Upload
g-schuh
View
215
Download
2
Embed Size (px)
Citation preview
PRODUCTION MANAGEMENT
Condition based factory planning
G. Schuh • A. Kampker • C. Wesch-Potente
Received: 30 April 2010 / Accepted: 15 October 2010 / Published online: 1 November 2010
� German Academic Society for Production Engineering (WGP) 2010
Abstract Consecutive planning approaches, common in
the theory of factory design today, fail to support planning
projects in practice. They neglect the interactions and
dynamics in the planning task and project as well as the
subjectivity introduced by the different stakeholders.
Unconsidered interactions, conflicting motives and inflexi-
ble project structure lead to time-consuming, expensive and
late adaptations. Local optimisation and deviations from the
overall objectives are consequences of insufficient syn-
chronisation and coordination. The approach proposed in
this paper strives for a paradigm shift from consecutive
processes to a modular, parallel approach, which can be
reconfigured according to the specific conditions of the
planning project and enterprise. This new approach inte-
grates the modularisation and configuration of the planning
process as well as aspects of management of instability and
second order observation. It has been successfully employed
in industry cases, which will be introduced in this paper.
Keywords Factory planning � Planning process �Modularisation � Configuration
1 Introduction
Today’s dilemma of factory planning is to design produc-
tion systems that, on one hand, last for decades but, on the
other hand, are adaptable to changing requirements of
the dynamic market environment. Furthermore, important
questions for process, resources and layout design can
often not be answered systematically due to uncertain
information and changes in requirements. Reliable prog-
noses are limited and planned flexibility increases the
required invest significantly. Therefore, several approaches
strive for a modular, reconfigurable production system to
cope with this discontinuity [1]. The continuous adapta-
tions to the dynamic requirements result in a growing
frequency of planning projects. While an average company
launches about one project per year, successful companies
realise twice as many projects in the same time [2]; thus the
acceptable duration of a project has decreased significantly.
Factory planning projects have to cope with an increasing
number of planning tasks and objects, needing to be inte-
grated into the planning scope whilst dealing with limited
information, resources and time. In addition to the external
dynamics, this demands for adaptations in the planning
sequence, parallelisation of planning tasks and redefinition
of interdependencies [1, 3].
Consecutive planning approaches, common in factory
design today, fail to support planning projects, which face
these dynamic conditions. They are characterized by
sequential, individual decisions that neglect the interac-
tions in the planning objects and in the stakeholders. The
fixed sequence does not meet the individual, enterprise
specific requirements of each project [3, 4].
Within the following paragraphs, the deficits of estab-
lished approaches of factory planning are discussed and a
new perspective of factory planning, named ‘‘Condition
Based Factory Planning’’ (CBFP) is presented.
2 New understanding of factory planning
As emphasised in the introduction factory planning is no
longer a task performed once in a decade or less. Modern
G. Schuh (&) � A. Kampker � C. Wesch-Potente
Laboratory for Machine Tools and Production Engineering
(WZL), RWTH Aachen University, Aachen, Germany
e-mail: [email protected]
123
Prod. Eng. Res. Devel. (2011) 5:89–94
DOI 10.1007/s11740-010-0281-y
factories have to be designed to adapt to changing, situa-
tion specific requirements [5]. In consequence factory
planning needs to combine the initial factory design and
continuous reorganisation of the production system.
Approaches, aiming to support factory planning projects
under dynamic circumstances, have to understand factory
planning as factory development in order to adapt to
changing requirements that vary from company to com-
pany. Single planning projects have to be accelerated in
order to fit into the increasing planning frequency and the
overall factory development plan [4]. Furthermore, the
people that interact working in the factories as well as
planning factories have to be considered in the planning
approach: factory and project team are a social system and
have to be designed and managed as social system.
Challenges for factory planning projects are the there-
fore fast realisation in order to follow the external
dynamics, the adaptation to situation specific requirements
of different projects and the mastering of conflicting per-
spectives of stakeholders in social systems. These chal-
lenges are addressed in the following topics:
– standardisation and automation of factory planning,
– configuration of individual adaptive planning process,
and
– coordination of social systems
2.1 Standardisation and automation of factory planning
Common solutions to accelerate processes are standardi-
sation and automation. Especially the digital support of
factory planning projects is strongly driven by integrated
solutions standardising both functionalities of the tools
(e.g. interfaces, methods and tasks) and, in particular, the
processes in which those functionalities interact [6].
The application of digital tools in factory planning
projects is constantly growing; approximately 64% of the
projects use the support of design and simulation tools [7].
These systems are designed for experts. The user-interface
and the operating are adapted for trained specialists [8].
The majority of projects in small and medium companies is
realised by project teams that consist of ‘‘amateurs’’. In
addition to limited time, the involved planners have little
experience with available tools. Consequently, learning
effects are scarce and the usage of supporting systems is
limited to single applications or own solutions e.g. in
Microsoft Excel.
The increased (simple and intuitive) usability of plan-
ning tools is one important challenge in order to reach the
necessary degree of professionalisation of the planning
project and methodology, even in small projects [9].
Nevertheless a standardisation of interfaces, methods and
tasks in the process needs to be pushed.
2.2 Configuration of individual adaptive planning
process
The described standardisation and automation of integrated
software solutions (e.g. Siemens PLM and Delmia) leave
little freedom for individual processes [6]. Integrated
solutions are particularly designed for big companies with
own planning departments and experts. Consequently they
are everything but modular or interchangeable [9]. Espe-
cially small companies criticise the limited compatibility of
interfaces and possibilities to individually adapt the soft-
ware to their specific processes and requirements [4].
Consecutive approaches in factory planning cause sim-
ilar limitations concerning the adaptation of standard
planning process and methods to the individual require-
ments and specific processes of companies. External and
internal restrictions often force the project team to plan
parallel tasks that are supposed to be handled consecu-
tively. Information required for the planning is missing,
decisions are postponed and other planning tasks are
accelerated. Existing approaches offer no support for these
requirements [4]. The adaptive configuration of planning
processes and software solutions are additional challenges
for factory planning that seem to contradict the demand for
standardisation.
2.3 Coordination of social systems
Factory planning projects always change the existing
organisation, processes and structures of social systems.
E.g. due to the product oriented segmentation of production
former organisational structures and dependencies as well
as processes within the structures (e.g. order processing,
maintenance) are reorganised or completely new designed.
In this case the production systems as well as the project
team need to be understood as social systems [8]. Factory
planning can be understood as self-creation (autopoiesis) of
a social system; the project team (in particular the
employees and workers part of the future system) plans its
own social system (Fig. 1). Members of the existing system
are selected as part of the project team, which plans the
new production system during the planning process. The
ramp up begins with pilot projects that are rolled out to
the new system. The members of the project team are
(re-)embedded into the new system.
Characteristic for classical planning approaches are
coupled decisions that are made separately by individuals
or sub-teams [10]. Conflicting motives and backgrounds
lead to local optimisation of isolated planning tasks
regardless of the complete system [8, 11]. Experts,
including employees and workers part of the designed
system, are not being integrated into the planning process
early enough to benefit from their know-how [8]. Main
90 Prod. Eng. Res. Devel. (2011) 5:89–94
123
challenges concerning the social system aspects of the
planning are the integration of the relevant stakeholders
and project members as well as their synchronisation in the
project progress.
3 Condition based factory planning
Condition Based Factory Planning (CBFP) describes a
modular, parallel approach, which can be reconfigured
according to the specific conditions both of the planning
project and of the company. In the following, three main
aspects of CBFP are presented.
The modularisation allows the standardisation of the
planning content (methods, tools, etc.) within planning
modules. These modules encapsulate the planning content
following the object oriented approach known from soft-
ware development [1]. Interconnections between modules
concerning input information from other modules and
results used by other modules are defined by interfaces.
This is the basis for the individual configuration of the
modules to a planning process that can be reconfigured
during the project adapting to changes in surrounding
conditions. In the same way the project team has to be set
up in sub-teams that plan the modules. By observation of
deviations of the project progress and changes in require-
ments, the occurring instabilities can be managed by
reconfiguration, negotiation, escalation and intervention.
3.1 Modularisation of the project
The planning task, team and software are modularised
based on the object oriented principles introduced by
Schuh for the modelling of production systems [1]. The
task-related encapsulation of methods and tools (e.g. for
planning of capacity, assembly processes or material sup-
ply) into modules allow the reduction of interdependencies
on defined interfaces. The standardisation concerning
methods and tools is encapsulated in the modules, which
can be combined according to the specific requirements of
the project. Changes in requirements have a defined
influence specified by the in- and output relations of each
module [1].
The CBFP approach is based on a framework consisting
of 28 basic modules and eight planning domains, which are
defined based on project experience of the Laboratory for
Machine Tools and Production Engineering (WZL). The
modules accomplish different planning duties like: capac-
ity planning, segmentation or workstation design. Figure 2
shows planning modules for material supply and assembly
process as well as the necessary planning information
‘‘input’’ and the results ‘‘output’’ of the planning module.
The planning-domains represent the involved disciplines
(stakeholders) in the project, like production process,
resource planning or logistics. Additionally, support-
domains, like ramp up and project management or digital
factory are established to control, (re-) configure and assist
the planning-domains. A planning-module can be executed
repeatedly in different levels of detail. That means that at
the beginning of the process a rough corridor for the nec-
essary capacity is planned, and then be specified within
consecutive iterations. The sequence of the modules in the
iterations are reconfigured and adapted during the project
[3].
In analogy to the object oriented modularisation of the
planning object [1] and the task, the planning team can be
divided into sub-teams with regard to the existing inter-
dependencies to improve the controllability of the teams
and their collaboration. The set up of the sub-team is
described in the following chapter.
The approach is complemented by a modularisation
concept for the software support. For the outlined dilemma
between standardisation and adaptiveness, especially small
and medium sized companies demand simple and intuitive
software solutions that can be adapted to their specific
Pilot Project
Existing Production System
Planning Team
Autopoiesis
New Production System
Planning Process
Fig. 1 Factory planning as self-creation of social systems
Material-supply
AssemblyProcess
Buffer number
Supply type
Supply lot size
Supply frequency
Buffer levels
Process times
Process chain
Variants tree
Replenishment time
Material cost
Service level
Production program
Set-up costs
CAD drawing
St. process chain
Resource structure
Features tree
Product structure
Customer tact
Input Planning Modul Output
Fig. 2 Planning modules for material supply and assembly process
Prod. Eng. Res. Devel. (2011) 5:89–94 91
123
needs. WZL has developed several small tools (e.g. for
layout planning, segmentation, levelling, production con-
trol) that function as add-in in commonly used software
suits, like Powerpoint, Excel etc. or as web-based solution
[9]. Figure 3 shows screenshots of these tools. One of the
major problems resulting from modularisation and decen-
tralisation is the appropriate configuration of the planning
modules and structural bonding of their interconnectivity
and the synchronisation of the collaboration in the project
team, described in the following paragraphs.
3.2 Configuration
The described planning modules have to be combined and
configured in order to accomplish a company and project
specific planning process. In a first step the planning scope
and specific (additional) interdependencies have to be
defined. Based on these restrictions the relevant modules
for the project are selected, dimensioned and specified
regarding applied methods and tools (Fig. 4). If the project
focuses on the reorganisation of an assembly workstation in
an existing building, modules that do not correlate with this
planning scope (e.g. building planning) can be skipped.
The planning sequence depends on the existing input
information and restrictions as well as the necessity of
decisions. Adaptations in the sequence can be realised by
reconfiguration of the modules, which encapsulate the
planning content. Circular dependencies are dissolved by
setting initial values and corridors which are specified
within consecutive iterations. This allows the parallel
planning of modules that circularly depend on each other as
well as changes in the planning sequence. In order to
coordinate the collaboration between the modules, thresh-
olds for specific parameters (e.g. the maximal cost or size
of a planning object) and the available degree of freedom
for results of each module have to be defined regarding the
interdependencies of the involved modules. Thus, potential
conflicts can be identified in the course of planning and
negotiated or escalated to the appropriate decision level. In
this way the structural interconnectivity of the planning
content is defined and thus the information exchange
between the modules. The scheduling of milestones
according to decision and synchronisation points sets the
time framework for the project. The resulting phases define
the tact of the project representing the quotient of project
duration and the number of decisions. The planning-mod-
ules are aligned within iteration cycles with defined results
for the milestones. Figure 5 shows the described perspec-
tive of the CBFP-Process over time.
Corresponding to the selected modules and domains, the
planning team is composed matching competences and
roles of the team members with the requirements of the
modules and the schedule. An important task is the
capacity planning according to the available time between
the milestones and the configuration of the iterations. Using
Segmentation Assembly Levelling
Layout.ppt Production Control
Fig. 3 Intuitive tools for segmentation, levelling, layout planning and
configuration of production control
Fig. 4 Interconnectivity of planning modules and configuration
t
ME
Production Control
Ramp UpProject Management
Pla
nnin
gD
omai
ns
Structure
LogisticsResources
Layout
Capacity
Production Process
Target and Restrictions
Decision Points
Initial Value
new
planned
Moduls LevellingTakt
Fig. 5 Synchronisation and reconfiguration of the planning process
over time
92 Prod. Eng. Res. Devel. (2011) 5:89–94
123
a revised capacity curve, based on the hyperbola of Bul-
linger [12], inefficiencies in the project team are considered
in the capacity planning. The revised capacity curve
(Fig. 6) is applied to estimate the required capacity for the
execution of the modules within iterations and the best size
for the sub-teams that work on the modules. On this basis
the project team is composed and dimensioned, considering
the number of interfaces and the complexity of coordina-
tion as well as the number of parallel tasks. Special
attention has to be paid to integrate the relevant experts and
their know-how and perspectives into the planning. This
allows considering and avoiding possible obstacles and
increasing the acceptance of decisions as well as negoti-
ating conflicts well-foundedly [10].
The CBFP Platform for the digital support is configured
and reconfigured according to the demands of the selected
planning modules and the capabilities of the involved
planners and existing infrastructure [9]. The standardised
interfaces of the tools developed by WZL ensure the
compatibility of results and data. The following paragraph
describes how the synchronisation and the reconfiguration
of the planning course is realised.
3.3 Management of instability by observation
The individual configuration and the set-up of the structural
interconnectivity is the basis to react to external require-
ments and targets as well as internal conditions. In the
course of the project, this initial configuration has to be
adapted or even radically reconfigured to meet the dynamic
of the circumstances. In consequence, modules can be
relocated or repeated because of new and changed infor-
mation and requirements. In the same way, the composition
of the project team has to be adjusted to correlate with the
capacity and competence needed for the modules.
According to the principles of second order observation
[13, 14], the project is monitored to identify deviations,
conflicts and local optimisation. Analogue to the method of
Statistic Process Control [15], the thresholds and degrees of
freedom for the planning results need to be controlled and
if needed reconfigured. A virtual control room (c.f. oper-
ations room of Beer [16]) is integrated into the CBFP
Platform to handle the various information concerning the
performance and progress of the planning modules. Con-
flicts between modules and changes in input-information
can be visualised using network diagrams and schedules.
The user interface can be configured according to the user
and his position and information demand. In case of per-
ceptible deviations that interact with other modules speci-
fied mechanisms work on the different levels of conflict.
On the planning level conflicts need to be negotiated in
order to find joint solutions broadly accepted by the
stakeholders and to avoid local optimisation [10]. Using the
Mechanism Design theory of Hurwitz [17], mechanisms to
negotiate the major conflicts in factory planning are
developed. These conflicts concern the allocation of space,
invest, personnel and resources. If conflicts can not be
negotiated, they need to be escalated to the next decision
level.
In addition to escalating decisions concerning conflicts
between planning modules, this level (e.g. project man-
ager) has to observe changes and instability in require-
ments that influence the planning and intervene if
necessary to initiate reconfigurations of the project struc-
ture (structural interconnectivity or schedule), the project
team or the software support [18].
4 Industry case: design of an assembly system
In order to illustrate the practical relevance and potentials
of Condition Based Factory Planning, a representative
planning project of WZL and an industrial partner is pre-
sented. The project focuses the design of the assembly
system and logistics for a new generation of control cabi-
nets which are developed parallel. The assembly unit is to
be situated in the existing buildings.
The initial project set-up was configured according to
the requirements (forecasted quantity, product specifics,
variants, available space etc.) and capabilities (available
project team, software tools, etc.) of the company and
WZL. Modules for the planning domains capacity, struc-
ture, production process, logistics, resources and layout
were selected and the required information checked. New
modules for the domains product and technology were
added and interconnected with the existing to consider the
parallel product development process. Within the project
duration several changes in the requirements and in the
composition and size of the project team evolved, which
resulted in changes in the sequence of the planning.
0 50 100 150 200 250 3000
5
10
15
20
25
Project duration in days
Num
ber
proj
ect m
embe
rsIdeal capacity hyperbola
Capacity with respect to inefficiencies caused by:
- Number of parallel problems/ tasks
- Communication losses at interfaces
Fig. 6 Capacity curve for the set up of the project team
Prod. Eng. Res. Devel. (2011) 5:89–94 93
123
Due to the encapsulation of the planning modules and
the defined interdependencies significant changes could be
handled fast and with consideration of consequences and
side effects. The reduction of the forecasted production
quantity by 30% resulted in the quick re-planning of the
production programme and the selective adaptation of the
assembly and the logistic system. The consequences of
the marketing driven increase of variants (46%) on the
assembly system (form of segmentation, number of work-
stations, cycle time, invest, etc.) could be illustrated and
escalated to the decision level (plant manager) on this
basis. Additional product specifics resulting from more
severe testing and security requirements led to new
assembly content, which was analysed and specified with
assembly workers integrated in the project team.
Conflicts concerning the available space for different
preassembly areas were negotiated with the affected par-
ties. During the project, several similar changes of
requirements (e.g. concerning testing procedures and ramp
up locations) as well as demand of synchronisation (e.g.
coordination of product changes and adaptations of the
assembly process) could be facilitated by the consequent
application of the principles of modularisation and defined
interdependencies, and interfaces. Altogether, the project
duration was reduced by 60% compared to the preceding
product launch with a similar dimension.
5 Summary
The dynamic environment of production systems demands
a new understanding of factory planning as factory devel-
opment. CBFP is a new approach to cope with the resulting
challenges. The paper introduces three main aspects of
CBFP:
– modularisation,
– configuration and structural interconnectivity, and
– management of instability by observation.
The modularisation of the planning content, software and
project team is based on the principles of object orientation
and is precondition for the configuration of the planning
project. The management of instability by observation
secures the synchronisation of the decentralised planning
and reconfiguration of the planning project.
While consecutive approaches and integrated IT-Solu-
tions, common in factory planning today limit the indi-
vidual adaptation of the planning process to the specific
requirements of companies and projects, the proposed
approach is to optimise the adaptiveness of the process.
First applications in industrial case-studies have verified
the relevance and potentials of the addressed issues. While
to a large extent the individual components of the solution
are known from various disciplines, their combination
discloses a number of questions which are being investi-
gated in ongoing research.
Acknowledgments The new approach of CBFP is being investi-
gated by the Laboratory of Machine Tools and Production Engi-
neering (WZL) within two publicly funded research and development
projects (German Research Foundation, DFG): the ‘‘Cluster of
Excellence–Integrative Production Technology for High Wage
Countries’’ and the Graduiertenkolleg 1491/1 (University graduate
training programme) ‘‘Interdisciplinary Ramp-Up’’.
References
1. Schuh G, Bergholz M (2003) Collaborative production on the
basis of object oriented software engineering principles. Ann
CIRP 52(1):393–396
2. Schuh G, Ripp S (2003) Survey smart factory. WZL RWTH
Aachen
3. Schuh G, Wesch C, Gottschalk S, Gulden A, Koch S (2007)
Object-oriented factory planning—Architecture and procedure.
wt Werkstattstechnik online 1–2:166–169
4. Schuh G, Franzkoch B, Burggraf P, Nocker J, Wesch-Potente C
(2009) Configurable planning processes for factory planning.
wt Werkstattechnik online 4:193–198
5. Schuh G, Gottschalk S (2008) Production engineering for self-
organizing complex systems. Prod Eng Res Dev 2:431–435
6. Milberg J, Neise P (2006) Organizational design of supply chains.
Prod Eng XIII/ 2:181–186
7. Straßburger S, Seidel H, Schady R, Masik S (2006) Werkzeuge
und Trends der digitalen Fabrikplanung. Tagungsband zur 12.
Fachtagung, Kassel, 26–27, Sept 2006, 391–402
8. Schuh G, Gottschalk S, Wesch C (2007) Potentials in Computer-
aided Factory Design–Negotiation-based Top-down-Bottom-Up
Approach. Computer-Aided Production Engineering (CAPE),
Conference Proceedings, pp 43–52
9. Schuh G, Gottschalk S, Nocker J, Wesch-Potente C (2008)
Flexible Interconnectivity vs. proprietary Integration. wt Werk-
stattechnik online 3:127–131
10. Lu SC-Y, Elmaraghy W, Schuh G, Wilhelm R (2007) A Scien-
tific foundation of collaborative engineering. Ann CIRP
56(2):605–634
11. Simon HA (1996) The sciences of the artificial. MIT Press,
Cambridge
12. Bullinger H-J (1995) Arbeitsplatzgestaltung. Teubner, Stuttgart
13. Von Foerster H (1982) Observing systems. Intersystems, Salinas
14. Schmidt S (2005) Unternehmenskultur: Die Grundlage fur den
wirtschaftlichen Erfolg von Unternehmen. Velbruck, Weilerswist
15. Pfeifer T (2001) Fertigungsmesstechnik. Oldenbourg, Munchen,
pp 359–376
16. Beer AS (1995) Brain of the firm. Wiley John and Sons Inc.,
New York
17. Hurwitz L, Reiter S (2006) Designing economic mechanisms.
Cambridge University Press, New York
18. Kruse P (2009) Next practice. Gabal, Offenbach
94 Prod. Eng. Res. Devel. (2011) 5:89–94
123