Comprehensive Facility
Study
DCIU Comprehensive Facility Study 2
Comprehensive Facility Studyo Multi-phased project, incorporating all DCIU
properties• Phase 1
oConsolidation of leased properties into a central facility
oAdditions and renovations to AstonoMinor renovations at MarpleoRoof replacement at Folcroft
• Future PhasesoFolcroft ImprovementsoMorton Upgrades
DCIU Comprehensive Facility Study 3
Project’s Path
Comprehensive Facility Study &
Future Plans
Examination- Aston & Folcroft Facilities
Special Education
Costing Out Study
Limitation of Existing Programs
due to Buildings
Development of Vision for CTE
Feasibility Study (MM Architects)
DCIU Comprehensive Facility Study 4
Educational Rationale• Early Childhood Education
o Expand DCIU’s ability to create an early childhood center for our typically developing children in Head Start and our students with disabilities in Early Intervention
o Create opportunities to serve children in need of Head Start services from the Penn Delco School District
o Expands DCIU’s ability to provide early childhood services to students in the community
o Strengthens opportunities for collaboration between Early Childhood Education and the CTE Early Childhood Programming
DCIU Comprehensive Facility Study 5
Educational Rationale• Special Programs
o Emotional Support Programs under one supervisor in new facility allowing implementation of a comprehensive Schoolwide Positive Behavior Support System for all students K-12
o Opportunities for creative scheduling and more effective utilization of highly qualified teachers, particularly for middle school and high school
o Provides additional opportunities for career and technical exploration/participation for high school students with emotional support needs
o Expand programming for student with mental health needs who do not display aggressive acting behaviors
DCIU Comprehensive Facility Study 6
Educational Rationale• CTE
o Create theory classrooms which are conducive to differentiated and cooperative instruction
o Program placement within a facility that maximizes accessibility by public clients
o Develop appropriate instruction space, with the necessary technology to administer the necessary testing and academic measures
o The reallocation and redistribution of physical space, in adherence to state and industry standards, to allow for potential program growth
DCIU Comprehensive Facility Study 7
Current DCIU Facilities
• Leased Facilitieso Community School, Borough of Collingdale - June 30,
2014
o TCA, The Christian Academy - June 30, 2015
o Pennington, GVSD - June 30, 2016
o Marcus Hook, June 2016
DCIU Comprehensive Facility Study 8
Facility Flexibility• Connected but separate facilities
o Provides necessary separation of programs as neededo Consolidates common area such as office space, gym, etc.o Combines infrastructure systems (HVAC, electrical, security)o Allows for future potential growth and consolidation of
programs
• Instructional space designed to accommodate a variety of programs
• Greater potential for industry partnerships
DCIU Comprehensive Facility Study 9
Schematic Design
DCIU Comprehensive Facility Study 10
Schematic Design
DCIU Comprehensive Facility Study 11
Schematic Design
DCIU Comprehensive Facility Study 12
TimelineSchedule: CTE Programs Would Relocate Off-Campus
Design Development May 1 – October 1, 2013
Construction Drawings October 1, 2013 – February 15, 2014
Bidding & Contracts March 1 – April 15, 2014
New Construction May 1, 2014 – May 1, 2015
Renovations June 1, 2015 – August 1, 2016
DCIU Comprehensive Facility Study 13
Next Steps• Tonight: Approve contract for Boundary, Topography and
Location Survey
• Continue working with the architects for design development
• DCIU Facility and Finance Committee meetings
• DCIU and DCTS Board Approvals
• Vo-Tech Authority Approval
• Begin Discussions with municipal authorities