25
Constructing Telescopes in Antarctica John W.V. Storey Image: Tony Travouillon

Constructing Telescopes in Antarctica John W.V. Storey Image: Tony Travouillon

  • View
    217

  • Download
    2

Embed Size (px)

Citation preview

Constructing Telescopes in Antarctica

John W.V. Storey

Image: Tony Travouillon

Getting the components there,

building the telescope,

and operating it.

Image: John Storey

• Davis• Mawson• Casey

• Hobart

Dome C is a French/Italian station that will be open year-round from 2005

Dome C

Image:

Australian Antarctic Division

Logistic support of Dome C is via Hobart.

Image: John Storey

L’Astrolabe brings heavy items from Hobart to Dumont d’Urville in 6 days...

Image: John Storey

...thence by tractor-traverse to Dome C.Image: Patrik Kaufmann

The tractor-traverse takes 11 days to get from the coast to Dome C.

• Three traverses/year (currently)

• Each traverse delivers ~150 tonnes

• Fuel consumption 600 litres/tonne

• Twelve-metre sleds – essentially no size or weight restrictions

Image:

Australian Antarctic Division

From 2005, the Australian Antarctic Division air-link will be in place.

Dome C3.9 hrs

The AASTINO was assembled by 3 people in 10 hours, at -30C.

Image: Patrik Kaufmann

Let’s assume that things take twice at long at Dome C...

Image: Geanpiero Venturi

...because some people just can’t resist goofing off.

Image: Karim Agabi

Image: Patrik Kaufmann

Image: John Storey

Image: EOST

EOST estimate for construction times (temperate site) for 2-metre telescope.

Mech Eng 3 – 4 weeks

Mech Tech 2 – 3 weeks

Elec Eng 2 weeks

Optical Eng 1 week

SW Eng 2 week

Total (worst case):

• 14 person-weeks

• 6 weeks elapsed time

• 5 personnel

Image: EOST

Let’s double these times (to account for the goofing off).

Total (worst case):

• 28 person-weeks

• 12 weeks elapsed time

• 5 personnel

This represents less than the combined UNSW and University of Nice deployment at Dome C for a single summer.

Construction costs

Image: John Storey

Image: John Storey

What did it cost us to build the AASTINO at Dome C, and what would it have cost if we’d done it at Siding Spring?

Dome C (actual costs) $Road transport, Sydney – Hobart, 4 tonnes (includes separate “dangerous goods” shipping) 5185Return airfare Sydney – Hobart, three people @ $500 1,860Accommodation in Hobart, 2 nights x 3 people 720Hire of bulldozer, 8 hrs 0Hire of crane, 2 x 1/2 day 0Connection to power grid 0Hire of three 2-way radios, 4 weeks 0Hire of container during construction 0Jet A1 fuel; 2,300 litres 0

------

Total Dome C $7,765

Siding Spring (estimated costs based on quotes) $Road transport, Sydney – SSO, 4 tonnes 2,000Hire of car, 4 weeks @ $300/week 1,200Accommodation at Lodge, 28 nights x 3 people @ $102.30 8,593Hire of bulldozer, 8 hrs @ $150/hr 1,200Hire of crane, 2 x 1/2 day @ $900 per 1/2 day 1,800Connection to power grid (including pole) 950Hire of three 2-way radios, 4 weeks 300Hire of container during construction 2,500Jet A1 fuel; 2,300 litres 2,300

-------

Total Siding Spring $20,843

PILOT: Pathfinder for an International Large Optical Telescope

Image: Patrik Kaufmann

For PILOT (15 tonnes gross weight), let’s ignore the possible savings, take the worst case and double it, and assume we have to pay for all the transport...

We’ll pay for our share of the icebreaker charter, and our share of its operating costs...

Image: John Storey

...we’ll pay for our share of the tractor-traverse to Dome C.

Image: Patrik Kaufmann

Image: Patrik Kaufmann

Then that all comes to...

...5% of an Astrolabe voyage, plus 10% of a traverse...

= A$54k.

...plus GST

Of course, there are also the violent storms that dump metres of snow in just a few hours...

...but fortunately they only occur on Mauna Kea. (Image courtesy Keck Observatory)