18
+381 11 377 47 67 I www.teamenergo.com Teamenergo engineering for life constructing planning logistics CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION LINES AND SYSTEMS PROJECTS IN SERBIA, BOSNIA AND HERZEGOVINA, MONTENEGRO AND GERMANY NUMBER OF EMPLOYEES – 122 HEADQUARTERS – BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

+381 11 377 47 67 I www.teamenergo.com

Teamenergoengineering for lifeconstructing planning logistics

CONSTRUCTION OF ELECTRICALAND TELECOMMUNICATION LINES AND SYSTEMS

PROJECTS IN SERBIA, BOSNIA AND HERZEGOVINA, MONTENEGRO AND GERMANY

NUMBER OF EMPLOYEES – 122

HEADQUARTERS – BELGRADE, ZEMUN

ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNEROF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

Page 2: CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

Integratedmanagementsystem

TEAMENERGO

HAS IMPLEMENTED

INTEGRATED MANAGEMENT SYSTEM

• Quality Management System ISO 9001:2008

• Environmental Management System ISO 14001:2004

• Health and Safety Management System OHSAS 18001:2007

• Business Continuity Management System ISO 22301:2012

• Information Security Management System ISO 27001:2013

• Energy Efficiency Management System ISO 50001:2011

For designing and construction of insfrusture facilities in the areas of

telecommuniaction, water, construction, power and gas systems

Page 3: CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE
Page 4: CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

SERVICES

• Consulting

• Designing and Construction of electrical

and telecommunication infrastructure

• Maintenance of electrical

and telecommunication infrastructure

• Technical Support 24x7

• Project Management

Page 5: CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

ENGINEERING EXPERTISETelecommunications, Traffic & Energy Systems

Page 6: CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

LICENCES

Local, regional and internationally

important licences for operators, railways,

airports and enterprise sector issued by

Ministry of Construction, Transport and Infrastructure

of the Republic of Serbia.

Page 7: CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

INFRASTRUCTURE CONSTRUCTION

FIXED NETWORKS

CONSTRUCTION WORKS

• Optical metro networks

(FTTH / FTTB) and All IP networks

• Transport and access networks

TRAFFIC SOLUTIONS & SERVICES(RAILWAY, ROAD, AIR)

• ITS and smart Cities

• Contact & Signaling networks

• Communication infrastructure & systems

(Two way radio, Intercom systems, VCS…)

• Radars, Air control systems…

ELECTRO ENERGY INFRASTRUCTURE CONSTRUCTION WORKS

• Installation works for public buildings, hotels, shopping malls

• Transmission lines and substations (voltage level up to 35kV)

• Monitoring and control systems for electricity networks (SCADA)

• Construction of ADSS network & public lighting

Page 8: CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

RESOURCES

122 EMPLOYEES

• 16 engineers from various

technological backgrounds

• 42 technicians

(low and high current)

• 17 Technicians certified

for work-at-height

• 47 others

EQUIPMENT

• The latest machinery,

equipment, instruments

and tools for quality service

providing in segments of building

of infrastructure, measuring, examining and commissioning.

Page 9: CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

TELECOMMUNICATION &ELECTRIC POWER NETWORKS

References

Page 10: CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

• Electric-installation works on 35kV cable line from• TS 35/10kV Industrial Park to TS 35/10kV "Pirot2“ for Jugoistok

• Reconstruction & building of power line 10kV 5 km long• (Stara Planina – Meždreja – Crni Vrh) for Jugoistok

• Building of ADSS network cables between TS 35/10kV Leskovac 6 to Administrative building for Jugoistok

• Installation of double line 10kV including connection and accompanying works near Adrovac for Jugoistok

CONSTRUCTION AND

MAINTANCE

ELECTRIC NETWORK

Reconstruction of Students apartments „Mika Mitrović“Belgrade for the students with special needso Building 5700 m2o Entire installation of low and high voltage power supply with

the delivery and installation of equipment and material

Page 11: CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

• Construction of access power line10/0,4kV with polesubstation of 400kVA in Slanci for Electrodistribution Belgrade

• Installation and connection of MBTS 630 KVA at 39 VojvodeVlahovića Street Electrodistribution Belgrade

• Construction of power facility of voltage level up to 10kV (> 50 facilities commissioned) for Electrodistribution Belgrade

• Maintenance of power facilities up to 35 kV (city network) for Electrodistribution Belgrade

• Reconstruction of power lines on the location Tegovište Mrtvica(installation of new wood- impregnated poles L=12m) for ED Vranje

CONSTRUCTION AND

MAINTANCE

ELECTRIC NETWORK

Page 12: CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

• Reconstruction and refurbishment of power installationmaking new power racks, installation and commissioning of UPS device for Nikola Tesla Belgrade Airport

• Construction of street lights on ring roads Bujanovac 1 (Corridor X) for Srbijaautoputevi

CONSTRUCTION AND

MAINTANCE

ELECTRIC NETWORK

Construction of power installationon runaway for Vršac Airport

Page 13: CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

CONSTRUCTION OFCOMMUNICATIONNETWORKS

• Construction of 300 km of

fiber optic infrastructure for

telecom operators

(Telecom Serbia, M:Tel,

Targo Telekom, VIP mobile)

o Construction of 12.000 users access

network for Telecom Serbia

o Maintenance of Telekom Srbija network

in Belgrade ( 600.000 users)

o Construction of micro-tranches for

housing cables of smaller capacity for

connecting users to optic metro network

(FTTH/FTTB/FTTC)

FIXED LINE ETWORKS

Page 14: CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

CONSTRUCTING OFFIBER OPTIC METRONETWORK

BELGRADE

Page 15: CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

THE FIXED TELEPHONE NETWORK

MODERNIZATION TELEKOM SRBIJA

• Optical access (FTTH) for a large number of customers, primarily in urban settings

• National coverage• User bitrates may reach up

to 1Gb/s

• Site survey Design documentation

• Building Permits• Construction works,

laying of optical cables and PE tubes

• FTTH components installation, IPAN SW, system commissioning

• As-build design

ALL IP – FTTH – FTTx Investor-

Huawei (Telekom Srbija)TURNKEY SERVICES

Page 16: CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

• Construction of signaling network• Fiber optic cable installation• Level crossing civil works• Reconstruction of building stations

SIGNALING TELECOMMUNICATION

SYSTEM ALONG RAILWAY

LINE - BOSNIA

RAILWAY BOSNIA

Page 17: CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

CERTIFIED PARTNERS

AND KEY CLIENTS

Page 18: CONSTRUCTION OF ELECTRICAL AND TELECOMMUNICATION … · HEADQUARTERS –BELGRADE, ZEMUN ESTABLISHED IN JANUARY 2014 AS A TECHNOLOGY PARTNER OF TELEGROUP SYSTEM WITH 20+ YEARS EXPERIENCE

THANK YOU!

MIJE ALEKSIĆA 43a

11283 BEOGRAD- ZEMUN

Tel: +381 11 3774 767

Fax: +381 11 406 52 49

mail: [email protected]

web: www.teamenergo.com