Connection to the Grid of AD Generation in the ROI

Eur Ing Carlos Galvan - Managing Director - Gridconnect

Page 2: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”

Connecting your AD generation tothe ESB owned network?

1. The connection process, are you planning to export power?

2. Connection types depending on generator electrical output

3. Our services

Page 3: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”

Connection process at present

Good news: you will be processed outside the GPA (Group processing approach AKA “gate system” CER/09/099)

Bad news: until the so-called “enduring access regime” is implemented, you will be processed in the same queue asThe 4,300+ megawatts of solar applications

Page 4: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”

Do I need to submit a connection applicationto ESBN?

• YES, even if you are not exporting into the grid

• If no export no application fee required, no queuing

• If exporting power, the application fee will depend on the output (MEC).Starting at €772 for 11<kW<50

Example: 500<kW<4000 MEC application fee €8,947

• Slightly different for micro-generators (6kW – 11kW). No application fee

Page 5: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”

Do I need a licence to generate?

If your output is less than 1MW you are not required to apply to theCER in order to receive an Authorisation to Construct/Licence toGenerate.

You are authorised by Order under Article 5 (1)(b) of S.I. No. 383 of2008/ licensed by Order under Article 5 (1)(b) of S.I. No. 384 of 2008

……happy days

Page 6: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”

Connection types:

• Most projects will connect into existing rural network (10kV or 20kV)

• Existing rural network (distribution system) overhead lines (woodenpoles)

• There are many connection types depending on the output of yoursite depending on MEC, available nearby grid access, etc

• There could be a few variations depending on existing installation i.e.metering arrangement, etc.

Page 7: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”

Option 1: <500kW

M

G

ESBAssets

HV Network(OHL/UC)

A.D Plant

Local loads

IPPAssets

ESB side costs:Approximately €13k* forexisting demand site andallowing €48k for greenfield site with good gridaccess

*depends on existinginfrastructure, connectionmethod, capacity ofexisting lines, etc

Page 8: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”

Option 2: <500kW to be added to existingdemand installation

M

G

ESBAssets

HV Network(OHL/UC)

A.D Plant

Local loads

IPPAssets

ESB side costs:Changes to allowimport/export meteringincluding insertion of extraswitchgear on MV side(Nu-Lec or EGIP)

Page 9: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”

Option 3: 500kW<MEC<2MW

M

ESBAssets

MV Network(OHL/UC)

G

Disconnect (KKK TYPE RMU)Nulec

Local loads

G10

MV

ESB side costs:Approximate total €45k*

IPPAssets

*depends on existinginfrastructure, connectionmethod, capacity ofexisting lines, etc

Page 10: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”

Option 4: >2MW

M

IPPAssets

MV Network(OHL/UC)

EGIP

G

Local loads

MV

ESBAssets

ESB side costs:Approximate total: €203k*

*depends on existinginfrastructure, connectionmethod, capacity ofexisting lines, etc

Page 11: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”

Our services:PRE-CONSTRUCTION SERVICES:

GRID CONNECTION FEASIBILITY STUDIES:-HOW MUCH FOR MY GRID?-WHEN? Timelines

Difficult to establish until enduring access regime is implemented

Page 12: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”

• SITE SURVEY (A “MUST” FOR EXISTING SITES)

• PREPARATION OF HIGH LEVEL DESIGN AND SUBMISSION OF NC5 FORMSTO ESBN

• PREPARATION OF SCOPE OF WORKS, SPECIFICATIONS AND EMPLOYER’SREQUIREMENTS

“YOU CAN SAVE THOUSANDS OF €€€€€ WITH A CAREFUL ASSESSMENT OF EXISTING ELECTRICAL ASSETS”

Page 13: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”

Our services:

CONSIDER THIS:1-Your electrical installation needs to comply with ETCI regulations, is your site safe and does it comply with regulations?2-Can I reduce my CAPEX/OPEX through an optimised electrical design?

Example:Your electrical losses can be minimised, this translates into thousands of euro over the lifetime of the project, example:Saving by electrical contractor reducing cable size (300mm² to 185mm² on a 50 m run) in 200kW outputinstallation:……………..approximately €250Value of added electrical losses over 25 year period with €0.10/kWh tariff:…………….€16,898 !!

ELECTRICAL ENGINEERING DESIGN:-Cable, transformer, protections and switchgear specification-Grid code compliance studies, earthing design, arc flash studies, etc.

Page 14: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”

IN A NUTSHELL…….

• Feasibility study considering interactions, grid capacity, existinginstallation, etc.

• Site survey highly recommended

• NC5 form submission including high level design

• Review of connection offer once received (enduring access regimewill fix current mess…)

• Preparation of scope of works and detail design