5
Constructing Envs; Week 6 - Model making Madelaine Walsh 635 805 Our group has been focusing on the extension of the MSLE building on campus at Melbourne University. A new structure/foyer area has been built which joins the two existing buildings together. The primary structures of the MSLE extension were identified as: Load bearing walls Steel beams Timber rafters Existing brickwork Existing concrete slab Secondary structures: Timber battens Timber joists Lino flooring Plaster board Colour-bond roof sheeting The roof structure over the new extension was constructed using steel L beams bolted into the existing brick walls. The primary wall structures were existing brick with timber stud walls, plaster board cladding and a fire curtains. The floor system was composed of an existing concrete and steel structure. After looking through the plans as a group, we found that the new MSLE extension receives structural support from the two adjacent buildings, which have pad and pile footings. The extension is set on an existing concrete slab. - When pad footings are used, there is usually a column or pier sitting in the middle of a square base. These types of footings help to spread the load out. - Piles are a less expensive type of foundation system and often depend on the soil type surrounding the structure. EXISTING LEVEL 1 SLAB. ASSUMED DOWNSTAND SHOWN TO REMAIN. CONFIRM ON INSPECTION STEEL ANGLE TO ENGINEER'S DETAIL 1 5 0 EXISTING CONCRETE WALL TO REMAIN AS UPSTAND

Constructing week 6

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: Constructing week 6

Constructing Envs; Week 6 - Model making

Madelaine Walsh 635 805  

Our group has been focusing on the extension of the MSLE building on campus at Melbourne University. A new structure/foyer area has been built which joins the two existing buildings together. The primary structures of the MSLE extension were identified as:

Ø Load bearing walls Ø Steel beams Ø Timber rafters Ø Existing brickwork Ø Existing concrete slab

Secondary structures:

Ø Timber battens Ø Timber joists Ø Lino flooring Ø Plaster board Ø Colour-bond roof sheeting

The roof structure over the new extension was constructed using steel L beams bolted into the existing brick walls. The primary wall structures were existing brick with timber stud walls, plaster board cladding and a fire curtains. The floor system was composed of an existing concrete and steel structure. After looking through the plans as a group, we found that the new MSLE extension receives structural support from the two adjacent buildings, which have pad and pile footings. The extension is set on an existing concrete slab.

- When pad footings are used, there is usually a column or pier sitting in the middle of a square base. These types of footings help to spread the load out.

- Piles are a less expensive type of foundation system and often depend on the soil type surrounding the structure.

SFL NEW LFR GF0.000

SFL NEW LFR L13.175

SFL

NEW LFR LEVEL26.350

CL

NEW LFR L1CEILING6.125

SFL PLANT ROOM9.700

SFLOLD LFR L1 3.700

SFL BASEMENT-2.630

SFL

PLANT ROOMROOF12.800

A C D EB

NEWLIFT

LANDING

NEWLIFT

LANDING

NEWLIFT

LANDING

CIRC000A

NEW ROOF WITH FIXEDSKYLIGHTS

NEW RAMPEDBRIDGE LINK

NEW GLAZED FACADE

SFL LIFT OVERRUN10.100

EXTENSION1780

ENTRY

OUTDOORDECK

BAL2 GL06

EXISTING STEPS DOWNTO BASEMENT

NEW METAL DECKROOF

NEW CONCRETEFLOOR

4A08.01

1A07.01

DG.27DG.29

NEW FIRE CURTAINS

FIPFIN

STUDENT'TOOL SHED'

EXISTING ROOF

5A10.01

DG.04

AUTOMATIC SLIDING DOOR

CFC SHEETCLADDING TOPARAPET WALL.WALL TYPE L4

D1.01

EXISTING PAVING

INFILL WALLS TOEXISTING OPENINGS

4A09.11

SFL NEW base-2.805

175

2185

SFLNEW LFR GF 0.000

SFLNEW LFR L1 3.175

SFL

NEW LFR LEVEL2 6.350

SFL

NEW LFR GFCEILING 2.900

CL

NEW LFR L1CEILING 6.125

SFL OLD LFR GF-0.300

CL

NEW LFR L2CEILING 9.300

SFLPLANT ROOM 9.700

SFL OLD LFR L13.700

CL

OLD LFR GFCEILING3.300

CL

OLD LFR L1CEILING7.300

SFLBASEMENT -2.630 SFL

OLD LFRBASEMENT-2.630

1 2 3 4 5 6 7 8 9 10 11 12 132

A06.06

14

SFLLIFT OVERRUN 10.100

1A06.07

GROUPSTUDYG07

STUDENTLOUNGEG11

CIRC000A

EXISTINGLABORATORYG29

FHR

2A06.07

3A06.06

2A09.104

A09.10

1A09.10

2A09.12

DG.04 CORRIDORDG.03 WG.08 WG.07DG.02

DG.20DG.19

BEAMBEAM BEAM

KITCHENETTE

NEW CONCRETE SLAB TOSTRUCTURAL ENGINEER'S DETAILS

THROUGH T

O

ACAD

EMIC

GREENHOUSE

THROUGH T

O

ACAD

EMIC

GREENHOUSE

NOT IN SCOPE OF WORKS

NOT IN SCOPE OF WORKS

5A09.11

7A09.11

MALE WCG06

SFLNEW base -2.805

SFL OLD LFR GF-0.300

SFL OLD LFR L13.700

CL

OLD LFR L1CEILING7.300

SFL BASEMENT-2.630

ACDE B

3000

GROUPSTUDYG07

CORRIDOR

OFP

TB03

BAL3WG.03WG.01

GL03

GL03

CON2

NOT IN SCOPE OF WORKS

NOT IN SCOPE OF WORKS

SFL NEW base-2.805

LEGENDEXISTING WALL

NOT WITHIN SCOPE OF WORKS

DATE PRINTEDCHECKED

SCALE

DRAWN BYPROJECT NO

DWG NO

TITLE

PROJECT

Revision No Date Name

Builders/Contractors shall verify job dimensions before any job commences. Figured dimensions shall takeprecedence over scaled work. Work shall also conform to the specification, other drawings and job dimensions.All shop drawings shall be submitted to the Architect/Consultant and manufacture shall not commence prior to thereturn of inspected shop drawings signed by the Architect/Consultant. © Copyright 2008 All rights reserved

Hayball Pty Ltd4/135 Sturt Street SouthbankVictoria Australia 3006T 03 9699 3644 F 03 9699 3708www.hayball.com.au

DirectorsLen Hayball, Richard Leonard Robert Stent, TomJordanLuc Baldi, Sarah BuckeridgeABN 84 006 394 261

CONSTRUCTION ISSUE

A 2010.08.10 CONSTRUCTION ISSUE

As indicated31/03/2011 2:28:00 PM

MELBOURNE UNIVERSITYMSLE BUILDING

SECTIONS - PROPOSED - SHEET 1

AuthorChecker

1564

A06.06

1 : 100A03.01

PROPOSED SECTION2

1 : 100A03.01

PROPOSED SECTION1

1 : 100A03.01

PROPOSED SECTION3

2

50mm LINISHED STAINLESS STEELCONTINUOUS HANDRAIL TO AS1428

50mm x 50mm LINISHED STAINLESSSTEEL SQUARE HOLLOW SECTION

PFC TO ENGR'S DETAIL

CLEAR GLASS TYPE GL06BALUSTRADE TO AS.1288.PROVIDE ALUMINIUM CAPPING ATTOP

40 x 35 TIMBER FLOORING

50

EXISTING BRICK WALL

865

100

BAL 1BAL 2

NEW WALL TO MATCH EXISTING TO INFILL WINDOW

5050

5010

00

1150

150 20

020

0

150MM HIGH TIMBER KERB - IN ACCORDANCE WITH AS 1428

1CA.12

SFL OLD LFR L13.700

2

NEW RAMP SUPPORT BEAM TO TIEBACK INTO OLD LFR FLOOR

EXISTING BRICK WALL

FRAMLESS GLASS TYPE GL06 BALUSTRADE

BAL2

LINISHED STAINLESSSTEEL UPRIGHTS ANDHANDRAIL INACCORDANCE WITH AS1428

NEW DOOR

50

865

10

100

50

150

100X30 TIMBERKERB WITH T-BARFIXED TO STEELTO RUN ALONGSIDES OF RAMPIN ACCORDANCEWITH AS 1428.

865

100

50

150

SFL NEW LFR L13.175

E

EXISTING LEVEL 1 SLAB. ASSUMED DOWNSTAND SHOWN TO REMAIN. CONFIRM ON INSPECTION

NEW CONCRETE SCREED

VINYL FINISH

TIMBER FINISH

STEEL ANGLE TO ENGINEER'S DETAIL

STEEL BEAM CLEATED TO ANGLE

150

METAL ANGLE RAMP KERBIN ACCORDANCE WITH AS.1428 TO BOTH SIDES OFRAMP

EXISTING CONCRETE WALL TO REMAIN AS UPSTAND

BALUSTRADE TYPE 1 INACCORDANCE WITH AS1428

DATE PRINTEDCHECKED

SCALE

DRAWN BYPROJECT NO

DWG NO

TITLE

PROJECT

Revision No Date Name

Builders/Contractors shall verify job dimensions before any job commences. Figured dimensions shall takeprecedence over scaled work. Work shall also conform to the specification, other drawings and job dimensions.All shop drawings shall be submitted to the Architect/Consultant and manufacture shall not commence prior to thereturn of inspected shop drawings signed by the Architect/Consultant. © Copyright 2008 All rights reserved

Hayball Pty Ltd4/135 Sturt Street SouthbankVictoria Australia 3006T 03 9699 3644 F 03 9699 3708www.hayball.com.au

DirectorsLen Hayball, Richard Leonard Robert Stent, TomJordanLuc Baldi, Sarah BuckeridgeABN 84 006 394 261

CONSTRUCTION ISSUE

A 2010.08.10 CONSTRUCTION ISSUE

1 : 1031/03/2011 2:28:42 PM

MELBOURNE UNIVERSITYMSLE BUILDING

RAMP SECTIONS - FIRST FLOOR

AuthorChecker

1564

A10.03

1 : 10A10.02

RAMP SECTIONDETAIL1

1 : 10A10.01

RAMP SECTIONDETAIL2

1 : 10A10.02

SECTION DETAIL3

Page 2: Constructing week 6

Constructing Envs; Week 6 - Model making

Madelaine Walsh 635 805  

The plans for the MSLE extension were drawn up at 1:100, so we aimed to complete our model at a scale of 1:50, which would be double what was seen in the plans. In class we worked with the floor, ceiling and roof plans to construct an appropriate model of the structural components of the MSLE extension. We started by with the floor as the base and built up from there. As the roof is composed of steel purlins that run horizontally across the roof we needed to figure out how these would have been attached to the existing walls. The plans showed the purlins being

bolted into the existing walls. We used pins as “bolts” to secure the purlins from one wall to the other. We were able to work out the length of the purlins by looking at the measurements of the floor as well as measuring the purlins on the architectural plans. In our first attempt of attaching the purlins we spaced them out evenly along the roof however, the plans actually showed that they were not evenly spaced along the width of the roof due to the placement of the skylights. The screenshot from the plans to the right shows the relationship between the steel purlins and the skylights on the roof of the extension. In the second attempt of this we followed the spacing used on the actual plans to the best of our ability to give a better representation of where the skylights would be in the roof.

SFLNEW LFR GF 0.000

SFLNEW LFR L1 3.175

SFL

NEW LFR LEVEL2 6.350

SFL

NEW LFR GFCEILING 2.900

CL

NEW LFR L1CEILING 6.125

SFL OLD LFR GF-0.300

SFL OLD LFR L13.700

1 2

EXISTINGLABORATORY CIRC

STUDENTLOUNGE

NEW 3 DEGREE PITCH ROOF

4A10.01

2A10.03

EXISTING WINDOW

NEW 2.5 DEGREE PITCHMETAL DECK ROOF

NEW 300MM WIDEBOX GUTTER

SFL U'SIDE EX. L13.400

GL01

PBL1

2A10.02

2650

2650

SKL

EQ970EQ

1 2

A

C

D

E

B 2A10.01

300 W

IDE

BOX

GUTT

ER

EXISTINGPIPES.PROVIDEPENETRATIONTHROUGH NEWROOF WITHFLASHING

"NEW

" LFR

BUI

LDIN

G

NEW SKYLIGHTS

PARAPET

NEW 3 DEG ROOF

RWH

LINE OF EXISTING EAVE OVERSHOWN DASHED

FALL

EXISTINGPIPES.PROVIDEPENETRATIONTHROUGH NEWROOF WITHFLASHING

"OLD

" LFR

BUI

LDIN

G

"NEW

" LFR

BUI

LDIN

GEX

ISTI

NGW

INDO

W

EXISTING METALDECK ROOF

EXISTING METALDECK ROOF

EX. FALL

EX. FALL

PARAPET TO EXTENDFROM EXISTINGUPSTAND

EXISTING GUTTER

EXISTINGROOF POP

EXISTING CONCRETE UPSTAND

SOAK

ER

FLASHING

FLASHING

SOAK

ER

FLASHING

FLASHINGSO

AKER

FLASHING

FLASHING

5A10.01

C.O.S3855

FAN

FAN

NEW 2.5DEGROOF

8023

1015

35

EQ EQ

1245

SKL

SKL

SKL

1 2

EXIS

TING

"OLD

" LFR

BUI

LDIN

G

300 X 150 BOX GUTTER

VELUX FIXED SKYLIGHT"FCM 2234"665 X 970 MM

EXISTING ROOF

COLORBOND KLIPLOKROOF SHEETING

COLORBOND ROOFFLASHING

C SECTION PURLINSTO ENGR'S DETAIL

NEW DOOR

EXIS

TING

"OLD

" LFR

BUI

LDIN

G

EXIS

TING

"NEW

" LFR

BUI

LDIN

G

PBL1

13MM FLUSH JOINTEDPLASTERBOARD CEILINGLINING ON SUSPENDEDMETAL SYSTEM

SOAKER

PARAPET BEYOND

ANGLE TO ENGR'S DETAIL

COLORBOND ROOFFLASHING SKL

PROVIDE DOUBLE GLAZINGSEAL AS SPECIFIED

970

6A10.01

R3.2 ROOF INSULATION

SFL NEW LFR GF0.000

SFL NEW LFR L13.175

SFL

NEW LFR LEVEL26.350

SFL

NEW LFR GFCEILING2.900

CL

NEW LFR L1CEILING6.125

SFLOLD LFR GF -0.300

SFLOLD LFR L1 3.700

CL

OLD LFR GFCEILING 3.300

CL

OLD LFR L1CEILING 7.300

12

WG.09 DG.04

EX. RWH

RWH

EXISTING SHOWNSHADED GREY

BR01

HATCHED AREAINDICATESEXTENT OF NEWBRICK QUIONINGFORMED TOMATCH BRICKQUIONING ABOVE(REUSE OFRECOVEREDBRICKWORK)

EXISTING OUT HOUSEFLOOR & PART WALLTO BE RETAINED

NOM

.32

5

WG.10

GL03GL03

GL03

CLB1

ZN01

ZN01

NEW ZINC CLADDING TOEXISTING BUILDIINGFACADE

NEW AUTOMATICSLIDER WITHINEXISTING BUILDING

NEW PARAPETWALL ABOVENEW GLAZING

2A10.02

CLB1

CL

NEW LFR L1CEILING6.125

EXISTING ROOF

NEW PARAPET WALL TOEXTEND FROM EXISTINGPARAPET WALL. COLORBONDCLADDING ON FURRINGCHANNELS

NEW COLORBONDKLIPLOK ROOF CLADDINGON AIR CELL SARKING &INSULATION BLANKET ASSPECIFIED.

ROOF PURLINS TOENGINEER'S DETAIL

EXISTING BOX GUTTER ANDEXISTING ROOF

FLUSH JOINTED PLASTERBOARDON SUSPENDED METAL CEILINGSYSTEM

40 X 400 PURPOSE MADEFOLDED COLORBONDBASE TRIM TO CLADDING /EXISTING WALL JUNCTION

970

GLASS TOP. REFER TOSPECIFICATIONS

EXTERNAL CONDENSATIONWEEP HOLES

CLOSURE OF RIB END TO ROOFSHEETING

GRADED SUPPORT UPSTANDAS REQUIRED. HEIGHT OFUPSTAND TO MIN. 65mmABOVE ROOF SHEET PROFILE

APRON FLASHING TOUPSTAND

1200x600 TRANSLUCENTDIFFUSER TO RAKEDPLASTERBOARD

LINE INTERNAL SHAFTWITH 13mmPLASTERBOARD. PAINTFINISH

N

DATE PRINTEDCHECKED

SCALE

DRAWN BYPROJECT NO

DWG NO

TITLE

PROJECT

Revision No Date Name

Builders/Contractors shall verify job dimensions before any job commences. Figured dimensions shall takeprecedence over scaled work. Work shall also conform to the specification, other drawings and job dimensions.All shop drawings shall be submitted to the Architect/Consultant and manufacture shall not commence prior to thereturn of inspected shop drawings signed by the Architect/Consultant. © Copyright 2008 All rights reserved

Hayball Pty Ltd4/135 Sturt Street SouthbankVictoria Australia 3006T 03 9699 3644 F 03 9699 3708www.hayball.com.au

DirectorsLen Hayball, Richard Leonard Robert Stent, TomJordanLuc Baldi, Sarah BuckeridgeABN 84 006 394 261

CONSTRUCTION ISSUE

A 2010.08.10 CONSTRUCTION ISSUE

As indicated31/03/2011 2:28:37 PM

MELBOURNE UNIVERSITYMSLE BUILDING

CONNECTING ROOF DETAILS

AuthorChecker

1564

A10.01

1 : 50A10.01

SECTION2 1 : 50A03.04

ROOF PLAN1

1 : 20A10.01

SECTION DETAIL4

1 : 50A15.19

ELEVATION3

1 : 10A06.06

ROOF PARAPETDETAIL5

1 : 10A10.01

SKYLIGHT DETAIL6

SKYLIGHT LENGTH

B 2010.11.10 DIMENSIONS ADDED TO ROOF SKYLIGHTS

C

C 2010.11.23 REVISED DIMENSION TO SUIT EXISTING CONDITION

Spacing of steel purlins according to the roof plans, larger gaps left for skylights.

Page 3: Constructing week 6

Constructing Envs; Week 6 - Model making

Madelaine Walsh 635 805  

After successfully constructing the roof, we looked at the construction of the mezzanine level. Leading up from the stairs at the rear of the extension the mezzanine level sits on a number of galvanised steel beams. The steel beams are bolted into the existing brick wall and support the load/ weight of the additional level. The first time we attempted to build in the 6 “steel beams” we laid them flat, however this turned out to not be enough to support the weight of the mezzanine. We tried again, this time turning the beams around so that they were able to better support the additional level. Once again we used pins to secure/bolt the beams into the walls. This method worked quite well as it held the beams in the correct place.

Galvanised steel would have been used in the roof structure of this area, as seen in the image above, There was galvanised steel beams that would’ve been bolted to the existing buildings in order for the roof to hold lateral and vertical forces.

Beams turned on vertical axis were able to better support the load of the mezzanine level.

Beams placed flat/horizontally, bolted into existing wall were not able to effectively support extra load.

Page 4: Constructing week 6

Constructing Envs; Week 6 - Model making

Madelaine Walsh 635 805  

The final part of the structure we added to our model was the stairwell area at the rear of the building. This area continues on from the corridor between the two existing buildings and houses the staircase leasing up to the mezzanine. Using the width of the floor already in place we took more measurements form the plans and constructed the rectangle and hexagonal floor for the stairwell. We then built the walls up from here. Overall our model was able to depict the major structural elements of the MSLE extension even though it may not have been the neatest/ most precise model. If we were to redo the model I think it would have been a better idea to use a combination of pasteboard and balsa wood to effectively show the structure of the building. I think balsa wood would have been good to use for the steel beams and purlins.

Page 5: Constructing week 6

Constructing Envs; Week 6 - Model making

Madelaine Walsh 635 805  

References

Chapter 1; Footings and Foundations2012, [Recampus], [Online]. Available: http://www.recampus.com/documents/book15_c01.pdf [2013, September 11th].

Ching, F.D.K. 2008, "Chapter 3; Foundation Systems" in, 4th Edition edn, John Wiley & Sons, Inc., pp. 3.02-3.25.

Ching, F.D.K. 2008, "Chapter 6; Roof Systems" in, 4th Edition edn, John Wiley & Sons, Inc.