21
Considerations and Infrastructure Milestones for A Research Reactor Project 1 A. M. Shokr, 2 K. Alldred, 2 P. Adelfang, 1 D. Ridikas, 1 H. Abou Yehia 1 RRSS/NSNI/NS/IAEA 2 RRS/NEFW/NE/IAEA 3 PS/NAPC/IAEA International Conference on Research Reactors: Safe Management and Effective Utilization 14-18 November 2011, Rabat, Morocco

Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

Considerations and Infrastructure Milestones for A

Research Reactor Project

1A. M. Shokr, 2K. Alldred, 2P. Adelfang,1D. Ridikas, 1H. Abou Yehia

1RRSS/NSNI/NS/IAEA 2RRS/NEFW/NE/IAEA

3PS/NAPC/IAEA

International Conference on

Research Reactors: Safe Management and Effective Utilization

14-18 November 2011, Rabat, Morocco

Page 2: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

Contents

• Introduction

• IAEA milestone approach for a research reactor project

• Specific considerations in different phases of establishing the first research reactor

• IAEA assistance to countries establishing their first research reactor

• Concluding remarks

Page 3: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

Introduction

• For more than 60 years, research reactors have been a

corner stone in the development and application of nuclear

science and technology.

• Some countries considered research reactor as an

important step to the development of a power reactors.

• Recently, a number of countries have started planning to

build their first research reactor as a tool to develop the

necessary national infrastructure for embarking on a

nuclear power programme.

Page 4: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

Introduction

• When the research reactor is the Member State’s first

significant nuclear facility, this requires establishing a

dedicated infrastructure, which is not an minor undertaking.

• The IAEA recommends that Member Sates adopt a

systematic approach for decision making for research

reactor project, and for establishing supporting

infrastructure in phases that are matched to the needs for a

project.

• Guidance on establishing such infrastructure is provided in

a recently developed IAEA document on specific

considerations and milestones for a research reactor

project.

Page 5: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

PHASE 3

ImplementationPHASE 1 Pre-project PHASE 2

Project Formulation

5 – 10 years

Pre-Project Assessment Report and Preliminary

Strategic Plan

Preparatory work for a

research reactor after a policy

decision has been taken

Implementation of a

research reactor

Operations

Feasibility

Study

Bid

Specification

Commissioning

Licence

Research

Reactor

Justification

INFRASTRUCTURE MILESTONE 1

Ready to make a knowledgeable

commitment to a Research Reactor

project

Continuous development of

infrastructure elements,

Ongoing research reactor

technology assessment & fuel

cycle assessment

Decommissioning

License

Research Reactor

Decomm-issioning

INFRASTRUCTURE MILESTONE 2

Ready to invite bids for a Research Reactor

INFRASTRUCTURE MILESTONE 3

Ready to commission and operate the

Research Reactor

Considerations before

a decision to launch a

research reactor

project is taken

Possibility of

a research

reactorconsidered

Re

sea

rch

Re

act

or

Pro

ject

Infr

ast

ruct

ure

De

ve

lop

me

nt

Pro

gra

m

Justification for

Research Reactor

IAEA milestone approach: Phases of Implementation

of the first research reactor

Page 6: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

Infrastructure issues and milestones

ISSUES MILESTONE 1 MILESTONE 2 MILESTONE 3 National position

Nuclear safety

Management

Funding and financing

Legislative framework

Safeguards

Regulatory framework

Radiation protection

Research Reactor utilization

Human resources development

Stakeholder involvement

Site survey, site selection and evaluation

Environmental protection

Emergency planning

Nuclear security

Nuclear fuel management

Radioactive waste

Industrial involvement

Procurement

Page 7: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

Major safety activities and the supporting main IAEA Safety

Standards

Ready to make a knowledgeable

commitment to a Research Reactor Project

Ready to invite bids for a

Research ReactorReady to commission and operate the

Research Reactor

Phase 1 Phase 2 Phase 3

Issuance of the

nuclear law

Issuance of safety requirements needed

for bid specification

Establishing the

basic regulatory

framework

Justification

Contract

Application for construction licenceSafety

Evaluation

of bids Preparation

of safety

documentation

Assessment

by the

regulatory

body

Site

preparationConstruction

stage

Issuance of the construction licence

Start of construction

Fuel DeliveryPreliminary

Environmental Impact Assessment

Progressive application

of IAE

A S

afety Requirem

ents

GS-R-3 – The Management System for Facilities and Activities

GSR Part 3 – Radiation Protection and the Safety of Radiation Source, and BSS115

GSR Part 4 – Safety Assessment for Facilities and Activities

GSR-Part 1 – Government, Legal and Regulatory Framework for Safety

WS-R-2 – Predisposal Management of Radioactive Waste including Decommissioning

GS-R-2 – Preparedness and Response for a Nuclear or Radiological Emergency

TS-R-1 – Regulations for the Safe Transport of Radioactive Material

NS-R-4 – Safety of Research Reactors

Initial Site

Studies

Page 8: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

Involvement of the main entities throughout the

establishment of the Infrastructure elements

Ready to make a

knowledgeable decision

Ready to

commission

Phase 1 Phase 2 Phase 3

Ready to

invite bids

Ready to make a knowledgeable

commitment to a RR programme

M2 M1

Ready to commission and

operate the first RR

M3

Involvement of the Operating Organization

Involvement of the Regulatory Body

Involvement of the Government

Page 9: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

Use of a graded approach

• The duration of implementation of the activities depends on:

– Existing infrastructure at the beginning of the project;

– Resources available to the project;

– Reactor type, size, and utilization programme;

– Contract methodology.

• While all safety requirements shall be considered, a graded

approach may be used in their application based on the

potential hazard of the reactor. Examples include size of the

regulatory body, and requirements on human resources

development, emergency preparedness, and radioactive

waste management.

Page 10: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

Specific considerations in the different phases of

building the first research reactor

Page 11: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

Phase 1: Feasibility study

• Justification of the need for a research reactor;

• Clear definition of the reactor purpose, utilization programme and users, pre-selection of the reactor type, size, and experimental facilities;

• Advantages and disadvantages of using alternative technologies;

• Possible use of research reactors in the region;

• Availability of a suitable site: Identification of the preferred candidate site(s) on the basis of existing data, supported by a radiological impact assessment.

Page 12: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

Phase 1: Feasibility study

• Government commitment to adhere to the international obligations and to apply the IAEA Code of Conduct on the Safety of RRs and the IAEA Safety Standards, including:

– Establishment of legal and regulatory framework;

– Establishment of a sustainable financing system for all safety activities;

– Establishment of an effective management system;

– Provision of adequate arrangements for human resources development;

– Development of a national strategy for long-term management of radioactive waste and spent fuel, and decommissioning;

– Provision of adequate arrangements for emergency preparedness and response.

Page 13: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

Phase 2: Project formulation

• Establishment of the regulatory body and operating

organization.

• Involvement of the regulatory body as early as possible

including establishment of the safety requirements for the

bidding process.

• Establishment of a licensing process.

• Site selection, including definition of the parameters which

are needed for the reactor design and operation and

inclusion in the bid specifications.

• Attention to be given to the availability of expertise in site

selection, bidding, and evaluation of technical offers.

Page 14: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

Phase 2: Project formulation

• Development of human resources and competences is a high

priority task for both regulatory body and operating organization:

– Establishing regulations, performing regulatory review and

inspection;

– Safety assessment, commissioning, operation, utilization,

maintenance, radiation protection;

– Reactor physics, thermal-hydraulic, core management and

fuel handling, quality assurance, safety culture.

• Training could be obtained from the reactor vendor in

accordance with the technical specifications of the bid. The

project organization chart should include a group (or an

individual) responsible for human resources development.

Page 15: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

Phase 3: Project implementation

• Technical evaluation of the bids:

– Safety assessment of the design;

– Adherence of the design to the IAEA Safety Standards

should be one of the selection criteria of the winning bid.

• The project schedule should include hold points for

regulatory assessment and licensing of safety related

stages/activities.

• Recruitment of staff should start early in this phase:

significant development and training for all levels of staff,

including participation in activities of different stages of the

project.

Page 16: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

Phase 3: Project implementation

• Preparation of the SAR should start as early as possible:

– Proper interaction with the reactor designer;

– Assessment of the regulatory body prior to issuing the construction license.

• During construction, the operating organization should ensure (and the regulatory body should verify) that:

– Systems and components important to safety are installed according to the approved design;

– A process addressing changes in design is in place, in accordance with the management system;

– Knowledge in the design and construction are maintained during the reactor lifetime.

Page 17: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

Phase 3: Project implementation

• Development of management programmes for reactor operation:

– Operating procedures;

– Maintenance, periodic testing, and inspection programmes;

– Operational radiation protection programme and emergency plan: should be fully applied at the time fuel is received at the rector building.

• Preparation for commissioning include:

– Revision of the SAR, including establishment of the OLCs for commissioning;

– Commissioning programme and procedures;

– Assessment by the regulatory body and licensing of commissioning stage.

Page 18: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

IAEA assistance to countries establishing their first

research reactors

• Publications: Safety Standards and technical guidelines;

• Fact-finding missions at the project planning stage:

– Results of the mission include identification of gaps and the

associated action plans for establishing the necessary technical and

safety infrastructures;

– Upon request, the IAEA assists also in carrying out the established

action plans.

• Development of human resources for different stages of project

phases, including a training workshop on the establishment of a

new research reactor. This is conducted on the basis of the IAEA

safety standards and international best practices, and addresses

planning and implementation of different activities of the project.

• Supplementary publications and guides are planned

Page 19: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

IAEA assistance to countries establishing their first

research reactors

• Advisory service and expert missions in different phases of RR

lifetime:

– Regulatory infrastructure and licensing process;

– Justification of the RR and preparation of the feasibility study;

– Organizational issues for sustainability and utilization planning

– Site characterization and evaluation;

– Project management;

– Bidding process, including safety considerations of the technical

specifications;

– Strategy for human resources development;

– Review of safety and technical provisions of the design;

– Preparation and review of safety documents;

– Commissioning programme and results;

– Preparation for routine operation.

Page 20: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

Concluding remarks

• Decision to build a research reactor should be based on a

feasibility study evaluating the real needs, utilization

programme and availability of a suitable site, and should

show the commitment to establish the necessary safety

infrastructure.

• Establishment of the infrastructure should start early in the

process and achieved progressively during different phases

of the project; safety infrastructure is best achieved through

the effective application of the IAEA Code of Conduct on

the Safety of Research Reactors and the supporting Safety

Standards.

Page 21: Considerations and Infrastructure Milestones for A Research … · 2011. 12. 20. · rector building. • Preparation for commissioning include: –Revision of the SAR, including

Thank you for your attention