CONSTRUCTION MANAGEMENT AND ADMINISTRATION . UNIT-V Optimisation. Unit-V: List of topics. Introduction Optimisation through linear programming Formulation of LPP Applications of linear programming Graphical method Advantages of LP Limitations of LP Simplex method References: - PowerPoint PPT Presentation

Citation preview

Page 1: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

CONSTRUCTION MANAGEMENT AND ADMINISTRATION

UNIT-V Optimisation

Page 2: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Unit-V: List of topics1. Introduction 2. Optimisation through linear programming3. Formulation of LPP4. Applications of linear programming5. Graphical method6. Advantages of LP7. Limitations of LP8. Simplex methodReferences:“Operations Research” by SD Sharma“Optimization Methods” D Nagesh Kumar, IISc, Bangalore NPTEL web

Page 3: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Introduction

• Numerical Methods of Optimization– Linear programming– Integer programming– Quadratic programming – Nonlinear programming– Stochastic programming– Dynamic programming– Combinatorial optimization– Infinite-dimensional optimization– Constraint satisfaction

Optimization is the selection of a best element (with regard to some criteria) from some set of available alternatives

Page 4: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Optimisation through linear programming• Linear programming is a technique for determining an optimum schedule

of interdependent activities in view of the available resources and constraints

• Programming is just another word for planning and refers to the process of determining a particular plan of action from amongst several alternatives

• The word linear stands for indicating that all relationships involved in a particular problem are linear

• Linear programming indicates the right combination of the various decision variables which can be best employed to achieve the objective taking full account of the practical limitations with in which the problem must be solved

• Linear programming problems consist of a linear objective (cost) function (consisting of a certain number of variables) which is to be minimized or maximized subject to a certain number of constraints

Page 5: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Formulation of LP problems Production allocation problem:A firm manufactures two types of products A and B and sells them at a profit of Rs.2 on

type A and Rs.3 on type B. Each product is processed on two machines G and H. type A requires 01 minute of processing time on G and 02 minutes on H; type B requires 01 minute on G and 01 minute on H. The machine G is available for not more than 6hours 40 minutes while machine H is available for 10hours during any working day. Formulate the problem as a LPP.

Let x1 be the number of products of type A; x2 be the number of products of type B

Machine Time of products (min) Available time (min)Type A (x1 units) Type B (x2 units)

G 1 1 400

H 2 1 600

Profit per unit Rs.2 Rs.3

Total Profit, P=2*x1+3*x2 (objective function)

1*x1+1*x2 <=400; 2*x1+1*x2 <=600 ;Non-negativity constraints x1>=0; x2 >=0

constraints

Page 6: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Formulation of LP problems The manufacturer of patent medicines is proposed to prepare a production plan for

medicines A and B. there are sufficient ingredients available to make 20000 bottles of medicine A and 40000 bottles of medicine B, but there are only 45000 bottles into which either of the medicines can be filled. Further it takes 3hours to prepare enough material to fill 1000 bottles of medicine A and one hour to prepare enough material to fill 1000 bottles of medicine B, and there are 66 hours available for this operation. The profit is Rs.8 per bottle for medicine A and Rs.7 per bottle for medicine B.

Formulate the problem as a Linear Programming Problem.

Let x1 1000 be the number of bottles of medicine A

x2 1000 be the number of bottles of medicine B

Total Profit, P=8000*x1+7000*x2 (objective function)

3*x1+1*x2 <=66;1*x1+1*x2 <=45 ; x1<=20; x2 <=40;

Constraints Non-negativity constraints

x1>=0; x2 >=0

Page 7: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

General formulation of LP problem

In order to find the values of n decision variables x1, x2,..…xn to maximize or minimize the objective function

z = c1x1+ c2x2+ c3x3+……....cnxn and also satisfy m-constraints:

a11x1+a12x2+…….a1jxj….….a1nxn (<= or >=)b1

a21x1+a22x2+……..a2jxj……..a2nxn (<= or >=)b2

: : : : :ai1x1+ai2x2+……...aijxj………ainxn (<= or >=)bi

: : : : :am1x1+am2x2+…….amjxj…….amnxn (<= or >=)bm

Also non-negativity constraints x1 >=0, x2 >=0,….xj >=0,….xn >=0

Page 8: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Applications of LP1. Personal assignment problem2. Transportation problem3. Efficiencing on operation of system of dams4. Optimum estimation of executive compensation5. Agricultural applications6. Military applications7. Production management8. Marketing management9. Manpower management10. Physical distribution

Page 9: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Graphical method (eg.1)

Page 10: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Step 1: consider each inequality constraint as equation and Plot all the constraints one by one on a graph paper

Page 11: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Step 2: Identify the common region of all the constraints

Page 12: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Step 3: Plot the objective function assuming any constant, k

6x+5y=kThis is known as z linePull z line until the extreme points of

feasible regionIn the maximization case this line will

stop from farthest from the origin and passing through at least one corner of the feasible region

In the minimization case this line will stop nearest to the origin and passing through at least one corner of the feasible region

Page 13: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Step 4: Read the coordinates of extreme points and find the maximum/minimum value of z

It can be visually noticed that value of the objective function will be maximum when it passes through the intersection of x+3y=7 and 4x+y=15 (straight lines associated with the 2nd and 3rd inequality constraints). This is known as optimal point.

The optimal point of the present problem is x=3.091 and

y=2.636 .

And the optimal solution is 6x+5y =31.727

Page 14: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

The manufacturer of patent medicines is proposed to prepare a production plan for medicines A and B. there are sufficient ingredients available to make 20000 bottles of medicine A and 40000 bottles of medicine B, but there are only 45000 bottles into which either of the medicines can be filled. Further it takes 3hours to prepare enough material to fill 1000 bottles of medicine A and one hour to prepare enough material to fill 1000 bottles of medicine B, and there are 66 hours available for this operation. The profit is Rs.8 per bottle for medicine A and Rs.7 per bottle for medicine B.

Formulate the problem as a LPP.

Let x1 1000 be the number of bottles medicine A

x2 1000 be the number of bottles of medicine B

Total Profit, P=8000*x1+7000*x2 (objective function)

3x1+x2 <=66;x1+x2 <=45 ; x1<=20; x2 <=40;x1>=0; x2 >=0

(constraints)

Graphical method (eg.2)

Page 15: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

3x1+x2 <=66;x1+x2 <=45 ;x1<=20; x2 <=40;x1>=0; x2 >=0

Step 1: consider each inequality constraint as equation and Plot all the constraints one by one on a graph paper

0 10 20 30 40 50 60 700

10

20

30

40

50

60

70

x1 +x

2 <=45 3x

1 +x2 <=66

x1<=20

x2 <=40

Page 16: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

3x1+x2 <=66;x1+x2 <=45 ;x1<=20; x2 <=40;x1>=0; x2 >=0

0 10 20 30 40 50 60 700

10

20

30

40

50

60

70

x1 +x

2 <=45 3x

1 +x2 <=66

x1<=20

x2 <=40

Step 2: Identify the common region of all the constraints

Feasible region

Page 17: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

0 10 20 30 40 50 60 700

10

20

30

40

50

60

70

x1 +x

2 <=45 3x

1 +x2 <=66

x1<=20

x2 <=40

Step 3: Plot the objective function assuming any constant, k

Total Profit, P=8000*x1+7000*x2 (objective function)

k=8000*x1+7000*x2

K=100000, x1=0: x2=100/7x2=0; x1=100/8

Page 18: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

0 10 20 30 40 50 60 700

10

20

30

40

50

60

70

x1 +x

2 <=45 3x

1 +x2 <=66

x1<=20

x2 <=40

Total Profit, P=8000*x1+7000*x2 (objective function)

Maximum point

x1=10.5 X2 =34.5 8000*10.5+7000*34.5=325000

It can be visually noticed that value of the objective function will be maximum when it passes through the intersection of 3x1+x2=66 and x1+x2=45 ( 1st and 2nd constraints).

This is known as optimal point. The optimal point of the present problem is

Step 4: Read the coordinates of extreme points and find the maximum/minimum value of z

Page 19: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Graphical method (eg.3)

Minimize z=1.5x1+2.5x2

Subject to : x1+3x2>=3x1+x2>=2x1, x2 >=0

Page 20: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

x1+3x2>=3

x1+x2>=2

x1, x2 >=0

Step 1: consider each inequality constraint as equation and Plot all the constraints one by one on a graph paper

0 0.5 1 1.5 2 2.5 3 3.50

0.5

1

1.5

2

2.5

x1 +3x

2 >=3

x1 +x

2 >=2

Page 21: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

0 0.5 1 1.5 2 2.5 3 3.50

0.5

1

1.5

2

2.5

Step 2: Identify the common region of all the constraints

Feasible region

x1 +3x

2 >=3

x1 +x

2 >=2

x1+3x2>=3

x1+x2>=2

x1, x2 >=0

Page 22: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

0 0.5 1 1.5 2 2.5 3 3.50

0.5

1

1.5

2

2.5Objective function Minimize z=1.5x1+2.5x2

Let constant k=4

1.5x1+2.5x2=4

Step 3: Plot the objective function assuming any constant, k

Feasible region

x1 +3x

2 >=3

x1 +x

2 >=2

k=1.5x1+2.5x2

Page 23: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Step 4: Read the coordinates of extreme points and find the maximum/minimum value of z

0 0.5 1 1.5 2 2.5 3 3.50

0.5

1

1.5

2

2.5

Feasible region

x1 +3x

2 >=3

x1 +x

2 >=2

x1=1.5 X2 =0.5 1.5*1.5+2.5*0.5=3.5

It can be visually noticed that value of the objective function will be minimum when it passes through the intersection of x1+x2=2 and x1+3x2=3 ( 1st and 2nd constraints).

This is known as optimal point. The optimal point of the present problem is

Objective function z=1.5x1+2.5x2

Page 24: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Slack and Surplus variablesSlack variables: if a constraint has ≤ sign, in order to make it an

equality, we have to add something positive to the left hand side. The non-negative variable which is added to the left hand side of the constraint to convert it into equation is called the slack variable Eg. x1+x2 ≤ 4

2x1+4x2 ≤5We add slack variables x3, x4 ≥0

x1+x2 +x3 =4 2x1+4x2 +x4 =5

Page 25: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Slack and Surplus variablesSurplus variables: if a constraint has ≥ sign, in order to make it an

equality, we have to subtract something non-negative from its left hand side. The non-negative variable which is subtracted from to the left hand side of the constraint to convert it into equation is called the surplus variable Eg. x1+x2 ≥ 4

2x1+4x2 ≥5We subtract surplus variables x3, x4 ≥0

x1+x2 -x3 =4 2x1+4x2 -x4=5

Page 26: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Standard form of LP Problem1. All the constraints should be converted to equations except

for the non-negativity restrictions which remain as inequalities2. The right side element of each constraint should be made

non-negative (if not)– Eg. 3x-4y≥-4

3x-4y-z=-4-3x+4y+z = 4

3. All variables must have non-negative values4. The objective function should be of maximization form

Min. f(x)= - Max. [--f(x)]Min. z = c1x1+c2x2+…+cnxn

Max.(-z), i.e. Max z’≈ - c1x1-c2x2-..…-cnxn with z=-z’.

Page 27: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Standard form of general LPP with ≤ constraints

• Max. z= c1x1+c2x2+…+cnxn +0xn+1+…+0xn+m

• Subject to a11x1+a12x2+…….a1nxn+xn+1 =b1

a21x1+a22x2+…....a2nxn +xn+2 =b2

: : : : :am1x1+am2x2+…..amnxn +xn+m =bm

where x1≥0, x2≥0,….xn≥0, xn+1 ≥0, xn+m≥0

Page 28: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Matrix form of LP Problem

Maximize z = CXT (objective function)• Subject to A X = b, b≥0 (Constraint equation)• X≥0 (No-negativity restriction)Where

X=(x1, x2, …xn, xn+1, ……xn+m)C= (c1, c2,…cn, 0, 0, 0….0) and b= (b1, b2, ……,bm)A= a11 a12 . . .a1n 1 0 . . . 0

a21 a22 . . .a2n 0 1 . . . 0. . . . . . . . . .am1 am2 . . .amn 0 0 1

Page 29: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Assumptions in LPP

a) Proportionality– Objective function and every constraint function must be linear

b) Additivity– A machine takes x hours of processing time for product A and for product B

it takes y hours then for both A&B together it take x+y hours time

c) Multiplicativity– 1hour for 1product then 10hours for 10products– The total profit from N no.of units is the unit profit times the no.of units sold

d) Divisibility – It means that the fractional levels of variables must be permissible besides

integral values

e) Deterministic – All the parameters in the linear programming models are assumed to be

known exactly

Page 30: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Advantages of LP1. Linear programming technique helps in making the optimum utilization of

productive resources. It also indicates how a decision maker can employ his productive factors most effectively by choosing and allocating these resources

2. The quality of decision may also be improved by linear programming techniques. The user of this technique becomes more objective and less subjective

3. Linear programming technique provides practically applicable solutions since there might be other constraints operating out side the problem which must also be taken into consideration just because, so many units must be produced does not mean that all those can be sold. So the necessary modification of its mathematical solution is required for the sake of convenience to the decision maker

4. In production processes, high lighting of bottlenecks is the most significant advantage of this technique. For example, when bottlenecks occur, some machines cannot meet the demand while others remain idle for some time

Page 31: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Limitations of LP1. In some problems objective functions and constraints are not linear. Generally, in

real life situations concerning business and industrial problems constraints are not linearly treated to variables

2. There is no guarantee of getting integer valued solutions, for example, in finding out how many men and machines would be required to perform a particular job, rounding off the solution to the nearest integer will not give an optimal solution. Integer programming deals with such problems

3. LP model does not take into consideration the effect of time and uncertainty. Thus the model should be defined in such a way that any change due to internal as well as external factors can be incorporated

4. Sometimes large-scale problems cannot be solved with LP techniques even when the computer facility is available. Such difficulty may be removed by decomposing the main problem into several small problems and then solving them separately

5. Parameters appearing in the model are assumed to be constant. But in real life situations they are neither constant nor deterministic

6. LP deals with only single objective, whereas in real life situations problems come across with multi-objectives. Goal programming and multi-objective programming deals with such problems

Page 32: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Some Important definitions• Solution to LPP: Any set X={x1, x2,..…xn+m} of variables is called a solution to LP

problem, if it satisfies the set of constraints only

• Feasible solution (FS): Any set X={x1, x2,..…xn+m} of variables is called a Feasible solution to LP problem, if it satisfies the set of constraints and non negativity restrictions also

• Basic solution (BS): it is a solution obtained by setting any n variables (among m+n variables) equal to zero and solving for remaining m variables, provided the determinant of the coefficients of these m variables is non-zero. Such m variables are called basic variables and remaining n zero-valued variables are called non-basic variables

• Basic Feasible solution (BFS): it is a basic solution which also satisfies the non negativity restrictions, that is all basic variables are non-negative– Non-degenerate BFS: it is the basic feasible solution which has exactly m basic variables

are positive and the remaining n variables will be all zero – Degenerate BFS: a basic feasible solution is called degenerate, if one or more basic

variables are zero valued

Page 33: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Some Important definitions

• Optimum Basic Feasible Solution: a basic feasible solution is said to be optimum, if it also optimizes (maximize/minimize) the objective function

• Unbounded Solution: if the value of the objective function z can be increased or decreased indefinitely, such solutions are called unbounded solutions

Page 34: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Canonical form of standard LPP• Canonical form of standard LPP is a set of equations consisting of

the ‘objective function and all the ‘equality constraints’ (standard form of LPP) expressed in canonical form.

• Understanding the canonical form of LPP is necessary for studying simplex method, the most popular method of solving LPP

• Let us consider a set of three equations with three variables for ease of discussion.

• The system of equations can be transformed in such a way that a new set of three different equations are obtained, each having only one variable with nonzero coefficient. This can be achieved by some elementary operations

Page 35: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

• The following operations are known as elementary operations.– Any equation Er can be replaced by kEr, where k is a nonzero constant– Any equation Er can be replaced by Er + kEs, where Es is another equation

of the system and k is as defined above

• Note that the transformed set of equations through elementary operations is equivalent to the original set of equations. Thus, solution of the transformed set of equations will be the solution of the original set of equations too

• Now, let us transform the above set of equations (A0, B0 and C0) through elementary operations

Canonical form of standard LPP cont...

Page 36: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

• Note that variable x is eliminated from equations B0 and C0 to obtain B1 and C1 respectively. Equation A0 in the previous set is known as pivotal equation.

• Following similar procedure, y is eliminated from A1 and C1 as follows, considering B1 as pivotal equation.

Canonical form of standard LPP cont...

Page 37: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

• Finally, z is eliminated form A2 and B2 as follows, considering C2 as pivotal equation

• Thus we end up with another set of equations which is equivalent to the original set having one variable in each equation. Transformed set of equations, (A3, B3 and C3), thus obtained are said to be in canonical form

• Operation at each step to eliminate one variable at a time, from all equations except one, is known as pivotal operation

Canonical form of standard LPP cont...

Page 38: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Simplex method• Simplex method is the most popular method used for the

solution of Linear Programming Problems (LPP)• Solution of a LPP, if exists, lies at one of the vertices of

the feasible region. All the basic solutions can be investigated one-by-one to pick up the optimal solution.

• For 10 equations with 15 variables there exists 15C10= 3003 basic feasible solutions. Too large number to investigate one-by-one.

• This can be overcome by simplex method

Page 39: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

General procedure of Simplex method

1. General form of given LPP is transformed to its canonical form

2. Find a basic feasible solution of the LPP (there should exist at least one).

3. Move to an adjacent basic feasible solution which is closest to the optimal solution among all other adjacent vertices.

4. Repeat until optimum solution is achieved.

Step three involves ‘Simplex Algorithm’

Page 40: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Simplex Algorithm

• Consider following LPP

Page 41: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

LPP is to be transformed to its standard form

Simplex Algorithm …contd.

Page 42: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Set of equations, including the objective function is to be transformed to canonical form

Basic feasible solution of above canonical form is x4 = 6, x5= 0, x6= 4, x1= x2= x3= 0 and

Z= 0

Simplex Algorithm …contd.

Page 43: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Symbolized form

• The left-most column is known as basis as this is consisting of basic variables

• The coefficients in the first row (C1,....,C6) are known as cost coefficients

Simplex Algorithm …contd.

Page 44: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

This completes first step of algorithm. After completing each step (iteration) of algorithm, following three

points are to be examined:1. Is there any possibility of further improvement?

– If any one of the cost coefficients is negative further improvement is possible

2. Which non-basic variable is to be entered into the basis?– Entering variable is decided such that the unit change of this variable

should have maximum effect on the objective function. Thus the variable having the coefficient which is minimum among all cost coefficients is to be entered, i.e., xs is to be entered if cost coefficient cs is minimum

3. Which basic variable is to be exited from the basis?– After deciding the entering variable xs, xr(from the set of basic variables)

is decided to be the exiting variable if br/crs is minimum for all possible r, provided crs is positive.

– Crs is considered as pivotal element to obtain the next canonical form

Simplex Algorithm …contd.

Page 45: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

• Entering variable :– c1is minimum (-4), thus, x1is the entering variable for the next

step of calculation• Exiting variable:– r may take any value from 4, 5 and 6– It is found that b4/c41 = 6/2=3, b5/c51=0/1 , b6/c61=4/5– As , b5/c51 is minimum r=5 thus x5 is to be exited

• c51 ( = 1) is considered as pivotal element and x5 is replaced by x1in the basis. Thus a new canonical form is obtained through pivotal operation

Simplex Algorithm …contd.

Page 46: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Pivotal operation• Pivotal row is transformed by dividing it with the pivotal element.

In this case, pivotal element is 1. • for other rows: Let the coefficient of the element in the pivotal

column of a particular row be “l”. Let the pivotal element be “m”. Then the pivotal row is multiplied by ‘l / m’ and then subtracted from that row to be transformed.

• This operation ensures that the coefficients of the element in the pivotal column of that row becomes zero, e.g., Z row: l = -4 , m = 1. So, pivotal row is multiplied by l / m = -4 / 1 = -4, obtaining -4x1+16x2-8x3+0x4-4x5+0x6=0 .

• This is subtracted from Z row, obtaining 0x1-5x2+6x3+0x4+4x5+0x6+z=0,

• The other two rows are also suitably transformed.

Simplex Algorithm …contd.

Page 47: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

• After the pivotal operation, the canonical form obtained as follows

• The basic solution of above canonical form is x1= 0, x4= 6, x6= 4, x2= x3= x5= 0 and Z= 0

• Note that cost coefficient c2is negative. Thus optimum solution is not yet achieved. Further improvement is possible

Simplex Algorithm …contd. -(-4/1*E3-E1)-(2/1*E3-E2)

-(5/1*E3-E4)

Page 48: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

• Entering variable: c2is minimum (-15), thus, x2 is the entering variable for the next step of calculation

• Exiting variable: r may take any value from 4, 1 and 6. However, c12 is negative (-4). Thus, r may be either 4 or 6. It is found that b4/c42=6/9=0.667 and b6/c62=4/18 =0.22.

• As b6/c62 is minimum, r is 6. Thus x6 is to be exited.• c62 ( = 18) is considered as pivotal element and x6 is to be replaced

by x2 in the basis Thus another canonical form is obtained

Simplex Algorithm …contd.

Page 49: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

• The canonical form obtained after third iteration

• The basic solution of above canonical form is x1= 8/9, x2= 2/9, x4= 4, x3= x5= x6= 0 and Z= 10/3.

• Note that cost coefficient c3 is negative. Thus optimum solution is not yet achieved. Further improvement is possible

Simplex Algorithm …contd.-(-15/18*E4-E1)

-(9/18*E4-E2)

-(-4/18*E4-E3)

(E4/18)

Page 50: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Simplex Algorithm …contd.

• Entering variable: c3is minimum (-4), thus, x3 is the entering variable for the next step of calculation

• Exiting variable:x4 is the exiting variable. Thus c43 ( = 4) is the pivotal element and x4is to be replaced by x3 in the basis. Thus another canonical form is obtained

Page 51: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

• The canonical form obtained after fourth iteration

• The basic solution of above canonical form is x1= 14/9, x2= 8/9, x3= 1, x4= x5= x6= 0 and Z= 22/3

• Note that all the cost coefficients are nonnegative. Thus the optimum solution is achieved

Simplex Algorithm …contd.-(-4/4E2-E1)

(E2/4)

-(-1/6*E2-E3)

-(-1/6E2-E4)

Page 52: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

The “key element” or “pivot element”

• What is Key element– The element at the intersection of minimum ratio arrow( )

and incoming vector arrow ( ) in the simplex table is called the “key element” or “pivot element”

– key element indicates that the current table must be transformed in such a way that the key element becomes 1 and all other elements in that column become 0

Page 53: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Need of artificial variable in LP model

• LP problems, in which constraints may also have ≥ and = signs after ensuring that all bi are ≥ 0, are considered in two phase method. In such problems, basis matrix is not obtained as an identity matrix in the starting simplex table, therefore we introduce a new type of variable called the Artificial variable

• These variables are fictitious and cannot have any physical meaning

• The artificial variable technique is merely a device to get the starting basic feasible solution, so that simplex procedure may be adopted as usual until the optimal solution is obtained

• Artificial variables can be eliminated from the simplex table as and they become zero (non-basic)

Page 54: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

linear programming in Construction Management

Linear programming can be used in construction management to solve many problems such as:

1. Optimizing use of resources2. Determining most economic product mix.3. Transportation and routing problems.4. Personnel assignment.5. Determining Optimum size of bid.6. Location of new production plants, offices and warehouses

Page 55: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Examples of use of linear programming in construction

A pre-mixed concrete firm has to supply concrete to three different projects A, B, and C. The projects require 200, 350, and 400 cubic meters of concrete in a particular week.The firm has three plants P1, P2, and P3 which can produce 250, 400 and 350 respectively. The cost is different from each Pant to each project since distance will vary. It is required to determine the quantity to be supplied from each plant to each project such that cost to be incurred is a minimum

Page 56: CONSTRUCTION MANAGEMENT AND ADMINISTRATION

Assignment -5• Applications of LP in construction management• Advantages of LP• Limitations of LP• What is Canonical Form of LP?