NEPA Decision Documents
Environmental Impact Statement : Record of Decision (ROD)
Environmental Assessment: Finding of No Significant Impact (FONSI)
Categorical Exclusion: CE Closeout
Part 3 of the Prospectus
RoleProject Classification (EIS, EA, CE)Documentation Requirements
ComponentsNarrativeChecklist
Type of Projects“c” and “d” list
CE Closeout
Role: Confirms Project Classification (EIS, EA, CE) Includes Required Documentation Verifies Type of CE (“c” or “d” list) Signifies completion of NEPA process
Should also include: Changes in project scope Avoidance and minimization measures Environmental commitments
Programmatic CE
No significant environmental impacts
No unusual circumstances Does not involve:
More than minor amounts of R/W Residential or commercial
displacement Adverse effect of historic resource Coast Guard permit or individual
Corps permit Work encroaching on floodway or
affecting 100-year flood elevation
Does not involve: Work in or adjacent to Wild and Scenic
River More than minor wetland impacts Change in access control Use of temporary road, detour or ramp
closure Known hazmat site Goal exception
Conforms with Air Quality State Implementation Plan
Consistent with Oregon Coastal Zone Management Plan
Does not involve federally-listed T&E species or critical habitat
CE Approvals
Categorical Exclusion:RECODOT Environmental ManagerFHWA Environmental Program Mgr.
Programmatic Categorical Exclusion:RECODOT Environmental Manager
Once these documents are signed, NEPA has been completed.
When is the CE Closeout Needed?
Prior to start of right of way process (if federal funds are used)
Prior to approval of construction funds
Things to remember:
Include copies of all required environmental documents, such as: No Effect memo or BO Section 106 documents 4(f) documentation
Include a copy of the Part 3
Include a project location map