Complaints of People from neighbouring villages to the NGT and the response from the proponent M/s. Coromandel Sugars Ltd., Makavalli village, Mandya District, Karnataka state A Because the proposed project consists of a Distillery, cogeneration plant and power plant and Molassesbased Distillery has been classified as a Category 'A' industry at Entry No. 5(g) of the Schedule to the Environment Impact Assessment Notification, 2006, and a 'red category' industry, and in light of the same it was essential that the environment impact assessment was carried out in a scientific and comprehensive manner so as to ensure that an independent and objective assessment was done in the interests of the environment and the local populations in the vicinity of the proposed project. However, this has not been done We have obtained the environmental clearance following the due process as mentioned in SO 1533 dt. 14.9.2006 by the Ministry of Environment Forests and Climate Change (MoEFCC). B Because, the grant of environmental clearance is clearly in violation of the Environment Impact Assessment notification 2006 and various judgments of the Hon'ble Supreme Court and High Courts and therefore needs to be set aside National Green Tribunal, Chennai advised the EAC and MoEFCC to review the documentation once again in view of the objections raised by the appellants. C Because the project proponents have a long history of environmental pollution in the operation of their Sugar Industry on which premises the Distillery Cogen and power plant are proposed, and hence it is unjustifiedthat they be permitted to start another highly polluting industry in the same region in such a mechanical manner. The existing unit obtained Consent to Operate vide letter no. PCB/111/HPI/2010/1012 from Karnataka State Pollution Control Board (KSPCB) dt. 06.11.2014. The unit is in operation from 1996. The unit modified the Effluent treatment plant during 2013 and established ventury scrubbers as advised by the KSPCB from time to time. The reports of monitoring conducted both by the KSPCB and third party laboratory is observed to be within the limits. The results are presented in Annexure I. D Because the Environmental Appraisal Committee has failed to apply its mind to the facts and circumstances of the Project and the Terms of Reference framed are not comprehensive and fail to take into consideration various social and environmental aspects, or the probable environmental pollution and degradation and social impacts possible from the proposed project. The TOR's have omitted the existing pollution caused by the sugar industry and the implications that the proposed new plants have in that context The details of effluent treatment plant are presented in page no. 116 to 129 of EIA report. The TORs do not even make any mention of the Flyash Notification, 1999 as amended from time to time issued by the Ministry of Environment and Forests, placed as Annexure A27, which is unjustifiable The proposal is for a cogeneration plant of 30 MW using a combination of 15:85 of coal and bagasse. The fly ash notification is applicable for TPP's that utilize 100% coal. E Because, the entire approach of the EAC/MOEF has been to recommend the project for approval without considering the ecological and sociocultural impacts of the project and by turning a blind eye to the shoddy EIA report prepared by M/s Enviro Care India Private Limited, the illegal manner in which the public hearing was conducted and the report prepared and the failure to consider the valid objections raised by the villagers including the Appellants The project authorities obtained terms of reference for preparation of EIA vide letter no. F.No. J11011/565/2010IA II (I) dated. 23.03.2011

Complaints We the 14.9.2006 (MoEFCC).environmentclearance.nic.in/writereaddata/modification/Extension/Attach_file/0_0... · Complaints of People from neighbouring villages to the

  • Upload
    dolien

  • View
    213

  • Download
    0

Embed Size (px)

Citation preview

Complaints of People from neighbouring villages to the NGT and the response from the proponent M/s. Coromandel Sugars Ltd., Makavalli village, Mandya District, Karnataka state 

A  Because  the  proposed  project  consists  of  a  Distillery,  cogeneration  plant  and  power  plant  and Molasses‐based  Distillery  has  been  classified  as  a  Category  'A'  industry  at  Entry  No.  5(g)  of  the Schedule to the Environment Impact Assessment Notification, 2006, and a 'red category' industry, and in  light of  the  same  it was essential  that  the  environment  impact  assessment was  carried out  in  a scientific and comprehensive manner so as to ensure that an  independent and objective assessment was done in the interests of the environment and the local populations in the vicinity of the proposed project. However, this has not been done 

  We have obtained the environmental clearance following the due process as mentioned in SO 1533 dt. 14.9.2006 by the Ministry of Environment Forests and Climate Change (MoEFCC).  

B  Because, the grant of environmental clearance is clearly in violation of the Environment Impact Assessment notification 2006 and various judgments of the Hon'ble Supreme Court and High Courts and therefore needs to be set aside 

  National Green Tribunal, Chennai advised the EAC and MoEFCC to review the documentation once again in view of the objections raised by the appellants.  

C  Because  the project proponents have a  long history of environmental pollution  in  the operation of their Sugar Industry on which premises the Distillery Cogen and power plant are proposed, and hence it is unjustified‐that they be permitted to start another highly polluting industry in the same region in such a mechanical manner.  

  The  existing  unit  obtained  Consent  to  Operate  vide  letter  no.  PCB/111/HPI/2010/1012  from Karnataka State Pollution Control Board (KSPCB) dt. 06.11.2014. The unit is in operation from 1996. The unit modified  the Effluent  treatment plant during 2013 and established ventury  scrubbers as advised by the KSPCB from time to time.    The reports of monitoring conducted both by the KSPCB and third party laboratory is observed to be within the limits.   The results are presented in Annexure ‐ I.  

D  Because  the  Environmental  Appraisal  Committee  has  failed  to  apply  its  mind  to  the  facts  and circumstances of the Project and  the Terms of Reference  framed are not comprehensive and  fail  to take  into  consideration  various  social  and  environmental  aspects,  or  the  probable  environmental pollution and degradation and social impacts possible from the proposed project. 

    The TOR's have omitted the existing pollution caused by the sugar industry and the implications that the proposed new plants have in that context 

    The details of effluent treatment plant are presented in page no. 116 to 129 of EIA report.      The     TORs     do     not   even     make     any     mention     of      the     Fly‐ash Notification, 1999 as 

amended  from  time  to  time  issued  by  the Ministry  of  Environment  and  Forests,  placed  as Annexure ‐ A27, which is unjustifiable 

    The proposal  is for a cogeneration plant of 30 MW using a combination of 15:85 of coal and bagasse.  The fly ash notification is applicable for TPP's that utilize 100% coal.  

E  Because,  the entire approach of    the   EAC/MOEF   has     been      to  recommend      the     project      for   approval     without      considering      the  ecological  and  socio‐cultural  impacts  of  the  project  and  by turning     a blind eye to the shoddy EIA report prepared by M/s Enviro Care India Private Limited, the illegal   manner in which the public hearing was conducted and the report prepared and the failure to consider the valid objections raised by the villagers including the Appellants 

  The project authorities obtained  terms of  reference  for preparation of EIA vide  letter no. F.No.  J‐11011/565/2010‐IA II (I) dated. 23.03.2011 

The public hearing for the project was conducted on 09.12.2011 at Factory premises. The final EIA was appraised by the honourable Environment Appraisal Committee (EAC) on 24‐25th September, 2012 The EC was issued vide letter no.F.No. J‐11011/565/2010‐IA II (I) dt. 31.12.2012 from MoEFCC The CTE was obtained vide letter no.PCB/111/HPI/2011/90 dt. 24.04.2013 from KSPCB.  

F  Because the non‐application of mind by the Project proponent and the lack of scrutiny by the EAC and the MoEF where they have simply accepted the submissions made by the project developer without any independent verification, is contrary to the precautionary principle 

  The final EIA was appraised by the honourable Environment Appraisal Committee (EAC) on 24‐25th September, 2012  

G  Because,   as   per   the   accreditation   granted   by   the   Ministry   of Environment and Forests, M/s Enviro Care India Private Limited are competent to take up Category 'B' projects and not Category 'A', whereas the present project is on categorized under Category 'A', and in  the  light  of  the  same,  the  entire   process   of   the   grant   of Environmental Clearance gets vitiated. The relevant extracts of the List of Accredited EIA Consultants Organizations as per  the Ministry of Environment and  Forests  is placed as Annexure A‐28. 

  The  proposal  was  presented  by  Team  Labs  and  Consultants  in  the  EAC  meeting,  which  was Accredited EIA Consultant for Category “A” Projects of EIA notification category 5(g)  

H  Because the project proponents and the EIA Report suppresses the fact that the proposed project  is within  1.5  km  of  the  Hemavathi  river,  which  is  apparent  even  from  the  records  of  the  KSPCB, reference being made  to Annexure  ‐ A24, wherein  the KSPCB has stated  that  the distance between the  factory and  the Hemavathi  river  is between 1.2  to 1.6 kms. The establishment of  the proposed industry  is  contrary  to  the Siting Guidelines  for new  industries brought out by  the Karnataka State Pollution Control Board/ applicable to distilleries which states that "No new  industry specified below shall be permitted to be  established within 1.5 k.m.from the embankment of the streams, rivers, dams as indicated below,  If any of these water bodies are the source of drinking water, then such distance shall  be  stipulated  which  will  not  affect  such  waters  by  discharge  of  the  pollutants."  The  Siting Guidelines notified by the KSPCB is placed as Annexure ‐ A29. 

   KSPCB has categorically informed the NGT that the site is 2 km away from Hemavathi river.   "The Tribunal is of the considered view that the present project is only an expansion of the existing industry and the KSPCB has filed its reply stating that the Hemavathi river is situate at a distance of 2 km from the project. Much significance cannot be attached to the distance criteria since the location of the expanded facility is in the same premises as that of the existing industry. Hence, this point is decided  in  favour of  the 3rd  respondent  industry"  (Para No. 81, Page No. 67‐68 of  the NGT order dated 12.05.2012).  

I  Because all the land impacted by the Coromandel Distillery project and all components integral to the project  have  not  been  included  in  the  environmental  and  social  impact  assessment  making  the decision made on this incomplete information liable to be set aside.  

   The impact area considered is 10 km radius area surrounding the plant site.  

J  Because  the EIA Report does not meet  the ToRs  issued, evidenced by  the Table placed above) For instance 

  i  In regard to the TOR  'Present  land use based on satellite  imagery',  it  is found that the detail of site and  information related to environmental setting within 10 km radius of the project site  is 

not provided. Further, the Draft EIA Report consciously suppresses the true number of villages and  towns  in  the  vicinity of  the project. Moreover/  the  fact  that  the Hemavathi River  is  less than1/2 km away from the proposed project is suppressed 

     The land use land cover map is presented in Annexure ‐ III of the EIA report.  An updated land use land cover map is also prepared and the same is enclosed in Annexure ‐ II. 

  ii  In regard to the TOR 'Storage for bagasse', no details of the storage facility are provided      

The total bagasse requirement for proposed 140 TPH boiler is 1560 TPD and same was stored in covered shed. Baggase storage area is indicated in Plant Layout (Annexure ‐ III)  

  iii  In regard to the TOR 'Hydro‐geological study of the area for availability of ground water', no   reference is made to the Hemavathi River and further extremely sketchy baseless and unreliable information is provided without any sources or supporting documents cited 

     The hydrogeological study of the area was not conducted as the existing and propsoed plants depend on Hemavathi river for its water requirement.    Government of Karnataka permitted withdrawl of surface water Hymavathi river to an extent of 1.293 cusec (3176 KLD).  The water requirement  after  the  expansion  is  2850  KLD,  and  no  additional  water  permission  is warranted.   

  iv  In regard to the TOR 'List of flora and fauna in the study area', an extremely casual presentation of  supposed  findings  is provided. For  instance at page 95  reference  is made  to  'sussels viper' when in fact it is Russell’s viper. Moreover, the bird species are not even identified. There is no mention of the bird sanctuary at near Hemagiri falls, which though not declared as a sanctuary Houses. There is no assessment on the probable impact on the aquatic life in Hemavathi River. Further  the  fact  there  is  a  massive  State  Forest,  Krishnaraya  Forest,  within  4  kms  of  the proposed plant has been suppressed and there has been no assessment of the flora and fauna in the forest which is known to have endemic flora and several species of fauna including wild pigs, peacocks, deer, Kirba (cheetah), rabbits, foxes, etc. 

     The proposal initially depended on the toposheet (57 D/6) issued by the SOI in 1972‐73, which does not reflect any forest within the imapct area.   Recently we have acquired the latest SOI toposheets  (copyright 2011)  for  this area and  it was observed  to have a  reserve  forest at a distance  of  8.87  km  in  SW  direction.   We  shall  submit  a  detailed  ecology  and  biodiversity report of this area  in view of the RF in the impact area.   

  v  In  regard  to  the TOR  'Details of  socio‐economic welfare activities’, no clarity  is provided as  to   whether the survey was for villages within 5km radius (para 3.9.1) or 10 km radius (para 3.9.2), and there  is no supporting  information or details. Shockingly, table 3.8  is meteorological data! Further, para 3.9.4 is completely misleading inasmuch as that there are more than two crops and no reference is made to canal irrigation 

    The updated socioeconomic data for the imapct area is presented in Annexure ‐ IV.   

K  Because the EIA report is of a poor quality and indicates both a lack of authenticity   and   expertise in the   EIA   consultants,   showing   a combination of poor secondary research of scientific papers and poor  fieldwork, and  indicating a poor  study of both ecological and  socio‐cultural aspects  in  the EIA report. The concocted nature of the draft EIA  is exposed on pursuing Chapter 3 of the Report titled 'Existing environmental status', A false claim is made that the baseline data was monitored from April to  June 2011  and  secondary data was  collected  from  various  government  and NGOs, which  is not made out in the Chapter. 

    No  data  in  regard  to  the  micro‐meteorological  conditions  including  temperature,  rainfall, relative humidity, wind direction, wind speed has been collected at all, and instead all the data presented pre‐dates the TORs.  

    Ambient Air Quality (AAQ) data and micrometeorological data was collected during April 2011 to June 2011 after submission of application for Terms of Reference (TOR). 

    The  baseline  data  of  soil  quality  presented  in  the  said  chapter  is  undated  and  bereft  of  the methodology adopted in regard to the sampling and assessment of soil quality  

    Soil  sampling was  done  as  per  the  guidelines  of  ECI‐SOP‐SAM‐35,  and  the monitoring was conducted during April 2011.   

    The water quality parameter of ground water and surface resources is unreliable since the same is bereft of any details in‐regard to the methodology of sampling and details of testing. Further, there is no assessment or even reference made to the Hemavathi River, which flows less than11/2 km from the site of the proposed project 

    Both ground and surface water samples were collected using IS method no.IS: 3025:P1: 1999, and the samples were analysed on the basis of IS: 3025/P14/2002 and its parts.  

    The ambient air quality  referred  to at para 3.5  suffers  from  the  same  critical drawbacks and shockingly there is no reference even made to the existing sugar industry and its impacts on the ambient air quality. Similar is the case with the parameters of the noise environment. 

    Ambient air quality was monitored while  the sugar plant was operational during April 2011.   The noise quality was monitored during April 2011.  

    A perusal of the so‐called studies on land use (para 3.7), which except for stating the objectives of the land use studies, provides no other details whatsoever. As pointed above, the assessment of the biological environment (para 3.8) has at best,  if at all carried out,     been     cursory     and   carried   out   without   any   sense   of responsibility.  

    Land Use and Land Cover Map is presented in Annexure III of EIA report.   

    The  lackadaisical approach  is also brought out  in  regard  to  the analysis of  the socio‐economic environment (para 3.9), wherein at 3.9.1 it is claimed that the socio‐ economic study was carried out  in a 5 km  radius, whereas at 3.9.1  it  is claimed  that  it carried out  in villages  in  the 10 km radius.. Further, while  it  is stated  in para 3.9.2, that there are 8 villages  in the 10km radius,  in reality there are at least 15 Panchayats consisting of scores of villages and several towns within this radius 

    The updated socioeconomic data for the imapct area is presented in Annexure ‐ IV.   

    The evaluation of agriculture in para 3.9.4, it is falsely1 stated that there is insufficient irrigation facilities, without even making a reference to the surface  irrigation through canals and directly from the river. 

    Majority of the  imapct area has dry  land agriculture with crops of Ragi and black eyed peas, while the canal and borewell irrigated area has sugar cane and paddy as main crops.  The area also has coconut and eucalyptus plantation in few patches of land.  

    Though there are existing and proposed industry around this proposed industry (para 4.3.2), no reference is made whatsoever in regard to these industries and the pollution being caused and the impacts suffered. 

    No major industries or distilleries  are located within the impact area. (TOR no.7)   

    The  EIA  Report  states  that  there  are  no  forest/wildlife within  25  kms, which  is  completely contrary  to  the  facts  on  ground.  There  is  the  Krishnaraya  State  Forest within  4  kms  of  the proposed  project  with  various  species  of  flora  and  fauna.  It  is  submitted  that  this  is  also reflected in a Report prepared by the Deputy Environmental Officer, KSPCB, Mysore at the time of  issuance  of  consent  for  establishment  of  the  sugar  industry  at  Makavalli  Village  dated 26/02/1998, placed herewith as Annexure ‐ A29, wherein it is clearly stated that "There is social  forestry, forest on north eastern and south eastern direction at a distance of about 3 KM from the proposed site." 

    The proposal initially depended on the toposheet ( 57 D/6) issued by the SOI in 1972‐73, which does not reflect any forest within the imapct area.   Recently we have acquired the latest SOI top  sheets  (copyright 2011)  for  this area and  it was observed  to have a  reserve  forest at a distance  of  8.87  km  in  SW  direction.   We  shall  submit  a  detailed  ecology  and  biodiversity report of this area  in view of the RF in the impact area.  

    The claim  in the EIA Report that there are no hill/ mountains within 25 kms  is false, as there  is mountainous region within 4kms of the proposed project on which the forests are 

    The highest MSL observed in the impact area is 840 m and the plant site MSL is 823 m.     The impact area  consists of open agricultural  lands  sloping mainly  towards Hemavathi  river and draining into the river and or its drains.  A  minor part of the imapct area in the northern side drains  into Kikkeri tank. The North eastern     The southwestern region of the  impact area has hillocks raising to a height of 840 m with MSL of 823 m.   The impact area is also  irrigated by Hemagiri and High level Hemavathi left bank canal.   

    The  claim  that  there  are  no  historical  places within  25  kms  of  the  Project  is  false, which  is blatantly  false since there are several historical and archeologicai sites within 10 kilometers of the proposed plant including 

         Lakshminarayana Temple at Hosaholalu is a magnificient example of Hoysala architecture of the 

thirteenth century. The intricate carvings in stone depict various images from the Mahabharata and other epics 

         Panchalingeshwara Temple dating to pre‐Hoysala period, and others within 10 kms.          Brahmeshwara  Temple,  Kikkeri,  which  is  a  fine  specimen  of  Hoysala  architecture  and  was 

constructed in A.D.1171          ASI site on the island in Hemavathi River near. Akkihebalu which dates to the reign of Tipu Sultan          In fact Shravanabelagola  is within a 19 kms radius of the proposed plant,  is the  location of the 

57‐feet tall monolithic statue of Gommateshvara, which  is considered to be the world's  largest monolithic stone statue. The following table presents the notified archaeological monuments by both ASI and state ASI, with reference to their distance and bearing from the plant site.  

     S.No  Name of the Monument  Notified 

by Distance  from  the project site (km) 

Direction 

1  Lakshminarayana temple ASI  9.29   SE 2  Panchalingeshwara  ASI  8.83  NW 3  Brahmeshwara  State ASI  7.22  N 

ASI: Archaeological Survey of India  

L  Because Chapter 4 titled Impact Analysis1 is an exercise in speculation without any scientific or rational basis. For instance 

    The  impact  analysis  only  puts  forth  a  cursory  understanding  of    the  impact  during  the construction  phase, which  is  unreliable  and  unscientific.  In  regard  to  the  operational  phase, there are no details forthcoming of the effect of the distillery plant or the power place or the cumulative effect of the same. 

    The air quality impact predictions considered the anticipated emissions from the proposed 140 TPH  coal  and  bagasse  fired  (15:85)  boiler.      The  boiler  is  provided with  ESP  to  control  the emissions.    

Technical Specifications of Electrostatic Precipitator – 140 TPH Boiler S.NO  DESIGN PARAMETER  100% IMPORTED 

COAL 100% BAGASSE 

1  DESIGN GAS FLOW RATE IN AM3/HR  254628  363663 2  TEMPERATURE DEG.C (OPERATING)  160  160 3  CASING MECHANICAL DESICN TEMPERATURE 

DEG.C 250  250 

4  DUST TYPE  FLY ASH  FLY ASH 5  MAXIMUM INLET DUST LOADING (GM/NM3)  25  2.84 6  OUTLET EMISSION FOR ESP(MGM/NM3)ALL 

FILED WORKING 50  50 

7  OUTLET EMISSION FOR ESP(MGM/NM3)‐FIRST FIELD OUT OF SERVICE 

100  100 

8  MOISTURE IN GAS (% V/V)  9.9  50 9  UNBURNT CARBON IN FLY ASH (%)  10  10 10  COLLECTION AREA M2  5630.4(N)4222.8 

(N‐1) 5630.4(N)4222.8 (N‐1) 

11  SPECIFIC COLLECTION AREA M2/M3/SEC.  79.60/59.70  55.74/41.80 12  NO OF GAS PASSAGES  23  23 13  EFFECTIVE C E WIDTH (METER)  3239  3239 14  EFFECTIVE C E HEIGHT (METER)  9.448  9.448 15  VELOCITY THIROUGH ESP M/SEC  0.8  1.14 16  TREATMENT TIME (SEC).  16.2/12.10  11.3/8.50 17  NO OF FIELDS IN SERIES  4MECH /4 ELECT  4MECH /4 ELECT 18  MIGRATION VELOCITY(CM/SEC)  6.90/8.06  7.25/8.00 19  DESIGN PRESSURE (mm WG)  ±400  ±400 20  DUST DENSITY FOR POWER (KG/M3)  1100  1100 21  DUST DENSITY FOR DISCHARGE (KG/M3)  800  400 22  FLG TO FLG PRESSURE DROP (mm WC)  25  25 23  EFFICIENCY(%)  99.59  98.24 

 

ASH COLLECTION RATE IN EACH FIELD (KG/HR) SR.NO  FUEL  100% IMPORTED COAL  100% BAGASSE 

1  FIELD‐1  1475(0)  414(0) 2  FIELD‐2  373(1578)  151(438) 3  FIELD‐3  94(317)  55(143) 4  FIELD‐4  24(64)  20(47) 5  DUST COLLECTED IN SP(KG/HR)S  1967(1959)  640(628) 

VALUES IN PARENTHESIS ARE FOR FIRST FILED OUT OF SERVICE 

     At para 4.3.2.  (a), the ash from Bagasse  is estimated to be 30 tonnes/ day, while the ash from coal is estimated to be 40 tonnes/ day without any basis whatsoever. This is a recurring theme in the chapter and the Report. 

    It is proposed to use agrofuels in combination with coal (15%) in 140 TPH boiler. The total ash generation shall be in the order of 15 TPD.    

    In the para titled  'Air Environment', (para 4.3.5), there is no reference made whatsoever on the ash content and the sulphar content which  is to used  in the cogent plant which  is the primary factor  to  determine  quantum  of  fly  ash,  nature  of  emissions  including  SOx.  As  such  there  is absolutely no scientific analysis of the  impacts that the project would have  in regard to the air environment. 

    Fuel analysis  Ultimate analysis of Bagasse 

S.no  Ultimate analysis   Input Values  Units 1  Carbon  23.5  % 2  Hydrogen  3.25  % 3  Oxygen  21.75  % 4  Ash  1.5  % 5  Moisture  50  % 6  Sulphur  0  % 7  Nitrogen  0  % 

   Total  100  %    GCV  2272  Kcal/kg Ultimate analysis of coal 

S.No  Ultimate analysis   Input Values  Units 1  Carbon  55.4  % 2  Hydrogen  4.91  % 3  Oxygen  20.25  % 4  Ash  2.0‐3.0  % 5  Moisture  10  % 6  Sulphur  0.81  % 7  Nitrogen  0.95  %    Total  100  % 

   GCV  5545  Kcal/kg  

M  Because the chapter on the * Environment Management Plan1 (chapter 5) cannot be relied upon for any purpose whatsoever, in view of the fact that the analysis of the existing environmental parameters is shoddy and furthermore the assessment of the impacts of the proposed project have not even been identified or scientifically evaluated. 

   N  Because,  as  per  the  EIA  notification  2006  'deliberate  concealment,  and/or  submission  of  false  or 

misleading  information or data which  is material  to screening or scoping or appraisal or decision on the application shall‐make the application liable for rejection, and cancellation of prior environmental clearance   granted   on     that   basis'.      In     the      instant     case     the     project proponents are guilty of several material suppressions that vitiate the entire process. 

  No comment O  Because the Draft EIA Report falls woefully short of the standards set  in the  'Technical EIA  'Guidance 

Manual for Distilleries' prepared for the Ministry of Environment and Forests by IL&FS Ecosmart Ltd   EIA  report was made  based  on  the  Terms  of Reference  (TOR)  issued  by MOEFCC  vide  letter  no. 

F.No.J‐11011/565/2010‐IA II (I) dt. 23.03.2011.   

P  Because, misleading and wrong Information amounts to fraud and any decision made on the basis of such fraudulent information is liable to be set aside with exemplary cost 

  No comment.  

Q  Because although there are more than 15 Gram Panchayat consisting of scores of villages and several urban conurbations  within a 10 km radius of the proposed project, information in regard to the public hearing was only provided to the Makavalli Gram Panchayat, hence denying all other affected persons the  right  to  participate  in  these  proceedings.  Further  even  according  to  the minutes  of  the  public hearing  a  copy  of  the  draft  EIA  Report  was  only  displayed  at  the  office  of  the  Makavalli  Gram Panchayat.  In  this  regard,  reference could be drawn  to Annexure  ‐ A15, wherein  the Chowdenahalli Gram Panchayat passed a resolution dated 10/08/2012 which was submitted to the KSPCB, wherein it was noted  that  all 13  villages  coming under  the Gram Panchayat  limits, which  are  adjacent  to  the proposed plant will be affected by the project 

  The notification of the public hearing was advertised in English (The Hindu) and Kannada (Prajavani) on  08.11.2011.    The  public  hearing  was  conducted  on  09.12.2011,  chaired  by  the  district commissioner (collector), Mandya district.    The public hearing was attended by over 100 people of the local villages along with the local public representative MLA of Krishnarajpet  Taluk.   The minutes of  the meeting  reflect  various  concerns expressed during the public hearing.    The honourable NGT observed  the  following; “hence,  the  contention put  forth by  the appellant’s side that the public hearing was not conducted as contemplated under the EIA notification, 2006 is without force and has to be rejected".  

R  Because even the villagers at Makavalli village only became aware of the said public hearing only a few days  before  the  same,  in  contravention  of  the  EIA  Notification,  2006,  The  persons were  also  not informed that the same was a public hearing which was an opportunity to raise objections, but merely as a meeting that they were to attend. Further, even during the meeting, the Deputy Commissioner informed them that this was not the final meeting, and a subsequent meeting would be held to take a decision in regard to the proposed project 

  The notification of the public hearing was advertised in English (The Hindu) and Kannada (Prajavani) on  08.11.2011.    The  public  hearing  was  conducted  on  09.12.2011,  chaired  by  the  district commissioner (collector), Mandya district.    The public hearing was attended by over 100 people of the local villages along with the local public representative MLA of Krishnarajpet  Taluk.   The minutes of  the meeting  reflect  various  concerns expressed during the public hearing.    The honourable NGT observed the following; “hence, the contention put forth by the appellant’s side that the public hearing was not conducted as contemplated under the EIA notification, 2006 is without force and has to be rejected".  

S  Because the draft EIA report is available only in English, and not in the local language, i.e. Kannada, in contravention  of  the  EIA Notification,  rendering  the  entire  process  of  public  consultations  a mere formality. Pertinently, the fact that the draft EIA Report was not available in Kannada was specifically raised  in  the  public  hearing  by  one  of  the  speakers,  and  the  same  has  neither  been"  denied  nor addressed. 

  The notification of the public hearing was advertised in English (The Hindu) and Kannada (Prajavani) on  08.11.2011.    The  public  hearing  was  conducted  on  09.12.2011,  chaired  by  the  district commissioner (collector), Mandya district.   

The public hearing was attended by over 100 people of the local villages along with the local public representative MLA of Krishnarajpet  Taluk.   The minutes of  the meeting  reflect  various  concerns expressed during the public hearing.    KSPCB  informed NGT that the proponents have to submit the summary documents  in both English and Kannada while EIA report is submitted in English.   The honorable NGT observed the following; " hence,  the contention put forth by the appellants side that  the  public  hearing was  not  conducted  as  contemplated  under  the  EIA  notification,  2006  is without force and has to be rejected".    

T  Because  the  entire  draft  EIA  report was  not made  available  to  the  local  populations  for  reference before  the public hearing was held, due  to which  the public hearing was rendered a mere  formality and their participation mere tokenism. The  lack of critical and correct  information suppressed by the project  proponents  clearly  reveals  their  deliberate  and  intentional  strategy  to  scuttle  the  entire process and efforts of environmental protection. 

  The honorable NGT observed the following; " hence,  the contention put forth by the appellants side that the public hearing was not conducted as contemplated under the EIA notification, 2006 is with out force and has to be rejected".  

U  Because,  the  public  hearing was  not  conducted  in  compliance with  the  EIA  notification  2006  and orders  of  various  Courts.  Persons  from  other  affected  villages  in  about  15  Gram  Panchayats  and numerous   towns were not  informed about the public hearing and hence were denied their right to participate in the same. 

  The honorable NGT observed the following; " hence,  the contention put forth by the appellants side that  the  public  hearing was  not  conducted  as  contemplated  under  the  EIA  notification,  2006  is without force and has to be rejected".  

V  Because the minutes of the public hearing have not been prepared in accordance with law and instead have been drafted in the confines of the Deputy Commissioner, contrary to Section 6.4 of Appendix IV of the EIA notification that states that: "...The summary of the public hearing proceedings accurately reflecting all  the viexos and concerns expressed shall be  recorded by  the  representative of  the SPCB or UTPCC  and  read  over  to  the  audience  at  the  end  of  the  proceedings  explaining  the  contents  in  the local/vernacular  language and  the agreed minutes shall be  signed by  the District Magistrate/ District Collector/Deputy Commissioner or his or her  representative on  the  same day and  forwarded  to  the SPCB/UTPCC concerned." 

  The honorable NGT observed the following; " hence,  the contention put forth by the appellants side that the public hearing was not conducted as contemplated under the EIA notification, 2006 is with out force and has to be rejected".  

W  Because, the manner in which the approval has been granted clearly reflects non‐applicajtion of mind to  relevant  considerations,  and  a perusal of  the  records  reveals  that  the whole  effort has been  to justify the project without these considerations. Few examples as an illustration are provided below: 

       There was no mention of  the outcome of  the public hearing  in  the EAC minutes and  therefore 

there was no detailed scrutiny. As per  the EIA notification 2006, "Appraisal means  the detailed scrutiny  by  the  Expert  Appraisal  Committee  or  State  Level  Expert  Appraisal  Committee  of  the application and other documents  like  the Final EIA    report, outcome of  the public consultations including  public  hearing  proceedings,  submitted  by  the  applicant  to  the  regulatory  authority concerned  for  grant  of  environmental  clearance."  However,  the  EAC  has  not  done  a  detailed scrutiny of the 'outcome of the public consultations including public hearing procedures' 

    Copy of the presentation made to the EAC is enclosed.   

    The EAC has not discussed the present pollution being caused by the very same industry     Copy of the presentation made to the EAC is enclosed. 

 X  Because,  the approval granted and  the proceedings of the EAC reveals non‐application of mind and 

also is contrary to principles of administrative law which requires that reasons be given for every decision by‐a public authority 

  No comment.  

Y  Because, the manner in which the EAC dealt with the issue reveals a casual and lackadaisical   No comment. 

 Z  Because the Environmental Clearance granted is based on false and fabricated information, which has 

been blindly believed, despite I objections being raised against the same   No comment. 

 AA  Because there is no compliance with the Flyash notification, when the draft EIA states that about   40 

tones/day would be generated from the Cogen plant during off season (page 128 of Draft EIA).   The proposal is for a cogeneration plant of 30 MW using a combination of 15:85 of coal and bagasse.  

The fly ash notification is applicable for TPP's that utilize 100% coal.  

BB  Because  the  water  requirements  for  the  proposed  distillery,  cogeneration  and  power  plants  are sought to be met entirely from the Hemavathi river flowing nearby which is impermissible in view of the fact that the 3rd respondent only has permission to draw water from the Hemavathi river directly for the purposes of running the sugar factory only. Further, it is the major source of drinking water for K.R. Pete taluk. Hence, the allocation for the proposed project is also contrary to the National Water Policy, 2002 as per which the water allocation priorities should be as follows; • Drinking water • Irrigation • Hydro‐power • Ecology • Agro‐industries and non‐agricultural industries • Navigation and other uses  

  Water  requirement after expansion  is 2850 m3 per day  is well within  the permission accorded by Govt.  of  Karnataka.  Copy  of  permission  to withdraw water  from Hemavathi  river  is  enclosed  at Annexure ‐ V  

CC  Because the project proponents have already begun construction activities towards establishment of   the project without even securing all  the necessary clearances, permissions  .and NOCs  including the Consent for Establishment from the Karnataka State Pollution Control Board. 

  Consent  for  Establishment  was  obtained  for  expansion  from  KSPCB  vide  letter  No. PCB/111/HPI/2011/93 dated 24.04.2013 and the erection of co‐generation plant is completed while the construction of distillery is yet to be commenced.   We have also obtained the permission from the honorable NGT to conduct  test run the co‐generation plant, however we have not completed the test run. (Photographs  enclosed) 

 

ANNEXURE – II: Land Use and Land Cover Map 

 

ANNEXURE – II: Land Use and Land Cover Map 

 

ANNEXURE – III: Layout Showing Baggase Storage Shed 

    

ANNEXURE – IV: Updated Socio Economic Data of the Impact Area Population Distribution – Study Area 

Category  kms  Total 1‐3 3‐5 5‐7 7‐10 

Total Population  7534 9732 24208 72075  113549Total Population – Male  3819 4915 12128 36111  56973Total Population – Female  3715 4817 12080 35964  56576Population <6 years  790 924 2420 7286  11420Male <6 years  400 469 1223 3719  5811Females < 6years  390 455 1197 3567  5609Scheduled Caste Population ‐ Total  1126 942 3439 9191  14698Male – SC  584 482 1735 4565  7366Female – SC  542 460 1704 4626  7332Scheduled Tribe Population Total  317 83 420 2248  3068Male – ST  158 42 212 1117  1529Female – ST  159 41 208 1131  1539

 Literacy  Study Area 

Category  kms  Total 1‐3  3‐5  5‐7  7‐10 

Total Population  7534 9732 24208 72075  113549Total Population – Male  3819 4915 12128 36111  56973Total Population – Female  3715 4817 12080 35964  56576Population <6 years  790 924 2420 7286  11420Male <6 years  400 469 1223 3719  5811Females < 6years  390 455 1197 3567  5609Total Literates  4636 5829 15258 47162  72885Male –Literates  2714 3413 8639 26211  40977Female – Literates  1922 2416 6619 20951  31908Total Illiterates   2898 3903 8950 24913  40664Male –Illiterate  1105 1502 3489 9900  15996Female – Illiterate  1793 2401 5461 15013  24668

 Employment ‐ Study Area 

Category  kms  Total 1‐3  3‐5  5‐7  7‐10 

Total Population  7534 9732 24208 72075  113549Total Population – Male  3819 4915 12128 36111  56973Total Population – Female  3715 4817 12080 35964  56576Total Workers  3403 4181 11990 32859  52433Total Workers – Male  2513 3133 7909 22641  36196Total Workers – Female  890 1048 4081 10218  16237Total Main Workers  2822 3568 9642 25618  41650Main workers – Male  2361 2919 7369 19984  32633Main Workers – Female  461 649 2273 5634  9017Total Marginal Workers  581 613 2348 7241  10783Marginal Workers – Male  152 214 540 2657  3563Marginal Workers – Female  429 399 1808 4584  7220Total Non Workers  4131 5551 12218 39216  61116Non Workers – Male  1306 1782 4219 13470  20777Non Workers – Female  2825 3769 7999 25746  40339

 

Main workers Study Area Category  kms  Total 

1‐3  3‐5  5‐7  7‐10 Total Population  7534 9732 24208 72075  113549Total Population – Male  3819 4915 12128 36111  56973Total Population – Female  3715 4817 12080 35964  56576Total Main Workers  2822 3568 9642 25618  41650Main workers – Male  2361 2919 7369 19984  32633Main Workers – Female  461 649 2273 5634  9017Total Cultivators   1977 2415 6061 12289  22742Cultivators – Male  1805 2101 4978 10313  19197Cultivators‐ Female  172 314 1083 1976  3545Total Agriculture Labor   377 902 1633 4614  7526Agriculture Labor – Male  179 611 873 2663  4326Agriculture Labor – Female  198 291 760 1951  3200Total Household Workers  70 9 164 376  619Household Workers – Male  65 9 136 267  477Household Workers – Female  5 0 28 109  142Total Others  398 242 1784 8339  10763Others – Male  312 198 1382 6741  8633Others – Female  86 44 402 1598  2130

  

Land Utilization Pattern 

Category kms  Total Area, 

Ha 1‐3  3‐5  5‐7  7‐10 Forest Land  19  145  304  173  641 Area not available for cultivation  276  332  889  2520  4017 Cultural Waste Land  467  969  1028  3080  5544 Total Irrigated Land  874  781  2175  4156  7986 Un Irrigated Land  873  1645  2313  6066  10896 Total  2508  3872  6709  15995  29084   

PERMISSION FOR THE WITHDRAWAL OF WATER

PERMISSION FOR THE WITHDRAWAL OF WATER