Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Taylor Thomson Whitting (NSW) Pty Ltd (ACN 113 578 377) as trustee for the Taylor Thomson Whitting NSW Trust (ABN 59 514 956 558) I Consulting Engineers Level 3, 48 Chandos Street, St Leonards NSW 2065
Construction Impacts –
Response to
Submissions
SCEGGS DARLINGHURST
25 SEPTEMBER 2019
181375 - SAAB
SCEGGS Darlinghurst 25 SEPTEMBER 2019 Construction Impacts – Response to Submissions 181375 - SAAB
Taylor Thomson Whitting (NSW) Pty Ltd © 2019 Taylor Thomson Whitting Page 2 of 8
Contents
1.0 Introduction ............................................................................................................................... 3
2.0 Site Location ............................................................................................................................. 4
3.0 Proposed Development ............................................................................................................ 4
4.0 Geotechnical Investigation ........................................................................................................ 4
4.1 Foundations .................................................................................................................... 5
4.2 Adjacent Structures ........................................................................................................ 5
5.0 Excavation and Retention System ............................................................................................ 5
5.1 Monitoring of Excavation ................................................................................................ 5
6.0 Conclusions .............................................................................................................................. 6
Appendix A ............................................................................................................................................ 7
Appendix B ............................................................................................................................................ 8
SCEGGS Darlinghurst 25 SEPTEMBER 2019 Construction Impacts – Response to Submissions 181375 - SAAA
Taylor Thomson Whitting (NSW) Pty Ltd © 2019 Taylor Thomson Whitting Page 3 of 8
1.0 Introduction
Taylor Thomson Whitting has been commissioned to prepare a report to advise on the construction impacts of the development at SCEGGS Darlinghurst on the adjacent heritage buildings, and the potential risk to their structural integrity from excavation equipment and methodologies. These queries have been raised by the City of Sydney and adjacent residents in the response to the DA Submission. This report illustrates the proposed excavation and foundation system; and assess any likely impacts to the adjacent heritage structures.
The proposed masterplan development consists of the Multi-purpose building, the Administration Building and the Wilkinson House redevelopment. This report only considers the Multi-Purpose Building and Administration Building, which include excavation adjacent to existing heritage buildings.
The Multipurpose Building includes a large basement that will be excavated adjacent to existing buildings on the site; the Chapel Building, Barham Building, Yellow Building, Art Building, and terrace houses in Forbes and Thomson Street. Bourke Street is situated along the Western edge of the site. The Administration Building includes a basement that will be excavated adjacent to the Barham Building.
A geotechnical investigation report has been provided to TTW that covers investigations for a previous development, of similar size and type, within the same site. This report has been prepared by Douglas Partners, Report number 45427, dated April 2008. The proposed excavation and retention system has been based on the recommendations stated within this report and our own experience with other similar types of development. TTW recommends this development undertaking further geotechnical investigations to confirm these assumptions.
2.0 DA Response to Submissions
This report is to address the following responses:
- The proposed excavation is significant in scale and located in close proximity to the Chapel with the potential to affect the structural integrity of the Chapel. The Southern façade of the multi purpose building is also located in very close proximity to the heritage listed terraces on Thomson Street. There is insufficient information to determine whether the likely impacts are acceptable or not’
- Concerns regarding potential damage to heritage buildings during construction:
o Potential structural and vibration damage to adjoining heritage properties during construction – on-going monitoring and remedial actions where needed
SCEGGS Darlinghurst 25 SEPTEMBER 2019 Construction Impacts – Response to Submissions 181375 - SAAA
Taylor Thomson Whitting (NSW) Pty Ltd © 2019 Taylor Thomson Whitting Page 4 of 8
3.0 Site Location
The overall site is bounded by Bourke St, Forbes St and St Peters Street in Darlinghurst. The Multipurpose Building is located at approximately 188 Bourke St, Darlinghurst. An overall masterplan image is provided in the figure below.
Figure 1: Overall site plan, excavation zone denoted in green
Responses to the DA Submission included queries on the construction impacts of the proposed excavation for the basement structures, on the Chapel Building and any adjacent heritage buildings, including terrace houses in Forbes and Thomson Street.
4.0 Proposed Development
The masterplan includes up to seven levels of new learning space for the school. The Multipurpose Building will consist of a basement parking, with up to three levels of excavation. The lowest basement RL is approximately RL 26.94. The existing Bourke Street level is approximately RL 28.50. The Chapel Building ground floor is approximately RL 38.30. The lowest basement RL of the Administration Building is approximately RL 37.14.
The proposed structure will consist of a concrete framed building. The basement retention system is expected to be high level shoring system of soldier piles at approximately 2m centres to restrain the fill layer, up to 1m deep. The sandstone will be vertically cut without temporary restraint. A geotechnical engineer is to inspect the excavation at intervals to verify if any rock bolting is required.
5.0 Geotechnical Investigation
The report prepared by Douglas Partners involved a geotechnical investigation for the adjacent site, the Science and Technology Building. This investigation involved test pits and boreholes up to 10m in depth.
The site subsurface conditions have been described as:
- Approximately 1m of clayey sand fill overlying;
- Weathered medium strength sandstone down to 2m in depth,
SCEGGS Darlinghurst 25 SEPTEMBER 2019 Construction Impacts – Response to Submissions 181375 - SAAA
Taylor Thomson Whitting (NSW) Pty Ltd © 2019 Taylor Thomson Whitting Page 5 of 8
- High to medium strength sandstone extending for quite some depth
Groundwater is predicted to be well below the bulk excavation level, with no noticeable groundwater found in the test drilling. It is expected some seepage will occur through the rock profile, but this is not expected to be significant.
5.1 Foundations
The proposed development will be founded on the medium to high strength sandstone, and is likely to be high level pad footings. The foundation system will be detailed so as not to place additional load on the adjacent existing foundations or structure. The foundation material will be inspected and verified by a geotechnical engineer prior to construction of the footing.
5.2 Adjacent Structures
It is predicted that the existing foundations are high-level pad or strip footings. This is common for the construction era of these buildings. It is likely these footings are resting on the weathered sandstone level, however during the proposed construction these footings are to be investigated and the founding material verified.
The structural engineer is to be notified if the supporting ground profile to these existing footings is found not to be sandstone, as underpinning will be required. The contractor is not to continue with excavation in this case until underpinning can be completed and the existing structure is founded on competent bedrock.
6.0 Excavation and Retention System
The proposed excavation for the basement is expected to be within the high to medium strength sandstone. Due to the proximity of the adjacent buildings, a rock saw and small rock breakers are expected to be used around the perimeter of the basement to limit the vibrations on the adjacent structures.
The report prepared by Wilkinson Murray on Construction and Operational Noise Report (report number 18180, dated July 2019) outlines the acceptable vibration criteria for the occupants in the adjacent buildings, and for the acceptable limits without impact on the adjacent buildings during construction. Excavation equipment is to be chosen based on the criteria setout in the Wilkinson Murray report.
Excavation trials are to be carried out, as recommended by the geotechnical report. During these trials, the adjacent structures are to be monitored for movement and vibrations levels to ensure no impact on the structure. These trials are to prove the vibration limits set out in the Wilkinson Murray report are not exceeded. Rock saws, line drilling or mill drilling are to be used in close proximity of the adjacent structures, in lieu of major rock breaking equipment. Hydraulic rock hammering is not to be used within 10m of adjacent structures.
6.1 Monitoring of Excavation
A monitoring plan is to be submitted by the contractor to the client, including inclinometers and tilt meters. All movements are to be continuously reported to the client and structural engineer during excavation; at a minimum of weekly reports.
The apparatus’ are to be installed on the existing adjacent structures, on every wall elevation that faces the proposed excavation at 2m above ground.
7.0 Adjacent Heritage Structures
The excavation is significant in scale, adjacent to the existing Heritage Chapel Building and the existing Heritage terrace structures. These risks in construction will be mitigated by:
SCEGGS Darlinghurst 25 SEPTEMBER 2019 Construction Impacts – Response to Submissions 181375 - SAAA
Taylor Thomson Whitting (NSW) Pty Ltd © 2019 Taylor Thomson Whitting Page 6 of 8
- Using construction equipment and drilling equipment that are low vibration impacts through the ground profile. This will reduce any significant ground movement and protect the adjacent structures. A vibration and/or acoustic consultant is to provide advice on the allowable vibration limits at certain distances from the adjacent structures. The contractor is to choose construction and drilling equipment that are within these limits set, and to perform excavation tests to ensure the ground movement is minimised.
- The adjacent heritage structures are to be protected throughout the construction period with hoarding rated to the Australian Standards. No dangerous construction activity is to occur within proximity of the existing buildings.
- The retention system designed to hold back the excavation will be designed by a qualified structural engineer, and for minimal lateral movements in the temporary and permanent case. Less than 10mm of deflection will be experienced at the top of the retention system design. Movements of this magnitude will not be detrimental to the adjacent buildings. Localised cracking that may occur can be remediated easily with crack filler. The retention systems movement will be monitored using the approach mentioned in Section 6.1
- The proposed excavation will not undermine the adjacent buildings. The ground profile will remain intact and in place during construction. The foundations of the existing buildings will not be disturbed in any way
8.0 Conclusions
If the strategies and methodologies recommended in this report are implemented, the proposed excavation and any vibrations to construct this excavation, will have a negligible impact on the adjacent heritage buildings. The construction impacts will be minor to the heritage buildings, consisting of localised cracking at mortar joint locations. These will not affect the structural integrity of the existing buildings and can be remediated simply.
Prepared by Authorised By
TAYLOR THOMSON WHITTING (NSW) PTY LTD in its capacity as trustee for the TAYLOR THOMSON WHITTING NSW TRUST
TAYLOR THOMSON WHITTING (NSW) PTY LTD in its capacity as trustee for the TAYLOR THOMSON WHITTING NSW TRUST
JANE ARMSTRONG BARRY YOUNG Associate (Structural) Director
P:\2018\1813\181375\Reports\TTW\Response to Submissions\190925_SCEGGS Darlinghurst_Response to Submissions_Construction Impacts_Rev B.docx
SCEGGS Darlinghurst 25 SEPTEMBER 2019 Construction Impacts – Response to Submissions 181375 - SAAB
Taylor Thomson Whitting (NSW) Pty Ltd © 2019 Taylor Thomson Whitting Page 7 of 8
Appendix A
Geotechnical Report
REPORT on GEOTECHNICAL INVESTIGATION PROPOSED SCIENCE AND TECHNOLOGY BUILDING SYDNEY CHURCH OF ENGLAND GIRLS GRAMMAR SCHOOL DARLINGHURST Prepared for SCEGGS Darlinghurst Project 45427 April 2008
REPORT on GEOTECHNICAL INVESTIGATION PROPOSED SCIENCE AND TECHNOLOGY BUILDING SYDNEY CHURCH OF ENGLAND GIRLS GRAMMAR SCHOOL DARLINGHURST Prepared for SCEGGS Darlinghurst Project 45427 April 2008
Douglas Partners Pty Ltd ABN 75 053 980 117
96 Hermitage Road West Ryde NSW 2114 Australia
PO Box 472 West Ryde NSW 1685 Phone (02) 9809 0666 Fax (02) 9809 4095 [email protected]
Geotechnical Investigation Project 45427 St Peters Street, Darlinghurst April 2008
TABLE OF CONTENTS Page 1. INTRODUCTION ..................................................................................................... 1 2. PREVIOUS INVESTIGATION ................................................................................. 2 3. SITE DESCRIPTION AND GEOLOGY ................................................................... 3 4. FIELD INVESTIGATION.......................................................................................... 4
4.1 Methods ....................................................................................................... 4 4.2 Results ......................................................................................................... 4
5. Proposed Development ........................................................................................... 6 6. Engineering Evaluation............................................................................................ 6
6.1 Ground Conditions ....................................................................................... 6 6.2 Excavation ................................................................................................... 7 6.3 Excavation Support...................................................................................... 7 6.4 Underpinning of Adjoining Structures .......................................................... 8 6.5 Foundations ................................................................................................. 8 6.6 Vibrations ..................................................................................................... 9 6.7 Groundwater ................................................................................................ 10 6.8 Pavement Design......................................................................................... 10 6.9 Seismic Design ............................................................................................ 11
Appendix A: Locality and Borehole Plans Appendix B: Test Bore and Test Pit Logs and Notes Relating to this Report B1: Previous Investigations B2: Current Investigation
Page 1 of 11
Geotechnical Investigation Project 45427 St Peters Street, Darlinghurst April 2008
MJT:jlb
Project 45427
5 April 2008
GEOTECHNICAL INVESTIGATION
PROPOSED SCIENCE AND TECHNOLOGY BUILDING SCEGGS DARLINGHURST
1. INTRODUCTION
This report details the results of a geotechnical investigation carried out on the site of the
proposed Science and Technology Building to be constructed within the grounds of Sydney
Church of England Girls Grammar School in Forbes Street (SCEGGS), Darlinghurst. The work
was undertaken for SCEGGS and was carried out in consultation with Hughes Trueman,
Consulting Engineers for the project.
The project is for the construction of a new six storey school teaching building which will include
two levels of below ground parking. Site investigation was carried out to determine the
subsurface conditions and subsequently provide advice on:
• Suitable foundation types and design bearing pressures;
• Stability of permanent and temporary excavation slopes;
• The depth of the water table and potential seasonal fluctuations;
• Seismic design parameters for earthquake loading;
• Recommendations on methods of underpinning existing structures;
• Recommended vehicle and pedestrian pavement profiles.
Page 2 of 11
Geotechnical Investigation Project 45427 St Peters Street, Darlinghurst April 2008
The investigation comprised test bore drilling and test pit excavation followed by engineering
evaluation and geotechnical analysis where appropriate. Details are given in the report
together with comments on design and construction practice.
The geotechnical investigation was carried out simultaneously with a contamination assessment
and waste classification for material to be disposed of off-site as a result of the basement
excavation. Laboratory testing for the contamination assessment is currently in progress and
the results of this investigation will be reported separately.
2. PREVIOUS INVESTIGATION
In June 1994, Douglas Partners (DP) carried out a geotechnical investigation for the sports
building which is located immediately to the south of the proposed structure. This investigation
comprised six bores drilled to depths of up to 8.5 m below the existing surface level to obtain
detailed information on the soil and rock stratigraphy. The results of the investigation were
provided in a Report No 20080 for Tierney & Partners, Consulting Engineers for the sports
building design.
The investigation indicated that sandstone bedrock was generally located less than 0.5 m below
surface level. Furthermore, the sandstone was medium or high strength from near the surface
and DP assessment was that the vertical excavations could be made in the sandstone but that
rock bolts would be required to stabilise areas where steeply dipping joints intersect the
excavation faces at unfavourable orientations. It was also determined that localised shotcreting
of low and very low strength bands would be required to minimise weathering and deterioration
of these beds.
The investigation also comprised mapping of the sandstone cliff-face on the site which was
eventually excavated for the sports complex. This mapping identified a weak zone in the
Hawkesbury Sandstone and contended that this weak zone could have been caused by a fault
in the sandstone or by an igneous dyke intersecting the excavation at about right angles to the
Forbes Street frontage. If the weak zone was a dyke, it is possible that similar geological
features could intersect the site of the current proposed building.
Page 3 of 11
Geotechnical Investigation Project 45427 St Peters Street, Darlinghurst April 2008
3. SITE DESCRIPTION AND GEOLOGY
SCEGGS is located in an intensely developed residential and commercial area of Darlinghurst
about 1 km from the Sydney Central Business District. Overall the site occupies an irregular
shaped area measuring about 150 m x 60 m and is currently occupied by many school buildings
which range in age from relatively recent to in excess of 50 years old. The school itself is
located on the corner of Forbes Street and St Peters Street with the particular site being
currently developed having a frontage of approximately 40 m on St Peters Street and an overall
depth of some 30 m. Most of the area being considered for development is currently used as
car parking with the eastern portion presently occupied by an elevated demountable classroom
over car parking. Immediately adjacent to the development site, to the east, is Wilkinson House
which is a multi-storey brick building of some considerable age. On the southern boundary of
the development site is Barbara Chisholm Hall and on the western boundary is the backyard of
private residences.
SCEGGS is located in undulating country with gentle slopes to the north towards
Woolloomooloo Bay estimated to be about 5%. The area being considered for development is
relatively level with an overall fall in a north-westerly direction diagonally across the site
estimated to be of the order of 2 m.
The 1:100 000 Series Geological Sheet for Sydney indicates that the site is underlain by
Hawkesbury Sandstone. This geological formation usually comprises medium to coarse
grained quartz sandstone with minor shale lenses. Previous investigations on the site confirm
the geological mapping with Hawkesbury Sandstone at shallow depths below the surface.
Sandstone was also exposed in a cutting along Forbes Street prior to excavation for the existing
sports hall.
An extract from the aerial photograph of the area is given on Drawing 1 in Appendix A and
shows SCEGGS school on the corner of Forbes Street and St Peters Street, Darlinghurst. The
proposed development site is the open car parking area and adjoining white roof area facing St
Peters Street.
Page 4 of 11
Geotechnical Investigation Project 45427 St Peters Street, Darlinghurst April 2008
4. FIELD INVESTIGATION
4.1 Methods
The field investigation for the geotechnical assessment was carried out simultaneously with the
contamination investigation and comprised five bores and three test pits conducted at the
locations shown on the site plan in Appendix A.
Bores 101, 102 and 103 were drilled to depths of about 10 m below existing surface level using
a truck mounted auger/rotary drilling rig. Initially the bores were advanced using spiral flight
augers to the point of refusal on bedrock. Thereafter the bores were continued using rotary
drilling techniques to obtain 50 mm diameter cores of the bedrock strata. Bores 104 and 105
were drilled using spiral flight augers through the soils to collect samples for contamination
testing and were terminated at refusal.
Test Pits 202 and 203 were excavated by hand to determine bedrock levels and possibly
expose the foundations of adjacent buildings. Originally it was intended to excavate a Test Pit
201 adjacent to Wilkinson House but inspections indicated that the footings of Wilkinson House
are supported by Sandstone Bedrock above the level of the car parking beneath the
demountable building and tennis court. Consequently it was considered sufficient to map the
sandstone outcrop and photograph the footings to provide information on the need to underpin
footings of Wilkinson House.
4.2 Results
Details of the conditions encountered in the test bores and test pits are given on the respective
logs in Appendix B which also contains notes on the standard terms used to classify the strata
and on the strength classification of bedrock.
The current investigations indicate a profile comprising about 1 m of filling overlying weathered
sandstone and then medium and high strength sandstone from depths of 0.35 m to 1.0 m. The
medium and high strength sandstone had some moderately weathered zones in the upper 2 m
as indicated by some core loss and clay filled joints. Below depths of about 3 m, however,
sandstone was generally medium and high strength fresh unbroken rock with few defects.
Page 5 of 11
Geotechnical Investigation Project 45427 St Peters Street, Darlinghurst April 2008
Table 1 below summarises the results of the current series of bores together relevant bores
conducted in the vicinity during the previous investigation.
Table 1 – Summary of Bore Data Data RL of Interface of Strata (m)
Description BH4 BH5 BH6 BH101 BH102 BH103
SL 33.2 30.3 30.1 28.15 27.15 28.28
FILLING/ CLAYEY SAND – Topsoil, Sandstone rubble and weathered residual soil
32.95 29.98 29.20 27.15 26.45 28.08
SANDSTONE – Extremely low strength NE NE NE
32.95 29.98 26.91 26.15 27.93
SANDSTONE – medium and high strength, moderately weathered
32.95 29.98 29.20 25.68 23.00 25.58
SANDSTONE – medium or high strength fresh, slightly fractured
29.7 26.3 28.1 18.15 17.15 18.28
BD BD BD BD BD BD SL = Surface level NE = Not encountered BD = Bore Discontinued
The results indicate relatively uniform conditions with approximately 1 m of filling and weathered
material overlying medium or high strength bedrock. The bedrock surface appears to be
dipping generally in a north-westerly direction, following the natural surface contours. The
overall level difference diagonally across the proposed development site of the surface of the
medium or high strength rock appears to be of the order of 4 m from the previously drilled Bore
5 to Bore 102 in the north-western corner of the site.
No free groundwater was observed during the current investigation phase and this is consistent
with observations made during the previous investigation in 1994. It is expected, however, that
after periods of heavy rainfall some seepage will occur along the bedrock surface. The
permanent water table within the intact bedrock is expected to be at many tens of metres below
the current site level with groundwater flow along bedding planes and through vertical joints
Page 6 of 11
Geotechnical Investigation Project 45427 St Peters Street, Darlinghurst April 2008
being extremely low. Conditions encountered at the three proposed test pit locations are also
described on the test pit logs in Appendix B. The conditions are to be confirmed at a later date
but bedrock is above the surface level at TP 201.
5. PROPOSED DEVELOPMENT
It is understood that the proposed development will comprise a new six storey school teaching
building with two levels of below ground parking. The building will be a reinforced concrete
frame structure with column working loads indicated by the consulting engineers to be in the
range of 4,000 to 5,000 kN. The building abuts existing buildings which means that
underpinning of adjacent footings will be required if they are not founded on sandstone bedrock.
The excavation for the construction of the underground car park is expected to extend to depths
of 6 – 7 m below existing road level. As the car park will extend to the edges of the site, vertical
excavations will be required for the car park construction.
6. ENGINEERING EVALUATION
6.1 Ground Conditions
The investigation indicates that the site is underlain by approximately 1 m of filling and
weathered material over generally medium or high strength bedrock. Whilst these conditions
are favourable insofar as vertical excavations are generally feasible (as indicated below) and
relatively high bearing pressures can be adopted, on a small site such as this excavation can be
difficult and vibration issues become critical in carrying out the bulk excavation works. These
aspects of the development are discussed in the following subsections of the report.
Page 7 of 11
Geotechnical Investigation Project 45427 St Peters Street, Darlinghurst April 2008
6.2 Excavation
The excavation for the proposed basement construction will be up to about 7 m below existing
surface level and will therefore be mostly in medium to high strength sandstone with some
minor low or very low strength bands. Generally, it is considered that the excavation of sites of
this size underlain by medium and high strength sandstone, would be difficult and under normal
circumstances would need a heavy bulldozer, such as a D10 (or larger), and also the use of
rock breakers to break some of the stronger layers and to trim the final excavation faces.
However, due to the proximity of buildings which are sensitive to vibrations it may be necessary
to utilise a rock saw around the perimeter of the excavation and to use small rock breakers to
assist in the excavation so as to limit the vibration of adjacent structures. For this reason it is
suggested that potential excavation contractors be provided with the test bore logs and core
photographs and be required to make their own assessment of the equipment needed to carry
out the excavation, being mindful of the need to limit vibration so as to not cause damage to
nearby residences and other school buildings. It should also be mandatory for an excavation
trial to be carried out using the equipment proposed for the work before the main excavation
work commences to establish whether the vibration limits given below can be achieved. If the
trial proves satisfactory, then bulk excavation works could commence but if the vibration levels
are too high it may be necessary to get the contractor to either adjust their excavation
techniques or to utilise smaller equipment.
6.3 Excavation Support
Whilst it should be generally possible to excavate medium and high strength sandstone
vertically it is considered likely that rock bolts or pins may be required to stabilise areas where
steeply dipping joints intersect the excavation faces at unfavourable orientations. Localised
shotcreting of low and very low strength bands may also be required to reduce weathering and
deterioration of these bands.
In order to determine the requirement for rock bolts or pins it is recommended that inspections
of the excavation faces be undertaken by an experienced geotechnical engineer or engineering
geologist at regular intervals during construction. For a depth of excavation of 7 m it will
probably be necessary for the inspections to take place on each excavation face at least twice
so that remedial measures on the upper part of the excavation can be implemented before
Page 8 of 11
Geotechnical Investigation Project 45427 St Peters Street, Darlinghurst April 2008
excavation continues to a point where stabilisation measures might be difficult to install and
safety of the workers in the site is compromised.
While the overburden soils and filling are likely to be relatively thin (ie generally less than 1 m)
these materials should be battered back at a maximum slope of 2H :1V. Alternatively, they
could be supported by a retaining structure.
6.4 Underpinning of Adjoining Structures
The investigation indicates that the site is underlain by a relatively shallow depth of filling and
soil overlying medium strength bedrock. The foundations of the adjacent structures also appear
likely to be supported on medium strength bedrock so there appears to be no need for
underpinning of adjoining structures. It is, however, recommended that the entire footings of all
buildings near the excavation face be inspected when excavation commences to ensure that
the conditions observed on the site during the investigation are representative of all conditions
beneath the footings of existing buildings. If underpinning is required it will have to be done in
short panel no greater than about 1.5 m lengths by excavating under the footings and providing
temporary support until concrete blade walls can be installed from the underside of the footing
down to competent bedrock.
6.5 Foundations
The foundation material underlying the proposed science and technology building will mostly
comprise medium to high strength sandstone with the possibility of some minor low or very low
strength bands. Pad or strip footings founded on this material are considered to be suitable
footing types. For these conditions it is considered that the building footings could be designed
on the basis of an ultimate bearing pressure of 20 MPa. Even with a very low geotechnical
strength reduction factor it is still possible that excessive settlements could occur so it is
recommended that a maximum allowable bearing pressure of 3.5 MPa be adopted without the
need for any spoon testing in the foundation excavation or 6 MPa if spoon testing is undertaken
in at least half of the footing excavations during construction.
Page 9 of 11
Geotechnical Investigation Project 45427 St Peters Street, Darlinghurst April 2008
During the previous investigations weak zones were identified in the rock face along Forbes
Street. Although the area where the weak zones occurred is located some distance from the
present site, it was contended that the weak zones may have been caused by an igneous dyke.
If this were correct then the current site may also be intersected by such weak zones. It is
therefore imperative that all foundations be inspected to ensure that foundations conditions are
not impacted by igneous intrusions.
6.6 Vibrations
Excavation of the medium and high strength rock will cause some vibration but with care this
can be maintained at levels which are below the critical levels for major building damage. The
sandstone bedrock underlying the proposed development site is expected to extend into
adjacent properties and is likely to transmit vibrations generated by the excavation process.
Consequently, it will be necessary to adopt appropriate construction methodologies and
equipment to limit the vibration at adjacent buildings to acceptable levels.
If hydraulic rock hammering is required it may result in vibrations being transmitted to the
surrounding ground and any buildings or structures in the vicinity. It will generally be necessary
to use smaller excavation plant or alternatively methods such as rock sawing, line drilling or a
milling head when in close proximity to existing structures. It is DP’s experience that particular
care is warranted when using hydraulic rock hammers within 10 m of adjacent structures and
within 15 – 20 m of structures that are old or of heritage significance. To limit the risk of causing
vibration induced damage to existing structures it is recommended that monitoring of the
vibration be carried out during an initial excavation trial. If acceptable vibrations are recorded
using the techniques and equipment proposed for bulk excavation then excavation could
continue. If excessive vibrations occur it may be necessary to amend the excavation plan.
The propagation of vibrations at a site depends upon the plant used to carry out the excavation
and the prevailing ground conditions together with the type of construction and foundation of the
structures receiving the vibrations. The ground conditions such as rock strength and defects
are unique to every particular site and therefore it is recommended that excavation trials be
subject to vibration monitoring to establish the extent to which vibration are attenuated by the
local geological conditions.
Page 10 of 11
Geotechnical Investigation Project 45427 St Peters Street, Darlinghurst April 2008
The Australian Explosives Code (AS2187.2-1993) recommends a peak particle velocity (PPV)
of 10 mm per/sec for residential structures subject to blasting vibration. Ground vibrations
arising from excavation plant, however, are continuous and not transient as would be blasting
vibrations. Therefore, more stringent vibration limits should apply. On the basis of the above it
is considered that the vibrations should be limited to a maximum PPV of 5 mm per/sec at the
building line of the existing adjacent structures.
It should also be noted that humans are very sensitive to vibration, even at levels which are
considered inconsequential for buildings and utilities. It may therefore be beneficial to give
ample notice to local residents that excavation is to commence. It would also be prudent to
undertake a dilapidation survey on all adjacent buildings so that any pre-existing damage can
be identified and therefore avoid claims that the excavation has caused deterioration in adjacent
structures.
6.7 Groundwater
As indicated above it is expected that the groundwater would be located many tens of metres
below the existing site. It is, however, probable that some seepage will occur along the
sandstone bedrock after periods of heavy rainfall. The quantity of flow should not be significant
but provision will need to be made to collect any seepage flows and to dispose of this into the
local stormwater drainage system.
6.8 Pavement Design
For areas within the excavation medium or high strength sandstone bedrock will be exposed at
subgrade level. For areas restricted to normal passenger vehicles and light delivery vehicles up
to 3 tonne it is considered that a flexible pavement thickness of 200 mm would be sufficient.
Alternatively, 130 mm of concrete on a 100 mm sub-base layer would be sufficient for the same
loads.
In areas where pedestrian traffic only is anticipated a 100 mm concrete pavement should be
sufficient. All pavements should be placed on a subgrade compacted to 100% standard density
ratio and with a moisture content suitable for achieving the compaction with the plant available.
Page 11 of 11
Geotechnical Investigation Project 45427 St Peters Street, Darlinghurst April 2008
6.9 Seismic Design
The Earthquake Loading Code (AS1170.4-1993) indicates that general structures in Sydney
should be designed using an acceleration coefficient of 0.08. Furthermore, the site is underlain
by shallow sandstone and Table 2.4(a) of the code dictates that a site factor of 1.0 is applicable
for sites underlain by rock which is at least extremely low strength.
Yours faithfully DOUGLAS PARTNERS PTY LTD Reviewed by Michael J Thom Fiona MacGregor Principal Principal
APPENDIX A Locality and Borehole Plans
Sydney, Newcastle, Brisbane, Wollongong, Campbelltown
Melbourne, Perth, Wyong, Townsville, Cairns, Darwin
Title Locality Map New Science & Technology BuildingSydney Church of England Girls Grammar School Darlinghurst
Client: SCEGGS Office: Sydney
Drawing No.1Drawn by: MJT Scale: NTS Project No: 45427
Approved by: Date: 25 March 2008
SITE
Sydney, Newcastle, Brisbane, Wollongong
Melbourne, Perth, Wyong, Townsville, Cairns
Drawn by: MJT Scale: NTS Wollongong, Campbelltown, Darwin
Title Bore and Test Pit Location PlanNew Science & Technology BuildingSydney Church of England Girls Grammar School Darlinghurst
Note: TP201 was not excavated as sandstone was above ground level
Client: SCEGGS
Approved by: Drawing 2
Project Number: 45427
Date: 25March 2008
Office: Sydney
WILKINSON HOUSE
BH103
BH6
BH 6
BH 5
BH104 BH101
BH105
BH102
about 15 m
TP 202
TP 201
TP 203
APPENDIX B Test Bore and Test Pit Logs
and Notes Relating to this Report
APPENDIX B1 Previous Investigations
0.01
C
C 98
8.5
3.75
1.1
0.83
0.3
C
FractureSpacing
(m)
98
72
90
SCEGGS DarlinghurstJoan Freeman Building
100
89
PL(D) = 1.5MPa
0.83m: CORE LOSS:270mm
PL(A) = 0.7MPa
PL(A) = 1.5MPa
0.1
PL(A) = 1.2MPa
PL(A) = 1.4MPa
PL(A) = 2.2MPa
PL(D) = 0.9MPa
- with some clay seams from 6m to6.3m
0.05
- medium to high strength from7.85m
SANDSTONE - high strength,slightly weathered, slightly fractured,light grey and brown mediumgrained sandstone
- with some clay seams around 3m
SANDSTONE - high strength,slightly weathered, slightly fractured,purple and brown medium grainedsandstone
SANDSTONE - high strength,slightly weathered, slightly fractured,orange brown and brown mediumgrained sandstone with a possibleextremely low strength band
ROADBASE - grey gravelBITUMEN
Bore discontinued at 8.5m
BORE No: 1PROJECT No: 45427DATE: 30 Jun 94SHEET 1 OF 1
Wat
er
RockStrength
Test Results&
Comments
DRILLER: Cooper
EW
HW
MW
SW
FS FR
BOREHOLE LOG
Depth(m)
These bores are a summary of the original bore logsREMARKS:WATER OBSERVATIONS: No free groundwater observed
SAMPLING & IN SITU TESTING LEGEND
SURFACE LEVEL: 38.6EASTING:NORTHING:DIP/AZIMUTH: 90°/--
CLIENT:PROJECT:
CHECKED
Date:
Degree ofWeathering
Initials:
Descriptionof
Strata
CASING: Uncased
RQ
D%
TYPE OF BORING: Solid flight auger to 0.30m then HQ3 Coring
0.50
0.10
Ex
Low
Ver
y Lo
wLo
wM
ediu
mH
igh
Ver
y H
igh
Ex
Hig
h
Discontinuities Sampling & In Situ Testing
TypeB - Bedding
S - ShearJ - JointD - Drill Break
St Peters Street, Darlinghurst
LOGGED: Patel
3837
3635
3433
3231
3029
1.00
A Auger sample pp Pocket penetrometer (kPa)D Disturbed sample PID Photo ionisation detectorB Bulk sample S Standard penetration testUx Tube sample (x mm dia.) PL Point load strength Is(50) MPaW Water sample V Shear Vane (kPa)C Core drilling Water seep Water level
Cor
eR
ec. %
LOCATION:
RIG: Scout
RL
1
2
3
4
5
6
7
8
9
Gra
phic
Log
C
C
C
0.01
8.5
FractureSpacing
(m)
100
95
100
SCEGGS DarlinghurstJoan Freeman Building
100
97
100
3.02
PL(D) = 0.3MPa
5.79
BITUMEN
PL(A) = 0.8MPa
CLAY - brown sandy clay
PL(A) = 0.2MPa
SANDSTONE - high strength,slightly to moderately weathered,slightly fractured, orange brown,grey and purple medium grainedsandstone
PL(A) = 1.1MPaPL(D) = 2.1MPa
PL(D) = 1.2MPaPL(A) = 1.1MPa
PL(D) = 1.9MPaPL(A) = 1.3MPa
PL(D) = 0.9MPa
0.05
0.50.4
0.1FILLING - dark brown sand
5.39
Bore discontinued at 8.5m
SANDSTONE - medium strength,slightly weathered, fractured toslightly fractured, light grey fine tomedium grained sandstone withsome minor very low to low strengthbands
SANDSTONE - low to mediumstrength, slightly weathered,fractured, light brown and grey finegrained sandstone with some clayseams and a very low strength band
SANDSTONE - high strength,slightly weathered, slightly fractured,light grey and brown mediumgrained sandstone with some minorclay seams
BORE No: 2PROJECT No: 45427DATE: 01 Jul 94SHEET 1 OF 1
Wat
er
RockStrength
Test Results&
CommentsEW
HW
MW
SW
FS FR
BOREHOLE LOG
Depth(m)
These bores are a summary of the original bore logsREMARKS:WATER OBSERVATIONS: No free groundwater observedTYPE OF BORING: Solid flight auger to 0.50m then HQ3 Coring
SAMPLING & IN SITU TESTING LEGEND
SURFACE LEVEL: 38.5EASTING:NORTHING:DIP/AZIMUTH: 90°/--
CLIENT:PROJECT:
CHECKED
Date:
Degree ofWeathering
Initials:
Descriptionof
Strata
LOGGED: PatelDRILLER: Cooper
1.00
0.50
0.10
Ex
Low
Ver
y Lo
wLo
wM
ediu
mH
igh
Ver
y H
igh
Ex
Hig
h
Sampling & In Situ Testing
Cor
eR
ec. %
TypeB - Bedding
S - ShearJ - JointD - Drill Break
Discontinuities
LOCATION:
3837
3635
3433
3231
3029
RQ
D%
St Peters Street, Darlinghurst
CASING: HW to 0.6mRIG: Scout
RL
1
2
3
4
5
6
7
8
9
Gra
phic
Log
A Auger sample pp Pocket penetrometer (kPa)D Disturbed sample PID Photo ionisation detectorB Bulk sample S Standard penetration testUx Tube sample (x mm dia.) PL Point load strength Is(50) MPaW Water sample V Shear Vane (kPa)C Core drilling Water seep Water level
C
C
C
0.05
73
81
8485
100
100
SCEGGS DarlinghurstJoan Freeman Building
8.5
PL(A) = 0.8MPa
FILLING - brown to dark brown sandwith gravel and sandstone rubble atbase
BITUMEN
SANDSTONE - extremely lowstrength, highly weathered, greysandstone
PL(A) = 0.8MPa
PL(A) = 1MPa
PL(A) = 0.3MPa
PL(A) = 0.5MPa
2.82m: CORE LOSS:200mm
4.56
4.15
2.82
2.12.0
0.05
SANDSTONE - very low strengthsandstoneSANDSTONE - medium strength,slightly weathered, fractured toslightly fractured, orange brown andlight grey medium grainedsandstone with a possible extremelylow strength band
Bore discontinued at 8.5m
SANDSTONE - medium strength,slightly weathered, slightly fractured,light grey medium grainedsandstone with some very lowstrength bands and some clayseams above 7.2m
0.01
BORE No: 3PROJECT No: 45427DATE: 01 Jul 94SHEET 1 OF 1
CASING: HW to 0.5m
Wat
er
RockStrength
Test Results&
Comments
Degree ofWeathering
BOREHOLE LOG
Depth(m)
These bores are a summary of the original bore logsREMARKS:WATER OBSERVATIONS: No free groundwater observedTYPE OF BORING: Solid flight auger to 0.50m then HQ3 Coring
FractureSpacing
(m)
SAMPLING & IN SITU TESTING LEGEND
SURFACE LEVEL: 37.9EASTING:NORTHING:DIP/AZIMUTH: 90°/--
CLIENT:PROJECT:
CHECKED
Date:
LOGGED: Patel
Initials:
Descriptionof
Strata
EW
HW
MW
SW
FS FR
Sampling & In Situ Testing
DRILLER: Cooper
RQ
D%
1.00
0.50
0.10 C
ore
Rec
. %
TypeB - Bedding
S - ShearJ - JointD - Drill Break
Ex
Low
Ver
y Lo
wLo
wM
ediu
mH
igh
Ver
y H
igh
Ex
Hig
h
St Peters Street, Darlinghurst
3736
3534
3332
3130
2928
A Auger sample pp Pocket penetrometer (kPa)D Disturbed sample PID Photo ionisation detectorB Bulk sample S Standard penetration testUx Tube sample (x mm dia.) PL Point load strength Is(50) MPaW Water sample V Shear Vane (kPa)C Core drilling Water seep Water level
Discontinuities
LOCATION:
RIG: Scout
RL
1
2
3
4
5
6
7
8
9
Gra
phic
Log
0.01
FILLING - topsoil and sandstonerubbleSANDSTONE - medium strength,slightly weathered, fractured, grey,medium grained sandstone withsome slighty fractured lengths and aminor extremely low strength band
- high strength from 3.2m
Bore discontinued at 3.5m
0.25
3.5PL(D) = 1.5MPa
0.05
Discontinuities
J - JointD - Drill Break
B - BeddingS - Shear Ty
pe
70
SCEGGS DarlinghurstJoan Freeman Building
Ex
Low
Ver
y Lo
wLo
wM
ediu
mH
igh
Ver
y H
igh
Ex
Hig
h
FractureSpacing
(m)
C 75
70
100
100
100
C
Sampling & In Situ Testing
C
PL(D) = 0.6MPa
PL(D) = 0.4MPa
PL(D) = 0.9MPa
Wat
er
RockStrength
WATER OBSERVATIONS: No free groundwater observed
Test Results&
Comments
Descriptionof
Strata
BORE No: 4PROJECT No: 45427DATE: 26 Jun 94SHEET 1 OF 1
BOREHOLE LOG
Depth(m)
These bores are a summary of the original bore logs
SAMPLING & IN SITU TESTING LEGEND
SURFACE LEVEL: 33.2EASTING:NORTHING:DIP/AZIMUTH: 90°/--
CLIENT:PROJECT:
CHECKED
Date:
Degree ofWeathering
EW
HW
MW
SW
FS FR
Initials:
TYPE OF BORING: Hand auger to 0.25m then NMLC Coring
RL
RIG: Portable
LOCATION: St Peters Street, Darlinghurst
REMARKS:
1
2
3
4
5
6
7
8
9
0.10G
raph
icLo
g
Cor
eR
ec. %
A Auger sample pp Pocket penetrometer (kPa)D Disturbed sample PID Photo ionisation detectorB Bulk sample S Standard penetration testUx Tube sample (x mm dia.) PL Point load strength Is(50) MPaW Water sample V Shear Vane (kPa)C Core drilling Water seep Water level
RQ
D%
1.00
3332
3130
2928
2726
2524
0.50
LOGGED: Patel CASING: NW to 0.5mDRILLER: Chittleburgh
C
100
B - BeddingS - Shear
SCEGGS DarlinghurstJoan Freeman Building
C
C
Discontinuities
0.01
FractureSpacing
(m)
42
88
100
78
17
CONCRETE
SANDSTONE - medium strength,slightly weathered, fractured toslightly fractured, grey mediumgrained sandstone 1m: CORE LOSS:
420mmSANDSTONE - extremely low tovery low strength, moderatelyweathered, grey fine to medium tocoarse grained sandstone
PL(D) = 1.7MPa
PL(D) = 0.7MPa
PL(D) = 1.4MPa
PL(D) = 0.4MPa
J - JointD - Drill Break
4.0
1.75
1.00.85
FILLING - sandstone rubble andsandy clay
0.1
Bore discontinued at 4.0m
SANDSTONE - high strength,slightly weathered, fractured, greymedium to coarse grainedsandstone with some clay bands to20mm above 3m
0.32
Wat
er
RockStrength
Test Results&
Comments
Descriptionof
Strata
BORE No: 5PROJECT No: 45427DATE: 28 Jun 94SHEET 1 OF 1
BOREHOLE LOG
Depth(m)
0.05
REMARKS:
SAMPLING & IN SITU TESTING LEGEND
SURFACE LEVEL: 30.3EASTING:NORTHING:DIP/AZIMUTH: 90°/--
CLIENT:PROJECT:
CHECKED
Date:
Degree ofWeathering
EW
HW
MW
SW
FS FR
Initials:
WATER OBSERVATIONS: No free groundwater observed
Gra
phic
Log
These bores are a summary of the original bore logs
Cor
eR
ec. %
RQ
D%
1.00
TYPE OF BORING: Hand auger to 0.32m then NMLC Coring
0.10
1
2
3
4
5
6
7
8
9
Ex
Low
Ver
y Lo
wLo
wM
ediu
mH
igh
Ver
y H
igh
Ex
Hig
h
Sampling & In Situ Testing
Type
0.50
DRILLER: Chittleburgh CASING: NW to 0.5mLOGGED: Patel
3029
2827
2625
2423
2221
A Auger sample pp Pocket penetrometer (kPa)D Disturbed sample PID Photo ionisation detectorB Bulk sample S Standard penetration testUx Tube sample (x mm dia.) PL Point load strength Is(50) MPaW Water sample V Shear Vane (kPa)C Core drilling Water seep Water level
St Peters Street, DarlinghurstLOCATION:
RIG: Portable
RL
FractureSpacing
(m)
0.01
0.05
Discontinuities
J - JointD - Drill Break
0.9
0.1
Type
Sampling & In Situ Testing
89
SCEGGS DarlinghurstJoan Freeman Building
0.50
1.00 R
QD
%
B - BeddingS - Shear
PL(D) = 1.6MPa
100C
2.0
0.10
PL(D) = 1.7MPa
FILLING - topsoilFILLING - sandy clay and sandstonerubble
SANDSTONE - high strength,slightly weathered, fractured toslightly fractured, grey and brownmedium grained sandstone
Bore discontinued at 2.0m
Depth(m)
Cor
eR
ec. %
Ex
Low
Ver
y Lo
wLo
wM
ediu
mH
igh
Ver
y H
igh
Ex
Hig
h
BOREHOLE LOG BORE No: 6PROJECT No: 45427DATE: 29 Jun 94SHEET 1 OF 1
CHECKED
These bores are a summary of the original bore logs
RockStrength
Wat
er
Degree ofWeathering
EW
HW
MW
SW
FS FR
Descriptionof
Strata
Initials:
Test Results&
Comments
3029
2827
2625
2423
2221
Gra
phic
Log
1
2
3
4
5
6
7
8
9
RL
RIG: Portable
LOCATION: St Peters Street, Darlinghurst
A Auger sample pp Pocket penetrometer (kPa)D Disturbed sample PID Photo ionisation detectorB Bulk sample S Standard penetration testUx Tube sample (x mm dia.) PL Point load strength Is(50) MPaW Water sample V Shear Vane (kPa)C Core drilling Water seep Water level Date:
LOGGED: Patel CASING: NW to 0.9mDRILLER: ChittleburghTYPE OF BORING: Hand auger to 0.9m then NMLC CoringWATER OBSERVATIONS: No free groundwater observedREMARKS:
SAMPLING & IN SITU TESTING LEGEND
SURFACE LEVEL: 30.1EASTING:NORTHING:DIP/AZIMUTH: 90°/--
CLIENT:PROJECT:
APPENDIX B2 Current Investigation
4.2
SCEGGS DarlinghurstJoan Freeman Building
69
5.2
2.85
2.47
1.24
1.0
0.6
0.20.120.02
10.0
C
A
A
C
C
C
C
PL(A) = 1.7MPa
4.9m: B0°, 5mm clayeysand
4.16m: J30°, ironstained
3.46m: B0°, 2mm clay
3.2m: J40°
2.85m: CORE LOSS:350mm
2.41m: B5°, 5mm
1.24m: CORE LOSS:110mm
Note: Unless otherwisestated, rock is fracturedalong rough, clayveneered, planarbedding or joints dipping0°- 10°
PL(A) = 1.4MPa
PL(A) = 1.9MPa
PL(A) = 2MPa
PL(A) = 1.4MPa
PL(A) = 0.7MPa
PL(A) = 1.7MPa
PL(A) = 0.8MPa
PL(A) = 1.3MPaSANDSTONE - medium and highstrength, moderately weathered andfresh, slightly fractured, light greyand brown medium to coarsegrained sandstone
Bore discontinued at 10.0m
SANDSTONE - high strength, fresh,slightly fractured then unbroken,light grey medium to coarse grainedsandstone
5.2m: B0°, 3mm clayeysand
SANDSTONE - high strength, fresh,slightly fractured, light grey mediumto coarse grained sandstone
5.52m: J30°, ironstained
SANDSTONE - extremely lowstrength, light grey brown, mediumgrained sandstone
FILLING - light grey brown mediumgrained, sand filling with somegravel
SLAG FILLINGROADBASE GRAVELBITUMINOUS CONCRETE
SANDSTONE - medium strength,fresh, slightly fractured, light greymedium grained sandstone
2827
2625
2423
2221
2019
BORE No: 101PROJECT No: 45427DATE: 05 Mar 08SHEET 1 OF 1
BOREHOLE LOG
Depth(m)
REMARKS:WATER OBSERVATIONS: No free groundwater observed whilst augeringTYPE OF BORING: Solid flight auger to 1.0m; NMLC-Coring to 10.0m
DRILLER: E Grima CASING: HW to 1.0m
1
2
3
4
5
6
7
8
9
10
A Auger sample pp Pocket penetrometer (kPa)D Disturbed sample PID Photo ionisation detectorB Bulk sample S Standard penetration testUx Tube sample (x mm dia.) PL Point load strength Is(50) MPaW Water sample V Shear Vane (kPa)C Core drilling Water seep Water level
St Peters Street, DarlinghurstLOCATION:
RIG: Bobcat LOGGED: SI
SAMPLING & IN SITU TESTING LEGEND
SURFACE LEVEL: 28.15EASTING:NORTHING:DIP/AZIMUTH: 90°/--
CLIENT:PROJECT:
CHECKED
Date:
Test Results&
Comments
Descriptionof
Strata
EW
HW
MW
SW
FS FR
Degree ofWeathering
Wat
er
RockStrength
Initials:
RL
FractureSpacing
(m)
87
87
99
100
0.05
Discontinuities
69
100
88
100
100
Type
0.50
0.10
Ex
Low
Ver
y Lo
wLo
wM
ediu
mH
igh
Ver
y H
igh
Ex
Hig
h
0.01 R
QD
%
Sampling & In Situ Testing
1.00
B - BeddingS - Shear
J - JointD - Drill Break C
ore
Rec
. %
Gra
phic
Log
0.3
C
C
10.0
4.15
0.7
A0.150.02
C
1.0
100
100
A
100
SCEGGS DarlinghurstJoan Freeman Building
100
100
PL(A) = 1.8MPa
PL(A) = 1.7MPa
PL(A) = 2.7MPa
PL(A) = 2.1MPa
PL(A) = 1.7MPa
PL(A) = 1MPa
PL(A) = 1.7MPa
PL(A) = 1.5MPa
Note: Unless otherwisestated, rock is fracturedalong rough planarbedding or joints dipping0°- 10°
PL(A) = 1.7MPa
Bore discontinued at 10.0m
SANDSTONE - medium to high thenhigh strength, fresh, slightlyfractured and unbroken, light grey,medium to coarse grainedsandstone
SANDSTONE - high strength,moderately to slightly weathered,slightly fractured, light grey brown,medium to coarse grainedsandstone
SANDSTONE - very low strength,light brown medium grainedsandstone
CLAYEY SAND - orange brown,medium grained clayey sand
FILLING - yellow brown, fine tomedium grained sand filling
BITUMINOUS CONCRETE
C
9.8m: B0°, clayey
7.47m: B15°, clayveneer
6.07m: B0°, clay smear
3.72m: B5°, ironstained
3.55m: B15°, 2mmsandy clay
ROADBASE GRAVEL
REMARKS:
RockStrength
Test Results&
Comments
BORE No: 102PROJECT No: 45427DATE: 3-4/3/08SHEET 1 OF 1
Depth(m)
WATER OBSERVATIONS: No free groundwater observed whilst augeringTYPE OF BORING: Solid flight auger to 1.0m; NMLC-Coring to 10.0m
DRILLER: E Grima CASING: HW to 1.0mLOGGED: SI
BOREHOLE LOG
SAMPLING & IN SITU TESTING LEGEND
SURFACE LEVEL: 27.15EASTING:NORTHING:DIP/AZIMUTH: 90°/--
CLIENT:PROJECT:
CHECKED
Date:
Wat
er
Initials:
Descriptionof
Strata
EW
HW
MW
SW
FS FR
Degree ofWeathering
0.05
Sampling & In Situ Testing
TypeB - Bedding
S - Shear
2726
2524
2322
2120
1918
Discontinuities
0.01
FractureSpacing
(m)
98
100
100
J - JointD - Drill BreakG
raph
icLo
g
A Auger sample pp Pocket penetrometer (kPa)D Disturbed sample PID Photo ionisation detectorB Bulk sample S Standard penetration testUx Tube sample (x mm dia.) PL Point load strength Is(50) MPaW Water sample V Shear Vane (kPa)C Core drilling Water seep Water level
St Peters Street, DarlinghurstLOCATION:
RIG: Bobcat
RL
1
2
3
4
5
6
7
8
9
10
Ex
Low
Ver
y Lo
wLo
wM
ediu
mH
igh
Ver
y H
igh
Ex
Hig
h
Cor
eR
ec. %
RQ
D%
1.00
0.50
0.10
10.0
4.0
1.5
0.350.2
0.11
Bore discontinued at 10.0m
SANDSTONE - medium to high thenhigh strength, fresh, unbroken, lightgrey, medium to coarse grainedsandstone
0.03
100
83
100
100
100
FILLING - crushed sandstone filling
SCEGGS DarlinghurstJoan Freeman Building
97
100
PL(A) = 2.4MPa
PL(A) = 1.9MPa
PL(A) = 1.5MPa
C
C
SANDSTONE - high strength,moderately weathered and fresh,slightly fractured, light grey andbrown medium grained sandstone,with extremely low strength band at1.35-1.68m
C
PL(A) = 1.7MPa
C
1.10-1.35m: J85°
ROADBASE GRAVELBITUMINOUS CONCRETE A
A
PL(A) = 2MPa
1.5m: CORE LOSS:170mm
PL(A) = 1MPa
0.6m: B0°, 15mm clay C
C
PL(A) = 1.7MPa
PL(A) = 2.1MPa
PL(A) = 2MPa
PL(A) = 2.8MPa
SANDSTONE - very low strength,light grey brown, medium grainedsandstone
Note: Unless otherwisestated, rock is fracturedalong rough planarbedding planes or jointsdipping 0°- 10°
DRILLER: E Grima
Test Results&
Comments
BORE No: 103PROJECT No: 45427DATE: 04 Mar 08SHEET 1 OF 1
BOREHOLE LOG
Depth(m)
REMARKS:
St Peters Street, Darlinghurst
TYPE OF BORING: Solid flight auger to 0.35m; NMLC-Coring to 10.0m
Wat
er
CASING: HW to 3.5mLOGGED: SI
2827
2625
2423
2221
2019
WATER OBSERVATIONS: No free groundwater observed whilst augering
Initials:
SAMPLING & IN SITU TESTING LEGEND
SURFACE LEVEL: 28.28EASTING:NORTHING:DIP/AZIMUTH: 90°/--
CLIENT:PROJECT:
CHECKED
Date:
RockStrengthDescription
ofStrata
EW
HW
MW
SW
FS FR
Degree ofWeathering
LOCATION:
97
A Auger sample pp Pocket penetrometer (kPa)D Disturbed sample PID Photo ionisation detectorB Bulk sample S Standard penetration testUx Tube sample (x mm dia.) PL Point load strength Is(50) MPaW Water sample V Shear Vane (kPa)C Core drilling Water seep Water level
B - BeddingS - Shear
J - JointD - Drill Break
Discontinuities
0.05
0.01
FractureSpacing
(m)
100
Type
100
100
67
RQ
D%
RIG: Bobcat
RL
1
2
3
4
5
6
7
8
9
10
Gra
phic
Log
1.00
0.50
0.10
Ex
Low
Ver
y Lo
wLo
wM
ediu
mH
igh
Ver
y H
igh
Ex
Hig
h
Sampling & In Situ Testing
Cor
eR
ec. %
0.17
Type
RIG: Bobcat
LOCATION: St Peters Street, Darlinghurst
LOGGED: AHP
WellConstruction
Details
TYPE OF BORING: Concrete core 120mm solid filght augerWATER OBSERVATIONS: No free groundwater obsesrvedREMARKS:
Depth(m)
BOREHOLE LOG
A Auger sample pp Pocket penetrometer (kPa)D Disturbed sample PID Photo ionisation detectorB Bulk sample S Standard penetration testUx Tube sample (x mm dia.) PL Point load strength Is(50) MPaW Water sample V Shear Vane (kPa)C Core drilling Water seep Water level
SANDSTONE - highly weathered, very low strength, whitesandstone
0.3
0.5
FILLING - brown silty sand filling, some sandstone gravel
CASING: Uncased
Bore discontinued at 0.5m- refusal on sandstone
CONCRETE AND BRICK
Results &CommentsD
epth
Sampling & In Situ Testing
1
Initials:
Gra
phic
Log
SURFACE LEVEL: --EASTING:NORTHING:DIP/AZIMUTH: 90°/--
Sam
ple
BORE No: 104PROJECT No: 45427DATE: 03 Mar 08SHEET 1 OF 1
Descriptionof
Strata
SCEGGS DarlinghurstJoan Freeman Building
Date:
CHECKEDSAMPLING & IN SITU TESTING LEGEND
1
RL
Wat
er
DRILLER: E Grima/DT
CLIENT:PROJECT:
A
A
0.5
0.4
0.170.2
1.05
0.95
WellConstruction
Details
0.6
LOGGED: AHP
0.03
Type
LOCATION:
A Auger sample pp Pocket penetrometer (kPa)D Disturbed sample PID Photo ionisation detectorB Bulk sample S Standard penetration testUx Tube sample (x mm dia.) PL Point load strength Is(50) MPaW Water sample V Shear Vane (kPa)C Core drilling Water seep Water level
0.2
- strong hydrocarbon odour at 0.2m
FILLING - dark brown fine gravel filling
- brick at 0.15m
FILLING - dark grey brown silty snd filling, fine gravel,strong hydrocarbon odour
FILLING - light to dark grey brown silty clayey sand,strong hydrocarbon odour and some fine gravel
SANDSTONE
Bore discontinued at 1.05m- refusal on sandstone
St Peters Street, Darlinghurst
ASPHALT
RL
BORE No: 105PROJECT No: 45427DATE: 03 Mar 08SHEET 1 OF 1
1
Results &Comments
CASING: UncasedRIG: Bobcat
Gra
phic
Log
Sampling & In Situ Testing
1
Wat
er
Dep
th
Sam
ple
Descriptionof
Strata
TYPE OF BORING: Solid flight augerWATER OBSERVATIONS: No free groundwater obsesrvedREMARKS:
Depth(m)
BOREHOLE LOG
Initials:
Date:
CHECKED
CLIENT:PROJECT:
SAMPLING & IN SITU TESTING LEGEND
DRILLER: E Grima/DT
SURFACE LEVEL: --EASTING:NORTHING:DIP/AZIMUTH: 90°/--
SCEGGS DarlinghurstJoan Freeman Building
A
A
0.95
0.8
0.6
0.5
0.4
0.2
0.1
0.02
A
1.05
hydrocarbon odour at0.2m
A
A
Dep
th
Sam
ple
Gra
phic
Log
Type
Initials:
Dynamic Penetrometer Test(blows per mm)
Descriptionof
StrataFILLING - brown sandy filling, with some sandstone gravel
Pit discontinued at 0.6m- refusal on sandstone
0.6
Results &Comments
Sampling & In Situ Testing
1
2
3
4
5
6
7
8
9
Wat
er
TEST PIT LOG
Date:
3029
2827
2625
2423
2221
LOGGED: F Volbrecht
REMARKS:
WATER OBSERVATIONS: No free groundwater observed whilst excavating
Depth(m)
PIT No: 202PROJECT No: 45427DATE: 28 Mar 08SHEET 1 OF 1
5 10 15 20
Sand Penetrometer AS1289.6.3.3 Cone Penetrometer AS1289.6.3.2Surface level interpreted from Tanner Architects site plan
SAMPLING & IN SITU TESTING LEGEND
CLIENT:PROJECT:
CHECKED
SURFACE LEVEL: 30.2EASTING:NORTHING:DIP/AZIMUTH: 90°/--
1
2
3
4
5
6
7
8
9
SCEGGS DarlinghurstJoan Freeman Building
RL
RIG: Hand tools
LOCATION: St Peters Street, Darlinghurst
A Auger sample pp Pocket penetrometer (kPa)D Disturbed sample PID Photo ionisation detectorB Bulk sample S Standard penetration testUx Tube sample (x mm dia.) PL Point load strength Is(50) MPaW Water sample V Shear Vane (kPa)C Core drilling Water seep Water level
Results &Comments
Sampling & In Situ Testing
1
2
3
4
Wat
er
Dep
th
Dynamic Penetrometer Test(blows per mm)
Descriptionof
Strata Gra
phic
Log
0.1CONCRETEFILLING - brown sandy filling, with some sandstone graveland brick fragments
SANDSTONE - very low to low strength, red brownsandstoneSANDSTONE - low to medium strength, light greysandstonePit discontinued at 0.8m- limit of investigation
0.70.750.8
Sam
ple
Surface level interpreted from Tanner Architects site plan
5 10 15 20
LOCATION:
PIT No: 203PROJECT No: 45427DATE: 28 Apr 08SHEET 1 OF 1
Type
Depth(m)
3231
3029
28
WATER OBSERVATIONS: No free groundwater observed whilst excavating
RIG: Hand tools
A Auger sample pp Pocket penetrometer (kPa)D Disturbed sample PID Photo ionisation detectorB Bulk sample S Standard penetration testUx Tube sample (x mm dia.) PL Point load strength Is(50) MPaW Water sample V Shear Vane (kPa)C Core drilling Water seep Water level
REMARKS:
LOGGED: B O'Kane
TEST PIT LOGCLIENT:PROJECT:
Initials:
Date:
Sand Penetrometer AS1289.6.3.3 Cone Penetrometer AS1289.6.3.2
SURFACE LEVEL: 32.0EASTING:NORTHING:DIP/AZIMUTH: 90°/--
SAMPLING & IN SITU TESTING LEGEND
SCEGGS DarlinghurstJoan Freeman Building
1
2
3
4
RL
St Peters Street, Darlinghurst
CHECKED
Log!
GR
AP
HIC
-SY
MB
OLS
24
/11/
2003
4:3
8:57
PM
GRAPHIC SYMBOLS FOR SOIL & ROCK
CONGLOMERATE
CONGLOMERATIC SANDSTONE
BOULDER CONGLOMERATE
SANDSTONE FINE GRAINED
SANDSTONE COARSE GRAINED
BITUMINOUS CONCRETE
CONCRETE
FILLING
TOPSOIL
PEAT
CLAY
SOIL
GRAVELLY CLAY
SHALY CLAY
SILT
CLAYEY SILT
SILTY CLAY
COBBLES/BOULDERS
SANDY CLAY
SANDY SILT
SAND
CLAYEY SAND
SILTY SAND
GRAVEL
SANDY GRAVEL
LAMINITE
MUDSTONE, CLAYSTONE, SHALE
COAL
LIMESTONE
IGNEOUS ROCK
GNEISS
QUARTZITE
DOLERITE, BASALT
SEDIMENTARY ROCK
SILTSTONE
METAMORPHIC ROCK
CLAYEY GRAVEL
SLATE, PHYLITTE, SCHIST
GRANITE
TUFF
PORPHYRYTALUS
Issued: October 1998 Page 1 of 4
NOTES RELATING TO THIS REPORT
Introduction These notes have been provided to amplify the
geotechnical report in regard to classification methods, specialist field procedures and certain matters relating to the Discussion and Comments section. Not all, of course, are necessarily relevant to all reports.
Geotechnical reports are based on information gained from limited subsurface test boring and sampling, supplemented by knowledge of local geology and experience. For this reason, they must be regarded as interpretive rather than factual documents, limited to some extent by the scope of information on which they rely.
Description and Classification Methods The methods of description and classification of soils
and rocks used in this report are based on Australian Standard 1726, Geotechnical Site Investigations Code. In general, descriptions cover the following properties - strength or density, colour, structure, soil or rock type and inclusions.
Soil types are described according to the predominating particle size, qualified by the grading of other particles present (eg. sandy clay) on the following bases:
Soil Classification Particle Size
Clay less than 0.002 mm Silt 0.002 to 0.06 mm Sand 0.06 to 2.00 mm Gravel 2.00 to 60.00 mm
Cohesive soils are classified on the basis of strength
either by laboratory testing or engineering examination. The strength terms are defined as follows.
Classification Undrained
Shear Strength kPa Very soft less than 12 Soft 12—25 Firm 25—50 Stiff 50—100 Very stiff 100—200 Hard Greater than 200
Non-cohesive soils are classified on the basis of relative
density, generally from the results of standard penetration tests (SPT) or Dutch cone penetrometer tests (CPT) as below:
Relative Density SPT “N” Value (blows/300 mm)
CPT Cone Value (qc — MPa)
Very loose less than 5 less than 2 Loose 5—10 2—5 Medium dense 10—30 5—15 Dense 30—50 15—25 Very dense greater than 50 greater than 25
Rock types are classified by their geological names. Where relevant, further information regarding rock classification is given on the following sheet.
Sampling Sampling is carried out during drilling to allow
engineering examination (and laboratory testing where required) of the soil or rock.
Disturbed samples taken during drilling provide information on colour, type, inclusions and, depending upon the degree of disturbance, some information on strength and structure.
Undisturbed samples are taken by pushing a thin-walled sample tube into the soil and withdrawing with a sample of the soil in a relatively undisturbed state. Such samples yield information on structure and strength, and are necessary for laboratory determination of shear strength and compressibility. Undisturbed sampling is generally effective only in cohesive soils.
Details of the type and method of sampling are given in the report.
Drilling Methods. The following is a brief summary of drilling methods
currently adopted by the Company and some comments on their use and application.
Test Pits — these are excavated with a backhoe or a tracked excavator, allowing close examination of the in-situ soils if it is safe to descent into the pit. The depth of penetration is limited to about 3 m for a backhoe and up to 6 m for an excavator. A potential disadvantage is the disturbance caused by the excavation.
Large Diameter Auger (eg. Pengo) — the hole is advanced by a rotating plate or short spiral auger, generally 300 mm or larger in diameter. The cuttings are returned to the surface at intervals (generally of not more than 0.5 m) and are disturbed but usually unchanged in moisture content. Identification of soil strata is generally much more reliable than with continuous spiral flight augers, and is usually supplemented by occasional undisturbed tube sampling.
Continuous Sample Drilling — the hole is advanced by pushing a 100 mm diameter socket into the ground and withdrawing it at intervals to extrude the sample. This is the most reliable method of drilling in soils, since moisture content is unchanged and soil structure, strength, etc. is only marginally affected.
Continuous Spiral Flight Augers — the hole is advanced using 90—115 mm diameter continuous spiral flight augers which are withdrawn at intervals to allow sampling or in-situ testing. This is a relatively economical means of drilling in clays and in sands above the water
Issued: October 1998 Page 2 of 4
table. Samples are returned to the surface, or may be collected after withdrawal of the auger flights, but they are very disturbed and may be contaminated. Information from the drilling (as distinct from specific sampling by SPTs or undisturbed samples) is of relatively lower reliability, due to remoulding, contamination or softening of samples by ground water. Non-core Rotary Drilling — the hole is advanced by a rotary bit, with water being pumped down the drill rods and returned up the annulus, carrying the drill cuttings. Only major changes in stratification can be determined from the cuttings, together with some information from ‘feel’ and rate of penetration. Rotary Mud Drilling — similar to rotary drilling, but using drilling mud as a circulating fluid. The mud tends to mask the cuttings and reliable identification is again only possible from separate intact sampling (eg. from SPT). Continuous Core Drilling — a continuous core sample is obtained using a diamond-tipped core barrel, usually 50 mm internal diameter. Provided full core recovery is achieved (which is not always possible in very weak rocks and granular soils), this technique provides a very reliable (but relatively expensive) method of investigation. Standard Penetration Tests
Standard penetration tests (abbreviated as SPT) are used mainly in non-cohesive soils, but occasionally also in cohesive soils as a means of determining density or strength and also of obtaining a relatively undisturbed sample. The test procedure is described in Australian Standard 1289, “Methods of Testing Soils for Engineering Purposes” — Test 6.3.1.
The test is carried out in a borehole by driving a 50 mm diameter split sample tube under the impact of a 63 kg hammer with a free fall of 760 mm. It is normal for the tube to be driven in three successive 150 mm increments and the ‘N’ value is taken as the number of blows for the last 300 mm. In dense sands, very hard clays or weak rock, the full 450 mm penetration may not be practicable and the test is discontinued.
The test results are reported in the following form. • In the case where full penetration is obtained with
successive blow counts for each 150 mm of say 4, 6 and 7 as 4, 6, 7 N = 13
• In the case where the test is discontinued short of full penetration, say after 15 blows for the first 150 mm and 30 blows for the next 40 mm as 15, 30/40 mm. The results of the tests can be related empirically to the
engineering properties of the soil. Occasionally, the test method is used to obtain samples
in 50 mm diameter thin walled sample tubes in clays. In such circumstances, the test results are shown on the borelogs in brackets.
Cone Penetrometer Testing and Interpretation Cone penetrometer testing (sometimes referred to as
Dutch cone — abbreviated as CPT) described in this report has been carried out using an electrical friction cone penetrometer. The test is described in Australian Standard 1289, Test 6.4.1.
In the tests, a 35 mm diameter rod with a cone-tipped end is pushed continuously into the soil, the reaction being provided by a specially designed truck or rig which is fitted with an hydraulic ram system. Measurements are made of the end bearing resistance on the cone and the friction resistance on a separate 130 mm long sleeve, immediately behind the cone. Transducers in the tip of the assembly are connected by electrical wires passing through the centre of the push rods to an amplifier and recorder unit mounted on the control truck.
As penetration occurs (at a rate of approximately 20 mm per second) the information is plotted on a computer screen and at the end of the test is stored on the computer for later plotting of the results.
The information provided on the plotted results comprises: — • Cone resistance — the actual end bearing force divided
by the cross sectional area of the cone — expressed in MPa.
• Sleeve friction — the frictional force on the sleeve divided by the surface area — expressed in kPa.
• Friction ratio — the ratio of sleeve friction to cone resistance, expressed in percent. There are two scales available for measurement of
cone resistance. The lower scale (0—5 MPa) is used in very soft soils where increased sensitivity is required and is shown in the graphs as a dotted line. The main scale (0—50 MPa) is less sensitive and is shown as a full line.
The ratios of the sleeve friction to cone resistance will vary with the type of soil encountered, with higher relative friction in clays than in sands. Friction ratios of 1%—2% are commonly encountered in sands and very soft clays rising to 4%—10% in stiff clays.
In sands, the relationship between cone resistance and SPT value is commonly in the range:—
qc (MPa) = (0.4 to 0.6) N (blows per 300 mm) In clays, the relationship between undrained shear
strength and cone resistance is commonly in the range:— qc = (12 to 18) cu
Interpretation of CPT values can also be made to allow estimation of modulus or compressibility values to allow calculation of foundation settlements.
Inferred stratification as shown on the attached reports is assessed from the cone and friction traces and from experience and information from nearby boreholes, etc. This information is presented for general guidance, but must be regarded as being to some extent interpretive. The test method provides a continuous profile of engineering properties, and where precise information on soil classification is required, direct drilling and sampling may be preferable.
Issued: October 1998 Page 3 of 4
Hand Penetrometers
Hand penetrometer tests are carried out by driving a rod into the ground with a falling weight hammer and measuring the blows for successive 150 mm increments of penetration. Normally, there is a depth limitation of 1.2 m but this may be extended in certain conditions by the use of extension rods.
Two relatively similar tests are used. • Perth sand penetrometer — a 16 mm diameter flat-
ended rod is driven with a 9 kg hammer, dropping 600 mm (AS 1289, Test 6.3.3). This test was developed for testing the density of sands (originating in Perth) and is mainly used in granular soils and filling.
• Cone penetrometer (sometimes known as the Scala Penetrometer) — a 16 mm rod with a 20 mm diameter cone end is driven with a 9 kg hammer dropping 510 mm (AS 1289, Test 6.3.2). The test was developed initially for pavement subgrade investigations, and published correlations of the test results with California bearing ratio have been published by various Road Authorities.
Laboratory Testing Laboratory testing is carried out in accordance with
Australian Standard 1289 “Methods of Testing Soil for Engineering Purposes”. Details of the test procedure used are given on the individual report forms.
Bore Logs
The bore logs presented herein are an engineering and/or geological interpretation of the subsurface conditions, and their reliability will depend to some extent on frequency of sampling and the method of drilling. Ideally, continuous undisturbed sampling or core drilling will provide the most reliable assessment, but this is not always practicable, or possible to justify on economic grounds. In any case, the boreholes represent only a very small sample of the total subsurface profile.
Interpretation of the information and its application to design and construction should therefore take into account the spacing of boreholes, the frequency of sampling and the possibility of other than ‘straight line’ variations between the boreholes.
Ground Water
Where ground water levels are measured in boreholes, there are several potential problems; • In low permeability soils, ground water although present,
may enter the hole slowly or perhaps not at all during the time it is left open.
• A localised perched water table may lead to an erroneous indication of the true water table.
• Water table levels will vary from time to time with seasons or recent weather changes. They may not be
the same at the time of construction as are indicated in the report.
• The use of water or mud as a drilling fluid will mask any ground water inflow. Water has to be blown out of the hole and drilling mud must first be washed out of the hole if water observations are to be made. More reliable measurements can be made by installing
standpipes which are read at intervals over several days, or perhaps weeks for low permeability soils. Piezometers, sealed in a particular stratum, may be advisable in low permeability soils or where there may be interference from a perched water table.
Engineering Reports
Engineering reports are prepared by qualified personnel and are based on the information obtained and on current engineering standards of interpretation and analysis. Where the report has been prepared for a specific design proposal (eg. a three storey building), the information and interpretation may not be relevant if the design proposal is changed (eg. to a twenty storey building). If this happens, the Company will be pleased to review the report and the sufficiency of the investigation work.
Every care is taken with the report as it relates to interpretation of subsurface condition, discussion of geotechnical aspects and recommendations or suggestions for design and construction. However, the Company cannot always anticipate or assume responsibility for: • unexpected variations in ground conditions — the
potential for this will depend partly on bore spacing and sampling frequency
• changes in policy or interpretation of policy by statutory authorities
• the actions of contractors responding to commercial pressures. If these occur, the Company will be pleased to assist
with investigation or advice to resolve the matter.
Site Anomalies In the event that conditions encountered on site during
construction appear to vary from those which were expected from the information contained in the report, the Company requests that it immediately be notified. Most problems are much more readily resolved when conditions are exposed than at some later stage, well after the event.
Reproduction of Information for Contractual Purposes
Attention is drawn to the document “Guidelines for the Provision of Geotechnical Information in Tender Documents”, published by the Institution of Engineers, Australia. Where information obtained from this investigation is provided for tendering purposes, it is recommended that all information, including the written report and discussion, be made available. In circumstances where the discussion or comments section
Issued: October 1998 Page 4 of 4
is not relevant to the contractual situation, it may be appropriate to prepare a specially edited document. The Company would be pleased to assist in this regard and/or to make additional report copies available for contract purposes at a nominal charge.
Site Inspection The Company will always be pleased to provide
engineering inspection services for geotechnical aspects of work to which this report is related. This could range from a site visit to confirm that conditions exposed are as expected, to full time engineering presence on site.
Copyright © 1998 Douglas Partners Pty Ltd
AN ENGINEERING CLASSIFICATION OF SEDIMENTARY
ROCKS IN THE SYDNEY AREA
This classification system provides a standardized terminology for the engineering description of the sandstone and shales in the Sydney area,but the terms and definitions may be used elsewhere when applicable.
Under this system rocks are classified by Rock Type, Degree of Weathering, Strength, Stratification Spacing, and Degree of Fracturing. These terms do not cover the full range of engineering properties. Descriptions of rock may also need to refer to other properties (e.g. durability,abrasiveness, etc.) where these are relevant.
ROCK TYPE DEFINITIONS
Rock Type Definition
Conglomerate: More than 50% of the rock consists of gravel sized (greater than 2mm) fragments
Sandstone: More than 50% of the rock consists of sand sized (.06 to 2mm) fragments
Siltstone: More than 50% of the rock consists of silt-sized (less than 0.06mm) granular particles and the rock is not laminated
Claystone: More than 50% of the rock consists of clay or sericitic material and the rock is not laminated
Shale: More than 50% of the rock consists of silt or clay sized particles and the rock is laminated
Rocks possessing characteristics of two groups are described by their predominant particle size with reference also to the minor constituents,e.g. clayey sandstone, sandy shale.
DEGREE OF WEATHERING
Term Symbol Definition
ExtremelyWeathered
EW Rock substance affected by weathering to the extent that the rock exhibits soil properties - i.e. it can beremoulded and can be classified according to the Unified Classification System, but the texture of the original rock is still evident.
HighlyWeathered
HW Rock substance affected by weathering to the extent that limonite staining or bleaching affects the whole of the rock substance and other signs of chemical or physical decomposition are evident. Porosity and strength may be increased or decreased compared to the fresh rock usually as a result of iron leaching or deposition. The colour and strength of the original fresh rock substance is no longer recognisable.
ModeratelyWeathered
MW Rock substance affected by weathering to the extent that staining or discolouration of the rock substance usually by limonite has taken place. The colour and texture of the fresh rock is no longer recognisable.
SlightlyWeathered
SW Rock substance affected by weathering to the extent that partial staining or discolouration of the rock substance usually by limonite has taken place. The colour and texture of the fresh rock is recognisable.
Fresh Fs Rock substance unaffected by weathering, limonite staining along joints.
Fresh Fr Rock substance unaffected by weathering.
STRATIFICATION SPACING
Term Separation ofStratification Planes
Thinly laminated <6 mm
Laminated 6 mm to 20 mm
Very thinly bedded 20 mm to 60 mm
Thinly bedded 60 mm to 0.2 m
Medium bedded 0.2 m to 0.6 m
Thickly bedded 0.6 m to 2 m
Very thickly bedded >2 m
ROCK STRENGTH
Rock strength is defined by the Point Load Strength Index (Is 50) and refers to the strength of the rock substance in the direction normal to the bedding. The test procedure is described by the International Society of Rock Mechanics (Reference).
Strength Term Is(50)MPa
Field Guide Approx.qu MPa*
ExtremelyLow:
VeryLow:
Low:
Medium:
High:
VeryHigh:
ExtremelyHigh:
0.03
0.1
0.3
1
3
10
Easily remoulded by hand to a material with soil properties
May be crumbled in the hand. Sandstone is “sugary” and friable.
A piece of core 150 mm long x 50 mm dia. may be broken by hand and easily scored with a knife. Sharp edges of core may be friable and break during handling.
A piece of core 150 mm long x 50 mm dia. can be broken by hand with considerable difficulty. Readily scored with knife.
A piece of core 150 mm long x 50 mm dia. cannot be broken by unaided hands,can be slightly scratched or scored with knife.
A piece of core 150 mm long x 50 mm dia. may be broken readily with hand held hammer. Cannot be scratched with pen knife.
A piece of core 150 mm long x 50 mm dia. is difficult to break with hand heldhammer. Rings when struck with a hammer.
0.7
2.4
7
24
70
240
* The approximate unconfined compressive strength (qu) shownin the table is based on an assumed ratio to the point load index of 24:1.This ratio may vary widely.
DEGREE OF FRACTURING
This classification applies to diamond drill cores and refers to the spacing of all types of natural fractures along which the core is discontinuous.These include bedding plane partings, joints and other rock defects, but exclude known artificial fractures such as drilling breaks
Term Description
Fragmented: The core is comprised primarily of fragments of length less than 20 mm, and mostly of width less than the core diameter.
Highly Fractured: Core lengths are generally less than 20 mm - 40 mm with occasional fragments.
Fractured: Core lengths are mainly 30 mm - 100 mm with occasional shorter and longer sections.
Slightly Fractured: Core lengths are generally 300 mm - 1000 mm with occasional longer sections and occasional sections of 100 mm - 300 mm.
Unbroken: The core does not contain any fracture.
REFERENCE
International Society of Rock Mechanics, Commission on Standardisation of Laboratory and Field Tests, Suggested Methods for Determining the Uniaxial Compressive Strength of Rock Materials and the Point Load Strength Index, Committee on Laboratory Tests Document No. 1 Final Draft October 1972
SCEGGS Darlinghurst 25 SEPTEMBER 2019 Construction Impacts – Response to Submissions 181375 - SAAB
Taylor Thomson Whitting (NSW) Pty Ltd © 2019 Taylor Thomson Whitting Page 8 of 8
Appendix B
Construction and Operational Noise Report
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION CONSTRUCTION & OPERATIONAL NOISE REPORT
REPORT NO. 18180
VERSION B
JULY 2019
PREPARED FOR
SCECGS DARLINGHURST
C/- SANDRICK PROJECT DIRECTIONS
SUITE 412, NEXUS NORWEST
COLUMBIA COURT, NORWEST BUSINESS PARK
BAULKHAM HILLS NSW 2153
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
DOCUMENT CONTROL
Version Status Date Prepared By Reviewed By
A Final 3 October 2018 Brian Clarke Ben Lawrence
B Draft 22 July 2019 Brian Clarke Ben Lawrence
Note
All materials specified by Wilkinson Murray Pty Limited have been selected solely on the basis of acoustic performance.
Any other properties of these materials, such as fire rating, chemical properties etc. should be checked with the suppliers
or other specialised bodies for fitness for a given purpose. The information contained in this document produced
by Wilkinson Murray is solely for the use of the client identified on the front page of this report. Our client becomes the
owner of this document upon full payment of our Tax Invoice for its provision. This document must not be used for any
purposes other than those of the document’s owner. Wilkinson Murray undertakes no duty to or accepts any responsibility
to any third party who may rely upon this document.
Quality Assurance
Wilkinson Murray operates a Quality Management System which complies with the requirements of
AS/NZS ISO 9001:2015. This management system has been externally certified by SAI Global and
Licence No. QEC 13457 has been issued.
AAAC
This firm is a member firm of the Association of Australasian Acoustical Consultants and the work here
reported has been carried out in accordance with the terms of that membership.
Celebrating 50 Years in 2012
Wilkinson Murray is an independent firm established in 1962, originally as Carr & Wilkinson.
In 1976 Barry Murray joined founding partner Roger Wilkinson and the firm adopted the name which
remains today. From a successful operation in Australia, Wilkinson Murray expanded its reach into Asia
by opening a Hong Kong office early in 2006. Today, with offices in Sydney, Newcastle, Wollongong,
Orange, Queensland and Hong Kong, Wilkinson Murray services the entire Asia-Pacific region.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
TABLE OF CONTENTS
Page
GLOSSARY OF ACOUSTIC TERMS
1 INTRODUCTION 1
2 AMBINET NOISE MONITORING 3
2.1 Ambient Noise Levels at the Site 3
3 CONSTRUCTION NOISE & VIBRATION ASSESSMENT 5
3.1 Construction Noise Criteria 5 3.1.1 Construction Noise Management Levels 5
3.2 Hours of Operation & Programme 6
3.3 Vibration Criteria 7 3.3.1 Building Damage 8
3.4 Construction Equipment & Noise Source Levels 9
3.5 Construction Noise Predictions 10
3.6 Discussion of Results 11
3.7 Construction Vibration Assessment 12
3.8 Construction Noise & Vibration Mitigation Measures 13
3.9 Community Liaison & General Approaches to Mitigation 13
3.10 Noise & Vibration Management Plan 14
3.11 Management of Construction Noise & Vibration to the School 14
4 OPERATIONAL NOISE & VIBRATION 15
4.1 Operational Noise Criteria 15
4.2 Project Noise Trigger Levels 17
4.3 Mechanical Services 19
4.4 Wilkinson Building Noise Emissions 20
4.5 New Multi-Purpose Building 20
4.6 New Administration Building & Restoration of Barham 21
4.7 School Announcements & Bells 21
5 SUMMARY OF RECOMMENDATIONS 22
5.1 Construction Noise 22
5.2 Operational Noise 23
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
6 CONCLUSION 24
APPENDIX A – Noise Measurement Results
APPENDIX B – Response to Submissions
APPENDIX C – Draft Construction Noise & Vibration Management Plan
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
GLOSSARY OF ACOUSTIC TERMS
Most environments are affected by environmental noise which continuously varies, largely as a result of road
traffic. To describe the overall noise environment, a number of noise descriptors have been developed and
these involve statistical and other analysis of the varying noise over sampling periods, typically taken as 15
minutes. These descriptors, which are demonstrated in the graph below, are here defined.
Maximum Noise Level (LAmax) – The maximum noise level over a sample period is the maximum level,
measured on fast response, during the sample period.
LA1 – The LA1 level is the noise level which is exceeded for 1% of the sample period. During the sample
period, the noise level is below the LA1 level for 99% of the time.
LA10 – The LA10 level is the noise level which is exceeded for 10% of the sample period. During the sample
period, the noise level is below the LA10 level for 90% of the time. The LA10 is a common noise descriptor
for environmental noise and road traffic noise.
LA90 – The LA90 level is the noise level which is exceeded for 90% of the sample period. During the sample
period, the noise level is below the LA90 level for 10% of the time. This measure is commonly referred to as
the background noise level.
LAeq – The equivalent continuous sound level (LAeq) is the energy average of the varying noise over the
sample period and is equivalent to the level of a constant noise which contains the same energy as the
varying noise environment. This measure is also a common measure of environmental noise and road traffic
noise.
ABL – The Assessment Background Level is the single figure background level representing each assessment
period (daytime, evening, and night time) for each day. It is determined by calculating the 10th percentile
(lowest 10th percent) background level (LA90) for each period.
RBL – The Rating Background Level for each period is the median value of the ABL values for the period
over all of the days measured. There is therefore an RBL value for each period – daytime, evening and
night time.
Typical Graph of Sound Pressure Level vs Time
20
25
30
35
40
45
50
55
60
0:00 3:00 6:00 9:00 12:00 15:00
Monitoring or Survey Period (5 sec samples)
So
un
d P
ressu
re L
evel
(dB
A) L Amax
L A1
L A10
L Aeq
L A50
L A90
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 1
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
1 INTRODUCTION
This noise impact assessment (NIA) has been prepared to accompany a State Significant
Development Application for the proposed masterplan and redevelopment of the Sydney Church
of England Girls’ Grammar School, Darlinghurst (SCEGGS) site at 215 Forbes Street, Darlinghurst.
It accompanies an environmental impact statement (EIS) prepared in support of State Significant
Development Application SSD 8993 for the staged development of the SCECGS Darlinghurst
Campus.
The State Significant Development is for:
– a Masterplan Concept Development Application for building envelopes, building locations and
land uses across the campus, to guide development over the next 20 years, and;
– a Stage 1 Detailed Design Proposal for the first stage of works, comprising the replacement
of Wilkinson House with a new building. Details of the project are described in the following
sections.
This assessment responds to the issue raised in item 8 of the SEARs as follows:
8. Noise and Vibration
Identify and provide quantitative assessment of the main noise and vibration generation sources
during construction and operation, including consideration of public address system, school bell
and the use of the school hall for concerts etc. (both during and outside school hours) Outline
measures to minimise and mitigate the potential noise impacts on surrounding occupiers of land.
Relevant Policies and Guidelines:
• Noise Policy for Industry 2017 (EPA)
• Interim Construction Noise Guideline (DECC)
• Assessing Vibration: A technical Guideline 2006
• Development Near Rail Corridors and Busy Roads - Interim Guideline (Department of Planning
2008)
This report consists of the original NIA that was submitted to the Department of Planning along
with Appendix B which includes a response to submissions that relate to noise and vibration. In
addition, Appendix C includes a draft construction noise and vibration management plan.
Figure 1-1 shows the Masterplan site.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 2
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Figure 1-1 2040 Masterplan Site
Wilkinson House
The redevelopment of Wilkinson House will involve the demolition of the existing structure and
the construction of a new building maximising the potential of the site.
The design for a new building will provide the opportunity to:
• reconfigure the planning to provide large open spaces through a more efficient location of
the circulation core and the provision of a column free structure;
• align the floor levels with Joan Freeman Building;
• provide an additional floor level to the current number of levels;
• efficiently integrate services;
• improve the accessibility and amenity of the building; and
• improve security for the building.
The design is for flexible learning spaces, specialised learning areas, student facilities, and
administration areas.
New Multi-Purpose Building
The design will remain as a Masterplan concept. The Masterplan will allow the school options for
the final use and facilities to be provided in the building. This includes an option to provide an
indoor swimming pool or to use the space for another educational use. There may also be an
option to include a child-minding facility. It is envisaged that the new multi-purpose building will
be air-conditioned, and it will be designed to meet a 4-Greenstar rating or equivalent.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 3
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
2 AMBINET NOISE MONITORING
2.1 Ambient Noise Levels at the Site
Residential receivers surrounding the site that may be affected by construction and operational
noise have been identified in four areas and are detailed in Table 2-1 and shown in Figure 2-1.
Figure 2-1 Aerial showing Noise Monitoring Locations
Table 2-1 Surrounding Receivers
Receivers Comments
A – Thomson Street & Lane Residences Terrace residences
B – Bourke Street Terrace residences and Commercial receivers
C – Forbes Street Mix of single and multi-storey residential buildings
D – St Peters Street Church on the opposite of St Peters Street
In order to quantify the existing noise environment, long-term ambient noise levels were
monitored at two (2) locations surrounding the site, selected to cover the range of environments
in the potentially affected areas.
The locations are presented in Table 2-2. The noise logger locations are shown in Figure 2-1.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 4
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Table 2-2 Long-Term Noise Monitoring Locations
Logger Location Monitoring Period
1 Thomson Street boundary 14 – 24 September 2018
2 Horizon Apartments Forbes Street 14 – 24 September 2018
The noise monitoring equipment used for the Wilkinson Murray noise measurements consisted of
ARL Type EL-215 environmental noise loggers set to A-weighted, fast response, continuously
monitoring over 15-minute sampling periods. This equipment is capable of remotely monitoring
and storing noise level descriptors for later detailed analysis. The equipment calibration was
checked before and after the survey and no significant drift was noted.
The logger determines LA1, LA10, LA90 and LAeq levels of the ambient noise. LA1, LA10 and LA90 are
the levels exceeded for 1%, 10% and 90% of the sample time respectively (see Glossary for
definitions). The LA1 is indicative of maximum noise levels due to individual noise events such as
the occasional pass-by of a heavy vehicle. The LA90 level is normally taken as the background
noise level during the relevant period.
Detailed results for each monitoring location are shown in graphical form in Appendix A. The
graphs show measured values of LAeq, LA90, LA10 and LA1 for each 15-minute monitoring period.
Table 2-3 summarises the noise results, for daytime, evening and night time periods as defined
in the EPA’s Interim Construction Noise Guidelines (ICNG) and the NSW Noise Policy for Industry
(NPfI).
Table 2-3 Summary of Measured Ambient Noise Levels
Noise
Logging
Site
RBL (dBA) LAeq,period (dBA)
Daytime
7am-6pm
Evening
6-10pm
Night Time
10pm-7am
Saturday
8am-1pm
Daytime
7am-6pm
Evening
6-10pm
Night Time
10pm-7am
Saturday
8am-1pm
1 47 45 44 47 56 52 49 57
2 50 49 47 50 55 55 53 54
Background noise levels at all locations were free of the influence of extraneous noise sources,
such as plant or construction activities. Noise data measured during inclement weather was
excluded in accordance with EPA procedures.
Results of noise monitoring are presented in Appendix A.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 5
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
3 CONSTRUCTION NOISE & VIBRATION ASSESSMENT
This section of the assessment relates to Stage 1 works, whereby other stages of the development
will be assessed when applications are made for these works. It should be noted that the noise
and vibration criteria detailed in the following sections is applicable to all stages of the Masterplan.
3.1 Construction Noise Criteria
The following sections detail the applicable site-specific noise and vibration criteria based on the
EPA Interim Construction Noise Guideline.
3.1.1 Construction Noise Management Levels
The EPA released the Interim Construction Noise Guideline (ICNG) in July 2009. The guideline
provides noise goals that assist in assessing the impact of construction noise.
For residences, the basic daytime construction noise goal is that the LAeq,15min noise management
level should not exceed the background noise by more than 10dBA. This is for standard hours:
Monday to Friday 7.00am-6.00pm, and Saturday 8.00am-1.00pm. Outside the standard hours,
where construction is justified, the noise management level would be background + 5dBA.
Table 3-1 details the ICNG noise management levels.
Table 3-1 Construction Noise Management Levels at Residences using
Quantitative Assessment
Time of Day
Management
Level
LAeq,(15min)
How to Apply
Recommended
Standard Hours:
Monday to Friday
7am to 6pm
Saturday
8am to 1pm
No work on Sundays
or Public Holidays
Noise affected
RBL + 10dBA
The noise affected level represents the point above which there may
be some community reaction to noise.
Where the predicted or measured LAeq,(15min) is greater than the
noise affected level, the proponent should apply all feasible and
reasonable work practices to minimise noise.
The proponent should also inform all potentially impacted residents
of the nature of works to be carried out, the expected noise levels
and duration, as well as contact details.
Highly noise
affected
75dBA
The highly noise affected level represents the point above which
there may be strong community reaction to noise.
Where noise is above this level, the proponent should consider very
carefully if there is any other feasible and reasonable way to reduce
noise to below this level.
If no quieter work method is feasible and reasonable, and the works
proceed, the proponent should communicate with the impacted
residents by clearly explaining the duration and noise level of the
works, and by describing any respite periods that will be provided.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 6
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Time of Day
Management
Level
LAeq,(15min)
How to Apply
Outside
recommended
standard hours
Noise affected
RBL + 5dB
A strong justification would typically be required for works outside
the recommended standard hours.
The proponent should apply all feasible and reasonable work
practices to meet the noise affected level.
Where all feasible and reasonable practices have been applied and
noise is more than 5dB(A) above the noise affected level, the
proponent should negotiate with the community.
For guidance on negotiating agreements see Section 7.2.2.
In addition, the following construction noise management levels LAeq,15 min are recommended for
other receivers and areas:
• Active recreation areas (such as parks): external LAeq,15min 65dBA
• Industrial premises: external LAeq,15min 75dBA
• Offices, retail outlets: external LAeq,15min 70dBA
• Classrooms at schools and other educational institutions: internal LAeq,15min 45dBA
Based on the above, Table 3-2 presents the applicable noise management levels for construction
activities at surrounding receivers that have been adopted for all applications.
Table 3-2 Site-Specific Construction Noise Management Levels
Area
Construction Noise Management Level,
LAeq – dBA
Highly noise
affected Noise
Level, LAeq
dBA Day Evening Night Saturday*
A – Thomson Street & Lane Residences 57 50 49 57 75
B – Bourke Street 57 50 49 57 75
C – Forbes Street 60 54 52 60 75
D – St Peters Street 60 54 52 60 75
* Standard Saturday construction hours.
3.2 Hours of Operation & Programme
The proposed working hours for this project are as follows:
• Monday to Friday 7.00am to 7.00pm
• Saturday 8.00am to 1.00pm
• Sunday and Public Holidays No work
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 7
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
If required, after hours permits will be sought from the relevant authorities.
3.3 Vibration Criteria
Criteria for assessment of the effects of vibration on human comfort are set out in British Standard
6472-1992. Methods and criteria in that Standard are used to set “preferred” and “maximum”
vibration levels in the document Assessing Vibration: A Technical Guideline (2006) produced by
the NSW DECCW.
Acceptable values of human exposure to continuous vibration, such as that associated with
drilling, are dependent on the time of day and the activity taking place in the occupied space
(e.g. workshop, office, residence, or a vibration-critical area). Guidance on preferred values for
continuous vibration is set out in Table 3-3.
Table 3-3 Criteria for Exposure to Continuous Vibration
Place Time
Peak Particle Velocity
(mm/s)
Preferred Maximum
Critical working areas
(e.g. hospital operating theatres precision
laboratories)
Day or Night time 0.14 0.28
Residences Daytime 0.28 0.56
Night time 0.20 0.40
Offices Day or Night time 0.56 1.1
Workshops Day or Night time 1.1 2.2
In the case of intermittent vibration, which is caused by plant such as rock breakers, the criteria
are expressed as a Vibration Dose Value (VDV) and are presented in Table 3-4.
Table 3-4 Acceptable Vibration Dose Values for Intermittent Vibration (m/s1.75)
Location Daytime Night Time
Preferred Value Maximum Value Preferred Value Maximum Value
Critical areas 0.10 0.20 0.10 0.20
Residences 0.20 0.40 0.13 0.26
Offices, schools,
educational
institutions, and
places of worship
0.40 0.80 0.40 0.80
Workshops 0.80 1.60 0.80 1.60
Calculation of VDV requires knowledge of the number of events, and their duration in the relevant
time period.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 8
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
3.3.1 Building Damage
In terms of the most recent relevant vibration damage objectives, Australian Standard AS 2187:
Part 2-2006 “Explosives – Storage and Use – Part 2: Use of Explosives” recommends the
frequency dependent guideline values and assessment methods given in BS 7385 Part 2-1993
“Evaluation and measurement for vibration in buildings Part 2”, as they “are applicable to
Australian conditions”.
The British Standard sets guide values for building vibration based on the lowest vibration levels
above which damage has been credibly demonstrated. These levels are judged to give a minimum
risk of vibration-induced damage, where minimal risk for a named effect is usually taken as a
95% probability of no effect.
The recommended limits (guide values) from BS7385 for transient vibration to ensure minimal
risk of cosmetic damage to residential and industrial buildings are presented numerically in
Table 3-5.
Table 3-5 Transient Vibration Guide Values – Minimal Risk of Cosmetic Damage
Type of Building
Peak Component Particle Velocity in Frequency
Range of Predominant Pulse
4 Hz to 15 Hz 15 Hz and above
Reinforced or framed structures
Industrial and heavy commercial buildings 50mm/s at 4 Hz and above N/A
Un-reinforced or light framed structures
Residential or light commercial type buildings
15mm/s at 4 Hz increasing to
20mm/s at 15 Hz
20mm/s at 15 Hz increasing to
50mm/s at 40 Hz and above
The Standard states that the guide values in Table 3-5 relate predominantly to transient vibration
which does not give rise to resonant responses in structures, and to low-rise buildings.
Note that rock breaking / hammering, and sheet piling activities are considered to have the
potential to cause dynamic loading in some structures (e.g. residences) and it may therefore be
appropriate to reduce the transient values by 50%.
The British Standard goes on to state that “Some data suggests that the probability of damage
tends towards zero at 12.5 mm/s peak component particle velocity”. In addition, a building of
historical value should not (unless it is structurally unsound) be assumed to be more sensitive.
In addition to the British Standard, for the case of nearby heritage buildings, guidance for
structural damage is derived from the German Standard DIN 4150 -3 Structural Vibration Part 3
– Effects of Vibration on Structures. Table 3-6 details these recommendations for heritage
buildings.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 9
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Figure 3-1 Graph of Transient Vibration Guide Values for Cosmetic Damage
Table 3-6 DIN 4150 recommended PPV Vibration Level for Heritage Buildings
Guideline Values for Velocity – mm/s
1-10 Hz 10 to 15 Hz 40 to 50 Hz
3 3 to 8 8-10
3.4 Construction Equipment & Noise Source Levels
Sound Power Levels (SWLs) for typical construction plant are identified in Table 3-7. These SWLs
have been measured at other similar construction sites. The table gives both Sound Power Level
and Sound Pressure Levels (SPL) at 7m for the equipment. Sound Power Level is independent of
measurement position.
Table 3-7 Typical Construction Plant Sound Levels – dBA
Plant Sound Power Level Sound Pressure Level at 7m
Concrete Truck 109 84
Angle Grinder 109 84
Concrete Pump – 120 mm diameter / 50 bar 112 87
Concrete Saw 116 91
Mobile Crane 98 73
Dump Truck 108 83
Compressor 100 75
Bobcat 103 78
Hand Tools 90 65
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 10
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Plant Sound Power Level Sound Pressure Level at 7m
Excavator 108 83
Crawler Cranes 98 73
Tower Crane 104 79
Front End Loader 112 87
Excavator 107 82
Hammer Hydraulic 122 97
Bored Pile Rig 112 87
3.5 Construction Noise Predictions
Assessment of likely construction noise at surrounding receivers has been undertaken for the
proposed construction works for stage 1 works at Wilkinson House. Assessment has been based
on the construction of a new school building on the Wilkinson House site.
Site-related noise emissions were modeled with the “CadnaA” noise prediction program, using
the ISO 9613 noise prediction algorithms. Factors that are addressed in the noise modeling are:
• equipment sound level emissions and location;
• screening effects from buildings;
• receiver locations;
• ground topography;
• noise attenuation due to geometric spreading;
• ground absorption; and
• atmospheric absorption.
Modelling has been conducted for a number of construction scenarios. The three works scenarios
considered are summarised in Table 3-8.
Table 3-8 Construction Scenarios for Construction Works
Scenario Description Works
A Demolition
Removal of existing structure from behind the facade of the existing
building using excavators fitted with jaw crushers and hammers.
Truck Movements – loaded into trucks sent off site.
B Building Construction
This scenario includes concreting and lifting.
1 concrete pump, 2 forklifts, 1 compressor, 1 crane, a boom truck and
tower crane are assumed to operate in 15 minutes.
Also, concrete trucks and normal delivery trucks assumed to be two
movements in 15 minutes.
C Facade / Fitout
In the event that the construction of the facade occurs in isolation.
Forklift, truck, tower crane and power tools assumed.
Two truck movements in 15 minutes assumed.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 11
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Noise modelling has been conducted for each of the above scenarios, with plant located across
the Wilkinson House construction site.
The modelling assumes a “typical worst-case” scenario whereby all plant, is running continuously.
As such, the modelling represents likely noise levels that would occur during intensive periods of
construction. Therefore, the presented noise levels can be considered in the upper range of noise
levels that can be expected at surrounding receivers when the various construction scenarios
occur.
Once noise sources have been applied to the model, the resultant noise levels at identified
surrounding receivers are predicted. These results are then compared with established
site-specific noise criteria.
Table 3-9 details results of construction noise modelling for each scenario.
Table 3-9 Predicted Construction Noise Levels at Residence – LAeq(15 min) – dBA
Residential Receiver Predicted Noise Level NML Exceedance
Scenario A – Demolition
A – Thomson Street & Lane Residences 42 57 0
B – Bourke Street 51 57 0
C – Forbes Street 72 60 12
D – St Peters Street 71 60 11
Scenario B – Building Construction
A – Thomson Street & Lane Residences 33 57 0
B – Bourke Street 51 57 0
C – Forbes Street 65 60 5
D – St Peters Street 68 60 8
Scenario C – Façade / Fitout
A – Thomson Street & Lane Residences 27 57 0
B – Bourke Street 34 57 0
C – Forbes Street 60 60 0
D – St Peters Street 60 60 0
A review of results of construction noise indicates that these may be well above construction
noise management levels at nearby residences particularly in Forbes Street (which are the
residences immediately adjacent to the construction site), during demolition and construction
stages.
3.6 Discussion of Results
Exceedances of noise management levels of up to 12dBA at residences to the east of the site
may be expected during demolition period when major equipment is located on site. This
magnitude of exceedance is consistent with similar sites where residences overlook development
sites.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 12
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
During the structure and fitout stages, the magnitude of exceedance will reduce due to the nature
of construction activities.
Based on these findings, the adoption of reasonable and feasible noise management and
mitigation will be required. These measures should be determined in detail when a contractor,
with defined construction techniques, has been engaged on the project. However, “in-principle”
mitigation measures are detailed in the following sections.
3.7 Construction Vibration Assessment
Operation of rock breakers and the like generate ground vibration that has the potential to
transmit to nearby buildings.
Table 3-10 sets out the typical ground vibration levels at various distances for safe working
distances.
Table 3-10 Recommended Safe Working Distances for Vibration Intensive Plant
Item Description Safe Working Distance
Cosmetic Damage Human Response
Small Hydraulic Hammer (300kg – 5 to 12t Excavator) 2m 7m
Medium Hydraulic Hammer (900kg – 12 to 18t Excavator) 7m 23m
Large Hydraulic Hammer (1600kg – 18 to 34t Excavator) 22m 73m
Vibratory Pile Driver Sheet piles 2m to 20m 20m
Pile Boring ≤ 800mm 2m (nominal) N/A
Jackhammer Hand held 1m (nominal) Avoid contact with structure
• Construction Noise Strategy, 2012, Transportation Construction Authority
The highest vibration levels will occur when construction equipment is located on the eastern side
of the site near residences on the eastern boundary.
A review of the site plant and surrounding receivers indicates that the minimum distance between
the vibration generating activities and surrounding buildings will be in the order of 10 metres.
Therefore, the use of medium to large rock-breakers in the ground should be carefully managed
at distances closer than 20 metres from residences.
It is recommended that trial testing of vibration levels be conducted where identified equipment
having the potential to exceed the human comfort criteria is proposed.
Structural damage vibration criteria in residential buildings are much higher than human comfort
criteria and predicted vibration levels are within these criteria under most circumstances. The
exception, should heavy rock-breakers be used, is for areas near eastern residences on
Macpherson Street. Therefore, the uses of alternative excavation measures, such as rock-saws
on excavators are recommended. If hammers are required, test vibration monitoring is
recommended to ensure that vibration levels at residences are not excessive.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 13
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
3.8 Construction Noise & Vibration Mitigation Measures
Without mitigation, noise levels from construction activities have been predicted to exceed the
noise management levels nominated in the guidelines at some surrounding receivers. Therefore,
noise control measures are recommended to ensure that noise is reduced where feasible.
The following project specific mitigation measures are recommended;
• Installation a 2.4 metre plywood hoarding around the construction site;
• Selection of quietest feasible construction equipment;
• Use of jaw crushers in preference to rock-breakers where feasible;
• Localised treatment such as barriers, shrouds, and the like around fixed plant such as pumps,
generators, and concrete pumps; and
• Provision of respite periods.
In addition, the following measures should be included in a Noise and Vibration Management
Plan.
• Plant Noise Audit – Noise emission levels of all critical items of mobile plant and equipment
should be checked for compliance with noise limits appropriate to those items prior to the
equipment going into regular service. To this end, testing should be established with the
contractor.
• Operator Instruction – Operators should be trained in order to raise their awareness of
potential noise problems and to increase their use of techniques to minimise noise emission.
• Equipment Selection – All fixed plant at the work sites should be appropriately selected, and
where necessary, fitted with silencers, acoustical enclosures, and other noise attenuation
measures in order to ensure that the total noise emission from each work site complies with
EPA guidelines.
• Site Noise Planning – Where practical, the layout and positioning of noise-producing plant
and activities on each work site should be optimised to minimise noise emission levels.
The adoption of the above measures is aimed at working towards achieving the noise
management levels established at surrounding receivers.
3.9 Community Liaison & General Approaches to Mitigation
An effective community relations programme should be put in place to keep the community that
has been identified as being potentially affected appraised of progress of the works, and to
forewarn potentially affected groups (e.g. by letterbox drop, meetings with surrounding
owners/tenants, etc) of any anticipated changes in noise and vibration emissions prior to critical
stages of the works, and to explain complaint procedures and response mechanisms. This
programme should include a Community and Stakeholder Engagement Strategy developed
specifically for the Project.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 14
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Close liaison should be maintained between the communities overlooking work sites and the
parties associated with the construction works to provide effective feedback in regard to perceived
emissions. In this manner, equipment selections and work activities can be coordinated where
necessary to minimise disturbance to neighbouring communities, and to ensure prompt response
to complaints, should they occur.
3.10 Noise & Vibration Management Plan
A Construction Noise and Vibration Management Plan for the site is recommended which should
be prepared by the successful contractor. The plan should reference the findings of this
assessment. Areas that should be addressed in plan include:
• noise and vibration mitigation measures;
• noise and vibration monitoring;
• response to complaints;
• responsibilities;
• monitoring of noise emissions from plant items;
• reporting and record keeping;
• non-compliance and corrective action; and
• community consultation and complaint handling.
3.11 Management of Construction Noise & Vibration to the School
Noise and vibration levels from construction are likely to be similar to the levels predicted for
receivers immediately surrounding the site. Accordingly, measures that will be adopted to
manage the school which should are detailed in a Construction Management Plan.
Measures that can be adopted to manage noise and vibration impacts at the school will be
managed between the school and the successful contractor and could include:
• closing of classroom windows;
• relocating classes during busy construction periods; and
• scheduling works during school holidays.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 15
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
4 OPERATIONAL NOISE & VIBRATION
Operational noise from the proposed facilities will be from activities within the new buildings as
well as mechanical plant located predominantly on roofs.
4.1 Operational Noise Criteria
The NSW NPfI provides a framework and process for deriving noise criteria for consents and
licences that enable the EPA and others to regulate premises that are scheduled under the
Protection of the Environment Operations Act 1997. Whilst specifically aimed at assessment and
control of noise from industrial premises regulated by the EPA, the policy is also appropriate for
use by the DP&E when assessing major development proposals.
Having been designed for large industrial and agricultural sources, the monitoring and assessment
procedures may not be applicable to the smaller developments and noise sources regulated by
local government. It is recognised however, that Councils may find the policy to be of assistance
in noise assessment and land-use planning.
The NPfI documents a procedure for assessment and management of industrial noise which
involves the following steps:
• Determining the project noise trigger levels for a development. The project noise trigger
level is a benchmark level above which noise management measures are required to be
considered. They are derived by considering short-term intrusiveness due to changes in the
existing noise environment (applicable to residential receivers only) and maintaining noise
level amenity for particular land uses for residents and other sensitive receivers;
• Predicting or measuring noise produced by the development (having regard to any associated
annoying characteristics and prevailing meteorological effects);
• Comparing the predicted or measured noise level with the project noise trigger level and
assessing impacts and the need for noise mitigation and management measures;
• Considering any residual noise impacts following the application of feasible and reasonable
noise mitigation measures;
• Setting statutory compliance levels that reflect the best achievable and agreed noise limits
for development; and
• Monitoring and reporting environmental noise levels from the development.
The project noise trigger level represents the level that, if exceeded, may indicate a potential
noise impact upon a community. It is a benchmark or objective and is not intended for use as a
mandatory requirement.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 16
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Intrusiveness Noise Level
For assessing intrusiveness, the background noise level (LA90) is measured and the Rating
Background Level (RBL) determined. The intrusiveness of an industrial noise source may
generally be considered acceptable if the equivalent continuous noise level (LAeq) of the source
(measured over a 15-minute period) does not exceed the background noise level (RBL) by more
than 5dBA.
Amenity Noise Level
The amenity assessment is based on noise criteria specific to land use and associated activities.
The criteria relate only to industrial-type noise and do not include transportation noise (when on
public transport corridors), noise from motor sport, construction noise, community noise, blasting,
shooting ranges, occupational workplace noise, wind farms, amplified music/patron noise.
The amenity noise level aims to limit continuing increases in noise levels which may occur if the
intrusiveness level alone is applied to successive development within an area.
The recommended amenity noise level represents the objective for total industrial noise at a
receiver location. The project amenity noise level represents the objective for noise from a single
industrial development at a receiver location.
To prevent increases in industrial noise due to the cumulative effect of several developments, the
project amenity noise level for each new source of industrial noise is set at 5dBA below the
recommended amenity nose level.
The following exceptions apply to determining the project amenity noise level:
• For high-traffic areas the amenity criterion for industrial noise becomes the LAeq,period(traffic)
minus 15dBA.
• In proposed developments in major industrial clusters.
• If the resulting project amenity noise level is 10dB or lower than the existing industrial noise
level, the project amenity noise level can be set at 10dB below existing industrial noise levels
if it can be demonstrated that existing industrial noise levels are unlikely to reduce over time.
• Where cumulative industrial noise is not a consideration because no other industries are
present in, or likely to be introduced into the area, the relevant amenity noise level is assigned
as the project amenity noise level for the development.
Amenity noise levels are not used directly as regulatory limits. They are used in combination with
the project intrusiveness noise level to assess the potential impact of noise, assess mitigation
options and determine achievable noise requirements.
An extract from the NSW NPfI that relates to the amenity noise levels for surrounding receivers
is given in Table 4-1.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 17
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Table 4-1 Amenity Noise Levels
Receiver Noise
Amenity Area Time of Day1
Recommended Amenity
Noise Level
LAeq (dBA)
Residence Suburban
Day 55
Evening 45
Night 40
Note 1: Daytime 7.00am–6.00pm; Evening 6.00pm–10.00pm; Night 10.00pm-7.00am.
Maximum Noise Level Events
Noise sources of short duration and high level that may cause disturbance to sleep if occurring
during the night time need to be considered.
The approach recommended by the NPfI is to apply the following initial screening noise levels:
• LAeq,15min 40dBA or the prevailing RBL + 5dB, whichever is the greater; and/or
• LAFmax 52dBA or the prevailing RBL + 15dB, whichever is the greater.
The sleep disturbance screening noise levels apply outside bedroom windows during the night
time period.
Where the screening noise levels cannot be met, a detailed maximum noise level event
assessment should be undertaken. It may also be appropriate to consider other guidelines
including the NSW Road Noise Policy (RNP) which contains additional guidance relating to
potential sleep disturbance impacts.
A review of research on sleep disturbance in the RNP indicates that in some circumstances, higher
noise levels may occur without significant sleep disturbance. Based on currently available
research results, the RNP concludes that:
• “Maximum internal noise levels below 50dBA to 55dBA are unlikely to cause awakening
reactions.”
• “One or two noise events per night, with maximum internal noise levels of 65dBA to 70dBA,
are not likely to affect health and wellbeing significantly.”
4.2 Project Noise Trigger Levels
The amenity and intrusiveness noise levels and resulting project trigger levels (shown in bold)
applicable to sources of continuous operational noise associated with the project (i.e. mechanical
plant and equipment) are shown in
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 18
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Table 4-2.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 19
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Table 4-2 Project Noise Trigger Levels
Receiver Period
Intrusiveness
Noise Level1
LAeq,15min (dBA)
Project Amenity
Noise Level2
LAeq,15min (dBA)
A – Thomson Street & Lane Residences
Day
Evening
Night
52
50
49
58
48
43
B – Bourke Street
Day
Evening
Night
52
50
49
58
48
43
C – Forbes Street
Day
Evening
Night
55
54
52
58
48
43
D – St Peters Street
Day
Evening
Night
55
54
52
58
48
43
Note 1: Intrusiveness noise level is LAeq,15min ≤ RBL +5. Minumum background is 35dBA in the day period whilst the
minimum background in the evening and night is 30dBA.
Note 2: Project amenity noise level (ANL) is suburban ANL minus 5dBA plus 3dBA to convert from a period level to a
15-minute level.
For maximum noise level events (night time period only), the following screening noise levels
apply.
Table 4-3 Sleep Disturbance Trigger Levels
Receiver LAeq,15min LAFmax
A – Thomson Street & Lane Residences 49 59
B – Bourke Street 49 59
C – Forbes Street 52 52
D – St Peters Street 52 52
4.3 Mechanical Services
The major mechanical noise sources associated with the development will be exhaust fans and
plant that will be located on the roof of the new buildings. These will consist of roof mounted
condensers or plant that have yet to be determined.
Noise from most major plant, such fan coil units and pumps will be contained by the building
structure. Therefore, it is the roof condensers and air handling units that may require noise
mitigation to achieve the established site-specific noise criteria at surrounding receivers.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 20
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Detailed specifications of mechanical services equipment that would otherwise allow an acoustic
assessment of noise emissions from the site are not available at this stage of the project as
selection and design is conducted after project approval.
In line with the approvals for other developments, detailed assessment of operational noise
emission should form a conditional requirement of the development, to be satisfied to the PCA,
prior to the issue of the construction certificate.
To mitigate noise from mechanical plant, it is likely the some or all of the following noise control
measures may need to be adopted at the design stage to meet noise objectives:
• Silencers on carpark and other fans,
• Acoustic louvres,
• Noise barriers, and;
• Variable speed controls on condenser fans.
The mechanical plant will be designed to meet the criteria presented in Table 4-3 at the identified
nearby receivers.
4.4 Wilkinson Building Noise Emissions
The proposed use of the Wilkinson Building is for classes and, as such, noise generated within
this area is expected to be general classroom noise which will be adequately contained by the
facade of the building.
No special measures are required to protect the acoustic amenity of nearby residents.
4.5 New Multi-Purpose Building
The new multi-purpose building that will be subject to a separate project application in the future,
will at times, generate significant internal noise levels due to sports and musical events.
Therefore, adequate control of noise breakout will be required. Measures that will be adopted to
ensure that compliance with established noise criteria include:
• Ceiling and wall treatments to improve the sound isolation of these elements;
• Laminated or double glazing of doors and windows;
• Acoustic treatment of mechanical services; and
• Sound system design and installation of sound limiters where deemed necessary.
Given that the design of the multi-purpose building has not been developed in any detail, the
exact nature of these treatments cannot be specified, suffice to say that noise criteria has been
established for the development, consistent with the SEARs, and can be adequately addressed at
the appropriate point in time.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 21
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
4.6 New Administration Building & Restoration of Barham
Noise generated by activities in these areas will be acoustically insignificant. Any noise will be
contained within the facade of the buildings.
4.7 School Announcements & Bells
Announcements and school bells are typical activities associated with school operations.
Typically, these are produced by the school PA system and can vary significantly depending on
the final volume settings of the system.
At this stage, no design of the PA system has been determined. However, the following measures
should be adopted to ensure that their impact at all surrounding residences is minimised:
• Speakers should be located and orientated to provide good coverage of the school areas
whilst being directed away from residences. The coverage of the system should be subject
of the detail design of the system.
• The volume of the system should be adjusted on site so that announcements and bells are
clearly audible on the school site without being excessive. The system should initially be set
so that noise at surrounding residences does not exceed the ambient noise levels by more
than 5dBA.
• Once the appropriate level has been determined on site, the system should be limited to the
acceptable level so that staff cannot increase noise levels.
The system bell should be set so that it only occurs on school days.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 22
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
5 SUMMARY OF RECOMMENDATIONS
Based on Wilkinson Murray’s acoustic assessment of the project, the following findings have been
determined.
5.1 Construction Noise
Noise objectives for construction have been established based on EPA guidelines. The noise
management levels should be adopted as objectives to work toward in minimising any noise
impact at surrounding residences.
Table 5-1 presents applicable noise management levels at residential receivers in the vicinity of
the site.
Table 5-1 Site-Specific Construction Noise Management Levels – dBA
Area
Construction Noise Management Level,
LAeq – dBA
Highly noise
affected Noise
Level, LAeq
dBA Day Evening Night Saturday*
A – Thomson Street & Lane Residences 57 50 49 57 75
B – Bourke Street 57 50 49 57 75
C – Forbes Street 60 54 52 60 75
D – St Peters Street 60 54 52 60 75
* 8.00am to 1.00pm.
It has been determined that noise from construction activities for the construction of Stage 1
(Wilkinson House) during the day period will potentially exceed established construction noise
management levels. Therefore, the planning and management of construction activities must
consider the sensitivities of surrounding residents so as to minimise the impact of construction
activities at these receivers.
The control of construction noise and vibration should be addressed in a Noise & Vibration
Management Plan developed when the successful contractor has been appointed for the project.
The following project-specific mitigation measures are recommended:
• Selection of quietest feasible construction equipment;
• A 2.4m plywood hoarding around the construction site and between the Healy Gym site and
western residences;
• Use of jaw crushers or smaller rock breakers where feasible;
• Localised treatment, such as barriers, shrouds, and the like around fixed plant, such as
pumps, generators, and concrete pumps; and
• Provision of respite periods, particularly on Saturdays.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 23
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
5.2 Operational Noise
Site-specific noise criteria for the development have been established based on the lower of
intrusive and amenity noise criteria.
The applicable operational noise levels at residential and commercial receivers in the vicinity of
the site are presented in Table 5-2.
Table 5-2 Project Noise Trigger Levels – dBA
Receiver Period
Intrusiveness
Noise Level1
LAeq,15min (dBA)
Project Amenity
Noise Level2
LAeq,15min (dBA)
A – Thomson Street & Lane Residences
Day
Evening
Night
52
50
49
58
48
43
B – Bourke Street
Day
Evening
Night
52
50
49
58
48
43
C – Forbes Street
Day
Evening
Night
55
54
52
58
48
43
D – St Peters Street
Day
Evening
Night
55
54
52
58
48
43
Note 1: Intrusiveness noise level is LAeq,15min ≤ RBL +5dBA. Minumum background is 35dBA in the day period whilst the
minimum background in the evening and night is 30dBA.
Mechanical plant, such as rooftop exhausts and major plant associated with the development
should be assessed at the time of detailed design and selection, having regard to nearby
residential and commercial properties surrounding the development, and to future uses in the
school area.
To mitigate noise from mechanical plant, silencers could be incorporated in the outlets of the
exhaust fans. Silencers can be installed to the fans if required. The mechanical plant noise
emission would be designed to meet the criteria present in Table 5-2 at the closest receivers.
Noise from Wilkinson House, the New Administration Building and restoration of Barham will not
be acoustically significant and will be adequately contained by the building facade.
In the case of the proposed multi-function hall, noise will need to be contained by appropriate
design of the facade and roof. Given that the design of the multi-purpose building has not been
developed in any detail the exact nature of these treatments cannot be specified suffice to say
that noise criteria has been established for the development, consistent with the SEARs, and can
be adequately addressed at the appropriate point in time.
Noise from bells and announcements will be managed by design and adjustment techniques.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION PAGE 24
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
6 CONCLUSION
A construction and operational noise and vibration assessment of SCEGGS Darlinghurst
Masterplan and Stage 1 (Wilkinson House) development has been conducted. Site-specific noise
criteria that are applicable to this project have been presented.
A noise assessment has been conducted for the proposed construction activities associated with
the Stage 1 development to determine the potential for noise and vibration impact at surrounding
receivers. Exceedances of noise management levels are expected at surrounding receivers to the
east of construction site on Forbes Street.
Vibration associated with on-site construction activities is unlikely to impact on surrounding
receivers. Accordingly, management of noise from construction activities should be included in
the Site Construction Environmental Management Plan.
Site-specific operational noise criteria have been determined for the project based on ambient
noise monitoring. A review of likely major plant indicates that noise levels can comply with
established noise criteria during proposed operation with the inclusion of acoustic treatment. A
review of all plant with respect to site-specific noise criteria is required at detailed design stage.
Noise emissions from the proposed new multi-purpose building will be designed to achieve the
site-specific assessment criteria under operation. Noise from other facilities associated with the
Masterplan will be contained by standard facade design.
APPENDIX A
NOISE MEASUREMENT RESULTS
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX A-1
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX A-2
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX A-3
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX A-4
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX A-5
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX A-6
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX A-7
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX A-8
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX A-9
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX A-10
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX A-11
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX A-12
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
APPENDIX B
RESPONSE TO SUBMISSIONS
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX B-1
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
The following items relate to issues regarding noise and vibration in the Project Application noise
and vibration assessment. It should be noted that the description of operations contained in this
report is not comprehensive whereby the assessment uitilised descriptions contained in the EIS
that accompanied the application.
As such, items that have been raised in submissions that were not deemed “acoutsically
significant” were not been included in in the initail report.
Item 1 – Construtcion Noise and Vibration Assessment.
Sydney City Council has raised the following:
Wilkinson House building is proposed to be demolished as part of this application, with noise
management levels predicted to exceed the noise criteria by up to 12dB (i.e. background noise
level +22dB.) An updated acoustic report should be provided that includes site-specific noise
mitigation measures. If major exceedances are still predicted, alternative demolition
methodologies need to be considered to ensure that all reasonable and feasible measures to
reduce the noise level are fully explored.
Generic recommendations are inadequate. In addition, adequate respite periods must be
nominated.
The Department should also ensure that a Construction Noise and Vibration Management Plan is
submitted for approval prior to any construction certificate or demolition works commencing at
Wilkinson House.
Response
A preliminary assessment of potentail construction noise and vibration has been conducted to
deterimine the likley impact on surrounding noise sensitive receivers. The predictions are based
on indicative likley construtcion methods as the actual contractor will not be engaged until the
project is approved and designed. At such time, the exact contruction methedology will be know
and therefore can be assessed which is normal practice.
Site-specfic Noise Manangement Levels have been established based on noise monitring which
are not noise criteria but rather objectives to work towards where reasonable and feasible
meaures can be adopted.
The DA report conducted an assessment of likley impacts from noise and vibration whereby the
magnitude of prediected noise levels, which are typical worst case levels, are not unusual in the
context of the Sydney Area. As such, measures to reduce impacts on surrpounding receivers
have been identfied.
Consistent with the EPA’s Interim Contruction Noise Guideline noise mitigation meaures have
been recommended to be adopted where “reasonal and feasible”. These have been included in
the draft noise and vibration management plan in Apprendix C.
Tyically, where construtcion noise and vinration has been identified as an issue to manage the
project is conditioned so that a specific noise and vinration management plan is prepared prior
to issue of the Construtcion Certficate. As specific equipment and program will be know at this
time, appropraite site-specific noise mitiation meaures, including the need for respite can be
determined.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX B-2
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
As previously inidictaed the Draft Construction Noise and Vibration Management Plan can by
uitilsed in addressing Councils concerns and manageing noise and vibration asscoisted with
construction.
Given that the assessment has been based on the EPA policy it is recommdned that the hours
are consistent with EPA guidelines being:
• Monday to Friday 7.00am to 6.00pm
• Saturday 8.00am to 1.00pm
• Sunday and Public Holidays No work
This compares with council’s recommended hours of 7.30am and 5.30pm Monday to Friday and
7.30am to 3.30pm on Saturday.
Item 2 – Noise from Students
One respondant raised the issue of noise from Students during sport and lunchtime. This indiates
that student noise from otuside areas is an issue to at least one respondant.
Response:
The is proposed to be no increase in the Student population, apart from the potentail Childcare
Area which is discussed in further sections. As such, no increase in noise associsted with students
can be expected.
Item 3 – Mechanical Services Noise Emissions
Rooftop air-conditioning and other services should be silenced.
Response:
Site-specific noise criteria for emissions from the site have been established based on site noise
logging. All new mechancial plant will be silenced where necessary to meet the establihsed noise
criteria. Meaures shuch as silencers, linned duct and barriers will be deterined when the deatiled
design and selection of plant is know, as is standard practice.
Item 4- Multi-Purpose Building
No indication of the future use of the multi-purpose building so impacts of future noise have not
been assessed or considered.
Response
The future use of the multi-purpose building will be confirmed as part of a subsequent detailed
DA for it’s construction, operation, and fit out of the building. However it could accommodate an
information and research centre (contemporary library), early learning centre (maximum 90
children), classrooms and general learning areas, meeting rooms.
It is noted that the above activies are not what can be classified as “acoutsically significant”
activitities that could not be contained within the fabric of a future building. This fact and the
fact that a separate DA will be submitted when deatiled uses are known will ensure that noise
emssions from the facility will not adversely impact on surrouning residences.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX B-3
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
The only noise source associsted with the building will be mechancial plant that would be subject
to the same conditions as mentioned earelier and would be controlled using standard engineering
noise control.
It is noted that a early learning centre with up to 90 children is one of the likley uses. Whilst
details of the exact configuration of this area has yet to be defined it is likley that any outdoor
play area noise to be loacted on the northern side of the new building will be contained by
surrounding school buildings.
Should an outdoor play area be located on the southern side of the new multi-purpose building
resultant noise levels of 50dBA can be expected at Terraces on Thomson Steet. This assumes
30 children aged bewteen 3 and 6 playing in an eastern area at any one time (Sound Power Level
of 90dBA), distance attenuation and shielding by a boundary fence. This compares to a daytime
noise citerion of 52dBA at these residences.
Therefore, it can be concluded that the the operation of the muti-purpose nuilding is unlikley to
adverslely impact on surrouning residents not that a project specific assessment of oiperation will
be submitted when the Development Application for this stage is submitted.
Item 5 – Rooftop After Hours Activities on Rooftop Level
Rooftop level on the proposed multi-purpose building could be utilised for after school hour
activities which may have noise impacts to the surrounding properties.
Response:
A review of the EIS indicates that there is no proposal for the use of the rooftop level of the multi-
purpose for after hour functions. None the less, we have conducted a preliminary assessment of
noise emissions based on a scenario that up to 100 persons are located on the roof up to 10.00pm.
Based on a sound power of 90 persons speaking on the roof terrace (Sound Power Level of
96dBA) and distance of 15 metres to Thomson Street residences a resultant noise level of 53dBA
is predicted. This compares to an established evening criterion of 48dBA.
Therefore, if the roof terrace were to be used for after-hours functions additional measures such
as a southern acoustic screen would be required to protect the amenity of nearby residences.
Such a measure could be included in any future development application should the roof terrace
use be proposed.
It is noted the above calculation has been provided to demonstrate acoustic feasibility should the
roof terrace, in future, be proposed for after school functions. Such as use is not proposed in the
current application.
Item 6 – Number of Students
Acoustic Impact Report does not make any reference to the number of students.
Response:
A review of the EIS indicates that “The proposed Concept and Detailed DA does not include an
increase in the population of staff or students”. As there is no change in students, there will be
no acoustic change in student noise levels.
APPENDIX C
DRAFT CONSTRUCTION NOISE & VIBRATION MANAGEMENT PLAN
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX C-1
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
The following draft construction noise and vibration managemant plan has been prepared to be
included in Tender documentaion to ensure that noise and vibration from construction activities
in Stage 1 of the project are approaprotely managed. This plan should be finalised by the
sucessful contractor taking into account, conitions of consent, the recommended noise mitigation
measures, noise management levels and vibration objectives contained in the Plan.
In addition the plan should be prepared to compliment and be consistent with the SCEGGS
Preliminary Construction Management Plan dated 26 November 2018 prepared by Tracey
Brunstrom & Hammond.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX C-2
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
1 INTRODUCTION
The Contractor xxx Pty Ltd proposes the replacement of Wilkinson House with a new building.
The development was approved State Significant Development Application SSD 8993. The
Approval Conditions required preparation of a Construction Noise and Vibration Management Plan
(CNVMP).
This document is the draft CNVMP and addresses all conditions relating to construction noise and
vibration. The contents of this plan are to be reviewed by the successful contractor and
incorporated where appropriate into site management procedures.
The site location is shown in Figure 1-1. The proposal includes: (To be modified as required by
the contractor).
• Demolition of Wilkinson House;
• Building Construction; and
• Facade Installation.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX C-3
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
2 SENSITIVE NOISE RECEIVERS
The locations of noise sensitive receivers are listed in Table 1-1 and shown in Figure 1-1.
Table 1-1 Noise Sensitive Receivers
Receivers Comments
A – Thomson Street & Lane Residences Terrace residences
B – Bourke Street Terrace residences and Commercial receivers
C – Forbes Street Mix of single and multi-storey residential buildings
D – St Peters Street Church on the opposite of St Peters Street
Figure 1-1 Noise Sensitive Receivers
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX C-4
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
3 NOISE MANAGEMENT LEVELS
Construction Noise Management Levels, based on ambient noise logging, are detailed in the
following table.
Table 3-1 Site-Specific Construction Noise Management Levels
Area
Construction Noise Management Level,
LAeq – dBA
Highly noise
affected Noise
Level, LAeq
dBA Day Evening Night Saturday*
A – Thomson Street & Lane Residences 57 50 49 57 75
B – Bourke Street 57 50 49 57 75
C – Forbes Street 60 54 52 60 75
D – St Peters Street 60 54 52 60 75
* Standard Saturday construction hours.
In addition, the following construction noise management levels LAeq,15 min are recommended for
other receivers and areas:
• Active recreation areas (such as parks): external LAeq,15min 65dBA
• Industrial premises: external LAeq,15min 75dBA
• Offices, retail outlets: external LAeq,15min 70dBA
• Classrooms at schools and other educational institutions: internal LAeq,15min 45dBA
3.1 Hours of Operation
The proposed working hours for this project are as follows:
• Monday to Friday 7.00am to 6.00pm
• Saturday 8.00am to 1.00pm
• Sunday and Public Holidays No work
If required, after hours permits will be sought from the relevant authorities.
3.2 Vibration Criteria
Criteria for assessment of the effects of vibration on human comfort are set out in British Standard
6472-1992. Methods and criteria in that Standard are used to set “preferred” and “maximum”
vibration levels in the document Assessing Vibration: A Technical Guideline (2006) produced by
the NSW DECCW.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX C-5
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Acceptable values of human exposure to continuous vibration, such as that associated with
drilling, are dependent on the time of day and the activity taking place in the occupied space
(e.g. workshop, office, residence, or a vibration-critical area). Guidance on preferred values for
continuous vibration is set out in Table 3-3.
Table 3-2 Criteria for Exposure to Continuous Vibration
Place Time
Peak Particle Velocity
(mm/s)
Preferred Maximum
Critical working areas
(e.g. hospital operating theatres precision
laboratories)
Day or Night time 0.14 0.28
Residences Daytime 0.28 0.56
Night time 0.20 0.40
Offices Day or Night time 0.56 1.1
Workshops Day or Night time 1.1 2.2
In the case of intermittent vibration, which is caused by plant such as rock breakers, the criteria
are expressed as a Vibration Dose Value (VDV) and are presented in Table 3-4.
Table 3-3 Acceptable Vibration Dose Values for Intermittent Vibration (m/s1.75)
Location Daytime Night Time
Preferred Value Maximum Value Preferred Value Maximum Value
Critical areas 0.10 0.20 0.10 0.20
Residences 0.20 0.40 0.13 0.26
Offices, schools,
educational
institutions, and
places of worship
0.40 0.80 0.40 0.80
Workshops 0.80 1.60 0.80 1.60
Calculation of VDV requires knowledge of the number of events, and their duration in the relevant
time period.
3.2.1 Building Damage
In terms of the most recent relevant vibration damage objectives, Australian Standard AS 2187:
Part 2-2006 “Explosives – Storage and Use – Part 2: Use of Explosives” recommends the
frequency dependent guideline values and assessment methods given in BS 7385 Part 2-1993
“Evaluation and measurement for vibration in buildings Part 2”, as they “are applicable to
Australian conditions”.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX C-6
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
The British Standard sets guide values for building vibration based on the lowest vibration levels
above which damage has been credibly demonstrated. These levels are judged to give a minimum
risk of vibration-induced damage, where minimal risk for a named effect is usually taken as a
95% probability of no effect.
The recommended limits (guide values) from BS7385 for transient vibration to ensure minimal
risk of cosmetic damage to residential and industrial buildings are presented numerically in
Table 3-5.
Table 3-4 Transient Vibration Guide Values – Minimal Risk of Cosmetic Damage
Type of Building
Peak Component Particle Velocity in Frequency
Range of Predominant Pulse
4 Hz to 15 Hz 15 Hz and above
Reinforced or framed structures
Industrial and heavy commercial buildings 50mm/s at 4 Hz and above N/A
Un-reinforced or light framed structures
Residential or light commercial type buildings
15mm/s at 4 Hz increasing to
20mm/s at 15 Hz
20mm/s at 15 Hz increasing to
50mm/s at 40 Hz and above
The Standard states that the guide values in Table 3-5 relate predominantly to transient vibration
which does not give rise to resonant responses in structures, and to low-rise buildings.
Note that rock breaking / hammering, and sheet piling activities are considered to have the
potential to cause dynamic loading in some structures (e.g. residences) and it may therefore be
appropriate to reduce the transient values by 50%.
The British Standard goes on to state that “Some data suggests that the probability of damage
tends towards zero at 12.5 mm/s peak component particle velocity”. In addition, a building of
historical value should not (unless it is structurally unsound) be assumed to be more sensitive.
In addition to the British Standard, for the case of nearby heritage buildings, guidance for
structural damage is derived from the German Standard DIN 4150 -3 Structural Vibration Part 3
– Effects of Vibration on Structures. Table 3-6 details these recommendations for heritage
buildings.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX C-7
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Figure 3-2 Graph of Transient Vibration Guide Values for Cosmetic Damage
Table 3-5 DIN 4150 recommended PPV Vibration Level for Heritage Buildings
Guideline Values for Velocity – mm/s
1-10 Hz 10 to 15 Hz 40 to 50 Hz
3 3 to 8 8-10
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX C-8
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
4 CONSTRUCTION ACTIVITIES & SCHEDULE
The following works and indicative equipment are proposed:
• Demolition – Include description.
• Construction – Include description.
• Façade – Include description.
Table 4-1 lists typical source sound power level of equipment.
Table 4-1 Sound Power Levels for Construction Equipment
Plant Sound Power Level Sound Pressure Level at 7m
Concrete Truck 109 84
Angle Grinder 109 84
Concrete Pump – 120 mm diameter / 50 bar 112 87
Concrete Saw 116 91
Mobile Crane 98 73
Dump Truck 108 83
Compressor 100 75
Bobcat 103 78
Hand Tools 90 65
Excavator 108 83
Crawler Cranes 98 73
Tower Crane 104 79
Front End Loader 112 87
Excavator 107 82
Hammer Hydraulic 122 97
Bored Pile Rig 112 87
4.2 Predicted Noise Levels
Noise levels at receiver locations will vary considerable depending on the location and nature of
work being undertaken.
Table 4-2 shows predicted noise levels from each stage of construction.
Due to the proximity of the nearest receivers, significant exceedances of the NML will be expected
during demolition and excavation activities near the boundaries of the site. During the longest
phase, the construction phase, noise will generally comply once with building envelope is
commenced.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX C-9
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Table 4-2 Predicted Construction Noise Levels at Residence – LAeq(15 min) – dBA
Residential Receiver Predicted Noise Level NML Exceedance
Scenario A – Demolition
A – Thomson Street & Lane Residences 42 57 0
B – Bourke Street 51 57 0
C – Forbes Street 72 60 12
D – St Peters Street 71 60 11
Scenario B – Building Construction
A – Thomson Street & Lane Residences 33 57 0
B – Bourke Street 51 57 0
C – Forbes Street 65 60 5
D – St Peters Street 68 60 8
Scenario C – Façade / Fitout
A – Thomson Street & Lane Residences 27 57 0
B – Bourke Street 34 57 0
C – Forbes Street 60 60 0
D – St Peters Street 60 60 0
4.3 Construction Vibration Assessment
Sources of minor vibration would be expected during demolition phases. In the demolition /
excavation phase a 15-20t rockbreaker with a 500 kg head will result in vibration levels typically
of around 1mm/s at a distance of 10 metres from a receiver. Vibration levels of this magnitude
would be clearly perceptible at adjacent residences.
At a distance of 5m vibration levels would approach 4 – 5mm/s which would most likely cause
significant complaint by residences. Therefore, the following mitigation should be considered:
• Use of alternative methods, such as rock saws and / or rock crushers,
• Use smaller hydraulic hammers after saw cuts have been made.
• Use of smaller hydraulic hammers for finishing works.
Mitigation of vibration impacts is discussed in Section 5.
Should part of the Heritage Facade be retained compliance with criteria detailed in Table 3-6 is
to be achieved. Low vibration methods should be adopted within 5 metres of Heritage facades
such as auger piling, rock saws and smaller rockbreakers. Should large rockbreakers be proposed
in this zone trial hammering with rockbreakers is recommended.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX C-10
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
5 NOISE & VIBRATION MANAGEMENT PROCEDURES
The following project specific mitigation measures are to be adopted;
• Installation a 2.4 metre plywood hoarding around the construction site;
• Selection of quietest feasible construction equipment;
• Use of jaw crushers in preference to rock-breakers where feasible;
• Localised treatment such as barriers, shrouds, and the like around fixed plant such as pumps,
generators, and concrete pumps; and
• Provision of respite periods.
In addition, the following measures should be included in a Noise and Vibration Management
Plan.
• Plant Noise Audit – Noise emission levels of all critical items of mobile plant and equipment should be checked for compliance with noise limits appropriate to those items prior to the
equipment going into regular service. To this end, testing should be established with the
contractor.
• Operator Instruction – Operators should be trained in order to raise their awareness of
potential noise problems and to increase their use of techniques to minimise noise emission.
• Equipment Selection – All fixed plant at the work sites should be appropriately selected, and
where necessary, fitted with silencers, acoustical enclosures, and other noise attenuation measures in order to ensure that the total noise emission from each work site complies with
EPA guidelines.
• Site Noise Planning – Where practical, the layout and positioning of noise-producing plant
and activities on each work site should be optimised to minimise noise emission levels.
The adoption of the above measures is aimed at working towards achieving the noise
management levels established at surrounding receivers.
The following is a summary of the recommended procedure to manage noise and vibration.
The single most critical aspect it to ensure complete engagement with the nearby receivers so
that sufficient notifications are provided, complaints/enquires are handled quickly and that ALL
site personnel are briefed on the importance of undertaking what is reasonable and feasible in
reducing noise and vibration impacts.
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX C-11
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Table 5-1 Noise and Vibration Management Procedures
Issue Area of
Concern Manage Measures Responsibility
Noise Site Induction
All personnel, contractors and sub-contractors to work on site
will be given an environmental induction prior to the
commencement of work. This induction will include the
following:
• Advice of any operational restrictions and environmental
noise management levels;
• Explanation of the nearby noise and vibration sensitive
receivers and the level of sensitivity expected;
• The approved hours of operation;
• Site-specific noise and vibration mitigation measures; and
• Complaints procedures;
• All site employees, contractors and sub-contractors will be
made aware of the importance of following the procedures
in this CNVMP.
Site Manager
Noise
Neighbour
Friendly
Behaviour
Some basic rules are required at the site to ensure that
unnecessary noise is not created in a way that may affect
nearby residential receivers:
• No swearing on site;
• No unnecessary shouting or loud radios;
• No dropping of materials during work or unloading, such
as formwork;
• No unnecessary use of equipment on site which should be
turned off or left on low idle when not used.
All
Noise Site Monitoring
Monitoring maybe undertaken on the basis of noise complaints.
Monitoring should be carried out by qualified personnel.
LAeq and LAmax noise levels at or near the residential boundary
are to be measured.
Site Manager
Noise Equipment
Monitoring
Equipment may require noise testing if, for example:
• It is new to the site;
• Is the subject of repeated noise complaints.
Monitoring should be carried out by qualified personnel.
LAeq should be determined at 7m from the equipment and
should be compared to the levels in Table 4-1.
Site Manager
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX C-12
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Issue Area of Concern Manage Measures Responsibility
All Complaints
Handling
All complaints or enquiries will be kept in a register,
including the following details:
• Date and time of complaint or enquiry;
• Means by which the complaint or enquiry was made;
• Details of the complainant;
• The nature of the complaint or enquiry; and
• Any action taken to investigate the complaint or
enquiry and the date of follow up with the
complainant.
All complaints of noise and vibration shall be investigated
and action to be taken to remove the cause of the
complaint (where feasible and possible) shall be
determined and registered. In all cases, a response shall
be provided to the complainant after investigation. Call
back as soon as possible to keep people informed of
action to be taken to address noise problems. Call back
at night time only if requested by the complainant to
avoid further disturbance.
Site Manager
Vibration Monitoring
Vibration monitoring is to be conducted at the two
residential properties immediately adjacent to the site.
This is to be supplemented by trial testing at the
beginning of excavation works.
Where predicted vibration levels potentially exceed the
criteria for cosmetic damage to buildings, vibration
monitoring will be done.
Monitoring to be done by suitably qualified personnel.
Measure ppv vibration levels on the building foundations
or at an equivalent location. Where levels exceed the
10mm/s damage alert level, the offending operation must
cease, and alternate construction methods devised. It is
likely that human comfort limits will be exceeded in the
first instance and need to be managed.
Site Manager
Vibration Equipment Use of rocksaws during excavation, thereby minimising
rockbreakers.
All Communication
with Community
A noise and vibration complaint protocol shall be
developed for the site to apply during the construction
period. The contact details (phone number, email address
and postal address) shall be widely distributed to the
surrounding residential area.
The communication should include details of construction
timing.
Site Manager
All Site Notice
A site notice shall be erected on the site prior to any work
commencing and shall be displayed throughout the works
period.
The site notice must:
• be prominently displayed at the boundaries of the
site for the purposes of informing the public that
unauthorised entry to the site is not permitted;
• display project details including, but not limited to
the details of the builder, Principal Certifying
Authority and structural engineer;
Site Manager
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX C-13
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Issue Area of Concern Manage Measures Responsibility
• be durable and weatherproof and display the
approved hours of work, the name of the
site/project manager, the responsible managing
company (if any), its address and 24 hour contact
phone number for any inquiries, including
construction/noise complaint are to be displayed on
the site notice be mounted at eye level on the
perimeter hoardings/fencing and is to state that
unauthorised entry to the site is not permitted.
All Working Hours
Working hours must be within the hours stipulated in the
CoA:
• 7.00am to 5.30pm Monday to Friday and 7.00am to
1pm Saturday. Work is not to be carried out on
Sundays and public holidays.
Site Manager
All Work outside
Normal Hours
Where it is necessary for works to occur outside of these
hours (ie) placement of concrete for large floor areas on
large residential/commercial developments or where
building processes require the use of oversized trucks
and/or cranes that are restricted by the RTA from
travelling during daylight hours to deliver, erect or
remove machinery, tower cranes, pre-cast panels,
beams, tanks or service equipment to or from the site,
approval for such activities will be subject to the issue of
an "outside of hours works permit" from Council as well
as notification of the surrounding properties likely to be
affected by the proposed works.
Site Manager
All Tenders &
Contracts
Include in tenders, employment contracts, subcontractor
agreements and work method statements clauses that
require minimisation of noise and vibration and require
compliance with directions from management to minimise
noise.
Site Manager
All Worker Concerns
Workers may at times need to discuss or negotiate
practices with their managers if they are concerned
about noise and vibration.
Site Manager
All Maintain
equipment
• Regularly inspect and maintain equipment to ensure
it is in good working order;
• Also check the condition of mufflers;
• Equipment must not be operated until it is
maintained or repaired, where maintenance or repair
would address the annoying character of noise
identified;
• For machines with enclosures, check that doors and
door seals are in good working order and that the
doors close properly against the seals;
• Return any hired equipment that is causing noise
that is not typical for the equipment – the increased
noise may indicate the need for repair;
• Ensure air lines on pneumatic equipment do not
leak.
Site Manager
SCEGGS DARLINGHURST
MASTERPLAN & STAGE 1 PROJECT APPLICATION APPENDIX C-14
CONSTRUCTION & OPERATIONAL NOISE REPORT REPORT NO. 18180 VERSION B
Issue Area of Concern Manage Measures Responsibility
Noise
Operate
equipment in a
quiet and efficient
manner
Reduce throttle setting and turn off equipment when not
being used.
Site Manager
Noise Location of Plant Place as much distance as possible between the plant or
equipment and residences and other sensitive land uses. Site Manager
Noise Hoarding Hoarding to the side boundaries to be 2.4mm solid
plywood to act as a noise barrier to adjacent residences Site Manager
Noise Scheduling Nominate an off-site truck parking area, away from
residences, for trucks arriving prior to gates opening. Site Manager
Noise Scheduling Schedule deliveries to nominated hours only. Site Manager
Noise Reversing Alarms
Where possible minimise the use of reversing on-site OR
ensure that non-tonal reversing alarms are fitted to all
vehicles.
Site Manager