay-and-surrounds

Sarsfield Resolute Mining 250 Townsville Prospective ✓

Saxby Project Strategic Energy Resources

30 Possible ✓

Historic drilling at Saxby includes high grade zones of 9m @ 11.27g/t Au and 8m @ 15.1 g/t Au. Strategic Energy Resources will perform further drilling to test continuity and extent. https://www.strategicenergy.com.au/projects/saxby/

SCONI (Norinco) Scandium Project

Metallica Minerals

1300 Townsville Planned ✓ ✓ ✓ ✓

✓ ✓ ✓ ✓ 500

Sconi’s proposed development is based on three pits and a 2 million tonne-per-annum processing plant, with an 18-year mine life and average annual revenue from production estimated at $512 million. Projected to be completed Q4 2023. https://www.townsvillebulletin.com.au/news/townsville/life-of-greenvale-battery-metals-project-extended-to-30-years/news-story/f1b51735c6b11e15fdfca5b7b7289c8c

Sea View Hotel Paul Irvin Hotel Group

8 Townsville Under Construction

Rejuvenation of internal areas, redevelopment of new gaming room, renovation of beer garden, restoration of former public bar, relocation of bottle shop. https://www.townsvillebulletin.com.au/news/townsville/public-bar-of-townsvilles-seaview-hotel-will-be-restored/news-story/7d40c283e712cabcce4f318f30d41b4b

South Beach 5 Townsville Planned ✓

20 Construction of apartments (40) and restaurant complex.

Southern Suburbs New Sewer

Townsville City Council

23 Townsville Committed ✓ 20

Cost: Stage 1 – $10m, Stage 2 – $13m Tender: Stage 1 – Newlands, Stage 2 – BMD The new Southern Suburbs Rising Main will reduce pressure on sewerage and cater for growth. Stage 2 of these works will link the pump in Yolanda Drive, Annandale by installing an 11.15km pipeline. The project was expected to create 20 local jobs. The Queensland Government provided $5 million towards the project.

St Francis School Catholic Education

2 Burdekin Committed ✓

St Patrick's College St Patrick's College

15 Townsville Under Construction

✓ ✓

Performing arts, library and learning facility.

Steam Hub 80 Townsville Planned ✓

Alterations & Additions to the Science, Technology, Engineering, Arts & Mathematics precinct.

Page 15: Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

Page 15 of 18 Last Updated 4 June 2020

Pro

ject

nam

e

Pro

ject

Ow

ner

/Sp

on

sor

Pro

ject

Val

ue

$M

LGA

Pro

ject

Sta

ge

19

/20

20

/21

21

/22

22

/23

23

/24

20

19

QM

PP

20

20

QM

PP

CSQ

TEL

TSV

Bu

lleti

n

Job

s n

eed

ed

Co

mm

ents

Strand Lagoon Townsville City Council

85 Townsville Possible ✓ ✓

The ‘Townsville 2020’ Master Plan identified that safe all-year round water-based activities located on the Strand would redefine and enhance the city and provide a definitive local, domestic tourist attraction and statement. (TEL Opportunity Townsville North Queensland - Edition 04) The prospective lagoon will cover a total area of 10.5 hectares, and it will offer a wide variety of leisure activities and water sports, such as kayaking, paddle boarding, and swimming. On hold https://www.townsvillebulletin.com.au/news/townsville-mayor-says-strand-turtles-must-be-preserved/news-story/acb0f952427952f5641b577bb3a60810

Stuart Cell 3A - new landfill cell

Townsville City Council

5 Townsville Under Construction

The Stuart Landfill Cell 3A project is located at Council’s Stuart Landfill facility south of Townsville adjacent the Bruce Highway, off Vantassel Street. Valued at $4.7M, the project is required to provide the facility with additional landfill capacity to meet the needs of the city. http://www.mendi.com.au/project/stuart-landfill-cell-3a/

Sun metals Zinc Refinery Stage 2

Sun Metals 300 Townsville Under Construction

✓ ✓

✓ ✓ ✓

✓ 374

Zinc Refinery Expansion. "The expansion would … mean an additional $300 million invested in Townsville and is expected to support up to 827 construction jobs during peak construction, also with significant increase in permanent workers at the refinery and across Sun Metals. The expansion would also see an increase in economic activities for Townsville, with significant increase in Townsville Port activities, uplift for local suppliers and contractors and also, via use of new refining technology, reduced water usage and environmental footprint.” https://www.townsvillebulletin.com.au/business/premier-heading-overseas-to-talk-sun-metals-expansion/news-story/51932b47b76b8b568d15bc7627bc158d

Tec-NQ Student Accommodation

Tec-NQ 7 Townsville Committed ✓ ✓ ✓

Tec-NQ Beachside is a welcoming and nurturing boarding facility housing up to 33 boarders. The safe and secure facility is located in North Ward close to shops and The Strand in sunny, tropical Townsville. https://www.tecnq.com.au/accommodation

The Hive Gleeson Group 450 Townsville Planned ✓ ✓ ✓ ✓

561

Mixed Use Development including residential, commercial and cultural precinct to include Concert Hall, Convention Centre, indigenous Art Gallery and performance space. https://www.thehivetownsville.com.au/

The Village Enviro Development Queensland

163 Townsville Under Construction

✓ ✓ ✓ ✓ ✓

✓ 350

83ha residential development with plans for approximately 1,000 homes. Stages 1–6 and 10 completed. Stage 7 and 12 commenced. (TEL Opportunity Townsville North Queensland - Edition 04) https://www.thevillagetownsville.com.au/

Page 16: Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

Page 16 of 18 Last Updated 4 June 2020

Pro

ject

nam

e

Pro

ject

Ow

ner

/Sp

on

sor

Pro

ject

Val

ue

$M

LGA

Pro

ject

Sta

ge

19

/20

20

/21

21

/22

22

/23

23

/24

20

19

QM

PP

20

20

QM

PP

CSQ

TEL

TSV

Bu

lleti

n

Job

s n

eed

ed

Co

mm

ents

Tobruk Memorial Baths Redevelopment

Townsville City Council

11.3 Townsville Under Construction

Restoration of the Tobruk Memorial Baths including new eight lane pool, new toddler pool and improved disability access. Commenced Aug 2019, due for completion in April 2020. https://www.townsville.qld.gov.au/building-planning-and-projects/council-projects/tobruk-pool-redevelopment

Townsville Airport Redevelopment

Qld Airport Ltd 80 Townsville Planned ✓ ✓ ✓

✓ ✓ ✓ 207

Redevelopment of Townsville Airport. Excepted end date Q4 2023 Upgrade works would include refurbishment of the terminal, construction of a new terminal roof and new water fire and waste facilities. https://www.townsvillebulletin.com.au/news/major-80-million-townsville-airport-redevelopment-hits-milestone-with-naif/news-story/a310afb00a706219b7c4afea17524cbb

Townsville Eastern Access Rail Corridor

TMR 700 Townsville Planned ✓

The TEARC project is a proposed 8.3km rail freight line which would connect the North Coast rail line directly into the Port of Townsville through the Townsville State Development Area via a path parallel to the Port Access Road. The project is a proposed 8.3km rail freight line connecting the North Coast rail line directly into the Port of Townsville. https://www.tmr.qld.gov.au/Projects/Name/T/Townsville-Eastern-Access-Rail-Corridor.aspx

Townsville Flood Recovery 1500 Townsville Under Construction

✓ ✓ ✓

✓ 680 Q1 2019 to Q2 2021

Townsville Marine Tourism Precinct

Honeycomb property & Sealink

72 Townsville Committed ✓ ✓ ✓

Reclamation and development of approximately 34 hectares of land for marine-dependent industries. Project scheduled for 2020/2021, due to start May/June. On Hold** https://www.statedevelopment.qld.gov.au/assessments-and-approvals/townsville-marine-precinct.html https://www.ditid.qld.gov.au/our-work/attracting-tourism-fund/townsville-marine-tourism-precinct

Townsville Mater Hospital Carpark

Mater Townsville Committed ✓

400 space carpark. https://www.townsvillebulletin.com.au/news/20m-naif-funding-to-fix-parking-woes-at-townsville-mater-private-hospital/news-story/ee94a5b403f4b04bafdc9c54b419296e

Townsville Mater NQ Specialist Centre

PDS Qld 25 Townsville Planned ✓ ✓ ✓

Mater Private Hospital Townsville has commenced delivery of a 10-year Master Plan to enhance the health care services for the communities of the North Queensland region. The construction of the specialist centre is scheduled to start in August. https://www.matertsv.org.au/page/about-us/our-story/hospital-redevelopment https://www.townsvillebulletin.com.au/business/healthy-interest-expressed-in-townsville-specialist-centre/news-story/850344b39065900f42f6cdac2328383b

Townsville Ore Processing Facility

Pure Minerals 416 Townsville Possible ✓

532

Refinery - Nickel sulphate, Cobalt sulphate, Hematite, Alumina, Magnesium Project scheduled for Q3 2020 to Q4 2025 https://www.pureminerals.com.au/qpm/

Page 17: Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

Page 17 of 18 Last Updated 4 June 2020

Pro

ject

nam

e

Pro

ject

Ow

ner

/Sp

on

sor

Pro

ject

Val

ue

$M

LGA

Pro

ject

Sta

ge

19

/20

20

/21

21

/22

22

/23

23

/24

20

19

QM

PP

20

20

QM

PP

CSQ

TEL

TSV

Bu

lleti

n

Job

s n

eed

ed

Co

mm

ents

Townsville Port Expansion Project

Qld Government

1600 Townsville Committed ✓ ✓

Expansion of the Port of Townsville to accommodate forecast growth in trade at the port and address current capacity constraints. Planned completion by Q4 2040. http://statedevelopment.qld.gov.au/assessments-and-approvals/townsville-port-expansion.html

Townsville Port Expansion Project – Channel Capacity Upgrade

Qld Government

193 Townsville Under Construction

✓ ✓ ✓ ✓

✓ ✓ 120

The Channel Upgrade will be delivered over a period of six years from 2018 to 2023. Under the delivery schedule, it will create 120 FTE jobs in Townsville during construction and support 245 Full Time Equivalent jobs in Queensland. https://www.townsville-port.com.au/infrastructure/infrastructure-projects/channel-upgrade/project-schedule/

Townsville Port Expansion Project – Outer Harbour Expansion (berths 14+15)

Qld Government

200 Townsville Prospective ✓ ✓

Townsville Port Freight Terminal

Qld Government

48 Townsville Committed ✓

50

Open Cut Underground Mine - Thermal Coal. https://www.townsville-port.com.au/townsville-port-welcomes-pit-to-port-rail-freight-initiatives/ http://statements.qld.gov.au/Statement/2019/6/9/mount-isa-line-plan-puts-north-west-minerals-freight-on-fast-track

Townsville Port upgrades Qld Government

Townsville Under Construction

✓ ✓

Berth 10: Design of the works is completed, and tenders have been called. Construction is scheduled to start early 2020. Berth 4 and cargo terminal: Construction is underway and is scheduled to be completed by end of 2020. Truck staging area: Design of the works is expected to be completed in 2019 with construction scheduled to start early 2020. https://www.townsvillebulletin.com.au/news/townsville-port-to-extend-car-carrier-berth-for-larger-ships/news-story/97b093eea478170dd2ad8f28a72d83b0 https://www.townsville-port.com.au/infrastructure/infrastructure-projects/

Townsville Ring Road stage 5

Qld Government & Fed Government

230 Townsville Planned ✓ ✓ ✓

✓ ✓ ✓

The $230 million TRR5 project is jointly funded by the Australian and Queensland governments on an 80:20 basis under the 15-year, $12.6 billion Bruce Highway Upgrade Program. The Australian Government has committed $184 million and the Queensland Government has committed $46 million to deliver the TRR5 project. The Townsville Ring Road link is a 22-kilometre section of the 36-kilometre Bruce Highway route through Townsville, forming part of the National Highway which is Queensland's primary freight, passenger and tourism corridor. It also connects Townsville’s suburbs to key employment nodes and essential services. https://www.tmr.qld.gov.au/Projects/Name/T/Townsville-Ring-Road-Stage-5-project

Page 18: Construction Projects in the Townsville and North West ... · 4/6/2020  · Calcium Cattle Holding Facility Woodstock Pastoral Services Approved The project has the capacity to accommodate

Page 18 of 18 Last Updated 4 June 2020

Pro

ject

nam

e

Pro

ject

Ow

ner

/Sp

on

sor

Pro

ject

Val

ue

$M

LGA

Pro

ject

Sta

ge

19

/20

20

/21

21

/22

22

/23

23

/24

20

19

QM

PP

20

20

QM

PP

CSQ

TEL

TSV

Bu

lleti

n

Job

s n

eed

ed

Co

mm

ents

Townsville to Roma Corridor Upgrade

Qld Government & Fed Government

125 Townsville Announced ✓

Tropical Marine and Aquaculture Research Centre

Qld Government & Fed Government

100 Townsville Possible ✓ ✓

1547

An international marine research precinct that would promote advancements in marine and aquaculture commercialisation, research and innovation. This will enable infrastructure to underpin regional capabilities to ensure our marine industry is able to grow competitively and sustainably. (TEL Opportunity Townsville North Queensland - Edition 04)

Walford Creek Base Metals Project

Aeon Metals 785 Doomadgee Planned ✓

Open Pit Mine The Walford Creek Project is located approximately 350km north west of Mount Isa in Northwest Queensland, close to the Northern Territory border. The closest town is Doomadgee, approximately 70km to the east, which is accessed by a sealed road from Cloncurry. Doomadgee has a commercial airstrip connecting to other major centres within Queensland. https://www.aeonmetals.com.au/walford-creek/

Westmoreland Project Laramide 411 Possible ✓

262

Open Cut Mine - Uranium The Westmoreland Uranium Project, that is able to be developed as an open cut mining operation, is currently at an advanced exploration and development stage, as significant work in these areas has been carried out in the past by the project's former owner Rio Tinto. Located about 400km north our Mount Isa on the border of Queensland and Northern Territory border. http://mininglink.com.au/site/westmoreland

Whitsunday Shores Greater Rewards Group

900 Mackay Whitsundays

Committed ✓

112 Construction of residential dwellings (1800), aged care living precinct, childcare centre, sporting fields, community club house and tavern

Yepoon to Mount Isa Roadwork

190 Mount Isa Possible ✓

https://www.i-q.net.au/main/government-unveils-730m-road-plan-to-upgrade-700km