18
CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz Road BMS House Dagenham RM10 8PS May 2021

CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

   

CONSTRUCTION MANAGEMENT PLAN  

For the works at  1 Wantz Road BMS House Dagenham RM10 8PS    May 2021 

Page 2: CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

Contents    1. Introduction 2. Contact List 3. Programme 4. Hours of Work 5. Site Location 6. Security 7. Site Access 8. Deliveries 9. Storage of Materials 10. Waste Management 11. Asbestos 12. Environmental Design Control Measures 13. Environment Control Measures 14. Dust & Air Quality 15. Lighting / Noise                  

Page 3: CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

1. INTRODCUTION 

This  Construction  Management  Plan  (CEMP)  and  SWMP  has  been  prepared  by  Texo Construction  Ltd,  in  to  satisfy  the  requirements  of  Planning  Condition  23  as  determined  by Barking and Dagenham Area Planning Committee in relation to the conditional Permission for Development reference 16/00981/FUL.  This document sets out the management measures that the Contractors are required to adopt and implement for the construction of the Proposed Development at WANTZ RD BMS HOUSE DAGENHAM RM10 8PS  Planning  Condition  23  states:    No  development  shall  commence,  including  any  works  of demolition,  until  a  Construction  Environmental Management  Plan  (CEMP)  and  a  Site Waste Management  Plan  (SWMP)  have  been  submitted  to  and  approved  in  writing  by  the  Local Planning Authority. These Plans shall incorporate details of:  a. Construction traffic Management; b. The parking of vehicles of site operatives and visitors; c. Loading and unloading of plant and materials; d. Storage of plant and materials used in constructing the development; e. The erection and maintenance of security hoardings(s)  including decorative displays and 

facilities for public viewing, where appropriate; f. Wheel washing facilities; g. Measures to control the emission of dust, dirt and emissions to air during construction; such 

measures to accord with the guidance provided in the document "The Control of Dust and Emissions during Construction and Demolition", Mayor of London, July 2014; including but not confined to, non‐road mobile machinery (NRMM) requirements; 

h. Noise and vibration control; i. A  scheme  for  recycling/disposing  of  waste  resulting  from  demolition  and  construction 

works; j. The use of efficient construction materials; k. Methods to minimise waste, to encourage re‐use, recovery and recycling, and sourcing of 

materials; and l. A nominated Development/Resident  Liaison Representative with an address and contact 

telephone number to be circulated to those residents consulted on the application by the developer's representatives. This person will act as first point of contact for residents who have any problems or questions related to the ongoing development. 

Once approved the Plans shall be adhered to throughout the construction period.  Contractors are required to operate an induction scheme to ensure that all site operatives are aware of the site rules and their environmental responsibilities, to identify training needs  for personnel  and  to  provide  appropriate  training.  The  training  is  to  include  talks  for  site operatives to maintain an appropriate level of awareness of environmental issues. 

Page 4: CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

 All  works  undertaken  are  to  comply  with  the  Construction  (Design  and  Management) Regulations 2015.  All works are to comply with Policies 7.14 and 7.15 of the London Plan and all relevant policies 

of  the  Core  Strategy  with  Detailed  Policies.  Suitable  measures  are  to  be  adopted  for  the 

protection of trees and their root systems if affected by the works.  

For the purposes of pricing, the information and stipulations contained within this document and its appendices are to be considered the minimum acceptable. However, for the purposes of economy any divergence is to be suitably notified to the Contract Administrator with sufficient supporting  information.  Any  divergence  is  to  be  approved  in  writing  by  the  Contract Administrator and Project Manager.  On issues regarding demolition within the appendices, the method statement of the demolition contractor is superior to and supersedes any other references within the Construction Logistic Plan. All other stipulations regarding demolition and resultant site waste within the body of this document and other appendices are to be adhered to.

Page 5: CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

2. CONTACT LIST  

Principle     

Contractors Name  Texo Construction Ltd 

Name   

Telephone  020 3876 9092

Email 

 

Site Manager   

Contractors Name  Texo Construction Ltd 

Name   

Telephone  020 3876 9092 

Email   

   

Project Manager   

Contractors Name  Texo Construction Ltd 

Name  Matthew Sayer 

Telephone  020 3876 9092 

Email  [email protected] 

   

Quantity Surveyor   

Contractors Name  Texo Construction Ltd 

Name  Dermot Forkan

Telephone  020 3876 9092

Email  [email protected]

 

Architects   

Contractors Name  Front Architecture 

Name  Daniel Cross 

Telephone  01702 831415 

Email  dcross@front‐architecture.co.uk 

   

Structural Engineers   

Contractors Name  TBC 

Name  TBC 

Telephone  TBC 

Email  TBC 

   

Resident Liaison Officer   

Contractors Name  Texo Construction Ltd 

Name  Matthew Sayer

Telephone  020 3876 9092

Email  [email protected]

Page 6: CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

3. PROGRAMME  CONSTRUCTI ON PROGRAMME  The Project is to be completed under a JCT Design and Build form of contract with design due to commence in 2021.  The onsite works due to last in the region of 78 calendar weeks.  Construction Programme is provided upon request.  Sub‐Contractors will be required to provide short term programmes throughout the project to demonstrate  compliance with the overall Construction  Programme but also to demonstrate the planning of their works.  4. HOURS OF WORK  The operational hours on site will be between the hours of 0800 to 1700 Monday to Fridays and 0900 to 1300 hours on Saturday  Deliveries shall take place between Monday to Fridays, outside the hours of 0900 to 1330 hours and 1500 to 1700 in line with the conditions attached to the planning permission.  5. SITE LOCATIONS  Location including motorways  

Page 7: CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

DETAILED LOCATION PLAN 

 The site  is  located at  the  junction of Oxlow Land and Wantz Road which can be accessed via Oxlow Lane through the main entrance.  Contractor’s parking and storage spaces will be provided within the footprint during demolition and works  thereafter. Deliveries  and waste  removal  and  site  accommodation/welfare will  be provided within the site foot print.  Welfare will be in accordance with HSE Guidance ACOP L24.  6. SECURITY  Boundary Protection   The existing fencing is to be demolished and hoarding provided where natural protection 

to  boundaries  does  not  occur.  All  hoardings will  be  suitably  designed by  a  temporary structure designer, height will be no less than 2400mm. 

  The hoarding will not enter the public footpath and will remain within the site footprint. 

Notice will be given to the Highway Authority if the hoarding abuts the footpath and a hoarding licence is required.   

 

Page 8: CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

Where  hoarding  is  adjacent  to  the  highways,  they  will  be  designed,  erected  and dismantled by a competent contractor in accordance with current legislation.  

Consideration will be given to the use of a wireless and monitored CCTV system.  

The Site boundary will be sufficiently lit to allow cameras to pick up any breaches of the boundary. 

“KEEP OUT” warning signs will be placed at the boundary at regular intervals.  

GATES/VEHICLE ACCESS   Metal gates will provide access control to the site. 

  Gates will be kept locked at all times; signage will be placed on the gate to allow the gate 

controller to be contacted.  

Gates will open inwards to the site and allow for vehicles to pull off the road.  

Appropriate  visibility  displays will  be maintained  to  ensure  the  safety  of  vehicles  and pedestrians.  

7. SITE ACCESS  Traffic Management Plan to be provided.  8. DELIVERIES  Deliveries to site are arranged as on time and will be on a 30 min. turnaround from arrival to departure, where this is not possible, full or part road closures may be applied for in advance.   All vehicles will enter and exit the site via Wantz Road, lorries entering the site to clear 

debris arising from the piling and ground works will enter the site and follow the one‐way system illustrated by signage and show the route to egress site.  

Booking systems will not be required as the deliveries are to be on a turnaround basis.  

Where possible deliveries will be made in bulk to minimise the impact on the local area.  

Loading,  unloading,  turning  and  deliveries,  the  site  will  mainly  be  accessed  from  the direction shown on the traffic management plan (appendix 1 logistics plan). All vehicles are required to leave the site in forward gears where possible.  

The loading and unloading will be on timed deliveries, adhering to a turnaround on‐site arrangement. These vehicles will be clear of the public highway, where this is not possible, 

Page 9: CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

part or full road closures will be applied for on Wantz Road or Oxlow Lane, this will be subject to the Highways Officer preference.  

The project will mainly consist of deliveries for plasterboard and studs, mechanical lifting will be required as part of the delivery and a forklift will be available on site.  

Small skips will come to and from the land opposite the site averaging 2 per week for the duration of the project.  

Groundworks are limited with the majority of the waste deriving from the pile arisings. Grab lorries will be used where possible to remove spoil.  

Pedestrians will be encouraged  to use  the pavement opposite  the  site entrance when vehicles  need  access,  temporary  signs  will  be  located  at  crossings  prior  to  the  site entrance before deliveries to give prior warning to foot traffic.   

9. STORAGE OF MATERIALS  As we will be operating a delivered‐on ‐time approach, there will be a reduced need to store materials on site.   Plasterboard will form the bulk of the deliveries. Arrangements to ensure a full delivery 

of plasterboard will made available via crane or hoist.   Structural Steel will be required for the installation which is to be lifted via crane or hoist 

to position.  

Once demolition is completed the site foreman will be tasked to mark‐up a designated area in which a mobile cabin will be placed to allow for storage.  

ARRANGEMENT FOR PARKING OF CONTRACTORS VEHICLES  

A designated parking will be allocated within the site footprint once demolition is completed. Paid  parking  is  also  located  to  the  rare  of  the  petrol  station  located next to the site for use.

 WHEEL CLEANING ARRANGEMENTS   Wheel washing will be considered to minimise materials onto the main highway. At 

the  point  of  traffic  route  exit  from  site,  an  area  and  resource will  be provided  to ensure adequate vehicle cleaning takes place. 

 PERSONNEL ACCESS  

Page 10: CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

Access will be provided off Wantz Road via a pedestrian gate.   Access will be restricted via a numerical coded lock. 

  Access to areas of the building at height will be made available through the provisions 

of a tube and fitting designed scaffold.  

The scaffold will be designed in accordance with TG20:13 NASC and will be suitably designed to provide access and egress to site.  

10. WASTE MANAGEMENT  General construction waste;   12‐yard skips will be provided within the boundary of the land opposite the site for 

timber, Plasterboard, Metal, Recyclable Plastics, wood and general rubble.  

8‐yard skips for metal scraps/waste will be provided on the land opposite the site.  

11. ASBESTOS   Prior to the commencement of construction works all asbestos will be removed from 

site.  12. ENVIRONMENTAL DESIGN CONTROL MEASURES 

  Materials Storage areas designated for  stockpiling of  friable materials or materials 

susceptible  to  generating wind  borne  dust  will  be  positioned away from  sensitive receptors, where possible. As  far  as  is  reasonably practicable, stockpiles  intended for long‐term storage will be placed directly in their planned position rather than via temporary  storage  to  avoid  the  need  for  double  handling  that  could  give  rise  to emissions.  

Stockpiles  of  materials  that  are  consumed  as  part  of  a  construction  process  will  be assessed to determine the necessity  for dust suppression techniques to minimize dust generation. In each case, stockpiles will be shaped to avoid steep sides and sharp edges so as to reduce entrainment of dust by exposure to wind.  

Site  Area,  all  construction  work  activities  will  be  undertaken  within  the  designated construction site boundaries;  including areas designed to accommodate stockpiles and haul routes.  

Erection of physical barriers where appropriate, physical barriers will be erected around particularly dust generating activities. 

Page 11: CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

  Training all site personnel will receive training appropriate to the nature of their roles and 

responsibility; the training will  include specific information in relation to the air quality management. All staff will receive induction training that will incorporate environmental awareness training and specific training in relation to air quality if their work activities are assessed as potentially producing fugitive emissions on site.  

Tool  box  talks  training  will  enable  site  workers  to  understand  how  their  actions  will interact  with  the  environment  and  potentially  impact  upon  a  work  area’s  sensitive receptors.  

13. ENVIRONMENTAL CONTROL MEASURES   Following mitigation measures will be implemented to limit emissions from construction 

plant and equipment used.   Engines of vehicles and equipment shall not be left running unnecessarily. 

  Vehicles  and  equipment  shall  be maintained  by  a  programme  of  routine  servicing  in 

accordance with  the manufacturer’s  recommendations, with  records kept of  the work undertaken.  

Haul  routes  shall  be  located  and  equipment  operated  away  from  sensitive  receptors, where possible, including but not limited to houses and commercial properties.  

Avoid the use of diesel‐ or petrol‐powered generators and use mains electricity or battery powered equipment where practicable.  

All non‐road mobile machinery shall use fuels with sulphur content equivalent to ultra‐low sulphur diesel fuel meeting the specification within EN590:2004.  

Measures will be implemented to ensure that all diesel fuel used on‐site shall be ultra‐low  sulphur  diesel  (ULSD)  (<10mgS/kg).  The  measures  to  ensure  only  ULSD  fuel  is procured for use on‐site shall include the issue of written instructions to all contractors and audits/inspections of fuel delivery dockets.  

Diesel fuelled construction vehicles travelling off site shall also use ULSD.  

Dust  and  Particulate  Control  Measures  the  following  control  measures  will  be implemented to minimise dust and particulate generation and dispersion:  

The burning of material and or waste on‐site shall be strictly prohibited;  

Page 12: CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

Ensure an adequate supply of water and means of deployment  is available at all work areas for dust suppression measures;  

Dispose  of  runoff  water  from  dust  suppression  activities  in  accordance  with  the appropriate  legal  requirements  such  as  discharge  consents  and/or  surface  water discharge consents as appropriate;  

Maintain  all  dust  control  equipment  in  good  condition  and  record  maintenance  and servicing activities; 

  Keep site fencing, barriers and scaffolding clean using wet methods; 

  not blowing with compressed air lines etc.; 

  Provide easily cleaned hard standing for vehicles as appropriate; 

  Ensure regular cleaning of hard standings using wet sweeping methods; 

  Avoid dry sweeping of large areas; 

  Provide and ensure the use of wheel wash facilities near the site exit wherever there is a 

potential for carrying dust or mud out   of the work areas onto the public highways;   Ensure wheel wash facilities are fitted with rumble grids to dislodge accumulated dust 

and mud prior to leaving the work sites wherever there is a potential for carrying dust or mud out of the work areas; 

  Vehicles  and  equipment  shall  be maintained  by  a  programme  of  routine  servicing  in 

accordance with the manufacturers‟ recommendations, with records kept of the work undertaken; 

  Haul  routes  shall be  located and equipment operated awa y  from sensitive  receptors, 

where possible, including, but not limited to, houses and commercial properties;  

Avoid the use of diesel‐ or petrol‐powered generators and use mains electricity or battery powered equipment where practicable; and 

  Only use road vehicles that meet a minimum of Euro 4 standards during the works as set 

out in the EC Directive 98/69/EC.  

It is not anticipated that odour generation will be significant during the construction of the Authorised Project. However, we will adopt measures as appropriate  to avoid  the generation of odours. These measures will include, but not necessarily be limited to: 

 

Page 13: CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

Covering containers holding waste and regularly removing waste containers from site;   Careful programming to minimise the duration of work with potential to generate odour 

nuisance, including but not limited to that on sewers;   Removing odour generating materials sources in a timely fashion to limit the formation 

of odours;  Where odour forming materials are encountered and cannot be removed or avoided, the 

spraying with an approved oxidising agent will be undertaken to minimise the potential for release of odour; and  

Use of a n odour guard or masking agents will also be considered in situations where the risk of odour release cannot be eliminated or controlled.  

14. DUST AND AIR QUALITY   The dust inspections outlined below will be applied and undertaken by Site Environmental 

Engineer or nominated competent person.   Records  of  inspections  will  be  maintained  within  the  relevant  site  office.  The  dust 

inspections will include the following elements:  

Record all inspections of haul routes and any subsequent action in the dust log pro‐forma at least once per day;  

Conduct inspections to monitor compliance with dust control procedures in accordance with  the  measures  outlined  within  this  CoCP.  Record  the  results  of  the  inspections, including nil returns, in the dust log pro‐forma at least once per day;  

Increase the frequency of site inspections when activities with a high potential to produce dust are being carried out and during prolonged dry or windy conditions; and record any exceptional occurrences causing dust episodes on or off the site and the action taken to resolve the situation. 

  RELEVANT REQUIREMENT   Details of air quality monitoring  for  the HPC development  site  (Work No. 1A)  shall be 

developed prior to the commencement of construction works, pursuant to Requirement MS1B Air Quality Monitoring Scheme, as follows: 

  Project wide Requirement P30 No Burning of Materials (G10) requires that there shall be 

no burning of materials or refuse on the site a t any time during the construction of the Authorised Project. 

Page 14: CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

  Every  effort  is  to  be  made  to  minimise  noise  and  vibration  in  accordance  with  best 

practice  guidance  BS  5228‐1:2014.      All  equipment will  be  provided with  appropriate attenuation. 

 15. LIGHTING/NOISE   Lighting will be provided to the site to ensure a safe working environment. 

  Sub‐Contractors will be required to provide task specific lighting. 

  Power will be provided by Texo Construction to each floor.   Where possible rechargeable, 

wire free lighting will be preferred.  LIGHTING NUISANCE   Careful  consideration  and  design will  be  given  to  the  external  lighting  to  ensure  that 

neighbours are not disturbed.   Where a crane is to be provided suitably designed lighting will be provided. 

  Where scaffolding is erected over a pavement, suitable lighting will be provided to ensure 

pedestrian and workers safety. Lighting should not be excessive so to cause nuisance to neighbours, plant operators or vehicle driver. 

A summary of worst‐case noise emissions for each discreet phase of works described have been predicted on the basis of the proposed equipment, relevant noise data provided in BS5228 and the  advice  of  the  building  contractor  with  regard  to  number  of  items  in  use  and  likely operational ‘on times. This is summarised in the table below  Please  note  that  the  ‘on‐‐‐time’  represents  the  actual  time  that  the  noise  source  is  likely  to be present during a typical two‐‐‐hour period, allowing for  intermittent operation, downtime during setting‐‐‐up, equipment relocation and breaks.

We have used Annex F of BS 5228-1: 2009 as a minimum to predict the plant noise levels, to estimate the likely daily (LAeq, 10hr) at the nearest sensitive premises.

Page 15: CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

 Source  BS5228 Reference M No.  in 

@use On time  10 hr Laeq 

db (A) 

Concrete Saws 

Hand   Held pneumatic breaker 

10 2 15% 83 

Hoists  Caged Material Hoist 

10 1 15% 68 

Hand Breakers,  Cutters  drills and         small tools 

Cutter  10 5 20% 79 

Excavator breaker 

Tracker Excavator 

10 1 25% 77 

Piling Rig  Large rotary  bored piling rig 

10 1 20% 83 

Wheel Washer 

Water Pump 

10 1 25% 65 

Heavy G o o d s  Vehicle 

Lorry  10 2 15% 80 

 

Below,  we  have  given  some  examples  of methods  to  reduce,  as  far  as  possible,  noise  and 

vibration created by construction work. Texo Construction will choose machinery that has the 

quietest noise output available for the activity you are carrying out. Machinery and vehicles will 

be  fitted  with  effective  silencers  wherever  available,  and  kept  in  good  working  order. 

Equipment will be operated so  it produces as  little noise as possible. Equipment will be  shut 

down when it is not in use. Machinery will be based as far away from noise‐sensitive properties 

as reasonably possible. We will use barriers and enclosures if any activities are likely to be noisy 

at sensitive premises.   Timber Hoardings to reduce noise breakout from activities will also enclose the site. Gates and 

access points will not face onto any especially sensitive buildings such as residential property, 

Page 16: CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

hospitals, schools and businesses. Gates and access points along Wantz and Oxlow Lane will be 

kept open for as little time as possible. The timber hoarding will be free of any significant holes 

or gaps which will aid in resisting sound transfer.  Fixed items of construction equipment will be electrically powered rather than diesel or petrol 

driven.  If  this  is  not possible, we will  provide other  protection  against  noise  such  as  baffles, 

covers or enclosures e.g., the use of monoflex to scaffolding and Timber Hoarding along Oxlow 

Rd and Wantz Rd. Where practical, acoustic blankets shall be used around noisy plant.  Everyone on site will be advised to reduce noise as far as possible both to protect themselves 

and the community. We will not allow anti‐social behaviour such as shouting, using radios and 

swearing. 

 ACTIONS TO BE TAKEN WHERE NOISE EXCEEDS THE PREDICTED LEVELS  In the event that the limits have been exceeded the operation will be modified and the noise and/or vibration rechecked  from  that operation to verify  that  the corrective action has been effective.  These  actions  may  include  reducing  the  operating  hours,  resting  the  equipment, changing the method of working or temporary barriers. If in the event a review it is considered that there is no practical method of reducing the noise levels from a particular operation it will be carried out at particular times agreed by all parties. For regenerated structure borne noise where required Texo Construction will incorporate 2hr on/off respite periods to reduce impact to nearby sensitive receptors. Noisy works shall occur between 9am to noon and 2pm to 5.30pm and 9am to 1pm on Saturdays.  The  site‐specific Method Statements will  include general  site procedures  for reducing noise, detailing best practice  that will be  followed during  the construction works all  in line with the recommendations of BS5228.  The  site manager will monitor noise  generally  throughout  the  day  to  ensure we don’t  cause unnecessary nuisance, and this would include shouting, bad language, radios and out of hour’s deliveries.  Prior  to  starting  any works which would  create  excessive  noise,  site management will notify neighbours as to what we plan to do and for how long. The basic precautions that will be taken to minimise noise generated on the site include using silenced plant, segregation and exclusion through screening if operations are excessive, avoidance of leaving equipment running whilst not immediately engaged in operation.  In the event that a complaint or concern is raised, an immediate review will be completed by the site to remove the problem wherever possible or minimise the issue. The interested parties will 

Page 17: CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

also be notified. This would be recorded in a file kept on site which would be available to view at any time. In the event that there is still a problem after act ion was taken to reduce noise, the  complaint  will  be  reviewed  and  discussions  held with  the  third  party  to understand  the problem further  and  evaluate  whether  the problem can be rectified or at  least  improved. Communication will be maintained in conjunction with the interested authorities.  Texo  Construction  employs  Safety,  Health  and  Environment  Advisers  who  are  trained  and experienced  in  the  use of noise monitoring equipment. We retain our  own  noise monitoring equipment and regularly carry out monitoring checks during construction, to ensure noise levels adjacent  to the works are within specified limits.  The principal construction activities that will generate dust are typically demolition, excavation, foundations and external works.  The   materials   disturbed   by   excavation   activities   are   inert   materials (principally  crushed concrete  and    clay/gravel fill) and therefore the dust generated during their removal and transportation does not   represent  a hazard to either people or the environment. We will also add shielding to  cutting  equipment.  The site will be enclosed by a scaffold which will be protected by monoflex sheeting.  When activities are being carried out that risk generating large volumes of airborne dust, Texo Construction will employ dust suppression measures. This will normally take the form of damping down and dust Screens. Good site management will be strictly enforced to ensure work areas are always kept clean and tidy to prevent the migration of dust throughout the site.  We will erect a full site boundary, keeping away from sensitive receptors, and    there   will   be a    fully      trained    Manager on    site throughout    the construction period.  We will be using water as dust suppressant where applicable and muck‐away trucks will be covered to prevent wind effects on contents.  Texo Construction will have a  hose and pressure washer at  the main entrance  to prevent any dirt/dust leaving the site.  We will employ a road sweeper on a day‐to‐day basis, as required to maintain a clean road  surface. The main time where the roads will need to be cleaned within the project will be when ground works commence i.e., removal of soil /clay etc. We will monitor this carefully.  The footways in the general vicinity of the site will be kept  in a clean and tidy condition at all times (i.e., any significant spillages to be cleaned up as they occur). 

Page 18: CONSTRUCTION MANAGEMENT PLAN For the works at 1 Wantz …

APPENDIX 1 LOGISTICS PLANS   

1. Routes to and from site 2. Google Earth Image of construction vehicles to and from site. 

Matthew Sayer
Line
Matthew Sayer
Polygonal Line
Matthew Sayer
Polygonal Line
Matthew Sayer
Callout
Vehicle Entry and Exit Point