Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
CONCEPTUAL PLAN & EMP
FOR THE PROPOSED RESIDENTIAL APARTMENTS PROJECT
OF Sri. KOSURU VENKAT SURYA SUBBA RAJU
AT SY NO. 43,
BAHADURGUDA VILLAGE, SAROORNAGAR MANDAL, RANGA REDDY DISTRICT,
TELANGANA STATE
SUBMITTED BY: Sri. KOSURU VENKAT SURYA SUBBA RAJU H.NO: 1-9-630/1, 3rd FLOOR, GYANI COMMERCIAL COMPLEX, VIDYA NAGAR, HYDERABAD, TELANGANA STATE -500 044
PREPARED BY: M/s. RIGHTSOURCE INDUSTRIAL SOLUTIONS PVT. LTD. PLOT NO.203, H.NO.5-36/203, PRASHANTHI NAGAR, IDA-KUKATPALLY, HYDERABAD- 500072, TELANGANA PHONE: 040-23700602 E-MAIL: [email protected] QCI CERTIFICATE NO. NABET/EIA/1821/RA 0100
TABLE OF CONTENTS S.NO CONTENT PG. NO
1.0 INTRODUCTION 1-2 1.1 PURPOSE OF THE REPORT 1 1.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT 1
1.3 PROJECT COST 1
1.4 SALIENT FEATURES OF THE PROJECT 2 TABLE 1.1 SALIENT FEATURES OF THE PROJECT 2
2.0 PROJECT DESCRIPTION 3-15
2.1 LOCATION DETAILS 3
I. ACCESSIBILITY & EXISTING ROAD NETWORK 3
II. TOPOGRAPHY 3
III. WATER BODIES 3
FIGURE NO.2.1 LOCATION AND GOOGLE MAP 4
FIGURE NO:2.2 TOPOGRAPHICAL MAP 5
FIGURE NO:2.3 PROJECT SITE LAYOUT PLAN 6
TABLE 2.1 SALIENT FEATURES OF PROJECT SITE 7
2.2 BUILT-UP AREA: 8
TABLE 2.2 NUMBER OF FLOORS AND BUILT UP AREA 8
2.3 PARKING AREA 8
TABLE 2.3 PARKING SPACE PROVISION 8
2.4 ROAD NETWORK 8 2.5 WATER REQUIREMENT 8
TABLE 2.4 WATER REQUIREMENT 9 2.6 POWER REQUIREMENT 9
2.7 BACK-UP POWER DETAILS 9
2.8 FUEL REQUIREMENT 9
2.9 MAN POWER REQUIREMENT 9
2.10 STORM WATER DRAINS 10
2.11 ENVIRONMENTAL INFRASTRUCTURE 10
A). WASTE WATER GENERATION & MANAGEMENT 10
TABLE 2.5 WATER BALANCE 10
B). SEWAGE TREATMENT PLANT (STP) 11
TABLE 2.6 DESIGN PARAMETERS OF SEWAGE TREATMENT PLANT 11
FIGURE NO: 2.4 PROPOSED SCHEME OF TREATMENT 13
C). SOLID & HAZARDOUS WASTE DETAILS 14
D). STORM WATER MANAGEMENT & RAIN WATER HARVESTING STRUCTURES
15
TABLE 2.7 ESTIMATE OF RAIN WATER HARVESTING 15
3.0 IMPACT ASSESSMENT & MITIGATION MEASURES 16-27
3.1 IMPACT ASSESSMENT 16
TABLE 3.1 CONSTRUCTION PHASE - POTENTIAL IMPACTS AND MITIGATION MEASURES
16
TABLE 3.2 OPERATIONAL PHASE – POTENTIAL IMPACTS AND MITIGATION MEASURES
21
4.0 ENVIRONMENTAL MANAGEMENT PLAN 25-42 4.1 INTRODUCTION: 26 4.2 ENVIRONMENTAL MANAGEMENT PLAN 26 4.2.1 EMP FOR AIR ENVIRONMENT 26 A) CONSTRUCTION PHASE 26 TABLE 4.1 DUST CONTROL PLAN 27 B) OPERATION PHASE 28 4.2.2 EMP FOR NOISE ENVIRONMENT 29 A) CONSTRUCTION PHASE 29 B) OPERATION PHASE 29 4.2.3 EMP FOR WATER ENVIRONMENT 30 A) CONSTRUCTION PHASE 30 B) OPERATION PHASE 30 4.2.4 EMP FOR LAND ENVIRONMENT 31 A) CONSTRUCTION PHASE 31 B) OPERATIONAL PHASE 32 4.2.5 EMP FOR BIOLOGICAL ENVIRONMENT 33 A) CONSTRUCTION PHASE 33 B) OPERATION PHASE 34 TABLE 4.2 SUGGESTED TREES FOR GREEN BELT DEVELOPMENT 34 4.2.6 EMP FOR SOCIO-ECONOMIC ENVIRONMENT 34 4.2.7 EMP FOR ENERGY CONSERVATION 35 FIGURE NO: 4.1 FLOW DIAGRAM FOR ENERGY CONSERVATION 35 4.3 ENVIRONMENTAL MANAGEMENT SYSTEM AND MONITORING
PLAN 36
4.3.1 ENVIRONMENTAL MONITORING 37 4.3.2 AWARENESS AND TRAINING 38 4.3.3 RECORD KEEPING AND REPORTING 39 TABLE 4.3 RECORD KEEPING REQUIREMENTS 39 4.3.4 ENVIRONMENTAL AUDITS AND CORRECTIVE ACTION PLANS 39 4.3.5 ENVIRONMENTAL MANAGEMENT CELL 39
5.0 BUDGET FOR IMPLEMENTATION OF EMP 40-41 TABLE 5.1 BUDGETARY ALLOCATION - CONSTRUCTION PERIOD 40 TABLE 5.2 BUDGETARY ALLOCATION - OPERATION PERIOD 41
6.0 BENEFITS OF THE PROJECT 42 7.0 CONCLUSION 43
M/s. Right Source Industrial Solutions (P) Ltd. 1
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
CHAPTER –1 1.0 INTRODUCTION
1.1 PURPOSE OF THE REPORT:
Sri. Kosuru Venkat Surya Subba Raju is proposing to construct a Residential
Apartments Project at Sy No. 43, Bahadurguda Village, Saroornagar Mandal,
Ranga Reddy District, Telangana State. The Total plot area is 8,821.05 Sqmts,
affected road widening area is 16.50 Sqmts and the Net plot area is 8,804.55 Sq.mts
and the total Project built up area is 40,856.78 Sq.mts ( Cellar + Stilt + 8 Floors
with 2 Blocks).
As the total area proposed to be developed <1,50,000 Square Meters, as per the
EIA Notification dated 14th September 2006, the proposed project activity falls
under Building & Construction projects 8(a) Category B (B2), which necessities to
obtain Environmental Clearance from SEIAA, Telangana State. But due to Absence
of SEIAA, Telangana State we are submitting the application to EAC, MoEF&CC,
Govt. of India, New Delhi for obtaining Environmental Clearance.
1.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT:
The proposed Residential Apartments project is promoted by Sri. Kosuru Venkat
Surya Subba Raju and having their registered office at H.No: 1-9-630/1, 3rd Floor,
Gyani Commercial Complex, Vidya Nagar, Hyderabad, Telangana State -500 044.
1.3 PROJECT COST: The estimated cost for the proposed project will be 41.0 Crore.
M/s. Right Source Industrial Solutions (P) Ltd. 2
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
1.4 SALIENT FEATURES OF THE PROJECT: The salient features of the project are given below
TABLE 1.1 – SALIENT FEATURES OF THE PROJECT
Total Plot Area 8,821.05 Sq.mts Peripheral Road Area 16.50 Sq.mts Net Plot Area 8,804.55 Sq.mts Total Project cost 41.0 Crore Built-up Area Apartments & Amenities Area – 30,346.11 Sqm
Parking Area – 10,510.67 Sqm Total Area – 40,856.78 Sqm
Greenbelt Area 923.10 Sqm
Height of the building 23.99 Mts Nearest Fire station Malakpet – 4.4 Kms (NW) Water requirement & Source Total Water Requirement – 186.28KLD
Fresh Water – 117.62 KLD Recycle Water from S.T.P – 68.66 KLD
Power requirement & Source 1400 KVA, TSCPDCL
Backup Power 2 x 500 KVA & 1 x 82.5 KVA DG sets
Solid waste & mode of disposal
660.27 Kgs/day - Waste will be segregated and disposed as per SWM Rules 2016. 9.0 Kgs/day STP sludge used as manure.
Hazardous waste & mode of disposal
Used batteries – 3 No’s/Year Waste Oil – 100 Liters/Year will be sent to TSPCB Authorized Re-Cyclers/Re-Processors
M/s. Right Source Industrial Solutions (P) Ltd. 3
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
CHAPTER – 2 2.0 PROJECT DESCRIPTION
2.1 LOCATION DETAILS:
Sri. Kosuru Venkat Surya Subba Raju is proposing to construct a Residential
Apartments Project at Sy No. 43, Bahadurguda Village, Saroornagar Mandal,
Ranga Reddy District, Telangana State. The Total plot area is 8,821.05 Sqmts,
affected road widening area is 16.50 Sqmts and the Net plot area is 8,804.55 Sq.mts
and the total Project built up area is 40,856.78 Sq.mts (Cellar + Stilt + 8 Floors with
2 Blocks).
Features of the site:
The area earmarked for development of Residential apartment’s project is located
at Bahadurguda Village. The geographical co-ordinates of the site are
17°20'54.08"N Latitude and 78°32'18.28"E Longitude.
i. Accessibility & Existing Road network
The nearest major road is NH-9 is 1.0 Kms (NE) & Saroornagar Road is about 0.3
Kms (N) to the project site.
ii. Topography
The General topography is plain topography. Commercial and Residential flats are
surrounding the site.
iii. Water Bodies
The major surface water bodies within the 10 kms radius are Sarurnagar Cheruvu -
0.8 kms (W), Musi River - 3.1 Kms (N), Kapra Cheruvu - 4.6 Kms (SE), Nalla
Cheruvu - 6.9 Kms (NNE), Masab Cheruvu - 7.0 Kms (SSE), Pedda Cheruvu - 7.7
Kms (NNE), Jilavarkhan Cheruvu - 7.7 Kms (SE), Burankhan Cheruvu - 8.1 Kms
(SSW), Antayya Cheruvu - 9.1 Kms (SSW), Hussain Sagar - 9.4 Kms (NW),
Devalama Cheruvu - 9.5 Kms (SSW), Mir Alam Cheruvu - 9.7 Kms (W). The
Location Map of the project site is provided at Figure No.2.1, Topographical Map
of the study area is provided at Figure No.2.2 and Site Plan are provided at Figure
2.3.
M/s. Right Source Industrial Solutions (P) Ltd. 4
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
FIGURE NO.2.1 - GOOGLE MAP SHOWING PROJECT LOCATION
M/s. Right Source Industrial Solutions (P) Ltd. 5
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
FIGURE NO: 2.2 –TOPOGRAPHICAL MAP
M/s. Right Source Industrial Solutions (P) Ltd. 6
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
FIGURE NO: 2.3 – PROJECT SITE LAYOUT PLAN
M/s. Right Source Industrial Solutions (P) Ltd. 7
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
TABLE 2.1: SALIENT FEATURES OF PROJECT SITE
Village Mandal District
Bahadurguda Saroornagar Ranga Reddy
Latitude 17°20'54.08"N
Longitude 78°32'18.28"E Ambient Temperature Minimum 130 C
Maximum 430C Humidity 55 – 65 %Rainfall 800 – 1100 mm per Annum Climate Tropical & Semi-Arid
Type of soil Silty sand and morum Distance from nearest Air Port RGIA, Shamshabad – 15.0 Kms (NW) Reserve Forest Mansurabad RF - 3.0 Kms (ENE)
Gurramguda PF - 4.2 Kms (SE) Kuntlur RF - 8.4 Kms (ENE) Imarath Kamcha RF - 8.6 Kms (SSW) Kutbullapur RF - 8.9 Kms (ENE) Nadargul RF - 9.3 Kms (S)
Water Bodies Saroornagar Cheruvu - 0.8 kms (W) Musi River - 3.1 Kms (N) Kapra Cheruvu - 4.6 Kms (SE) Nalla Cheruvu - 6.9 Kms (NNE) Masab Cheruvu - 7.0 Kms (SSE) Pedda Cheruvu - 7.7 Kms (NNE) Jilavarkhan Cheruvu - 7.7 Kms (SE) Burankhan Cheruvu - 8.1 Kms (SSW) Antayya Cheruvu - 9.1 Kms (SSW) Hussain Sagar - 9.4 Kms (NW) Devalama Cheruvu - 9.5 Kms (SSW) Mir Alam Cheruvu - 9.7 Kms (W)
Any Historical monuments within 10 KM radius
Paigah Tombs – 3.7 Kms (WSW) Salarjung Museum – 6.6 Kms (WNW) Charminar – 6.9 Kms (WNW) Falaknuma Palace – 7.7 (WSW) Golkonda Fort – 14.7 (WNW)
Any Ecologically Sensitive areas within 10 KM radius
Mahavir Harina Vanasthali National Park – 4.6 Kms (E) Nehru Zoological Park - 9.1 Kms (W) KBR National Park – 14.1 Kms (NW)
Topography Plain and land locked
M/s. Right Source Industrial Solutions (P) Ltd. 8
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
2.2 BUILT-UP AREA:
Sri. Kosuru Venkat Surya Subba Raju are proposing to construct a Residential
Apartments Project and the floor wise details are provided in Table 2.2.
TABLE 2.2 – NUMBER OF FLOORS AND BUILT UP AREA
Blocks No. of Floors
No. of Flats Area (Sq.mts)
A 8 Floors 112 14,692.38 B 8 Floors 112 14,678.48
Amenities G + 4 Floors - 975.25
Total - 224 30,346.11
Cellar - - 6,931.88
Stilt - - 3,578.79
Total Built-up Area - - 40,856.78
2.3 PARKING AREA:
The total area allocated for parking is 10,510.67 Sqm, which can accommodate 260
No’s of four wheelers. The total parking area is being proposed in the proposed
project is given below:
TABLE 2.3 – PARKING SPACE PROVISION
S.No. Parking Facility Area(Sq.mts) 1 Stilt Floor Area 3,578.79 2 Cellar Floor Area 6,931.88
Total 10,510.67 2.4 ROAD NETWORK:
The nearest major road is NH-9 is 1.0 Kms (NE) & Saroornagar Road is about 0.3
Kms (N) to the project site.
2.5 WATER REQUIREMENT:
The total water requirement of the project during occupational stage is 186.28
KLD, out of that the fresh water requirement is 117.62 KLD will be sourced from
M/s. Right Source Industrial Solutions (P) Ltd. 9
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
sourced from HMWS&SB and the recycled water from S.T.P is 68.66 KLD. The
total sewage water generated is 156.22 KLD. It is proposed to treat the sewage in
STP of capacity of 190 KLD. The treated waste water is used for Flushing &
gardening and remaining will be sent to public sewers. The total water requirement
during occupational stage is given below;
TABLE 2.4 – WATER REQUIREMENT
S.No. Requirement Quantity (KLD)
1 Domestic Water 117.62 2 Flushing Water 61.13 3 Gardening 5.53 4 Washings & others 2.00
Total 186.28 As per suggestions of National Building Code, 2016(NBC), water requirement for
occupants is 135 liters/day/person and for visitors the requirement is 15
liters/day/person.
2.6 POWER REQUIREMENT:
The power requirement for the proposed project is estimated as 1400 KVA which
will be sourced from the TSCPDCL.
2.7 BACK-UP POWER DETAILS:
Entire power, lighting, UPS power shall be on emergency supply through 2 x 500
KVA & 1 x 82.5 KVA DG set.
2.8 FUEL REQUIREMENT:
The fuel requirement for 2 x 500 KVA & 1 x 82.5 KVA DG Set is 120 Liters. The
fuel used in DG sets is High Speed Diesel (HSD).
2.9 MAN POWER REQUIREMENT:
The maximum man power required for the development of proposed project during
construction phase is 100 persons.
M/s. Right Source Industrial Solutions (P) Ltd. 10
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
2.10 STORM WATER DRAINS:
All along the road network and the arterial roads of the proposed complex, storm
water drains would be provided to collect water during rains. They would
adequately sized to prevent over flooding of the site.
2.11 ENVIRONMENTAL INFRASTRUCTURE:
a). Waste Water Generation: Total quantity of wastewater generation is likely to be 156.22 KLD. The generated
waste water is collected and treated in in-house Sewage Treatment Plant of
190KLD capacity. The available water after treatment is 140.59 KLD, which will
be used for Gardening & Flushing and remaining will be sent to public sewer. The
water balance details are presented below.
TABLE 2.5 - WATER BALANCE
Input Requirement Quantity (KLD)
Out put Quantity (KLD)
Domestic 117.62 Domestic Waste Water 94.09 Flushing 61.13 Flushing waste water 61.13 Gardening 5.53 Waste Water from
Washings 1.00
Washings & Others 2.00 Evaporation & other Losses 30.06
Total 186.28 Total 186.28
The waste water generated from process i.e 156.22 KLD which will be treated in
190 KLD Capacity S.T.P. The available recycled water after treatment is 140.59
KLD, which will be used for Gardening & Flushing and the rest will be sent to
public sewer system. It should therefore be concluded there is no significant impact
on surface water quality & hydrology of the area. The proposed rainwater
harvesting scheme stabilizes the groundwater table in the area.
M/s. Right Source Industrial Solutions (P) Ltd. 11
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
b). Sewage Treatment Plant (STP):
A sewage treatment plant of 190 KLD capacity based on Sequential Batch Reactor
(SBR) technology is proposed to treat 156.22 KLD of sewage water generated in
the proposed project. After treatment the water will be used for Gardening &
Washings. The design of the STP shall be based on the parameters given in below
table.
TABLE 2.6 - DESIGN PARAMETERS OF SEWAGE TREATMENT PLANT
Parameter Unit Inlet
Concentration Outlet
Concentration pH -- 7.0 – 9.5 6.5 – 9.0 Oil & Grease Mg/l 20-30 <10 BOD Mg/l 250-350 <10 COD Mg/l 500- 600 <50 TSS Mg/l 150-300 <20
Sewage Treatment Process Description:
Primary treatment:
The sewage is collected and discharged into the treatment plant through inlet pipe. A
bar screen chamber is provided for retaining coarse matter. The screens are manual
type and are to be cleaned at regular intervals. Two stages of screens are provided
i.e. coarse screen followed by fine screens. The sewage is then taken to grit chamber
for removal of grit. From the grit chamber, the sewage is taken to an equalization
tank for reduce the variations in waste flow rate and its characteristics. It is proposed
to have equalization tank with detention time of 6 hours. For mixing and to avoid
solids from settling, air shall be bubbled in the equalization tank through a grid
placed at the base of the tank. The equalized sewage is pumped at a uniform and
constant rate for further treatment.
M/s. Right Source Industrial Solutions (P) Ltd. 12
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
Secondary treatment:
The SBR is a special form of activated sludge process in which the entire treatment
process takes place in the one reactor tank. The wastewater is treated in batch mode
and each batch mode is sequenced through a series of treatment stages like fill,
aeration, sludge settle and decant. The wastewater from the equalization tank is
entering into the filling phase of SBR. Mixing and aeration can be done during
filling phase of the tank to carry biological treatment. Next the wastewater which is
aerated enters into react phase. In the react phase, the aeration is continuously
allowed to increase the rate of organic removal.
Microorganisms + Organic matter Water + Gas + Biomass
Followed the react phase, the wastewater undergoes settle phase. During the settle
phase, no wastewater enters the tank and no mixing and aeration takes place. The
sludge is settled to the bottom of the tank and clear supernatant (liquid) is formed at
the top of the tank. In the final stage, the formed clear supernatant (liquid) is
decanted from the tank. It is important that no scum or surface foam should be
present. It is optimal that the decant wastewater volume is equal to the wastewater
in the fill phase.
Advantages:
It can be installed in a limited amount of space, as treatment takes place in a single reactor instead of more basins.
Respond to the flow and load variations
Low sludge production
Flexibility in operating and control
No odor production
Gives high treatment efficiency in a single step biological process
Capital cost savings for eliminating more reactor tanks.
Tertiary treatment: The clear liquid from SBR will be collected in chlorine
contact tank for the disinfection treatment. Then it is collected in a sump and
pumped to a pressure sand filter for removal of particulate matter and then taken
M/s. Right Source Industrial Solutions (P) Ltd. 13
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
through an activated carbon column for removal of trace organics and pollutants
(chlorine, color, trace organics etc.).
Sludge Treatment: The Sludge collected from the settling tank of SBR is
transferred to sludge sump tank. Filter press feed pumps are used for dewatering
process by transfer the sludge from sludge sump tank to filter press. After the
Dewatering process, the available solid organic mass is used as manure for crops
after undergo suitable treatment and the available water from the filter press is
recycled into the equalization tank.
Sewage treatment plant is designed to treat 156.22 KLD of Sewage per day. The
proposed scheme is depicted in the figure attached below.
FIGURE NO: 2.4– PROPOSED SCHEME OF TREATMENT
M/s. Right Source Industrial Solutions (P) Ltd. 14
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
c). Solid & Hazardous Waste Details:
S.No Type of Waste
Quantity Collection/storage Disposal
1 Garbage 660.27Kg/day Stored in Green, Blue and Red/Black bins for Recyclable, Non-Recyclable wastes and Hazardous Waste respectively. Collected and transported to the segregation point by Municipality.
Biodegradable Waste @ 40% will be treated in In-house Organic Waste Convertor and Non Bio-degradable waste @ 60% will be Sent to Authorized Vendors as per SWM Rules 2016.
2 STP Sludge
9.0 Kg/day Stored in HDPE bags. Used as manure and or given to farmers.
3 E-Waste 224.64 Kg/year - Sent to Authorized Recyclers as per EWM Rules 2016.
4 Used Batteries
3 No’s/ year - Sent to Authorized recyclers or returned to seller
5 Used Lubricant
100 Lit/year Stored in HDPE Carboy Sold to authorized recyclers
M/s. Right Source Industrial Solutions (P) Ltd. 15
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
d). Storm Water Management & Rain Water Harvesting Structures
Elaborate plans have been made for channelizing the storm water by constructing
water drains leading to the reservoirs. In order to minimize the surface runoff loss,
groundwater recharging through groundwater recharge pits at the project site has
been planned. Appropriate design considerations have been taken while designing
the recharge pits.
TABLE-2.7: ESTIMATE OF RAIN WATER HARVESTING
Rainwater Harvesting
Type of Area Area
(in m2)
Run-off Coefficient
Rainfall intensity (in m)
Rain water harvesting
potential/hour (in m3)
Roof-top area 3918.57 0.90 0.044 155.2
Green Area 923.10 0.15 0.044 6.1
Paved area 3962.9 0.80 0.044 139.5
Total storm water load on the site with per hour retention is 300.80
Considering 15 minutes retention time, total storm water load 75.2
Taking the radius as 1 m and effective depth as 2 m, volume of a RWH pit ( π r2h)
6.3
Hence no. of pits required in approx = Total storm water load considering 15 minutes retention time / Volume of a RWH pit
11.97
M/s. Right Source Industrial Solutions (P) Ltd. 16
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
CHAPTER – 3
3.0 IMPACT ASSESSMENT & MITIGATION MEASURES
3.1 IMPACT ASSESSMENT:
The potential impacts on the surrounding environment in the 10km radial distance
of proposed project site along with the mitigation measures during construction and
operational stages are summarized in Table 3.1 and Table 3.2.
The construction phase is for a period of 24 months. Considering this to be a
relatively short period, all construction impacts can be considered to be short term
and temporary.
As for the operational phase, the project proponent shall ensure that impacts are
minimized and are within applicable/ specified limits by TSPCB & CPCB by
providing relevant pollution control equipment and/ or mitigation measures
discussed in the following tables.
M/s. Right Source Industrial Solutions (P) Ltd. 17
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
TABLE – 3.1 - CONSTRUCTION PHASE - POTENTIAL IMPACTS AND MITIGATION MEASURES
S. No.
Environmental components
Potential impacts Source of impacts Mitigation measures Remarks
1. Water resources Minor negative & temporary impact on surface & ground water resources.
Water requirement of 50 - 70 KLD for construction activities
Judicious use of water; minimization of water consumption by use of high-pressure hoses for dust suppression
Water requirement will be sourced from the bore wells & water tankers. However, the bore wells shall not be tapped beyond their yield.
2. Surface water quality
No impact Erosion and run-off due to excavation/ construction activities, especially in monsoon season; Discharge of waste water, construction as well as domestic.
Avoiding excavation in monsoon season; providing appropriate measures for erosion and sediment control; providing adequate sanitation facilities for workers at site; avoiding discharge of untreated wastewater in the area.
-
3. Ground water quality
No impact Construction activities Storage area for fuels, paints, thinners, etc. to be such so as to avoid chances of spillage. No discharge to ground water body.
-
4. Air quality Temporary negative impact
Construction equipment; operation of DG sets for construction power
Carrying out construction activity in temporary enclosures, where feasible; water sprinkling for dust
-
M/s. Right Source Industrial Solutions (P) Ltd. 18
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
S. No.
Environmental components
Potential impacts Source of impacts Mitigation measures Remarks
requirement; vehicular traffic; excavation; concreting; etc.
suppression; regular maintenance of construction equipment & vehicles; use of fuel of proper quality; use of state-of-the-art construction equipment & methods
5. Noise Medium negative & temporary
Various construction activities; material and vehicular movement
Use of low noise generating state-of-the-art construction equipment and construction techniques; providing personnel protective equipment to workers; providing temporary enclosure for DG set and other construction activities, where feasible; avoiding construction work in the night time
-
6. Land (i) Land use/
requirement No impact The Net total plot area
is 8804.55 Sq. m. No land conversion is required as land is a vacant plot and is designated for Residential/ Commercial development by municipal corporation.
Site Premises is designated as Residential area
(ii) Solid wastes & land pollution
Temporary minor negative impact
Construction material handling; construction wastes handling and
Maintaining proper inventory control for reduced waste generation; substitution of
-
M/s. Right Source Industrial Solutions (P) Ltd. 19
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
S. No.
Environmental components
Potential impacts Source of impacts Mitigation measures Remarks
disposal hazardous raw materials by non-hazardous materials, where feasible; providing proper facility for storage and handling of fuel oils; disposal of spent oils, classified as hazardous waste by sale to authorized third party; proper handling and disposal of construction wastes.
(iii) Geology & Seismicity
No impact Construction of the Residential Buildings
No heavy structure planned as part of the project
All civil structures shall be constructed as per earthquake zone classification
7. Ecology Minor positive impact
Construction activity causing impact on existing ecosystem on-site and top soil; cutting of existing vegetation, if required;
No trees on the site shall be cut. Green belt will be developed all along the building boundary, roadside and lane divider. Water sprinkling during dust generation activities; erosion and sediment control; noise and fugitive dust control; restricting construction activity during night time.
No ecologically sensitive area such as forest/ agricultural land will be used for the project. Presently, the site has no trees. 923.10 Sq. m to be developed as greenbelt.
M/s. Right Source Industrial Solutions (P) Ltd. 20
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
S. No.
Environmental components
Potential impacts Source of impacts Mitigation measures Remarks
8. Socio-economic (i) Population and
literacy rate Minor negative and temporary
Increase in population due to possible temporary settling of construction workers from outside the study area for the project
Employing local people to the maximum extent possible
About 100 construction workers are expected to be employed
(ii) Employment Minor positive & temporary impact
Availability of construction jobs
Employing local people to the maximum extent possible
About 100 construction workers are expected to be employed
(ii) Amenities such as education, medical, water supply, sanitation, etc.
No impact Needs of construction workers;
Employing local people to the extent possible for construction work; making adequate provision through the contractors to handle water, sanitary, medical and fuel requirement of construction workers to ensure that the existing infrastructure is not strained.
-
(iv) Transportation Temporary negative impact
Increased traffic load due to transportation of construction materials and workers
Ensuring that traffic is well regulated. Use of non-peak hours for material transportation
-
M/s. Right Source Industrial Solutions (P) Ltd. 21
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
TABLE – 3.2 - OPERATIONAL PHASE – POTENTIAL IMPACTS AND MITIGATION MEASURES
S. No.
Environmental components
Potential impacts Source of impacts Mitigation measures Remarks
1. Water resources Minor negative impact on surface water resources Moderate negative impact on ground water resources due to consumption. Minor positive impact due to recharge by rainwater harvesting.
Total water requirement for the proposed project is 186.28 KLD.
Recycle water will be used Flushing and Gardening
The fresh water will be sourced from ground water.
2. Surface water quality
No impact Discharge of sewage and waste water from utilities.
Recycle water will be used Flushing and Gardening
-
3. Ground water quality
No impact Discharge of sewage and waste water from utilities
No discharge of wastewater to ground water body; use of treated sewage water for Flushing, Gardening
Rainwater from the rain water harvesting will be used to recharge ground water.
4. Air quality Minor negative impact (for SO2,
Fuel combustion in DG sets
All emissions will be well within the specified emissions
All emissions well within the specified
M/s. Right Source Industrial Solutions (P) Ltd. 22
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
S. No.
Environmental components
Potential impacts Source of impacts Mitigation measures Remarks
NOX and HC emissions)
standards; stack height = building height + 5 mts. for safe dispersal of pollutants; HSD with 0.05% sulfur content in DG sets; periodic maintenance of DG sets for reduced emissions
limits
5. Noise Minor negative impact
Noise generating rotating/ moving equipment
Proper equipment selection; mandatory acoustic enclosure for DG sets; regular maintenance of noise generating equipment; providing personnel protective equipment to persons working in noisy areas; suitable design and location of utility block; development of suitable green belt and landscaping
-
6. Land environment (i) Land use /
requirement No impact Requirement of land for
the proposed project 8,804.55 Sq.mts of area available for development
Once the project is operational, no additional land will be required.
M/s. Right Source Industrial Solutions (P) Ltd. 23
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
S. No.
Environmental components
Potential impacts Source of impacts Mitigation measures Remarks
(ii) Solid wastes & land pollution
Minor negative impact
Handling and disposal of hazardous and solid wastes
Segregation of wet and dry garbage – disposal of dry garbage through off-site recycling or to municipal waste collection system and wet waste to composting at site; disposal of waste lube oils by sale to authorized third party; buy-back arrangement for waste lead acid batteries
Though no solid/ hazardous waste will be disposed off on land, chances of inadvertent occasional spillage on land cannot be ruled out
(iii) Geology & Seismicity
No impact Improper building design not adhering to specified codes; improper building maintenance
Regular maintenance of the structures to withstand natural phenomena; carrying out the structural integrity testing
-
9. Ecology No impact Emissions and discharges from project operations; noise generation; improper disposal of wastes
All emissions and discharges including noise will be within specified standards; all solid/ hazardous waste will be disposed off in environmentally sound manner
-
10. Socio-economic factors (i) Population and
literacy rate No impact Increase in population
due to settlement of Employing personnel from within the study area to the
Employment Generation and New
M/s. Right Source Industrial Solutions (P) Ltd. 24
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
S. No.
Environmental components
Potential impacts Source of impacts Mitigation measures Remarks
personnel and their families from outside the study area for the proposed project
extent possible, subject to availability of skilled manpower requisite to the job requirement
Educational facilities will be established.
(ii) Employment Medium positive impact
Direct employment of personnel for proposed project.
Employing personnel from within the study area to the extent possible, subject to availability of skilled manpower requisite to the job requirement
Approximately 100 persons Direct employment and indirect employment are expected to be employed for the project
(ii) Amenities such as education,
medical, water supply,
sanitation, etc.
No impact Requirement of various facilities for the children of personnel employed from outside the study area
Employing personnel from within the study area to the extent possible, subject to availability of skilled manpower requisite to the job requirement.
Various amenities in the study area are adequate.
(iv) Transportation Medium negative impact
Burden on the existing road infrastructure due to the increased traffic from the proposed project
Ensuring that vehicular movement is controlled during peak traffic hours; providing bus services from the office to the nearest railway station; encouraging car-pools for office employees
-
M/s. Right Source Industrial Solutions (P) Ltd. 25
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
CHAPTER – 4
4.0 ENVIRONMENTAL MANAGEMENT PLAN
4.1 INTRODUCTION:
The Environmental Management Plan (EMP) is a site specific plan developed to
ensure that the project is implemented in an environmental sustainable manner where
all contractors and subcontractors, including consultants, understand the potential
environmental risks arising from the proposed project and take appropriate actions to
properly manage that risk. EMP also ensures the project implementation is carried out
in accordance with the design by taking appropriate mitigative actions to reduce
adverse environmental impacts during its life cycle.
The plan outlines existing and potential problems that may adversely impact the
environment and recommends corrective measures where required. Also, the plan
outlines roles and responsibility of the key personnel and contractors who are charged
with the responsibility to manage the site.
The EMP is generally: Prepared in accordance with rules and requirements of the MOEF and the
Telangana Pollution Control Board;
To ensure that the component of facility is operated in accordance with the design;
Process that confirms proper operation through supervision and monitoring;
System that addresses public inconvenience during construction and operation of
the facility; and
Plan that ensure remedial measures are implemented immediately.
The key benefits of the EMP are that it provides the organization with means of
managing its environmental performance thereby allowing it to contribute to improved
environmental quality. The other benefits include cost control as improved relations to
the stakeholders.
M/s. Right Source Industrial Solutions (P) Ltd. 26
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
EMP includes four major elements; Commitment & Policy: Project proponents will strive to provide and implement
the EMP that incorporates all issues related to air, land and water for the project.
Planning: This includes identification of environmental impacts, legal
requirements and setting environmental objectives.
Implementation: This comprises of resources available to the developers,
accountability of contractors, training of operational staff associated with
environmental control facilities and documentation of measures to be taken.
Measurement & Evaluation: This includes monitoring, corrective actions, and
record keeping.
It is suggested that as part of the EMP, a Monitoring Team should be formed by the
project proponent comprising of the site in-charge, project planning group
representative and project implementation team representative. This committee’s role
would be to ensure proper, operation and management of the EMP including the
regulatory compliance.
4.2 ENVIRONMENTAL MANAGEMENT PLAN
An Environmental Management Plan (EMP) will be required to mitigate the adverse
environmental impacts during construction and operation phase of the project and
these are as below:
4.2.1 EMP FOR AIR ENVIRONMENT
A) CONSTRUCTION PHASE
To mitigate the impact of PM (dust) during the construction phase of the proposed
project, the following measures are recommended for implementation:
a dust control plan; and
Procedural changes to construction activities.
M/s. Right Source Industrial Solutions (P) Ltd. 27
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
TABLE 4.1: DUST CONTROL PLAN
S.No Fugitive Dust Source Category
Dust Control Actions
1. Earth-moving - For any earth moving which is more than 30m from all property lines, conduct watering as necessary to prevent visible dust emissions from exceeding 100m in length in any direction.
2. Disturbed surface areas (except completed grading areas)
- Apply dust suppression in a sufficient quantity and frequency to maintain a stabilized surface; - Areas, which cannot be stabilized, as evidenced by wind driven dust, must have an application of water at least twice per day to at least 80 percent of the unstabilized area.
Disturbed surface areas (completed grading areas)
- Apply water to at least 80 percent of all inactive accessible disturbed surface areas on a daily basis when there is evidence of wind driven fugitive dust.
3. Inactive disturbed surface areas
- Apply dust suppressants in sufficient quantity and frequency to maintain a stabilized surface.
4. Unpaved roads -Water all roads used for any vehicular traffic at least twice per day of active operations; OR - Water all roads used for any vehicular traffic once daily and restrict vehicle speed to 30 kmph.
5. Open storage piles - Apply water to at least 80 percent of the surface areas of all open storage piles on a daily basis when there is evidence of wind driven fugitive dust.
6. Track-out control -Downwash of trucks (especially tyres) prior to departure from site.
The most cost-effective dust suppressant is water, because a source of water tends to
be readily available on a construction site. Water can be applied using water trucks,
handheld sprays and automatic sprinkler systems. Furthermore, incoming loads could
M/s. Right Source Industrial Solutions (P) Ltd. 28
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
be covered to avoid loss of material in transport, especially if material is transported
off-site.
B) OPERATION PHASE
To mitigate the impact of pollutants from diesel generator sets during the operational
phase of the site the following measures are recommended for implementation:
Diesel generator set emission control measures; and
Greenbelt development.
Diesel Generator Set Emission Control Measures
The most important pollutant requiring further control is NOx, as the impact of SO2
emission is minimal because of the use of low (~0.05%) Sulphur in diesel as fuel.
The following mitigation measures are proposed for NOx reduction:
add-on emission control technologies; and
NOx retarder
Among the above-mentioned options, inherent low NOx emissions technologies (i.e. a
temperature retarder) and better dilution through higher stack are preferred cost
effective mitigation measures. The add-on emission control technologies are not
considered as it leads to pollution transfer to another media and shall require further
mitigative measures.
Greenbelt Development
Increasing vegetation in the form of greenbelt is one of the preferred methods to
mitigate air pollution. Plants serve as a sink for pollutants, reduce the flow of dust and
reduce noise pollution.
M/s. Right Source Industrial Solutions (P) Ltd. 29
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
4.2.2 EMP FOR NOISE ENVIRONMENT A) CONSTRUCTION PHASE
To mitigate the impact of noise from construction equipment during the construction
phase of the site the following measures are recommended for implementation:
Noise Shields - Construction equipment producing the most amount of noise should
be fitted with noise shields. This shield is a physical barrier (composed of brick and
mud, with a non reflective internal plastering), approximately 3 meters in height,
which will provide adequate noise attenuation.
Time of Operation - Noisy construction equipment should not be permitted during
night hours.
Job Rotation and Hearing Protection - Workers employed in high noise areas will
be rotated. Earplugs/muffs, or other hearing protective wear will be provided to those
working very close to the noise generating machinery.
B) OPERATION PHASE To mitigate the impact of noise from diesel generator sets during the operational phase
the following measures are recommended for implementation:
Noise emissions control technologies; and
Greenbelt development.
Noise Emissions Control Technologies: All the diesel generators will be housed in a
suitable acoustic enclosure so that noise levels at a distance of one meter do not
exceed 75 dB(A) at 75% load (as per CPCB norms). The diesel generator set housing
will be equipped with walls and ceilings lined with glass wool to acoustically treat the
noise levels. This acoustic insulation shall be designed to meet the mandatory
standards based on a 25 dB(A) insertion loss.
M/s. Right Source Industrial Solutions (P) Ltd. 30
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
4.2.3 EMP FOR WATER ENVIRONMENT A) CONSTRUCTION PHASE To prevent degradation and maintain the quality of the water source, adequate control
measures have been proposed to check the surface run-off, as well as uncontrolled
flow of water into any water body. Following management measures are suggested to
protect the water quality during the construction phase.
Avoid excavation during monsoon season.
No discharge of treated wastewater to soil and ground water body.
Waste water channels from the site would be connected to septic tank during
construction to prevent wastewater from entering the water bodies.
To prevent surface and ground water contamination by oil/grease, leak proof
containers should be used for storage and transportation of oil/grease. The
floors of oil/grease handling area should be kept effectively impervious. Any
wash off from the oil/grease handling area or workshop shall be drained
through impervious drains, Clarifiers or oil/water separators shall be
constructed and effluent should be treated appropriately before releasing it.
Construction activities generate disturbed soil, concrete fines, fertilizer, oils
and other wastes. On-site collection and settling of storm water, prohibition of
equipment wash downs, and prevention of soil loss and toxic releases from the
construction site are necessary to minimize water pollution.
All stacking and loading areas should be provided with proper garland drains
equipped with baffles to prevent run off from the site to enter any water body.
B) OPERATION PHASE In the operation phase of the project, water conservation and development measures
need to be taken including all possible potential for conservation of water, reuse,
rainwater collection in reservoirs, and recycling of waste water. These could be in the
form of the following:
M/s. Right Source Industrial Solutions (P) Ltd. 31
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
Water source Development
Minimizing water consumption
Promoting reuse of water after treatment and development of closed loop
systems for different water streams.
4.2.4 EMP FOR LAND ENVIRONMENT
A) CONSTRUCTION PHASE:
Waste generated from construction activity includes construction debris, biomass from
land clearing activities (if any), waste from the labour camp, and. other waste. The
following section discusses management of each type of waste. Besides management
of topsoil is an important area for which management measures are required.
Construction Debris: Construction debris is bulky and heavy and re-utilization and recycling is an important
strategy for management of such waste. As concrete and masonry constitute the
majority of waste generated, recycling of this waste by conversion to aggregate can
offer benefits of reduced landfill space and reduced extraction of raw material for new
construction activity. This is particularly applicable to shopping mall project as the
construction is to be completed in a phased manner. Recycled aggregate will be used
for filler application, and as a sub-base for internal road construction. Mixed debris
with high gypsum, plaster, shall not be used as fill, as they are highly susceptible to
contamination, and will be given to recyclers. Construction contractors shall remove
metal scrap from structural steel, piping, concrete reinforcement and sheet metal work
from the site. A significant portion of wood scrap can be reused on site. Recyclable
wastes such as plastics, glass fiber insulation, roofing etc shall be sold to recyclers.
Solid and Other waste:
Construction sites are sources of many toxic substances, such as paints, solvents,
wood preservatives, pesticides, adhesives and sealants. Such wastes generated during
M/s. Right Source Industrial Solutions (P) Ltd. 32
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
construction phase shall be stored in sealed containers, labeled, and disposed of as
required by the Hazardous Wastes Management, Handling and Transboundary
Movement Amendment Rules (MoEF, 2016). Some management practices to be
developed are;
Herbicides and pesticide will not be over applied (small-scale applications) and
not applied prior to rain;
Paintbrushes and equipment for water and oil based paints shall be cleaned
within a contained area and shall not be allowed to contaminate site soils,
watercourses, or drainage systems.
Adequate storage facilities for such waste shall be provided and the waste
collection containers conveniently located. A separate designation to earmark
such waste will be made so that the waste storage areas are away from storm
drains or watercourses.
Clearly label all such waste containers with the waste being stored and the date
of generation.
Educate employees and subcontractors on waste storage and disposal
procedures.
B) OPERATIONAL PHASE: The philosophy of solid waste management will be to encourage the four R’s of waste
i.e. waste reduction, reuse, recycling, and recovery (materials & energy). This will
reduce in lesser reliance on land filling. Regular public awareness meetings will be
conducted to involve the occupants and the employees to ensure proper segregation,
storage and collection of waste as per the Solid Waste Management Rules 2016.
The Environmental Management Plan for the solid waste focuses on the Segregation,
Storage at source and Collection of the waste management system.
M/s. Right Source Industrial Solutions (P) Ltd. 33
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
Segregation and storage at source: Segregation of waste at source should be made mandatory for the activity. Segregation
or sorting waste at its source should be practiced in order to encourage
reuse/recycling. With segregation at source recyclables do not lose their commercial
value due to cross contamination. Waste generated at the residential activity should be
segregated as: Organic, Inorganic, recyclables and waste from changing oil. The entire
waste stream from the activity should be stored and collected separately.
4.2.5 EMP FOR BIOLOGICAL ENVIRONMENT:
Construction activities change the natural environment. But it also creates a built
environment for the surrounding. The project requires the implementation of
following choices exclusively or in combination.
A) CONSTRUCTION PHASE: Restriction of construction activities to defined project areas, which are
ecologically less sensitive.
Restrictions on location of labour camps and offices for project staff near the
project area to avoid human induced secondary additional impacts on the flora
and fauna species.
Cutting, uprooting, coppicing of trees or small trees present in and around the
project site for cooking, burning or heating purposes by the laborers will be
prohibited and suitable alternatives for this purpose will be found.
Along the major construction work the peripheral greenbelt should be
developed, so that; it will grow to become a full-fledged green cover by the
time the construction is over.
M/s. Right Source Industrial Solutions (P) Ltd. 34
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
B) OPERATION PHASE: Enhancement of current ecology at the proposed project site will entail the following
measures:
Plantation & Landscaping
Green Belt Development
The section below summarizes the techniques to be applied to achieve the above
objective
Plantation & landscaping:
Selection of the plant species will be based on their adaptability to the existing
geographical conditions and the vegetation composition of the forest type of the
region.
During the development of the green belt within the project area, it has to be
emphasized that those native plant species should be planted which are having good
ornamental values and fast growing with excellent canopy cover.
TABLE 4.2: SUGGESTED TREES FOR GREEN BELT DEVELOPMENT
Scientific Name Standard Name Time when flowering – fruiting occurs
Tamarindus indica Chinta March-April Syzygium cumini Jama June-July Mangifera indica Mango April-July Leucaena leucocephala
Subabul February-May
Emblica officinalis Usiri January Azadirachta indica Vepa or Neem June-July
4.2.6 EMP FOR SOCIO-ECONOMIC ENVIRONMENT:
The Social management plan has been designed to take proactive steps and adopt best
practices, which are sensitive to the socio-cultural setting of the region. The Social
Management Plan for the proposed project will focus on the following components.
M/s. Right Source Industrial Solutions (P) Ltd. 35
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
Opportunities during Construction and Operation phase:
Proposed project would provide employment opportunity during construction and
operation phase. There would also be a wider economic impact in terms of generating
opportunities for secondary occupation within and around the activity. The main
principles considered for employment and income generation opportunities are out
lined below:
Employment strategy would prefer employment of local people.
General recruitment procedures will be transparent, public, open to all and
recruitment should be publicized in advance.
There will be no discrimination on basis of gender, caste or other factors.
4.2.7 EMP FOR ENERGY CONSERVATION: Energy conservation program will be implemented through measures taken both on
energy demand and supply as given in Figure 4.1
FIGURE NO:4.1 FLOW DIAGRAM FOR ENERGY CONSERVATION
Energy conservation will be one of the focuses during the Residential Activity
planning and operation stages. The conservation efforts would consist of the
following:
Supply Demand Energy Conservation
Use energy efficient DG Sets
Exploring the possibilities of introducing renewable energy
Reduce Consumption
Use energy – efficient appliances
Create guest awareness
M/s. Right Source Industrial Solutions (P) Ltd. 36
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
ENERGY SAVING PRACTICES: Purchase of energy efficient appliances
Constant monitoring of energy consumption and defining targets for energy
conservation
Adjusting the settings and illumination levels to ensure minimum energy used
for desired comfort levels
Installing programmable on/off timers and sensors for low occupancy areas
Use of compact fluorescent lamps and low voltage lighting.
Sunscreen films on windows to reduce heating inside the buildings
4.3 ENVIRONMENTAL MANAGEMENT SYSTEM AND MONITORING
PLAN:
Apart from having an Environmental Management Plan, it is necessary to have a
permanent staff charged with the task of ensuring its effective implementation of
mitigation measures and to conduct environmental monitoring. The major duties and
responsibilities of the person – in - charge shall be as given below:
To implement the environmental management plan,
To assure regulatory compliance with all relevant rules and regulations,
To ensure regular operation and maintenance of pollution control devices,
To minimize environmental impacts of operations by strict adherence to the
EMP.
To initiate environmental monitoring as per approved schedule.
Review and interpretation of monitored results and corrective measures in case
monitored results are above the specified limit.
Maintain documentation of good environmental practices and applicable
environmental laws as ready reference.
Maintain environmental related records.
M/s. Right Source Industrial Solutions (P) Ltd. 37
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
Coordination with regulatory agencies, external consultants, monitoring
laboratories.
Maintain of log of public inconvenience and the action taken
4.3.1 ENVIRONMENTAL MONITORING:
The purpose of environmental monitoring is to evaluate the effectiveness of
implementation of Environmental Management Plan (EMP) by periodically
monitoring the important environmental parameters within the impact area, so that any
adverse affects are detected and timely action can be taken. The following areas will
be monitored regularly;
1) Raw water quality of Public Water Supply, Bore well water and tanker water
(whenever used) will be monitored regularly to ensure suitability for drinking
or other domestic usage.
2) The treated water quality shall also be checked on a regular basis particularly at
the points of actual use.
3) Water consumption in various areas and for different users will be measured on
a regular basis. Water measurement devices will be included in the design itself
so that representative water consumption data can be obtained and measures of
control instituted.
4) Raw and Treated Sewage will be monitored for general parameters like pH, SS,
COD, BOD and Oil & Grease. Also, residual chlorine and coliforms will also
be monitored for treated effluent.
5) Ambient air quality within the project area will be monitored quarterly in a
year for PM2.5, PM10, SO2, NOx & CO.
6) Stack emissions with respect to PM, SOx, and NOx level will be regularly
monitored from all stacks. The DG stack emissions especially are regulated as
per G.S.R- 489(E) dated July 9th, 2002 and compliance to these or TSPCB
standards if any, will be ensured.
M/s. Right Source Industrial Solutions (P) Ltd. 38
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
7) Noise levels will be checked at regular interval near service block with DG
sets, boilers, near STP and other noise generating areas.
8) Quantity of solid waste generation will also be measured for the different types
of solid waste.
9) Quantity of hazardous wastes generated (waste lube and transformer oil) shall
be measured on a regular basis and records of disposal maintained as per the
Hazardous Waste (Management & Handling Rules, 2016).
10) Numbers of used lead-acid batteries disposed off to authorized vendors/ dealers
will be monitored and requisite records maintained.
4.3.2 AWARENESS AND TRAINING
Training and human resource development is an important link to achieve sustainable
operation of the facility and environmental management. For successful functioning of
the project, relevant EMP’s should be communicated to the following groups of
people:
Site Staff:
Relevant personnel at site must be trained for the following:
Collection, Segregation and Storage of the solid and waste generated during oil
change.
Operation and maintenance of Sewage Treatment Plant and reclamation system
Requirements of the Emergency Response Plan in case of an emergency.
Techniques for waste minimization, water conservation and energy
conservation
Applicable environmental, health and safety regulations and compliance
requirements for the same.
Functioning of the Environmental Management System including
environmental monitoring, reporting and documentation needs.
M/s. Right Source Industrial Solutions (P) Ltd. 39
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
4.3.3 RECORD KEEPING AND REPORTING
Records should be maintained for regulatory, monitoring and operational issues.
Typical record keeping requirements for the project site is summarized in Table 4.3
Table – 4.3: RECORD KEEPING REQUIREMENTS
Parameter Particulars
Solid Waste Handling and Disposal Daily quantity of waste generated and sent for disposal
Sewage Treatment Daily quantity of raw and treated sewage Quantity and point of usage of treated wastewater quality
Regulatory Licenses (Environmental) Environmental Permits / Consents from TSPCB / MOEF Copy of Waste manifests as per requirement
Monitoring and Survey Records of all monitoring carried out as per the finalized Monitoring protocol.
4.3.4 ENVIRONMENTAL AUDITS AND CORRECTIVE ACTION PLANS
To assess whether the implemented EMP is adequate, the project Management
Committee will conduct periodic environmental audits. These audits will be followed
by Corrective Action Plans (CAP) to correct various issues identified during the
audits.
4.3.5 ENVIRONMENTAL MANAGEMENT CELL:
At least one permanent employee (Environmental Officer) with adequate educational
and professional qualification and experience to discharge responsibilities related to
environmental management including statutory compliance, pollution prevention/
waste minimization, environment monitoring, preventive maintenance of pollution
control equipment, green belt development and maintenance will be employed by the
project proponent. The Environmental Officer will be responsible for all issues related
to environmental management at proposed project and will report directly to the
management.
M/s. Right Source Industrial Solutions (P) Ltd. 40
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
CHAPTER–5
5.0 BUDGET FOR IMPLEMENTATION OF EMP
TABLE – 5.1: BUDGETARY ALLOCATION - CONSTRUCTION PERIOD
CAPITAL INVESTMENT (IN LAKHS)
S. NO PARTICULARS AMOUNT REMARKS
1 Acoustic Enclosures & Stack attached to DG sets
2.50 D.G. Room & Stack height and Monitoring Platform
2 S.T.P (Sewage Treatment Plant) 25.0 Civil Works, Plant & Machinery & Technical Consultancy charges
3 Rain Water harvesting & Storm Water Drain network
2.50 Civil Works for construction of pits & material
4 Solid waste management
7.50 Organic Waste Convertor, Storage Bins will be provided for Solid waste & Hazardous waste
5 Green Belt Development 2.50 Development of Pits, Sapling cost, Manure & Labour cost
6 Energy Efficient Lighting & Solar Power utilization
5.00 Solar Street Lights
Total 45.0
COST INCURRED DURING CONSTRUCTION PERIOD(IN LAKHS)
S. NO PARTICULARS AMOUNT REMARKS
1 Sanitary Facilities to workers 2.0 Temporary Toilet facilities to workers, Temporary sewerage lining & Transportation of excavated material. 2 Erosion & Sediment Control
measures 1.0
3 Safe disposal of excavated material 1.0
4 Safe disposal of construction spoils 1.0 (Bituminous, oil materials, spoiled cement, etc.)
5 Dust control/ Noise attenuation screens
1.0 Kirby Sheets will be provided
6 Sprinkler arrangement for dust control
1.0 Water sprinkling will be done regularly
7 Monitoring of Environmental Parameters
1.0 Air Sample analysis, Water & Waste Water Analysis, Soil Sample Analysis & Noise Levels
8 Environmental Services 2.0 Will be Outsourced
Sub Total 10
Grand Total 55.0
M/s. Right Source Industrial Solutions (P) Ltd. 41
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
TABLE – 5.2: BUDGETARY ALLOCATION - OPERATION PERIOD
COST INCURRED DURING OPERATION PERIOD
S.NO PARTICULARS AMOUNT (LAKHS)
REMARKS
1 Monitoring of Environmental Parameters
1.0 - Air Sample analysis - Water Analysis - S.T.P Inlet & Out let sample - Soil Sample Analysis - Noise Levels & - D.G. Stack (Quarterly Monitoring will be by third party)
2 S.T.P Operation & Maintenance 6.0 Chemicals, Employs, Power Charges & Replacement of machinery
3 Greenbelt Development 1.0 Maintenance Cost
4 D.G. Set 1.5 Maintenance Cost
5 Solid Waste Management 2.0 Replacement of Bins, MSW Collection Charges & Labour cost
6 Rainwater harvesting & Storm water drains network
1.0 Maintenance cost
Total 12.50
M/s. Right Source Industrial Solutions (P) Ltd. 42
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
CHAPTER–6
6.0 BENEFITS OF THE PROJECT
The project would benefit the project area in many aspects as detailed below:
The project would provide residential space at affordable costs.
The improvements in the physical infrastructure of the project result in the
development of commercial and service activities in the surroundings.
The implementation of project contributes to improvements in the social infrastructure
like roads, housing, water supply, electrical power, drainage, educational institutions
and hospitals etc., in the locality.
The project would create employment potential for skilled, semi-skilled and unskilled
labor both during construction and operational phases of the project to local
population.
Also for imparting any specialized skills to them to be eligible for such employment in
the project on a long term basis i.e., during operational and maintenance stages of the
project.
M/s. Right Source Industrial Solutions (P) Ltd. 43
Sri. Kosuru Venkat Surya Subba Raju – Residential Apartments Sy No. 43, Bahadurguda Village, Saroornagar Mandal, Ranga Reddy District, Telangana State Conceptual Plan & EMP
CHAPTER– 7
7.0 CONCLUSION The proposed project is aimed at developing Residential Apartments Project. The
proposed site is away from city traffic and located in serene environment which will
give comfort to guests. Adequate care is taken to protect, preserve and improve the
environment around the site. About 923.10 Sq.mts of the area earmarked for
development of greenery. It is proposed to take water from Ground Water so that
project need not draw ground water. Further rain water harvesting structures proposed
to enhance the ground water of area. The waste water is proposed to be treated in
ecologically friendly treatment methodology and re-use back.
As the site is well connected with existing road net work and outer ring road no
additional impact will be there on existing roads. Enough parking place is proposed to
be developed for vehicles within the complex.
Thus the project is environmentally viable and sustainable.